DESIGN/BUILD RIGHT OF WAY PROJECT PROGRESSION Tuesday, October 13, 2015 4:15 – 4:45 PM
Design/Build Right of Way Project Progression
2
Kerry Fulton Strategic Projects Division, ROW Texas Department of Transportation
Elizabeth T. Norris Right of Way and Utility Management Atkins
Ryan Bean Dallas/Fort Worth, Construction Kiewit
SPEAKERS
Strategic Project Division (SPD) ROW Projects Are Different
3
PPP
•Public Private Partnership
CDA
•Comprehensive Development Agreement
DB
•Design Build
DBOM
•Design Build Operate Maintain
Concession
•Form of project financing
Programs under the Strategic Projects Division include:
It Begins With Coordination and Communication
4
The P3 project model
Advanced Acquisition
when possible
Identify and
manage risk
SPD ROW Program
5
Early Communication
Utility Owners
County & Local
Judges
TxDOT District Office
Title Companies
Local cities and counties
Coordination Meetings:
SPD ROW Program Project Coordination
6
TxDOT PMC TxDOT SPD
TxDOT ROW Division
TxDOT District
Office of Attorney General
Acquisition Service Provider
Developer/DBC
Title Company Environmental Specialist
Utility Providers
CONDITIONAL AWARD What happens after the selection?
The SPD ROW Program Process
8
Notices in accordance with SB 18
Once procurement is complete, Design Builder will be tasked with acquiring the necessary right of way for the project.
TxDOT may undertake some right of way acquisition in order to progress the project during procurement.
Schedule
Flowcharts and Checklists
SPD ROW Program - Solution Driven
9
DBC is responsible for all ROW acquisition and relocation
Determine what ROW is necessary for constructability:
Good communication and due diligence will prevent problems later on that could affect schedule.
Proper training for all agents, especially relocation agents is critical; this is a very specialized field.
SPD PROGRAM APPROACH Programmatic and Consistent
SPD ROW Program - Positive Approach to Challenges
11
Identify and manage risk
Encourage negotiated settlements
Encourage design to mitigate damages
Execution with Integrity
12
Concurrent Activities
Consistency of Process and Deliverables
Acquisition and Condemnation
Packages
SPD ROW Program Acquisition Guidelines
13
ReceptionistDocument Control Oversight
Legend
Document Control Scanner scans transmittal
Document Control Scanner sends original transmittal and
package to Project Coordinator
Project Coordinator copies and files original transmittal and
confirms dates in ROW Tracker and inputs into Package
Tracking Log
Project Coordinator sets up Package Components for
Distribution
Reviewer sends package back to Project
Coordinator after Review and placed in Under Review Folder
Signed Appraisal Acceptance or Rejection Letter
Update ROW Tracker and Assignment Log
Project Coordinator sends Approval/Rejection to
Document Control.
Document Control Scanner scans Acceptance/
Recommendation Letter and Package and Upload to E-Managers and email
Document Control Oversight.
Project Coordinator sends out email notification
and enter date into ROW Tracker.
Receptionist receives package and date stamps transmittal.
Logs date in ROW Tracker and notifies Project Coordinator
and Document Control Scanner
YES
NOProject Coordinator
contacts ASP
Developer Prepares and Submits Acquisition Package
Project Coordinator adds assignment to ROW
Tracker
Project Coordinator alerts Task Leads
Task Lead assigns Reviewer & Notify Project Coordinator of
Assignment
Package Picked Up and Signed Out
Reviewer Signs Acceptance/
Recommendation Submittal Form
Package Picked Up and Signed Out
Reviewer Signs Acceptance/
Recommendation Submittal Form
Reviewer sends package back to Project
Coordinator after Review and placed in Under Review Folder
Package Picked Up and Signed Out
Reviewer Signs Acceptance/
Recommendation Submittal Form
Reviewer sends package back to Project
Coordinator after Review and placed in Under Review Folder
Package Picked Up and Signed Out
Reviewer Signs Acceptance/
Recommendation Submittal Form
Reviewer sends package back to Project
Coordinator after Review and placed in Under Review Folder
Package Picked Up and Signed Out
Reviewer Signs Acceptance/
Recommendation Submittal Form
Project Coordinator presents Approval/Recommendation or
Rejection Letter to TxDOT
TxDOT approves Packages and authorizes offer to Owner or
Approves rejection of Package
Is Package Approved
Document Control Scanner scans Rejection Letter and upload to E-Managers and emails Document Control
Oversight.
Document Control Oversight confirms upload and enters
Approval/Rejection date in ROW Tracker and sends notification
to Project Coordinator and places in Outbox.
Developer authorized to submit Initial Offer to Property Owner.
Document Control Scanner
Task Lead
Developer
YES
NO
Project Coordinator
TXDOT
Package Reviewed Package Reviewed Package Reviewed Package Reviewed Package Reviewed
Does Package Require Corrections
YES
NO
Developer addresses corrections
Developer sends corrected components to
Reviewer
Is Package Complete
Project Coordinator confirms.
TxDOT sends Package back to Project Coordinator.
Project Coordinator sends Package to TxDOT for Review
and updates Sign Out Log.
Project Coordinator makes a copy of Approval/Rejection
Letter for Hard File
Reviewer
Reviewer contacts ASP and Email Project Coordinator regarding details of Correction
NO
Reviewer sends package back to Project
Coordinator after Review and placed in Under Review Folder
Project Coordinator reviews package against Negotiation
Review Checklist
Developer picks up Package.
Receptionist obtains signature from ASP at time of pickup.
Project Coordinator alerts Appraisal Reviewer.
Project Coordinator alerts Survey Reviewer
Project Coordinator alerts Title Reviewer
Project Coordinator alerts ESA Reviewer
Project Coordinator alerts Acquisition Reviewer
Document Decision
START
End
SPD ROW Program – Rules and Innovation
14
Follow the Law •Senate Bill 18 •Uniform Act •TxDOT Right of Way Manuals •Development Agreement
DESIGN BUILD CONTRACTOR PROGRAM APPROACH
“…and they’re off!”
Communication
Key Points
Establish effective lines of communication early
Establish expectations, document in PMP, stay consistent
Consistent, predictable results
Task force decisions & resolutions
16
Integrated Project Schedule
Key Points
Primavera schedule integrating all aspects of project
Assign priorities, work where you can
Be realistic but not overly conservative, “can do!”
Communicate updates job wide immediately
17
Process Driven – Details!
Key Points
Monitor status of each process
Close coordination with design
Start with the end in mind
18
SPD ROW Program Compliance Verification
19
FHWA Audits
State Audits
Bond Market Auditors
TxDOT Internal Audits
TxDOT External Audits
THANK YOU No autographs please