Upload
erica-ray
View
220
Download
0
Embed Size (px)
DESCRIPTION
Objective PennDOT has initiated a fast track project to design and build a new bridge over Spring Creek. 3 spring creek
Citation preview
Design Project #1Replacement of Vehicle Bridge over Spring Creek
Centre County, PAIntroduction to Engineering Design
EDGSN 100 Section 001Team Armadillo
Design Team Number 7Marisa Coltabaugh
James RossArianna Vetrano
Dan Weisner
Presented to: Prof. Berezniak
Fall 2015
Statement of Problem
2
A bridge to Mt Nittany Medical Center, vital for emergency access, was recently destroyed by a hundred years flood.
*Not the actual Spring Creek bridge
Objective
PennDOT has initiated a fast track project to design and build a new bridge over Spring Creek.
3
spring creek
Design Criteria
PennDOT District 2-0 has established the design criteria for the replacement bridge to
include: standard abutments, no piers (one span), deck material shall be medium strength
concrete (0.23 meters thick), no cable anchorages and designed for the load of two AASHTO
H20-44 trucks (225kN) with one in each traffic lane. The bridge deck elevation shall be set at
20 meters and the deck span shall be exactly 40 meters. Both a Warren through truss bridge
and a Howe through truss bridge shall be analyzed. All other design criteria, such as: steel
member type, steel cross section type, and steel member size shall be selected by each
EDSGN100 design team.
4
Technical Approach Phase 1: Economic Efficiency
5
Results Phase 1: Economic Efficiency
Final Cost: $210, 905.88
6
Technical Approach Phase 2: Structural Efficiency
7
Results Phase 2: Structural Efficiency
The Howe Truss Bridge’s Structural Efficiency was 195.6
8
Technical Approach Phase 1: Economic Efficiency
9
High Strength Steel
Carbon Steel
Results Phase 1: Economic Efficiency
10
Final Cost: $246,355.81.
Technical Approach Phase 2: Structural Efficiency
11
Results Phase 2: Structural Efficiency
The Warren Truss Bridge’s Structural Efficiency was 334.7
12
Best Solution
To incorporate economic efficiency strategies from the Howe through truss bridge, with the structural efficiency of the Warren through truss bridge.
13
ConclusionsThe economic efficiency for the Howe through truss bridge was achieved by using hollow tubes in compression, and solid beams in tension. Smaller dimension members were applied in areas with smaller forces. However, the price was kept minimal by maintaining some uniformity in dimension sizes.
For structural efficiency, the top and bottom chords, as well as highest force members (both tension and compression) were reinforced and supported by the highest quality beams. However, it is believed that struts were not properly secured; that the hot glue did not set adequately.
The economic efficiency for the Warren through truss bridge was achieved by using the same size tubing for most of the bridge and then adjusting size and material as needed, per the weakest members.
For structural efficiency, we had seven triangles in our truss rather than five. The truss was doubled and tripled in certain sections for increased strength.
14
Recommendations
15
The previous bridge destroyed by the recent extreme flood event was not structurally stable and able to resist such flood. Therefore, tests should be done to assure that the next bridge will be able to withstand storms that may occur in the area. In addition, the piers should be taller and stronger so that the bridge will not collapse. The next step that should be accomplished to advance the project into Final Design for the replacement bridge is to contact fabricators and contract. For our physical bridges, make sure they are more structurally stable, for example, reducing the wobble.