Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Engineering. Management & Infrastructure Consultants
Rimal, Gaza – Palestine.
Tele: +972-8-2836155
Fax: +972-8-2840580
E-mail: [email protected]
July- 2020
Design Report
Zawayda Drinking Water Access Project
1
Table of Contents
1- INTRODUCTION ........................................................................................................... 2
2- THE STUDY AREA ....................................................................................................... 3
3- PROJECT DESCRIPTION:............................................................................................. 4
4- PROJECT OBJECTIVES ................................................................................................ 5
5- METHODOLOGY.......................................................................................................... 6
6- PROJECT ACTIVITIES ................................................................................................. 8
6.1 PROJECT MOBILIZATION .................................................................................... 8
6.2 SITE VISITS, DATA COLLECTION AND INTERVIEWS ........................................... 9
6.3 DESIGN OF DESALINATION PLANT .................................................................... 11
6.4 PLANT DESIGN CALCULATION .......................................................................... 11
6.5 NET WORK AND FILLING POINTS DESIGN ........................................................ 14
6.6 NETWORK DESIGN ............................................................................................. 17
6.7 STRUCTURAL DESIGN AND WATER TANK DESIGN ........................................... 19
7- TENDER DOCUMENTS ............................................................................................... 20
8- PROJECT IMPLEMENTATION PLAN .......................................................................... 21
APPENDIX A: CALCULATION SHEET FOR CIVIL WORK ....................................................... 22
A.1. INTRODUCTION: ....................................................................................................... 23
A.2. CONSTRUCTION MATERIAL: ...................................................................................... 23
A.3. SLAB LOADING ......................................................................................................... 24
A.4. ANALYSIS OF SOLID SLAB UNDER STEEL WATER TANK: ............................................. 25
A.5. DESIGN OF SLABS ..................................................................................................... 27
A.6. ANALYSIS AND DESIGN OF BEAMS ............................................................................. 29
A.7. DESIGN OF COLUMNS: ............................................................................................... 34
A.8. DESIGN OF PILES: .................................................................................................. 37
A.9. DESIGN OF CIRCULAR STEEL WATER TANK: .............................................................. 40
APPENDIX B: MEMBRANE AND HOUSING CALCULATIONS .................................................. 43
2
1- INTRODUCTION
The Gaza Strip’s only source of water is the groundwater coastal aquifer. In the absence
of other significant water resources, this resource is currently facing a serious challenge
in terms of quantity and quality, leading to severe water insecurity in the Gaza Strip.
Gaza’s coastal aquifer is suffering over abstraction due to municipal supply and
agricultural consumption, which is about four times as much as the low recharge rate
from rainfall runoff. This is causing a phenomenon called “seawater intrusion”, where
salty seawater is intruding inward to the water aquifer as the water table levels drop
below sea levels. Seawater intrusion has caused the concentration levels of chlorides and
nitrates to increase well beyond the World Health Organization’s (WHO) standard
concentration limits for potable water. This is in addition to the infiltration of
hydrocarbons and pathogens into the water aquifer from leaking untreated wastewater,
and improperly designed solid waste dumping sites. Hence, the water is unpotable and is
not safe to drink without prior treatment. As a result, Gaza has become reliant on brackish
groundwater and seawater desalination.
Currently, about 160 brackish water desalination plants in the Gaza Strip desalinate the
water from the aquifer for drinking water. Half of these plants are privately owned, the
other half are public, NGO, or school owned. These plants distribute to the Gazan
population via tanker trucks, which is a very expensive method of water transmission, a
cost burdening the average Gazan consumer. The trucks then fill 200L – 500L water tanks
at households used solely for drinking and cooking. However, due to lack of quality
assurance measures, technical capacities of the plant operators, and public awareness, a
2015 study showed that the level of biological contamination (when tested for Total
Coliform) of this drinking water has reached an average of 45% at the plant level. When
the chain is viewed overall, the contamination level increases to 57% through the
distribution process, and up to 68% at the household level.
The combined effects of the impending public health crisis, lack of access to safe potable
water, environmental degradation, lack of wastewater treatment and insufficient
electricity, highlight the need for immediate interventions to alleviate the suffering of the
Palestinian people in Gaza. Such interventions must be aimed at providing affordable
access to safe drinking water, as well as, reliable access to water and wastewater
infrastructure services.
Based on that Mercy Corps conducted a number of consultations with the relevant local
WASH experts and some key stakeholders, to assess the capacity of water delivery, water
treatment, and wastewater handling infrastructure throughout the Gaza Strip to look for
the critical gaps in the essential WASH service delivery in order to identify interventions
3
to address the basic needs of Gazans and respond to the increasing prevalence of
household vulnerability. One of their proposed interventions is to build a desalination
water plant in the vulnerable areas. So, Mercy Corps in partnership with the Initiative
for Palestinian Economy (IPE), targeted Zawayda area aiming to provide a better water
service at a lower price for their vulnerable neighborhood.
2- THE STUDY AREA
Zawayda is located in the center of the Gaza Strip, west of Al Maghazi camp. According to
PCBS, the current population (2020) is estimated to be around 26,718 people living in an
area of about 7.0 square kilometers, see Figure 1. There is one main road in Zawayda
called Khalid-bin-Alwaleed Street. As many other parts of Gaza, the residents suffer from
high poverty, unemployment, a lack of electricity, and poor infrastructure.
Figure 1: Zawayda Location and residential zones
The area is divided into 11 zones, table 1 presents the name, population, number of
buildings and size of each zone by 2017 according to PCBS.
4
Table 1: Zawayda population, area and buildings per zone in 2017
Zone # Zone _Name
Population (inhabitants) NO_ Buildings Zones.area_m2
Alamal 1810 280 682904 الامل حي 1
Al Anssar 1376 205 394182 الأنصار حي 2
Al Rahma 3467 498 1042356 الرحمة حي 3
Al Salam 1697 268 492479 السلام حي 4
Al Sahaba 1695 217 754482 الصحابة حي 5
Al Sedeq 2999 305 316280 الصديق حي 6
AlAwda 2235 366 458390 العودة حي 7
Al Farwq 3219 456 575666 الفاروق حي 8
AlWaha 583 142 533265 الواحة حي 9
Tal Azhour 3838 541 849977 الزهور تل حي 10
Salah El Deen 1180 215 458226الدين صلاح حي 11
Total 24,099 3493 6,558,207
The residents of Zawayda currently receive water from four water wells located within
the center of the neighborhood. An existing 60 cubic meters per hour (CMH) brackish
water well called “Aaesha” is located at a high elevation point on the southern side of
Zawayda. The aim of our project is to design and construct a desalination plant in Zawayda
complete with a dedicated network supplying filling points serving the population of
Zawayda.
3- PROJECT DESCRIPTION:
Mercy Corps want to build a desalination water plant for Zawayda. The proposed
desalination plant for Zawayda needs to be designed with enough capacity to run on
available grid power only, as there shall not be any reliance on backup generators to
operate the plant for the water quantities. This is to ensure that the running cost incurred
by the operator will be at a minimum. The desalination water plant will have built in
Aaesha Water well site, as this well will be used as a location for the desalination plant
and water storage tank. In addition to, the desalination plant will be equipped with SMBS,
Antiscalant, Caustic Soda, and Chlorination dosing pumps for the pre and post treatment
processes. Also, the tank will serve all the filling points by gravity as to ensure water is
available around the clock, especially when electricity isn’t available. The tank will supply
the filling points via the dedicated network.
5
4- PROJECT OBJECTIVES
The purpose of this contract is meant to ensure the execution of Design and Construction
Supervision by:
1. Phase 1: Design, producing and submitting high-level technical documentation
(i.e. technical drawings, BoQs and Technical Specifications) for the proposed
desalination water plant.
2. Phase 2: Supervising construction works execution on site.
The scope of consultancy services are as follows: ➢ Carry out a wide range of site survey and field investigation that are necessary
for sound planning and appropriate design of the required works.
➢ Send Mercy Corps a detailed project timeline.
➢ Design the project components and provide technical drawings and calculation
sheets for the below components:
1. Brackish Water Desalination Plant at Aaesha Water Well, the design will
consider
2. The desalinated water network of PE pipe.
3. Filling points distributed across the camp with a maximum walking distance
of 100m to any filling point. A minimum of 30 filling points as mentioned in
TOR.
4. Detailed design of elevated storage tank. Approximately 80 cubic meters.
➢ Develop the Tender Documents and Bill of Quantities for the project. (The Tendering process will be undertaken by Mercy Corps’ procurement department).
➢ Rehabilitation works for the existing water well manifold and structure including
the demolition and reconstruction of the well room.
Design Supervison
6
5- METHODOLOGY
The general approach that describes the methodology and work plan for the consultant
to carry out the design services in this contract.
The concept for the provision of consulting services for these services was based on the
principles discussed hereafter. The Consultant will form a professional team for the
proper execution of the required consulting services. The Consultant general concept to
the provision of consulting services throughout the project was based on ensuring that
value for money is obtained for the employer whilst never sacrificing quality. To achieve
this aim, the Consultant conducted the followings:
✓ Utilize his experience on similar projects and his experience in local markets.
✓ Assign his most experienced professional, management, review, and specialist
support and backstopping staff.
✓ Involve its management to the extent that would ensure total compliance with
owner requirements and achieve the work compatible with international standards
in terms of quality, durability and economy.
✓ Utilize computerized means for supervising, managing and communicating its work
and shall submit time schedule for its activities that would coincide the time
limitation.
✓ Undertake site visits and investigations.
✓ For collection of data meet with beneficiaries& representative.
✓ Preparing design of the above-mentioned components.
The consultants followed a sequence of steps to ensure the efficiency and effectiveness
in using the available resources to achieve the required goals of this consultancy service.
7
Figure 1: Project Methodology
Project Mobilization
Site Visit and data Collection
Design of project components
Tender documents
Client Aproval
Project Implementation plan
Client
Mercy Corps Approval
8
6- PROJECT ACTIVITIES
6.1 PROJECT MOBILIZATION
In this task the project activities were initiated with meetings between the Consultant’s
design team, Mercy corps, and representatives from Zawayda community in order to take
their input into consideration. The aims of such meetings are to introduce the consultant
staff and their understanding to the project. The community meetings aimed to introduce
the project to the community and share with them their roles and responsibilities during
construction and operation of the project, see photo 1
Photo 1: Meetings with community members
9
6.2 SITE VISITS, DATA COLLECTION AND INTERVIEWS
Our team conducted visits for the entire area affecting the design of the project The
reviewing works included the followings:
✓ Studying the project requirements as prepared by the Mercy Corps.
✓ Obtaining all available information and data necessary for the work. This
includes drawings, reports, etc.
✓ Review the roads condition such type of pavement and traffic conditions.
✓ Obtaining all available information and data necessary for the work. This
includes drawings, reports, photos, tests from competent authorities and
through field visits
In the same time, the consultant collected the following data from the municipality:
1. Map with residential zone’s name and size
2. Contour map for the municipality
3. map of roads with type of road (Asphalted, Interlock or unpaved)
the consultant collected from PCBS the existing and future population for the study
area. Also, the consultant conducted many visits and meetings with local firms that deal
with desalination plants and water tanks to ensure the capacity of local market to
supply and install the project components, see photo 2.
Photo 2: The Proposed Desalination Plant Location
10
Photo 3 : Typical Desalination Plant and Water Tank
Photo 4: Site visits to project location and local firms
Design of project components:
Our design team prepared design criteria and made detail design for the following
components:
A. Desalination Plant.
B. Water Supply Network
C. Filling points
D. Structural design and Steel Water tank
11
6.3 DESIGN OF DESALINATION PLANT
Plant capacity
The municipality operate ground water well (Aisha well) since 13 years and deliver
directly to existing network. The well is allocated at high area 35 m above sea level
within private land owned by one of its residents. The desalination plant will be
allocated in the same place of the well.
To determine the capacity of the desalination plant and water tank, the consultant
depended PCSB figures for population forecasting. According to PCBS, the population of
al Zawayda is 26,718 inhabitants by 2020 and increase with 3.5% annual growth rate. By
2030, the expected population is 37690. Assuming 4 liters are required per person per
day for drinking and 70% of population will depend of this source, this means that the
desalinated water required will increase from 75 m3/day by 2020 to 106 m3/day by
2030.
The elevated tank storage capacity is 80 m3 which means that it provide storage for one
day at 2020. Assuming the min power supply is 8 hours/day and max 12 hours. To
provide 106 m3 per day within 8 hours, the desalination plant capacity is designed to be
15 m3/hr. at 2020, the plant will operate 5 hr/day and increase to 7.5 hr/day by 2030.
6.4 PLANT DESIGN CALCULATION
Raw Water
➢ Source
Brackish water - Aaesha Water Well
➢ Capacity of treated water – Desalination Unit
The capacity of desalination Plant 360 m3/ day
➢ Working Hour
Average daily electricity Power on 8 h/ day
Grid power used ONLY.
Note : No standby generator .
➢ Raw water quality data
Projected and prospective raw water supply to RO units (contractor to verify raw
water quality data).
12
Design criteria for Desalination unit
Description Value UoM
Physical
TDS Design value 10,000 ppm
TDS Operating range 3,500 ppm
EC 7000 µS/c
Odor Undetectable m
Design Water Temperature 17 oC
Operating Water temperature 12÷28 oC
Density N/A --
Color Transparent --
Turbidity <5 NTU
Parameter Required Standard Unit
Plant production rate:
360
o per day [m3/day]
o per hour 15 [m3/h]
Design temperature
17
[Deg oC]
Water recovery rate 75 [%]
Required raw water flow 20 [m3/h]
Brine flow 5 [m3/h]
13
Product water quality data
The product water quality should be within the following limits, as indicated in
the table below
Description UoM Normal Reference Values
range
Physical
TDS mg/l < 150 Norm
Turbidity NTU 5 max.
Chemical
Organic Matter
Fat, Oil and harmful
elements Not present
Inorganic Matter
pH 7- 8 Min/max
Chlorides (Cl) mg/l <50 max.
Sulfates (SO4) mg/l < 50 max.
Nitrates (NO3) mg/l < 20 max.
Total hardness as CaCO3 ppm 50-200 Min-Max.
m-Alkalinity as CaCO3 ppm 30-50 Min-Max
Free Chlorine mg/l as < 1 max.
Cl2
Quality Control
Langlier Saturation Index LSI + 0,1÷ Positive
+0,3
For membrane and housing calculations, See Appendix B
14
6.5 NET WORK AND FILLING POINTS DESIGN
Filling point design:
The consultant allocated the filling points to cover the total area of Zawayda. The maximum
distance between filling points is about 500 m to make it accessible to all residents. The
consultant tried to make the location of filling points as much as possible within the walls of
public buildings as schools, mosques, youth clubs, …., etc. The GIS is the tools used to determine
the locations of filling points which based on:
1. The population densities of each neighborhood.
2. Existing of public services and facilities for the city (mosques, schools, clinics, etc.)
3. The distance between the water filling points should not be more than 500 m
4. The distance between the farthest building and the nearest filling point is not more than
350 m, depending on the road network.
The process followed using GIS was:
1. The population was calculated according to the municipality’s classifications. 2. Residential districts based on densities were classified into 3 categories (High, Medium
and Low) see Figure 2.
3. The city's public services were added and taken into consideration in the distribution of
water distribution points, see Figure 3.
Figure 2: Classification of residential zones based on density
15
Figure 3: Location of public services
4. The sites were initially chosen by buffer tools to determine the locations based on the
built-up area and for the distances between the water distribution points to do not
exceed 500 meters, see Figure 4 below.
5. Streets layer was added and a network analysis was done, so that the distance should not
exceed 300 meters from the house to the water distribution points.
6. The filling points location have been modified, according to all conditions, in terms of the
distance between the filling points, the distance between the buildings and accessible
roads
7. Based on that, 34 filling points are proposed which can cover 90% of built up area with
max walking distance of 300 m. Each filling point consists of three taps with 20 l/min the
capacity of each tap. This means that the filling point max capacity is 60 l/min. each filling
point will be feed through 1.5” HDPE pipe.
16
Figure 4: buffering zones per filling point
17
6.6 NETWORK DESIGN
According to client requirement, the consultants designed the desalination plant which
deliver desalinated water to the elevated tank. The effective tank capacity is 80 m3 and
allocated at 5 m above the ground. The minimum high of water at the tank is 6 m above
GL and the maximum is 10 m. Water will be distributed at the network by gravity, see
Figure 5. The consultant prepares a plan for the network which consists of 4” main pipe
and 3”, 2” and 1.5” secondary pipes. The netwok is divided into three zones to manage
the hydraulic performance.
Figure 5: water network layout
The consultant used WaterGEMS software to design the network considering the worst
case where all filling points are working with 50% capacity with min head of 5 m. as the
water head will depend on the tank elevation without pumping and the three zones will
be operated separately. The consultant proposed to install valves for each zone. Table 2
presents the number, ground level and head per filling point.
18
Table 2: Filling point’s number, ground level and head
ID G.L(m) Head(m)
1 35 4.45
2 26.8 7.68
3 26 8.37
4 29 3.29
5 29 3.1
6 22 9.21
7 28 3.03
8 27.8 2.24
9 21.7 7.16
10 21 8.35
11 25 4.47
12 25.2 4.28
13 22 7.26
14 17 12.14
15 23.5 13.43
16 23.2 13.4
17 25 11.87
18 13.6 18.16
19 7.5 20.56
20 4 15.74
21 3.3 17.59
22 3.5 17.09
23 5.2 15.03
24 6 14.08
25 7.2 11.78
26 6.42 15.12
27 12 13.94
28 15 10.95
29 13.69 11.41
30 11 14.45
31 5.5 19.91
32 7 17.82
33 6.5 19.1
34 6.9 18.06
AS stated before, hydraulic system is designed as a three hydraulic zones. Figure 6 presents the
network with its phases.
19
Figure 6: Network phasing
6.7 STRUCTURAL DESIGN AND WATER TANK DESIGN
The following structural system is used in design the building and the water tank
• Beam Column system (Skelton) to resist the vertical Loads.
• Solid Slab 30 cm with drop beams under the Steel Water tank
Ribbed slabs 25 cm one-way with a mix of hidden and drop beams.
• Galvanized Steel Sheets of 2 mm thick with 40 mm stiffener was used for
4.7 diameter steel water tank.
• Foundation type is Pile Foundations.
• Robot Structural Analysis software, Sap2000 and Excel are used in
analysis and design of concrete elements.
20
The Codes of Practice used in design are:
Structural Concrete Design Code is ACI 318M–14.
American Institute of Steel Construction AISC 15th Edition (2017).
General Concrete Building Code: ASCE 7-2010.
A detailed design report of the reinforced concrete structural elements and the steel water tank
is attached in Appendix A.
7- TENDER DOCUMENTS
In conjunction with the detail design, the tender documents was prepared. The
tender documents included:
• Letter of invitation and instruction to bidders, including appendices with
form of Tender, Tender Security Form, Form of Agreement, Form of
Performance Guarantee, information of financing and disbursement
conditions and other information relevant to tender and procurement
packages.
• General conditions.
• Special conditions.
• General specifications.
• Technical specifications.
• Detailed Bills of Quantities.
• Schedule of particular information.
• List of Detailed drawings.
• Based on the detailed B.O.Q, the cost estimate will be prepared.
21
8- PROJECT IMPLEMENTATION PLAN
The project is planned to be implemented within four months which includes mobilization, installation, testing and operation. Table ??? present
the implementation plan. The following table shows a proposed implementation plan of the project.
Activity
Month 1 Month 2 Month 3 Month 4
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 Mobilization
2 Network Installation
3 Filling Point
4 Civil Work
4.1 Demolition
4.2 Building Construction
4.3 Finishing
5 Water Tank
6 Desalination Plant
7 Fitting installation/Operation
8 Submission
APPENDIX A: CALCULATION SHEET FOR CIVIL WORK
23
A.1. INTRODUCTION:
i. STRUCTURAL SYSTEM:
• Beam Column system (Skelton) to resist the vertical Loads.
• Solid Slab 30 cm with drop beams under the Steel Water tank
Ribbed slabs 25 cm one-way with a mix of hidden and drop beams.
• Galvanized Steel Sheets of 2 mm thick with 40 mm stiffener was used
for 4.7 diameter steel water tank.
• Foundation type is Pile Foundations.
• Robot Structural Analysis software, Sap2000 and Excel are used in
analysis and design of concrete elements.
ii. CODES OF PRACTICE:
Structural Concrete Design Code is ACI 318M–14.
American Institute of Steel Construction AISC 15th Edition (2017).
General Concrete Building Code: ASCE 7-2010.
Loads Combinations:
For gravity and water loads
U = 1.40×D
U = 1.20×D+ 1.60×L
According to ASCE 7-16 (2.3): "Where fluid loads F are present, they shall be
included with the same load factor as dead load D in combinations 1 and 2".
A.2. CONSTRUCTION MATERIAL:
i. CONCRETE:
Ordinary Portland cement concrete is used for all structural elements with
compressive strengths shown below:
fc' for Columns: 250 kg/cm2 (B300)
fc' for Slabs and Beams: 250 kg/cm2 (B300)
fc' for Ground beams: 250 kg/cm2 (B300)
fc' for Ground slabs: 210 kg/cm2 (B250)
24
fc' for Foundation: 210 kg/cm2 (B250)
fc' for plain concrete: 180 kg/cm2 (B200)
ii. STEEL REINFORCEMENT:
Grade 60 (fy =4200 kg/cm2) deformed reinforcement steel bars complying with
ASTM-A615 are used as main reinforcement.
A.3. SLAB LOADING
i. SOLID SLAB LOADS:
• Dead load of Solid Slab 30 cm:
1- Own weight
(2.5× 0.3 = 0.75 t /m2)
2- Water Pressure from steel water tank H=4.95m
= 4.95 t/m2)
3- Load of buffer tanks (2x5m3) tanks H = 2.6 m
= 2.6 t/m2 < Steel water tank (govern)
Use water pressure of 4.95 t/m2
4- Steel Weight
(3.14 × 4.7 ×0.002× 4.95×7.5 / (3.14/4 ×4.72 ) = 0.1 t /m2
Tank Cover 0.05 t/m2
Total Dead Loads for the Solid Slab DL 6t/m2
ii. DEAD LOAD OF RIBBED SLAB 25 CM:
Own weight
- Slab thickness 25 cm
- Block Thickness 17 cm
- Total Volume
( 0.52× 0.25 × 0.25 = 0.0325 m3 )
- Volume of Block
( 0.4*0.25*0.17 = 0.017 m3 )
- Volume of Concrete
(0.0325 – 0.017 = 0.0155 m3 )
- Weigh of Concrete
(0.0155 × 2.5 / 0.52× 0.25 = 0.298 t/m2 )
- Weigh of Block
( 0.017 × 0.52 × 0.25 = 0.131 t/m2 )
Total Dead load for the Ribbed Slab DL = 0.43 t/m2
Live Load L.L = 0.2 t/m2
25
A.4. ANALYSIS OF SOLID SLAB UNDER STEEL WATER TANK:
i. ANALYSIS OF SLAB (FLEXURE X-X)-(KN.M/M):
ii. ANALYSIS OF SLAB (FLEXURE Y-Y)-(KN.M/M):
26
iii. ANALYSIS OF SLAB (SHEAR FORCE X-X)-(KN):
iv. ANALYSIS OF SLAB (SHEAR FORCE Y-Y)-(KN):
27
v. DEFORMED SHAPE OF ANALYZED SLAB (MM):
A.5. DESIGN OF SLABS
i. DESIGN OF THE SOLID SLAB
From the slab analysis the maximum positive moment is 7.5 t.m/m, while the maximum
negative moment is a round 11 t.m/m but we design for 7.5 t.m/m and put an additional
top reinforcement at support. So the slab was designed for 7.5t.m/m for negative and
positive moment.
u
u
M =7.5 t.m
V = 11.6 tons
B = 100 cm
H = 30 cm
d = 30-2.5-0.7 = 26.8 cm
28
Check slab thickness for beam shear
Vu Vc
ii. DESIGN OF RIBBED SLAB:
The ribs in the ribbed slab is consider as a simply supported beams with a total load of
W = 0.9 t/m2
M =
2WL
8 = 1.84 t.m
Input data unit
Mu 7.5 t.m/m
Vu 11.6 tons
B 100 cm
H 30 cm
d 26.8 cm
Diameter
(bar) 14 mm
Output data unit
Vc 16.5 tons
ρ 0.00284
ρmin 0.0018
Asteel 770 mm2
Ast (used) 800 mm2
# of bars 14 @15cm
(top & bottom)
Additional
rein. 14 @15cm at
supports
Input data unit
Mu 1.84 t.m
Vu 1.84 tons
B 12 cm
H 25 cm
d 21 cm
Diameter
(bar) 14 mm
Stirrup 8 mm
Output data unit
ρ 0.011 tons
ρmin 0.0033
ρmax 0.0161
Asteel 2.77 cm2 mm2
# of bars 2 14 / rib
1.1 Vc 1.71 tons
Vs 0.39 tons
Stirrup 8 / 20 cm
29
A.6. ANALYSIS AND DESIGN OF BEAMS
i. ANALYSIS AND DESIGN OF BEAM B1
a) Analysis of Beam B1 using Robot Software
Layout of analyzed beams (flexure)-(KN.m):
Layout of analyzed beams (Shear)-(KN):
30
b) Design of Beam B1
The following result obtained from robot structural analysis software: -
Mu = 35 t.m
Vu = 28 tons
B = 40 cm
H = 70 cm
d = 70-3-1-2 = 64 cm
Design for flexure: -
Design for Shear: -
c s = V +VnV
0.75 0.53 250 40 64
Vc = 16.3 tons1000
=
40
70
31
s
s
V = 37.33 - 21.45 = 15.88 tons
1.57×4200×64Vs= =15.88
S
S = 26.59 cm
V < 250×40×64=40.4 tons .So, the max S is smaller of d/2 or 60 cm
MB No. Section type Moment (T.m)
As req. (mm2)
As Used (mm2)
# of bars
Stirrups
MB1
Rec- Section
Positive
35
2000
3800
13Ø20
2 Ø 10 @ 15 cm
ii. ANALYSIS AND DESIGN OF BEAM B2:
a) Analysis Beam B2 using Robot Software:
Layout of analyzed beams (flexure)-(KN.m):
Layout of analyzed beams (Shear)-(KN.m):
32
b) Design of Beam B2 –
The following result obtained from robot structural analysis software: -
Mu = 16 t.m
Vu = 18.8 tons
MB No. Section type Moment (T.m)
As req. (mm2)
As Used (mm2)
# of bars
Stirrups
MB2
Rec- Section
Positive
16
900
3400
11Ø20
2 Ø 10 @ 15 cm
iii. DESIGN AND ANALYSIS OF BEAM B6
a) Analysis of Beam B6 using Robot Software
Layout of analyzed beams (flexure)-(KN.m):
Layout of analyzed beams (flexure)-(KN.m):
40
70
33
b) Design of Beam B6
The following result obtained from robot structural analysis software: -
Mu +ve = 0.55 t.m
Mu -ve = 1.52 t.m
Vu = 2.96 tons
MB No. Section type Moment (T.m)
As req. (mm2)
As Used (mm2)
# of bars
Stirrups
MB6
Rec- Section
Positive
0.55
41
923
6Ø14
2 Ø 10 @ 15 cm
Negative 1.52 41 923 6Ø14 2 Ø 10 @ 15 cm
60
25
34
A.7. DESIGN OF COLUMNS:
i. COLUMNS REACTIONS FROM ROBOT SOFTWARE:
Col B H LService (Ton) LUltimate (Ton)
C1 0.4 0.4 1.5 2.1
C2 0.4 0.4 56.1 78.5
C3 0.4 0.4 3.0 4.1
C4 0.4 0.4 46.5 64.8
C5 0.4 0.4 41.5 57.9
C6 0.4 0.4 1.5 2.1
C7 0.4 0.4 56.1 78.5
C8 0.4 0.4 3.0 4.1
C9 0.2 0.2 5 6
C10 0.2 0.2 5 6
35
ii. DESIGN OF COLUMN USING ACI318-14 CODE:
ρ min = 1%
36
COLUMN factored
load (Ton) Ag(cm2) B(cm) L (cm) As (cm2) # Bars
Spacing between ties
clear spacing bars
C1 2.1 1600 40 40 16.00 12 22 8
C2 78.5 1600 40 40 16.00 12 22 8
C3 4.1 1600 40 40 16.00 12 22 8
C4 64.8 1600 40 40 16.00 12 22 8
C5 57.9 1600 40 40 16.00 12 22 8
C6 2.1 1600 40 40 16.00 12 22 8
C7 78.5 1600 40 40 16.00 12 22 8
C8 4.1 1600 40 40 16.00 12 22 8
C9 6 400 20 20 4.00 4 22 4
C10 6 400 20 20 4.00 4 22 4
37
A.8. DESIGN OF PILES:
38
Design of Pile F1
The Soil is Sandy Soil with angle of friction = 35
Input Unit
D (diameter) 0.5 m
L (Length) 12 m
Pservice 600
Atmospheric Pressure Pa 100 kN/m2
Effective Soil Friction Angle ф 35 degree
Nq* 143
Soil Unite Weight ϒ 18 kN/m3
Factor of Safety F.S 3
Input data unit
fc' 210 kg / cm2
Fy 4200 kg / cm2
Cover 5 cm
Bar diameter 14 mm
39
2 2
2
st
min =0.008
Pu = 78.5 tons
As > 0.008 Ag
As > 0.008 50 = 15.7cm4
Use 14 14 (A Used = 21 cm )
Output Unit
Perimeter P 1.570796327 m
Cross-Setion Area Ap 0.196349541 m2
Effective Length L' 10 m
q' 216 kN/m2
q1 5006.5 kN/m2
Point Bearing Capacity Qp1 5064.8 KN
Limit of Point Bearing Capacity Qp2 983.0 KN
Ko 0.426
Kp 3.69
K avg 2.06
σ' 180 kN/m2
δ' 23.33
f 159.82 kN/m2
Point Bearing Capacity Qp 983.0
Frictional Resistance Qs 3012.4 KN
Ultimate Bearing Capacity Qu 3995.5 KN
Allowable Bearing Capacity Qall 1331.8 KN
Check for Capacity Safe
40
A.9. DESIGN OF CIRCULAR STEEL WATER TANK:
i. DESIGN OF STEEL SHEETS
Assume the tank is sliding at the base
The max pressure is equal to ϒ Hmax
So, the applied force on the Sheet is T at the ends
2Tmax = ϒ Hmax D
max
max
max
γ×H ×D 1 4.95 4.7T
2 2
T 11.6 t/m
= =
=
According to ASCE 7-16 (2.3): Where fluid loads F are present, they shall be included with
the -same load factor as dead load D in combinations 1 and 2.
u
u
u
Factored load T
T 1.4 11.6 16.2 t/m
The sheet is 55 cm long , so the applied tension force for each sheet
T 16.2 0.55 8.92 tons
= =
= =
Tmax Tmax
0.55
4.95 m
4.7 m
41
t n
n y g , t g
According to American code of steel design (ANSI/AISC 360-16):
The gross yielding design strength is ( P )
P = F A = 0.9 (LRFD) , A = gross area
The fracture design strength
t n
n u e , t e
y u
t y g
is ( P )
P = F A = 0.75 (LRFD) , A = effective net area
Steel Sheet Grade A36 (F = 250 MPa , F = 400 MPa)
1- Gross yielding design strength :-
0.9 2500 12.6 = F A =
1000
h
2
= 28.6 ton
2- Fracture design strength:-
-
(n: number of bolts , t: thickness of section , d : the hole diameter )
(63 0.2) - 2 1.4 0.2 12.04
The d
t u e
e g h
e
F A
A A nd t
A cm
=
=
= =
0.75×4000×12.04esign strength = = 36.12 ton
1000
Design Strength of the member in tension = smaller of (28.6 ton and 36.12 ton)
The applied tesion force < Design strength of member
9 ton < 28.6 ton ( the section is Safe )
42
ii. DESIGN OF CONNECTION (VERTICAL SPLICE):
n
n n b
n
According to American code of steel design (ANSI/AISC 360-16) :
The shear strength of one bolt is equal ( R ):
R = F A , 0.75 (LRFD)
( F : nominal tensile stress or shear st
=
b
2
3
ress ,
A : nominal unthreaded part area or threaded part area)
The minimum spacing and edge distance:
- min spacing (center to center of bolts) (2 )
- min edge distance (from
d
y u
center to an edge) applicable value from Table J3.4
* The Properties of bolts is:
Class 8.8 (f = 640 Mpa , F = 800 Mpa)
Nominal diameter (d) 12mm (M12)
Area of unthreaded part = 113 m
=
2
2
n b
m
Area of threaded part = 84.3 mm
The Shear strength per bolt:
0.75 6400 0.843 2 = F A = = 8.1 ton
1000
and the applied tensile force on the member is 9 ton. So , the existing numbe
2
3
r of bolts is enough.
** Check for distance and spacing:
min spacing = 2 ×12 = 20 mm
min edge distance = 20 mm
So , use min spacing (horizontally) = 40 mm
min spacing (Vertically) = 100 mm
min edge distance = 30 mm
30 40 30
100
30
100
100
100
100
30
43
APPENDIX B: MEMBRANE AND HOUSING CALCULATIONS
44
45
46
47
48
49
50