71
INTERNATIONAL SYMPOSIUM ON Bali, Indonesia, June 1 ST 6 TH , 2014 Design Optimization of Bauxite Residue Dam in Connection with Environment and Land Acquisition in Mempawah SGA, Indonesia A. Fitriyanto & W. Taruko PT. ANTAM (Persero) Tbk. [email protected] DESIGN OPTIMIZATION OF BAUXITE RESIDUE DAM IN CONNECTION WITH ENVIRONMENT AND LAND ACQUISITION IN MEMPAWAH SGA, INDONESIA Mining and mineral processing activities cannot be separated from tailing. In its operation, Smelter Grade Alumina processing plant will produce mud called bauxite residue. In order to accommodate the mud output, we should build dam. The development of bauxite residue dam is closely related to the environment and land acquisition. Because its form is mud, bauxite residue dam must be designed in such a way that is environmentally friendly. In addition, the design of bauxite residue dam sometime must be adjusted in the field because of the challenges in land acquisition. This paper will explain the strategies that can be taken in the design optimization of bauxite residue dam i.e. do pre-treatment by pressing and filtering the mud that would reduce the volume and the toxicity of the mud. The dam also needs to be built by staging system to overcome the challenges of land acquisition and to minimize catchment area of the dam. Because it is in a dry form, the bauxite residue can be disposed forming bench so that it will reduce the large of dam area required. The liner system also should be made to ensure there is no infiltration from the dam, so it is safe for the environment. Based on research that has been done, bauxite residue can be used as geopolymer brick with low compressive strength 53.5 kg/cm 2 and high compressive strength 238.9 kg/cm 2 . It can also reduce the large of dam area required. Keywords: bauxite residue dam, design optimization, environment, land acquisition 1. INTRODUCTION Mining and mineral processing activities cannot be separated from tailing. In its operation, Smelter Grade Alumina processing plant will produces mud called bauxite residue. In order to accommodate the mud output, we should build dam. The development of bauxite residue dam is closely related to the environment and land acquisition. Bauxite residue is waste product of the Bayer Process. It is disposed as slurry with 10-30% of solid concentration. Because Bayer Process uses dissolution of alumina in caustic soda for extraction of the same, the waste also contains approximately 3wt.% sodium hydroxide III- 1

Design Optimization of Bauxite Residue Dam in Connection with

Embed Size (px)

Citation preview

Page 1: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Design Optimization of Bauxite Residue Dam

in Connection with Environment and Land Acquisition

in Mempawah SGA, Indonesia

A. Fitriyanto & W. Taruko PT. ANTAM (Persero) Tbk.

[email protected]

DESIGN OPTIMIZATION OF BAUXITE RESIDUE DAM

IN CONNECTION WITH ENVIRONMENT AND LAND ACQUISITION

IN MEMPAWAH SGA, INDONESIA

Mining and mineral processing activities cannot be separated from tailing. In its operation,

Smelter Grade Alumina processing plant will produce mud called bauxite residue. In order to

accommodate the mud output, we should build dam. The development of bauxite residue dam is

closely related to the environment and land acquisition. Because its form is mud, bauxite residue

dam must be designed in such a way that is environmentally friendly. In addition, the design of

bauxite residue dam sometime must be adjusted in the field because of the challenges in land

acquisition. This paper will explain the strategies that can be taken in the design optimization of

bauxite residue dam i.e. do pre-treatment by pressing and filtering the mud that would reduce the

volume and the toxicity of the mud. The dam also needs to be built by staging system to overcome

the challenges of land acquisition and to minimize catchment area of the dam. Because it is in a

dry form, the bauxite residue can be disposed forming bench so that it will reduce the large of dam

area required. The liner system also should be made to ensure there is no infiltration from the dam,

so it is safe for the environment. Based on research that has been done, bauxite residue can be used

as geopolymer brick with low compressive strength 53.5 kg/cm2 and high compressive strength

238.9 kg/cm2. It can also reduce the large of dam area required.

Keywords: bauxite residue dam, design optimization, environment, land acquisition

1. INTRODUCTION

Mining and mineral processing activities cannot be separated from tailing. In its operation,

Smelter Grade Alumina processing plant will produces mud called bauxite residue. In

order to accommodate the mud output, we should build dam. The development of bauxite

residue dam is closely related to the environment and land acquisition. Bauxite residue is

waste product of the Bayer Process. It is disposed as slurry with 10-30% of solid

concentration. Because Bayer Process uses dissolution of alumina in caustic soda for

extraction of the same, the waste also contains approximately 3wt.% sodium hydroxide

III- 1

Page 2: Design Optimization of Bauxite Residue Dam in Connection with

that makes the mud highly alkaline (pH in the range of 12 to 13). The color of bauxite

residue is red. This color is caused by the oxidized iron, which can make up to 60% of the

mass of the bauxite residue. Because its form is mud, bauxite residue dam must be

designed in such way to meet environmental requirement.

Figure 1: The Sequence of Bauxite Mining and Processing Activities

2. OPTIMIZATION OF MATERIAL VOLUME AND TOXICITY

The processing of bauxite residue will be developed in stages in accordance with the

progress of plant operations Mempawah SGA. Bauxite residue mud from the mud line

through the clarification process is leading to pumping mud thickener. Inside the mud

thickener, its overflow which is a solution of caustic liquor will be recycled back to the

plant. While its underflow shaped high-density mud will be pumped directly to the disposal

area. For the next stage of development, the factory SGA Mempawah possible to install

vacuum filters in the red mud disposal area. The tool is a tool with an intensive and

operational special expertise needs, because it will installed accordance with the

development and needs of the plant. Vacuum Filters will filter the output becomes

oversized mud thickener and undersize. Undersize of vacuum filters will have a solid

output in the range of 150-300 kg/m2h. Furthermore, undersize will be pumped to the

system through a High Pressure Positive Displacement Pumping Mud Pump (PDP) headed

dam area. The oversize of vacuum filter will be transferred back to the mud thickener. The

simple diagram is as follows:

III- 2

Page 3: Design Optimization of Bauxite Residue Dam in Connection with

FLOCCULENT

MUD THICKENER

Dilute Mud Slurry

Overflow Recycle

To Plant

Underflow High Density Mud

High Pressure Mud Pumping

To Mud Droppers Via Mud Line

Evaporation

CLoud

Sprinkler

P-30

E-13

DECANT

RUN-off

Recycle to

Process

Bauxite Residue Dam Area

Vacuum Filter

Oversize

Undersize

NEUTRALIZING AGENT

From Plant

Bauxite Residue Dam –

Stage 1

The Development of Bauxite

Residue Dam – Stage 2

Figure 2: Press & Filter of Bauxite Residue Diagram

Bauxite residue as slurry has a solid concentration in the range of 10-30%. Pre-treatment

by pressing and filtering the slurry will reduce the volume and the toxicity of the bauxite

residue. After pressing and filtering the slurry, the bauxite residue has a solid concentration

in the range of 60-70%. The volume of bauxite residue can be reduced. The toxicity of

bauxite residue also can be reduced.

The following are the differences between bauxite residue in the form of filter-cake and

slurry:

No Filter-Cake Slurry

1

Dam is relatively more simple in design

(thinner). It is because active earth pressure

is only from solid material.

Dam is relatively more complex in design

(thicker). It is because active earth

pressure is from solid material and water.

The volume requirement is relatively

smaller.

The volume requirement is relatively

bigger.

Liner specification for coping the water

seepage is relatively lower.

Liner specification for coping the water

seepage is relatively higher.

Transportation

Must prepare road and transport

equipment (truck) because it can not be

transported through pipelines.

Material transport is carried by pipelines.

Filtration Must set up facilities for filtration.

Facilities for filtration is not needed. It is

because the bauxite residue is passed

directly (slurry).

Filtration There is a cost for filtering. There is no cost for filtering.

TransportThe cost for transport equipment (fuel) is

relatively high.

Operation cost is relatively low (cost is

only from fuel for pump machine).

OPEX

Description

Financial

CAPEX

Dam

III- 3

Page 4: Design Optimization of Bauxite Residue Dam in Connection with

Table 1: The Differences between Bauxite Residue in the Form of Filter-cake and Slurry

3. DESIGN OPTIMIZATION

3.1 Land Acquisition Limitation

After the Reformation Era in 1998, the land acquisition became the significant issue for all

projects in Indonesia. The government doesn’t have enough influence and power to

support the land acquisition. It causes many variations in price range and badly the land

lord usually offers much higher than the market price. The land lord decides what price is

appropriate for the land otherwise they don’t release the land. This situation affects to cost

and duration of project. The challenge for the project is how to manage the effective layout

plan in minimum area.

No Filter-Cake Slurry

2

Water Reclaim Water reclaim for process plant is higher. Water reclaim for process plant is lower.

Material

Transport

Using trucks. The possibility of redmud fall

is small.

Using pipelines. There is a potential

outbreak of slurry pipelines. It needs a

pipeline inspection.

VolumeVolume is relatively smaller (dam height is

relatively lower).

Volume is relatively bigger (dam Height is

relatively higher).

Stability Forming a more stable land. Relatively unstable.

ClosureRelatively easier. It is because the

embankment materials are solid.

Relatively more difficult. It is because the

embankment materials in the form of

mud.

3

Toxic liquid is filtered. Relatively more toxic.

Relatively lower. Relatively higher.

Piping potency is lower (potency of dam

failure is lower).

Piping potency is higher (potency of dam

failure is higher).

Noise and dust from vehicles (material

transport).

There are no noise and dust from vehicles

(material transport).

Lower. Higher.

Leakage potency (from material transport)

is smaller.

There is a potential outbreak of slurry

pipelines. It needs a pipeline inspection.

Possibility of overtopping is smaller (the

solid form reducing the quantity of the

water).

Possibility of overtopping is higher (the

solid form reducing the quantity of the

water).

Environment

Toxicity

Groundwater

Piping Potency

Air Pollution

Potency

Erosion Potency

Leakage Potency

(Material Transport)

Overtopping

Technical

Filtration

Transportation

Dam Design

Description

III- 4

Page 5: Design Optimization of Bauxite Residue Dam in Connection with

Figure 3: Progress of Land Acquisition at Project Area

The figure 3 shows progress of land acquisition at project area that had been started from

2012. The hatch areas are the land that had been acquired by Antam. The total area of land

acquisition is 353 hectares. Still some areas haven’t been acquired (blank area) and the

total requirement is 580 hectares.

According to the land acquisition progress, the development of bauxite residue area should

be started from the north side of plan area then go to southwest.

3.2 Staging System

Based on the progress of land acquisition, the design is divided by several stages. The

design should cover the total bauxite residue from plant operation in 30 years plus extra

20%. The bauxite residue production is 1.15 million m3 per year, so the total bauxite

residue production is 41.4 m3 for 30 years. We have 6 stages on the design. Each stage in

design covers 5 year operations with total production of bauxite residue is 5.75 m3 per

stage. The staging system also minimize catchment area of the dam, so the water that have

to be treat is reduced. The staging system can be seen at figure 4.

III- 5

Page 6: Design Optimization of Bauxite Residue Dam in Connection with

Figure 4: The Staging System of Bauxite Residue Dam

3.3 Benching System

Because the bauxite residue is in a dry form, it can be disposed forming bench. It will

reduce the large of dam area required. Based on the characteristic of the bauxite residue,

the slope can be designed with ratio 1:3. The following are the characteristic of bauxite

residue:

Figure 5: The Benching System of Bauxite Residue Dam

III- 6

Page 7: Design Optimization of Bauxite Residue Dam in Connection with

Figure 6: Stability Analysis of Bauxite Residue Dam (without Earthquake)

Figure 7: Stability Analysis of Bauxite Residue Dam (with Earthquake)

3.4 Counterweight System

Embankment on the outer side of bauxite residue heaping has a function as a

counterweight and planned as a barrier so that the bauxite residue does not splatter in times

of rain.

Figure 8: The Counterweight System of Bauxite Residue Dam

3.5 Liner System

The liner system also should be made to ensure there is no infiltration from the dam, so it

is safe for the environment. Clay layer with thickness 1 meter and permeability 1 x 10 -7

cm/s needs to be made under bauxite residue layer to prevent seepage of water that may

still be contained in the bauxite residue that has been pressed and filtered. In addition to

release water from the dam subgrade as an effort to accelerate the consolidation process, it

required sand layer with 30 cm of thickness below the clay layer, where the sand layer at

the same time also functioned as a leak detection layer.

III- 7

Page 8: Design Optimization of Bauxite Residue Dam in Connection with

Figure 9: The Liner System of Bauxite Residue Dam

3.6 Drainage System

Surface drainage channel is planned in the bauxite residue dam that drains the rain water

from dam area to the water storage pond. Bauxite residue which is carried by erosion will

settle on water pond and drained by opening the spillway. Some of the rain which fell on

dam area will be drained to the Waste Water Treatment Plant (WWTP) to be managed to

meet the environmental quality standards. Planned drainage system in the dam area is

separating the dam drainage and drainage of around the dam area. It minimizes the

environmental impact of the dam.

Figure 10: The Drainage System of Bauxite Residue Dam

3.7 Waste Water Treatment Plant

WWTP operation starts from anaerobic pond to maturation pond. Anaerobic pond is the

first collection tank for contaminated water, it functions to improve dissolved oxygen

(DO), solid precipitation, and stabilization in the influent. Facultative pond functions to

control biochemical oxygen demand (BOD). Maturation pond is to decrease waste

contaminant by evapotranspiration and bind metals.

Figure 11: Waste Water Treatment Plant

III- 8

Page 9: Design Optimization of Bauxite Residue Dam in Connection with

3.8 Closure

The final planning is dam closure plan. Dam closure must be done to return the function of

the area as green land. The surfaces of bauxite residue dam should be reshaping,

landscaping, and covering with 50 cm of fertile topsoil. The planting of trees is preferably

using endemic plants grown in the area (acacia).

Figure 12: The Planning of Dam Closure

4. RED MUD UTILIZATION

Based on research that has been done, bauxite residue can be used as geopolymer brick

with low compressive strength 53.5 kg/cm2 and high compressive strength 238.9 kg/cm

2

(mix design = bauxite residue : fly ash : tailing : lime = 35% : 25% : 30% : 10%). It can

reduce the large of dam area required.

Adding of Sodium Silicate (%) Compressive Strength (kg/cm2)

0 53,5

0,5 75,8

1 85,8

2 91,5

4 135,6

8 238,9

Table 2: Increase of Compressive Strength by Adding of Sodium Silicate

Figure 13: Micro-photographs of Geopolymer Brick

Left: Low Compressive Strength 53.5 kg/cm2

Right: High Compressive Strength 238.9 kg/cm2

III- 9

Page 10: Design Optimization of Bauxite Residue Dam in Connection with

5. CONCLUSION

The development of bauxite residue dam is closely related to the environment and land

acquisition. Bauxite residue is waste product of the Bayer process. Because its form is mud,

bauxite residue dam must be designed in such way to meet the environmental requirement

and land acquisition limitation. Pre-treatment by pressing and filtering the slurry will

reduce the volume and the toxicity of the bauxite residue.

The design should covers the total bauxite residue from plant operation in 30 years plus

extra 20%. The bauxite residue production is 1.15 million m3 per year, so the total bauxite

residue production is 41.4 m3 for 30 years. There are 6 stages on the design. Each stage in

design covers 5 year operations with total production of bauxite residue is 5.75 m3 per

stage.

Based on the characteristic of the bauxite residue, the slope can be designed with ratio 1:3.

The liner system made from clay layer with thickness 1 meter and permeability 1 x 10 -7

cm/s needs to be made under bauxite residue layer to prevent seepage of water that may

still be contained in the bauxite residue that has been pressed and filtered. Surface drainage

channel is planned in the bauxite residue dam that drains the rain water from dam area to

the water storage pond. Some of the rain which fell on dam area will be drained to the

Waste Water Treatment Plant (WWTP) to be managed to meet the environmental quality

standards.

Based on research that has been done, bauxite residue can be used as geopolymer brick

with low compressive strength 53.5 kg/cm2 and high compressive strength 238.9 kg/cm

2. It

can also reduce the large of dam area required.

REFERENCES

Tekmira and Antam (2011): Pencucian Bauksit, Pemanfaatan Tailing Skala

Pengembangan dan Pemanfaatan Residu Bauksit, Kerjasama Penelitian Antam

dengan Puslitbang Tekmira, pp. 12-35, Citatah, Indonesia.

Antam (2012): Basic Design for Bauxite Residue and Ash Disposal SGA Mempawah

Project, pp. various pages, Jakarta, Indonesia.

Davidovits, J. (2011): Geopolymer Chemistry and Applications, Institut Géopolymère,

Saint-Quentin, France.

Cablik, V. (2007): Characterization and Applications of Red Mud From Bauxite

Processing, pp. 2-9, Ostrava, Czech Republic.

Szépvölgyi, J. (2011): Properties, Disposal and Utilization of Red Mud, Institute of

Materials and Environmental Chemistry, CRC HAS, pp. 19-23, Budapest, Hungary.

III- 10

Page 11: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Design and construction of an exposed geomembrane sealing system

Paper Title Line 1 (14pt) hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj

for the Sar Cheshmeh tailings dam raising in Iran

2(14pt)

C. Noske & P. Sembenelli ATC Williams, Australia

SC Sembenelli Consulting, Italy

A. Scuero & G. Vaschetti Carpi Tech, Switzerland

ABSTRACT Sar Cheshmeh is a large copper mine in Iran. Its tailings dam comprises a 70m high Main

Embankment with inclined clay core and outer colluvial gravel shell. ATC Williams, engaged to

consider tailings management options for a production escalation involving almost 1 billion tonnes

of tailings over 31 years, designed a scheme comprising a 40m high downstream raise to the Main

Embankment in four stages. The critical design case included up to 20m of water ponding against

the upstream face. The design of the raised embankment was constrained by the existing inclined

core, as the raised core would become an upstream diaphragm with little rockfill cover to act as a

surcharge during seismic loading. Iran is a highly seismically active region, and the resultant seismic

factor of safety for this conventional raising approach was found to be unacceptable. Clay hence

needed to be eliminated from the raise, and a geomembrane sealing system on a rockfill embankment

was adopted. From a construction, performance and cost point of view, an exposed liner was

preferred. Due to its superior mechanical and durability properties, a 3mm thick PVC geocomposite

system, designed by Sembenelli and Carpi Tech, and supplied and installed by Carpi Tech,

represented the optimal solution. The geomembrane sealing system utilises a patented face

anchorage system fastening the geocomposite to a drainage layer of extruded porous concrete curbs.

This paper discusses the design issues and the installation of the first two stages of the raise,

completed in 2008.

Keywords: Geomembrane, geocomposite, PVC anchor strips.

1. INTRODUCTION

Designers of dams, particularly tailings dams, generally agree that the most cost effective

solution is to maximise the use of natural materials available on site. However, in some

situations a design cannot be made to work with the available materials. This was the

situation encountered at the Sar Cheshmeh mine tailings storage, located in a region of high

seismicity in central Iran.

Interest in the application of geomembrane sealing systems (GSS) in the design of

embankment dams for tailings storage facilities has been increasing in the last two decades

around the world. The reasons for this interest include favourable deformation

characteristics, environmental aspects (i.e. seepage minimisation), shortage of low

Abstract Number : 121

III- 11

Page 12: Design Optimization of Bauxite Residue Dam in Connection with

permeability materials, installation efficiency and general constructability of geomembrane

liners in a wide range of climatic conditions.

This paper, which describes the design and installation of a GSS for the first two stages of

the Sar Cheshmeh dam raising, conceptually follows and amplifies two papers presented at

ICOLD Congresses: in 2006, the GSS with flexible face anchorage adopted at Sar Cheshmeh

dam raising was discussed merely as a new design concept for construction of embankment

dams with a geomembrane facing [Scuero & Vaschetti, 2006]; in 2009, the GSS was

presented as first field application on a project that at the time the paper was written was still

under construction [Scuero & Vaschetti, 2009]. In 2014, after six years of operation, the

whole construction process can be described, and field results and conclusions can be drawn

regarding the performance of the lining system.

2. BACKGROUND

2.1. The existing dam

The existing Sar Cheshmeh tailings dam, owned by National Iranian Copper Industries

Company and commissioned in 1980, comprises a 75 m high embankment consisting of an

inclined clay core and of an outer colluvial gravel shell. The site is located within an area of

complex geology, consisting of rocky, sparsely vegetated terrain well above 2,000 m

elevation, in a climate ranging in temperature from about 40°C to well below freezing point.

Figure 1. Sar Cheshmeh dam prior to raising

Due to the changing political environment in Iran at the time, the documented design,

construction and performance history of the embankment were incomplete. It was however

evident from surveillance audits that repair works were carried out during the 1980s and

1990s to correct seepage, settlement and cracking issues relating to high pond levels.

2.2. The raising

ATC Williams were engaged in 2001 to design optimised tailings and water management

options for a proposed production escalation involving almost 1 billion tonnes of tailings

over 31 years. Integral to the project was the buttressing and raising the Main Embankment

and Saddle Dam No.1, to provide tailings storage for the remaining mine life.

The embankment design required a 40 m high, 1000 m long downstream raise constructed

in four stages, the first two of which, comprising 20 m of raising, are the subject of this

III- 12

Page 13: Design Optimization of Bauxite Residue Dam in Connection with

paper. The critical design case included up to 20 m of water ponding against the upstream

face. In order to maintain the embankment as a water retaining structure, the conventional

downstream raising approach would have resulted in a raised core effectively being an

upstream diaphragm with little rockfill cover to act as a surcharge during seismic loading.

Iran is one of the more seismically active regions in the world, evident by the peak ground

acceleration for the Maximum Design Earthquake of 0.8g. Stability analyses showed that

the seismic factor of safety for this approach was unacceptable. Compounding the issue was

a shortage of suitable clay-based soils in what is a semi-arid area, and that the borrow sources

used in the original embankment construction had since been covered by tailings.

A detailed study of alternative water retaining elements was conducted. Options investigated

included asphaltic cores, and bituminous and polymeric membranes. A cross-section

consisting of an upstream GSS on a rockfill embankment was subsequently adopted, on the

basis of it being a more stable, efficient and buildable arrangement.

Figure 2. Inferred cross section of the existing dam, and scheme of the raising

3. GEOMEMBRANE SEALING SYSTEM

3.1. Design criteria and assessment of GSS options

In order to establish the criteria for the final selection of the GSS, a detailed study of the

published literature was conducted, giving preference to publications by independent bodies

such as ICOLD [2010]. A number of GSS options were identified, with the short-list

consisting of a) bituminous concrete/membrane, b) high density polyethylene (HDPE)

synthetic geomembrane, c) polyvinyl chloride (PVC) synthetic geomembrane, and d)

geocomposite (consisting of a PVC geomembrane heat-coupled during extrusion to a

polypropylene non-woven geotextile). Each alternative was analysed with respect to

hydraulic properties, mechanical properties, durability, practical requirements, and

established precedents.

It is not in the purpose of this paper to go into details regarding the analysis and design of

the embankment raising, or the detailed rationale and selection process for the GSS. Such

details are discussed by Noske [2010]. Upon completion of the assessment, it was concluded

that an exposed PVC geocomposite represented the GSS solution that would best meet the

necessary requirements for Sar Cheshmeh.

An exposed geomembrane was preferred to a covered geomembrane for several reasons. In

order to maintain the existing, relatively steep slope 1.5:1 (horizontal to vertical), the only

III- 13

Page 14: Design Optimization of Bauxite Residue Dam in Connection with

viable membrane cover would be cast in situ concrete slabs. Flattening the slope to

accommodate a granular fill cover would result in a cost prohibitive increase in downstream

rockfill volume. Cast in situ concrete slabs, as with any type of cover, would require more

stringent Quality Control procedures, increase the risk of membrane damage, and increase

construction times and costs.

Over the last two decades, there have been considerable advances in the development of

geomembranes, additives, and anchorage methods. Exposed geomembranes are now a viable

alternative to a covered system, and in many ways they are now considered state of the art.

Exposed geomembranes have the advantages of minimised risk of membrane damage, easier

construction, access to the membrane for inspection or repair, and reduced overall

construction times and costs.

It was hence clear that from a construction, performance and cost perspective, an exposed

GSS should be preferred.

3.2. Upstream Exposed Geomembrane Sealing System

A tender process was initiated for the detailed design, manufacture, supply and installation

of an exposed PVC geocomposite GSS. Based on demonstrable experience with respect to

materials and installation expertise, the contract was awarded to Carpi Tech, a Swiss/Italian

specialist waterproofing company.

The selected waterproofing PVC geocomposite was SIBELON® CNT 4400 (manufactured

exclusively for Carpi Tech according to a proprietary formulation), consisting of a 3 mm

thick PVC geomembrane, heat-bonded during manufacturing to a 500 g/m2 non-woven

polypropylene geotextile. The SIBELON® manufacture and materials are specifically

formulated to impart to the geomembrane the tensile and weathering properties necessary to

survive in exposed conditions in the long term.

The design of the upstream face of the raise specified a relatively simple two-layer system

consisting of a GSS base/anchorage layer over a granular filter/transition/drainage layer.

This system was in turn supported by the rockfill body of the embankment raise.

The concept of the final design for the GSS, developed by SC Sembenelli Consulting of

Italy, was to provide imperviousness to the dam via a very deformable system that could

adapt to settlements and to seismic events. A key factor was the method of anchoring,

supporting and providing drainage for the GSS. An innovative method was devised, making

use of the so-called Ita method of support layer construction that was adopted for the dam.

The Ita method involves porous concrete extruded curbs 0.4 m high, installed on the

upstream face and providing a solid, uniform supporting layer for the placement, anchoring

and drainage of the GSS.

As the curbs are being extruded, 0.5 m wide anchor strips of geomembrane material are fixed

onto each curb; overlapping strips are heat-seamed, so that when the embankment is

completed continuous parallel bands of PVC geomembrane are embedded in the slope of the

embankment from crest to upstream toe. The horizontal spacing between adjacent PVC

anchor strips is 6 m, calculated as a function of the design wind uplift loads.

The waterproofing PVC geocomposite sheets are unrolled from the crest and anchored

against uplift by seaming them to the PVC anchor strips. Figure 3 shows the concept.

III- 14

Page 15: Design Optimization of Bauxite Residue Dam in Connection with

Figure 3. Cross section at curbs, and scheme of PVC geocomposite placement (1. Curbs, 2. PVC

geocomposite, 3. PVC anchor bands, 4. Plinth, 5. Seaming to PVC anchor bands)

The transition between the existing embankment and the raising comprises an upstream

sloping, 10 m wide compacted clay zone seated in the upper part of the existing core. The

crest of the core transition forms the bottom peripheral anchorage for the exposed PVC

geocomposite, which was placed in a trench excavated in the core transition and then

backfilled with clay. At the rock abutments, the watertight seal is of the mechanical tie-down

type to reinforced concrete plinths.

The top seal of the first intermediate stage of the raise is mechanical and placed on a curb

formed with mass concrete at the crest. Top anchorage for the second stage is required to be

more permanent, and was made by positioning the PVC geocomposite in a trench excavated

at the crest of the stage, and by ballasting it with a mass concrete anchor beam.

TYPICAL SECTION ON ANCHOR STRIPS

0.15

40mm

Heat weld

Temporary ballast (concrete, gravel,Porous concrete curb

Anchor strips w=0.50

PVC geocomposite

Sibelon CNT 4400

0.15

Interlock keys between curbs

4 m long centered between two

anchor strips.

0.30

0.1

0

sand, steel bar, etc.)

1 2

3

4

5

5

6

III- 15

Page 16: Design Optimization of Bauxite Residue Dam in Connection with

4. INSTALLATION

4.1. Curbs and anchor strips

The extruded porous concrete curbs upon which the GSS is anchored have the advantage of

very quick construction, provide a regular, non-erodible slope that can be quite steep, and

provide containment for the embankment fill during construction.

After each curb has been completed, a PVC geocomposite anchor strip is nailed to the curb

for temporary anchorage, permanent anchorage being provided by the compacted granular

fill placed against the curb as the embankment is raised. Each PVC anchor strip overlaps the

PVC strip installed on the curb underneath, and the two are heat-seamed at the overlap, thus

constructing parallel PVC anchor bands, 0.50 m wide, over the curbs. In this way, the

anchorage system for the PVC geocomposite is in place as soon as the embankment raise is

completed, as shown in Figure 4.

Figure 4. Heat-seaming of two overlapping PVC anchor strips, and the parallel PVC anchor bands

on the first stage of raising

This anchorage system is flexible and deformable, meeting the seismic design objectives for

the raise. PVC has an elongation at break greater than 230%, allowing the system to maintain

its integrity under the full range of predicted embankment deformations.

A

4.2. Placement and anchorage of PVC geocomposite

When the raising of the first, intermediate stage was completed, the waterproofing liner,

supplied in rolled sheets, was temporarily fastened at the crest and then deployed over the

curbs. The high friction at the geotextile/curb interface facilitates the positioning of the

geocomposite and increases the stability with respect to sliding.

The sheets of PVC geocomposite were placed to coincide with the PVC anchor strips, and

then permanently secured to the curbs by heat-seaming their edge to the PVC bands (Figure

5). Adjacent PVC geocomposite sheets were then watertight heat-seamed, forming one

continuous PVC liner over the curbs.

When the raising of the second stage was completed, the same procedure was followed. The

PVC geocomposite was deployed from the newly raised crest, down until it overlapped the

top anchorage of the first stage. A watertight, horizontal seal between the two sheets was

III- 16

Page 17: Design Optimization of Bauxite Residue Dam in Connection with

then created by heat-seaming and the placement of a PVC geomembrane cover strip, which

was itself heat-seamed to the two adjacent geocomposite stages as shown in Figure 6.

Figure 5. The PVC geocomposite sheets are unrolled from the crest and heat-seamed to the

underlying PVC anchor strips.

Figure 6. The PVC geocomposite sheets of the two stages (Stage II B is covered by dust) are

seamed at the overlapping, and the seam is covered by a PVC geomembrane strip

4.3. Perimeter sealing

4.3.1. Bottom sealing

The bottom seal was made by placing the PVC sheets in a trench excavated in the compacted

clay core transition at top of the existing embankment. The anchor trench was then backfilled

with compacted clay, as shown in Figure 7.

At the concrete plinths constructed at the abutments, the bottom seal was of the mechanical

tie-down type as shown in Figure 7. The surface of the concrete was regularised with epoxy

resin, and the PVC geocomposite anchored to the plinth using a 60 x 6 mm stainless steel

batten strip placed on an EPDM gasket, and tied-down with stainless steel anchor rods

embedded in chemical phials placed into the concrete at 150 mm spacing.

4.3.2. Top sealing

The top seal of the first, intermediate stage was of the tie-down type, placed on a mass

concrete curb at the crest, as shown in Figure 7, while the top seal at Stage II C is made in a

trench excavated along the crest and backfilled with a mass concrete anchor beam.

III- 17

Page 18: Design Optimization of Bauxite Residue Dam in Connection with

[Blank line 10 pt]

Figure 7. Perimeter sealing methods (first stage of raise)

Installation of the waterproofing system for the first stage of the raise started on 28 June

2008 and was completed on 14 August 2008. The second stage installation started on

12 October 2008 and was completed on 26 November 2008. Total installed geocomposite

was 20,500 m2 and 18,000 m2 for the first and second stages respectively.

5. SIX YEARS PERFORMANCE

After one year of service, the designer [Noske 2010] reported: “From the perspective of both

the designer and the owner, the selected GSS has resulted in an efficient and economic

waterproofing solution for the tailings storage raise. The extruded curbs have proven to be

an effective construction method, whilst the anchor strip installation became a simple,

routine process…. The installation was fast…. The overall construction period was also

significantly reduced…… Impoundment of water against the toe of raised embankment has

recently commenced, and seepage measurements downstream of the embankment have not

changed from their steady-state levels. It is concluded that the geocomposite faced rockfill

approach is a viable, effective means of tailings dam construction …. where natural materials

are either not available, or are unable to be used from a technical perspective”.

In 2014, after 6 years of service the raised embankment has continued to perform as intended,

although the water level at the toe of the raise has remained relatively static over the period

(refer to the photos in Figure 8). This has been due to the commissioning of the tailings

thickening system designed by ATC Williams, which has resulted in a steeper beach slope

depositing tailings further back up in the heads of the valleys. However, the decant pond

will continue migrating back towards the Main Embankment, bringing the PVC

geocomposite into full service in the near future.

III- 18

Page 19: Design Optimization of Bauxite Residue Dam in Connection with

4. CONCLUSIONS

The selected geomembrane sealing system with anchorage strips embedded in the upstream

face of the embankment during construction has minimised the impact that traditional

geomembrane installations have on the construction schedule of a dam. Installation of the

GSS is quick and easy, so that just a few weeks are required to complete the whole facing

system after completion of the embankment body. The waterproofing system is “more

forgiving” in comparison to conventional systems as far as construction skills are concerned.

Companies with limited previous experience in geomembranes can carry out the

construction of a relatively straight-forward rockfill embankment section and install the

extruded porous concrete curbs, while a specialised contractor supplies and installs the

waterproofing system to efficiently achieve a watertight retaining structure capable of

satisfying all necessary design and serviceability criteria.

After the Sar Cheshmeh tailings dam raising, other field applications of this new design have

been constructed, are under construction, or have been included in the design of embankment

dams yet to be built. Behaviour up to date indicates that the system constitutes a viable and

effective alternative to traditional upstream concrete facings and impervious cores.

Figure 8. Sar Cheshmeh dam raising at the end of the second stage construction works, and in

service during 2013.

REFERENCES

ICOLD, International Commission on Large Dams (2010): Bulletin 135. Geomembrane

sealing systems for dams - Design principles and review of experience, ICOLD,

Paris, France.

Scuero, A. M. and Vaschetti, G.L. (2006): Unconventional cross sections and materials in

embankment dams. ICOLD 22nd Congress, Barcelona, Spain. Proceedings Vol. I -

Question 84: pp. 87-105, International Commission on Large Dams - Paris – France.

Scuero, A. M. and Vaschetti, G.L. (2009): Unconventional design in dam raising: Sar

Cheshmeh tailings dam. ICOLD 23rd Congress, Brasilia, Brazil. Proceedings Vol. I

– Question 90: pp. 18-20, International Commission on Large Dams - Paris – France.

Noske, C. (2010): Geocomposite faced rockfill - an innovative means of water-proofing

tailings storages. Mine Waste 2010, Proceedings Vol. 1: pp. 291-302, Australian

Centre For Geomechanics, Perth, Australia.

III- 19

Page 20: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Tailings Storage Risk Reduction by Integrated Waste Management Mine

hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj

at Didipio Mine

2(14pt)

D.M. Brett, R.J Longey & S.P. Edwards GHD Pty Ltd, Hobart, Tasmania, Australia

[email protected]

ABSTRACT OceanaGold’s Didipio Mine Project comprises an open pit operation in the Dinauyan River valley

of northern Luzon, Philippines. The site is characterised by steep topography, high rainfall and

deeply weathered tropical soils (saprolite) prone to landslips on the steep valley slopes. In general

these conditions create a challenging situation for safe disposal of tailings, particularly

considering closure after completion of mining. The solution was developed by considering the

synergies of total waste from the mine; the estimated 40 million m3 of tailings and 70 million m3 of

waste rock over the projected 17 year mine life, moving the tailings dam upstream from its original

planned location and allowing it to be integrated into a conservatively stable waste rock dump.

“Flow-through” dump technology is being used to manage significant stream flow within the waste

storage area, creating “real-estate” for waste disposal and also managing the impact of peak

storm flows on the open pit which will eventually span across the valley floor with resultant risk of

flooding.

The integrated waste facility design allows a high degree of confidence to meet the closure

planning aims of ICOLD Bulletin 153 (draft) “Sustainable Design and Post-Closure Performance

of Tailings Dams”.

This paper outlines the design development of the Didipio tailings storage facility with reference to

ICOLD bulletin 153, and describes experience in the first two years of construction, including

initial placement of the “flow-through” dump structure.

Keywords: Integrated Mine Waste Management; Tailings Dams, Flow-Through Waste Dump

1. INTRODUCTION

OceanaGold‟s Didipio Project is a gold/copper deposit located near the village of Didipio,

on Luzon Island, Philippines, approximately 270 kilometres north of Manila and 100

kilometres to the east of the country‟s largest gold-copper mining operations centred in the

Baguio area, as shown in Figure 1.

The ore body is located beneath the Dinauyan River close to its confluence with the

Surong. The site is characterised by steep topography, high rainfall and deeply weathered

tropical soils (saprolite) prone to landslip on the steep valley slopes. In general these

conditions create a challenging situation for safe disposal of tailings, particularly

considering closure after completion of mining.

III- 20

Page 21: Design Optimization of Bauxite Residue Dam in Connection with

Figure 1. Didipio Project Location

Planning of the mine developed from a small open pit with underground mining, to a

significantly larger open pit, resulting in a mine life of 17 years generating an estimated 40

million m3 of tailings and 70 million m

3 of waste rock. This change led to the open pit

encroaching on the Dinauyan River, with consequent risk of pit flooding, but created the

potential for a much lower risk water and mine waste management methodology.

The original mine concept wrestled with the difficulties of creating a Tailings Storage

Facility (TSF) in a significant river, with relatively small volumes of waste rock materials

for construction. Water management was envisaged to involve diversion tunnels or major

pump installations and relied on rapid construction of a dam in a wet tropical climate. The

solution was to push the tailings dam further upstream to a tributary valley of the

Dinauyan, develop a “flow-through” rock drain in the main river channel and take

advantage of the much increased waste rock volume expected from the pit, to construct a

large waste rock dump (WRD) able to contain major flood flows and modulate outflows to

the river as it passed the pit area downstream.

2. DESIGN OVERVIEW

The design basis for the project evolved to allow for the following:

Mine life of 17 years, processing 365 days/year, 24 hr/day

Mill production of 2.5 Mtpa by the end of Year 2 and increasing to 3.5 Mtpa

Tailings delivery of 51 Mt at 60% solids with settled density 1.3 t/m3

Waste rock storage 136 Mt at average density 2.0 t/m3

Tailings geochemically benign Non-Acid Forming (NAF)

Waste rock is classified NAF with minor Potentially Acid Forming (PAF)

Design criteria based on o Australian National Committee on Large Dams (ANCOLD) guidelines;

o ICOLD Guidelines including Bulletin 153, Draft, 2011;

Didipio Project Location

III- 21

Page 22: Design Optimization of Bauxite Residue Dam in Connection with

o “Policy Guidelines and Standards for Mine Wastes and Mill Tailings

Management” Memorandum Order No. 99-32 (24th November 1999),

issued by the Philippine Department of Environment and Natural Resources

(DENR).

TSF Consequence Category (ANCOLD, 2012) „High C‟

Construction spillways to pass 1:5 ARI flow events

Post-construction emergency spillway to safely store/pass a Probable Maximum Flood (PMF);

TSF Decanting System to utilise pumping for removal of decant water and maintain minimum flood storage capacity for the 100 yr ARI 72 hr (1.5 Mm3) flood

TSF embankment utilising downstream construction methodology

Use waste rock from mining operations where economical to do so

Where waste rock is unsuitable, maximise use of locally won materials

Low permeability clay core to retain supernatant water when required and minimise

seepage.

Low permeability cut-off trench to minimise seepage

Filter protection for clay core piping failure protection

Seismic Loading for Maximum Design Earthquake (MDE)1:10,000 AEP, 0.50g;

WRD spillway to pass 100 yr ARI 72 hr event

Storage of PMF on WRD without overtopping following Year 5

Flow-through drain to pass wettest monthly flow (2.6 m3/s)

TSF/WRD Closure

o Partial wetland/water cover, land use available for revegetation or

cultivation

o Flooded pit with diversion of flow from TSF/WRD (Dinauyan River) as a

large water body

o Stable (negligible erosion, settlement, blockage risk) spillway for the long

term

The final landform proposed is shown in Figure 2.

Key features of the design as shown in Figure 2 are:

Tailings storage upstream of and buttressed by the WRD;

“Flow-through” drain in the river bed under the WRD;

“Retention dam” wall and flood-plain formed by the WRD;

Operational spillway formed from coarse rock at the WRD face;

Open Pit formed across the full extent of the Dinauyan Valley

III- 22

Page 23: Design Optimization of Bauxite Residue Dam in Connection with

Figure 2. Didipio Integrated Tailings and Waste Rock Storage

The design envisages a closure scenario where the pit is flooded and provides a silt-trap for

the upstream catchment while stable revegetation is developed. The long term spillway is

provided over the ridgeline to the south of the TSF to prevent the risk of discharge over the

face of the WRD in the event that the “flow-through” becomes blocked.

This concept closure design is considered to form the basis for sustainable closure in

accordance with ICOLD Bulletin 153 (ICOLD, 2011), meeting the aims of the Bruntland

Report (UNWCED, 1987) adopted by the International Council on Mining and Metals

(ICMM), namely, “development that meets the needs of the present without compromising

the ability of future generations to meet their own needs”. The integrated waste storage

facility is conservatively stable from both geotechnical and hydraulic aspects in the long

term, while providing potential for agricultural development on the final landform and

passive water quality management through a large water body at the downstream end of

the site. The final closure design is dependent on monitoring of performance during

operations and ongoing risk review as the final structure evolves.

3. SITE GEOTECHNICAL CONDITIONS

The valley slopes comprise residual diorite soils to varying depths, typically 5 m to 22 m,

overlying highly fractured, slightly to moderately weathered (MW-SW) Diorite. The

strength of the residual silty clay/clayey silt soils generally varies from firm to very stiff

consistency but strength reduces with increasing moisture content and mechanical

working. When exposed after excavation and subjected to wet conditions the residual soils

lose strength and cut slopes can fail if an adequate batter slope is not provided. Similarly

spreading and compaction can disrupt the soil structure.

Final Pit filling Dinauyan Valley

WRD Operational Spillway

WRD “Dam” Wall

WRD Floodplain

Final Long Term Spillway

Final Tailings Beach –

rehabilitated and vegetated

Flow-Through Drain Under

III- 23

Page 24: Design Optimization of Bauxite Residue Dam in Connection with

The valley floor in general consists of 2 to 4 m of silts, sands, gravels, cobbles and

boulders (up to 1.2 m in size) overlying residual diorite soil or in some areas moderately

weathered diorite.

4. TSF EMBANKMENT

The TSF comprises a zoned earth and rockfill dam located at the upstream end of the

WRD, in the catchment of Luminag Creek. The TSF is being built in stages from a starter

dam of 40m high, expected to eventually reach 100 m high and merging with the WRD to

become an integrated structure. The final TSF embankment volume will total nearly

20,000,000 m3, approximately 30% of total waste rock from the mine life. The internal and

external geometry of the TSF/WRD has taken into consideration the outcomes both of

stability analysis and a construction methodology. The major construction material to be

used in the TSF is fresh non sulphide waste rock (Zone 3) won from the open pit and

carted by the mine fleet consisting of Cat 777 off highway haul trucks and 40 tonne

articulated dump trucks.

A typical Cross-Section of the TSF is presented in Figure 3.

Figure 3. TSF Typical Cross-Section

The majority of the waste rock, particularly during the initial few years will be placed in

the TSF by paddock dumping, spreading in layers and compacted by truck/roller passes.

The downstream zones in later years may be placed by developing tip heads of 10m

maximum height.

The Zone 1 material comprises extremely weathered diorite rock (saprolite), comprising

medium to low plasticity silty clays and clayey silts with an average PI of 40 % and field

moisture contents (FMC) of +8 % wet of optimum moisture content (OMC). The wet

nature of the Zone 1 affected the maximum achievable compaction in the field as discussed

later in the paper.

The embankment features primary and secondary filters, which are produced by crushing

the fresh mine waste rock. A primary sand filter (Zone 2A) protects against piping through

the embankment and foundations. A horizontal width of 1.5 m has been specified for the

Zone 2A and 2B filters placed downstream of the clay core, considered the narrowest

practical width based on construction tolerances. The Zone 2A and 2B filter blanket along

the downstream foundation has a minimum thickness of 600mm, this again is considered

the practical minimum for construction. The Zone 2A and 2B filters in the TSF have been

III- 24

Page 25: Design Optimization of Bauxite Residue Dam in Connection with

extended to the crest level in the vertical direction and 30m beyond the extent of the Zone

1 clay core on the foundations in the horizontal direction. The horizontal (blanket) filter is

used to protect the extremely weathered diorite foundation from piping where there are

high hydraulic gradients in the foundation materials. The Didipio TSF embankment

materials zones pictured within Figure 4 are shown in a right to left direction (upstream to

downstream) Zones 3C, 1, 2A, 2B and Zone 3.

Figure 4. TSF Embankment Material Zones

5. WASTE ROCK DUMP

The WRD will be integrated with the TSF to form a single mass of waste rock in the latter

stages of the project. The WRD location and concept will provide the following benefits:

Sufficient waste storage capacity for the life of mine;

Provide additional stability to the TSF;

Provide a safe disposal cell for any Potentially Acid Forming (PAF) waste

materials;

Providing a method for passing normal flows of the Dinauyan River through the TSF and WRD in a controlled manner via a “flow-through” drain constructed at the

base of the dump;

Provide a method of safely storing flood flows from the Dinauyan River in a controlled manner by providing a detention basin formed between the TSF and

WRD, until such a time when the flow-through drain can pass the retained flood;

and

Provide a high level access to the TSF from the pit for materials haulage and access routes for tailings mill return water pipelines.

A key component of the WRD is the “flow-through” drain, which is proposed to be

constructed by dumping fresh, coarse NAF waste rock from a minimum tip head of 20m.

Upstream Zone 3C

Saprolite Abutment

Zone 1

Zone 2A

Zone 2B

III- 25

Page 26: Design Optimization of Bauxite Residue Dam in Connection with

This minimum tip head is designed to encourage segregation of the waste rock so the large

boulders fall first to the base of the drain forming a thick permeable zone for flow to pass

through before the general waste rock is dumped above the drain. The flow-through drain

will not be sufficient to pass the required design PMF, but is designed to cater for the

average wettest monthly average flow.

To cater for large flood flows, the WRD will be constructed in a way to allow for detention

of flood water once the flow-through drain has reached its full flow capacity. When the

drain reaches capacity, excess water will back up within the detention basin provided

between the WRD and TSF crests.

The WRD detention basin is sized to eventually cater for storage of a PMF event, however

there is potential for overtopping, particularly during the initial development of the dump.

Accordingly, the WRD features a coarse rockfill spillway designed to cater for a 1:100

ARI flood event (72 hr critical case).

6. FLOW-THROUGH DUMP EXPERIENCE & PERFORMANCE MONITORING

There are several notable examples of flow-through drains for waste rock dumps. The

authors have particular experience in the “flow-through” drain at the Savage River Mine in

Tasmania, Australia (Brett et al, 2003). This experience in the performance of existing

“flow-through” drains has been used in sizing of the Didipio “flow-through”.

As the future pit expands to cross the Dinauyan River, pipes are proposed to pass flows

around the pit on a bench, thus the “flow-through” outflow has been sized large enough to

pass the average wet month flows, but not so large that the flows become unmanageable to

deliver around the open pit by gravity pipes. Performance monitoring is currently being

installed upstream and downstream of the drain to assess its constructed flow capacity

against the design target. The instrumentation and flow monitoring performance

assessment will become a critical tool to allowing ongoing design calibration and

optimisation using the observational approach (ANCOLD 2012). Adopting this

observational approach to the design and construction of the “flow-through” will enable

informed decisions to be made regarding modifying the as-constructed drain capacity. If

the drain flow capacity is found to be undersized the drain can be expanded or duplicated

higher up in the dump, if the drain capacity is deemed too high the drain could be

„throttled‟ by placing finer rock over the drain inlet to achieve the desired design flow

capacity. The TSF and “flow-through” drain upstream intake are shown in Figure 6.

III- 26

Page 27: Design Optimization of Bauxite Residue Dam in Connection with

Figure 5. Didipio TSF Embankment Construction And Flow Through Dam Intake

7. SITE CONSTRUCTION EXPERIENCE

Construction of the Didipio Project TSF, especially the starter dam was a challenge for the

design and construction teams. The challenges encountered and project solutions

successfully implemented during the construction phase are briefly discussed in the

followings section.

The major source of materials for the TSF is the Didipio open pit, therefore careful

integration between the mine planning and TSF construction teams is critical to the success

of the project, especially in the very early stages of construction. The starter dam design

was reliant on fresh rock to construct the downstream shell of the TSF and to also provide

a coarse boulder overtopping spillway zone on the embankment. Difficulties with the

development of the mine starter pit occurred due to underestimation of pit stripping and

approval limitations which meant the TSF bulk rockfill shell material was not able to be

produced in significant quantities in the early stage of TSF construction. A solution was to

modify the starter embankment zoning to accommodate a less permeable highly weathered

rock and alluvial zone (Zone 3C) sourced from within the TSF storage combined with a

coarse rock drainage layer, this design was continued until the mine was able to strip the

starter pit and produce adequate rockfill volumes.

The same issue in delays with the starter pit resulted in the boulder zone for the TSF

overtopping spillway not being available, this was overcome by using a finer rockfill zone

sourced from the TSF surrounds. The finer rock available would have eroded in the

construction design flood flows thus a temporary reinforced mesh spillway was adopted.

The mesh spillway design was only to last 3 months until the boulders could be produced

from the mine starter pit. The temporary spillway design shown in Figure 6, utilised readily

available site materials including 50mm aperture mesh security fencing fastened to the fine

rock spillway surface using horizontal and vertical reinforcing bars, the bars on the

spillway face were secured by additional bars anchored within the embankment rockfill.

Flow Through Dam Intake TSF Construction

III- 27

Page 28: Design Optimization of Bauxite Residue Dam in Connection with

This mesh spillway design was far more cost effective than alternative concrete options

and suited the short design life. The 50m wide mesh spillway was designed to pass

velocities up to 1:5yr ARI flow events. In July 2012, the permanent coarse boulder

spillway had been constructed to 10m high on the downstream side of the 20m high mesh

spillway when a 180mm rainfall occurred within 2 hours over the TSF catchment,

equivalent to a 1:2yr ARI event. Both spillways performed adequately as designed, with

only minor movement observed of the finer rockill contained by mesh. The coarse

overtopping rock zone was not impacted and has been adopted for future spillway designs

as the dam is progressively raised in the downstream direction. The overtopping spillway

on the embankment uses flood retention to retain peak flood flows allowing the remainder

to safely pass through the coarse boulder zone in the downstream embankment at non

eroding velocities. The design has been adopted to prevent the need for cutting more

conventional type spillways into the naturally steep side slopes of the TSF abutments

preventing large costly excavations which would potentially destabilise the natural

topography.

Figure 6. Left Plate; TSF Temporary Mesh Spillway In Starter Dam. Right Plate; Stage 7

Overtopping Spillway

The use of saprolite soils which are classified as clayey Silts and silty Clays for the low

permeability Zone 1 upstream sloping core presented a challenge in using the site available

materials which are in excess of +8% wet of OMC. The construction rate and wet tropical

climate makes significant drying back of these materials to a more commonly specified -

1% to +2% OMC quite impractical. Therefore, the design specification allows for a lower

level of compaction with a minimum 95% maximum dry density (MDD) using standard

compaction. The design accounts for the reduced Zone 1 material strength due to the lower

compaction and high FMC. The Zone 1 design specification requires minimum undrained

shear strength (Su) of 60kpa, which was derived from lower bound laboratory triaxial test

results from samples remolded to suit achievable actual field compaction conditions, this

low strength material causes instability in the upstream direction if not addressed. The

upstream stability issue was overcome in the design by incorporating a 10m wide upstream

stability zone consisting of granular general fill (Zone 3C) which enables the embankment

to be raised up to 30m above the tailings level. The upstream Zone 3C material also

provides erosion protection should a tailings spigot blowout on the embankment face occur

or a flood event results in ponding and wave action on the upstream embankment wall. The

Zone 3C also provides for ease of constructability allowing a trafficable zone on both sides

of the Zone 1 material. The use of Zone 3C has also utilises waste materials from the pit

which do not meet either Zone 1 or Zone 3, this maximises the material usage from the pit

at all stages of mining.

III- 28

Page 29: Design Optimization of Bauxite Residue Dam in Connection with

The climate at the Didipio project site has a relatively high annual average rainfall of 3.3m

with three distinct seasons. The „dry‟ season lasts January through June, which has an

average monthly rainfall of 148mm, the „typhoon‟ season July through September having

300mm rainfall average per month and the „wet‟ season having 500mm average per month.

The wet climate combined with the naturally high MC saprolite soils, limits practical and

economical placing of the Zone 1 material in the „dry‟ season only. This requires a staged

construction of the TSF to suit the seasons such that the bulk of the downstream rockfill

shell zone is placed during the typhoon and wet seasons ready for raising of the Zone 1 and

filters by campaign in the dry season.

The remoteness of the Didipio mine and size of the TSF construction project made it a

necessity to setup an onsite soils testing laboratory. Laboratory technicians have been

trained to working to Australian Standard testing procedures for the TSF construction

QA/QC program. Laboratory testing has shown oven drying at standard temperatures

(110C) can impact the natural saprolite soil structure and thus compaction tests are

undertaken using the AS 1289.5.7.1 Rapid Hilf testing method using air drying techniques,

which has proven effective and results in quick turnaround time for compaction tests. In

addition to the field density tests for compaction a field shear vane is also used for both

compliance and indicative testing on Zone 1 materials placement. Required field vane tests

are set a minimum 15% higher than the required minimum design strengths to account for

field-lab vane variability.

9. CONCLUSION

The current design and construction of the Didipio Mine Waste Management system has

proven that integrated waste management can result in practical, economical and safe

storage of mine waste in a tropical climate in keeping with the recommendations within

ICOLD Bulletin 153. With planning and innovation, integrated waste management has

enabled the mine operation to successfully develop mine waste storage within a major

floodway which has also enabled future risk mitigation for managing pit flooding.

10. ACKNOWLEDGEMENTS

The authors express their gratitude to the management of OceanaGold Corporation for

permission to present this paper and to staff, consultants and contractors who have

contributed to the success of the project.

11. REFERENCES

ANCOLD, 2012: Guidelines On Tailings Dams - Planning, Design, Construction,

Operation And Closure, Australian National Committee on Large Dams.

Brett, D.M. and Hutchison, B. (2003): Design and performance of a “flow – through”

spillway at Broderick Creek waste rock dump – Savage River Mine, Australian

Journal of Water Resources, Vol 6 No.2, 2003, Institution of Engineers, Australia

ICOLD, 2011: Sustainable Design and Post-Closure Performance Of Tailings Dams,

International Committee of Large Dams

III- 29

Page 30: Design Optimization of Bauxite Residue Dam in Connection with

1

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

MANUAL FOR DESIGN, CONSTRUCTION AND OPERATION OF

TAILINGS DAMS IN IRAN

VAHID FARIDANI, HAMID REZA TAMANNAIE, REZA BAGHI Bandab Consulting Engineers, Tehran, Iran

[email protected]

SHAHROKH TAHOUNI National Iranian Committee of Tailings Dams Tehran, Iran

ABSTRACT: Comparing to regular water reservoir dams, tailings dams potentially have more environmental

impacts. After some incidents in tailings dams in recent years in the country, and considering the

insufficiency of technical documents and national regulations for these dams, the ministry of power

which is the governmental organization; responsible for water recourses, decided to prepare a

national technical document to promote knowledge in this field. The intention is to guide the

owners of the mines to a safer construction, operation and abandonment of tailings dams. This

document is titled “Manual on design, construction, and operation of tailings dams”, and takes

into consideration the current trends of design and construction of tailings dams in Iran. The

manual is prepared under supervision of the committee of tailings dams of Iranian national

committee on large dams (IRCOLD), and though concentrates mostly on the above ground

facilities; it is expected to be a helpful document for other kinds of tailings storage facilities as

well.

Major part of this guideline is based on published experiences of other countries and accepted

recommendations thereof, so in this paper, after briefly introducing the structure of the document,

only those parts of the manual which deal with the problems from a national viewpoint, will be

introduced with some details.

Keywords: Tailings Dam, Manual, Design-Construction-Operation.

1. INTRODUCTION

Growing mining activities in country; increased concern about the safety of tailings dams.

After some incidents in these dams in recent years with negative impacts on society, it has

become evident to the governmental authorities that, in addition to the lack of regulations,

there is a lack of criteria and standards related to all aspects of tailings dams. As the first

step to address this issue, the ministry of power, the governmental organization responsible

for water recourses, decided to prepare a national technical document to promote

knowledge in this field. This document is titled “Manual on design, construction, and

operation of tailings dams”. This Manual is prepared under supervision of the sub-

committee of the tailings dams of Iranian national committee on large dams (IRCOLD).

III- 30

Page 31: Design Optimization of Bauxite Residue Dam in Connection with

2

2. CONTENTS OF THE MANUAL

Considering the fact that, tailings dams potentially have more environmental impact in

comparison with regular water reservoir dams; the main road map in composing this

manual was to preserve the sustainability of tailing dams. This involves consideration of

environmental, economical and technical aspects throughout the life of the structure,

including its abandonment and post closure.

The manual concentrates mostly on the above the ground facilities and consists of nine

chapters. More than fifty percent of the contents (three chapters) deal with the design

problems, such as storage methods, storage design, and design of confining structures.

Since Iran is located on earth seismic belt, and most parts of the country have an arid to

semi-arid climate, which makes water a scarce commodity, more attention is given to

prevention of contamination of natural water resource, water recovery, and seismic design

of structures in these chapters. In other chapters some topics about risk analysis,

management, construction, and operation, surveillance, and post closure issues are covered

in brief.

Considering the fact that the back bone of this guideline is based on ICOLD publications,

and published experiences of other countries and accepted recommendations thereof, it did

not seem to be of much interest to present the whole manual completely, so only main

parts which deal with the problems from a national viewpoint, will be presented here.

3. DESIGN AND SAFETY EVALUATION FLOOD

The Ministry of Power of Iran is presently in the process of publishing a guideline for

classification of water reservoir dams in the country. This classification is used to

determine the design requirements for dams. To classify a dam, the following factors are

considered:

Dam height and reservoir capacity

Area of affected Irrigated land

Annual water supply for domestic and industrial needs

Installed capacity of hydropower stations

Population at risk

Based on this classification, appropriate design flood and safety evaluation flood for dams

can be determined from table 1.

Table1. Recommended Minimum Design, and Safety Evaluation Flood for Water Reservoir Dams

Dam Type Flood Class of The Dam

1 2 3 4

Earth Fill Design(AEP)

1:10000 1:5000 1:2000 1:1000

Safety Evaluation(AEP) PMF 1:10000 1:5000 1:2000

Concrete Design(AEP) 1:5000 1:2000 1:1000 1:500

Safety Evaluation(AEP) 1:10000 1:5000 1:2000 1:1000

Annual Exceedance Probability

III- 31

Page 32: Design Optimization of Bauxite Residue Dam in Connection with

3

It is obvious that the consequences of failure, or even any small deficiency in a tailings

dam, are much more hazardous than failure of a normal water storage dam, so a more

conservative approach should be considered to determine the design requirements of

tailings dams. In this context a qualitative assessment of consequences of tailings dams’

failure and water spillage from its reservoir by considering factors such as impact on

environment, damage to infrastructure, public health, social affects, and population at risk

is recommended. As Iran is a developing country and considerable changes in population

at risk and affected areas should normally be anticipated, it is recommended to carry out

this assessment periodically and in all stages of the life of the tailings dams. Results of this

assessment should then be compared with the requirements of an earth fill water storage

dam having similar sizes. The requirements for the tailings dam should be more than or

equal to the requirements of such water storage dam.

4. TAILING CONTAINMENTS TYPES

There are many different alternatives to design and construct a tailings dam. Description of

these alternatives could easily be found in literature, and selection amongst them for a

specific project depends upon the tailings properties, natural topography, site conditions,

and obviously economic factors. To facilitate a systematic approach to implement a

strategy to manage the tailings, it seemed necessary to classify these alternatives in a

manner shown in table 2.

Table2. Types of Tailings Containment

Construction

Method

Confining Structure

Construction Material Reservoir Location

Single or Multiple

Stage With Barrow Material

In Channel

Above

Ground Tailings

Dams

Up Stream Starter Dam+ Self-Stacking

Tailings (Raising Embankment) Down Stream

Centerline

Single or Multiple

Stage With Barrow Material

Side

Hill

Off

Channel

Up Stream Starter Dam+ Self-Stacking

Tailings (Raising Embankment) Down Stream

Centerline

Single or Multiple

Stage With Barrow Material

Paddock Up Stream Starter Dam+ Self-Stacking

Tailings (Raising Embankment) Down Stream

Centerline

Open Pits

Filling Existing Voids Co-Disposal with Mine Wastes

Underground Mines

Submarine Tailings Disposal Deposition in

The Environment

Notes: 1- Due to scarcity of water in the country, off channel construction is more encouraged.

2- Considering the high seismicity of most regions of the country, upstream construction method is less

implemented in Iran.

3- As there are almost no significant mining activities close to deep water in Iran, deep sea tailing placement is not an experienced practice in Iran.

III- 32

Page 33: Design Optimization of Bauxite Residue Dam in Connection with

4

5. ARRANGEMENT FOR TECHNICAL DIRECTION OF THE WORK

In compliance with general recommendations made in many references, the importance

and necessity of engagement of competent personnel in all aspects, related to tailings dams

is emphasized in this manual. However it should be noted that, a safe and technically

appropriate tailings dam can not be built by just relying on responsibilities of individuals

such as designers, construction companies, operators and even planners or managerial

bodies; engaged in the project. A system which organizes the relationship between

involved entities that carry out the work is also of major importance. In figure 1 below

recommended structures for execution of works by a contractor is shown. This structure for

an in-house construction could be seen in figure 2. Along with these structures following

principals are also stressed in the manual.

Regardless of the size of the project, the design works and duties of the supervision over construction should be entrusted to properly certified legal entities rather than an

individual- Real person.

As far as possible the designer and supervisory body should be of a single legal entity.

In cases where, two separate entities are employed for design and supervision work, every effort should be made to ensure an effective presence of the design body during

the construction period of the dam, and; preferably throughout the life of the structure.

Figure1. Proposed Framework for execution of project by a contractor

III- 33

Page 34: Design Optimization of Bauxite Residue Dam in Connection with

5

Figure2. Proposed Framework for in-house execution of project

ACKNOWLEDGEMENT

The writers wish to thank the Australian National Committee on Large Dams (ANCOLD)

who generously provided a copy of the final draft of the GUIDELINES ON TAILINGS.

The preparation of the manual for tailings dams in Iran, and also this paper, is supported by

Iran Ministry of power’s Bureau of Developing Plan of Water and Wastewater Technical

Standards and Criteria.

III- 34

Page 35: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Optimization of Tailings and Water Management Schemes

hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf

fffffjfjjfkkfjjj

in Taft and Dareh Alou Copper Mines

2(14pt)

H. R. Seif National Iranian Copper Industries Company, Integrated Water Master Plan, Tehran, Iran

[email protected]

A. Roshdieh ATC Williams, Melbourne, Australia

[email protected]

H. Zaker Middle East Water & Environment Consulting Engineers, Member of the Iranian National Committee on Large Dams,

Tehran, Iran

ABSTRACT The National Iranian Copper Industries Company is placing significant investment inexpanding its

existing mining complexes, as well as developing new mines. "Tailings and Water Management" is

regarded as a crucial aspect of these development projects. Regarding the dry climate and severe

shortages in water resources in Iran, maximizing the water recovery from the tailings outflow from

the concentrator plant, has been a major objective in the related engineering designs. In this paper,

Tailings and Water Management of two of the more recent mine development projects in the very

dry region of Central Iran are reviewed. Three major components of the "Tailings and water

Management" studies including tailings "Dewatering", "Transport" and "Storage" and different

combinations of the available options are investigated. Technical and economic aspects of these

components and their role in the overall "Feasibility Studies" of these projects are discussed. In

view of the water scarcity in the regions, raw water resourcing and transfer costs are also taken

into account. Both mines have mineable ore capacities of about 140 Million tons. Concentrator

plants with nominal capacities of 7 Mtpa (900 ton per hour), are designed to operate for 20 years

of mine life. The study shows that despite similarities in the mine and concentrator plant capacities,

Capital Costs of the optimized Tailings and Water Management Schemes may differ significantly,

mostly due to the topographic and environmental restrictions in each region.

Keywords: Water, Tailings, Feasibility, Copper, Stacking, Filtration, Beach Slope

1. INTRODUCTION

Technical, economic, environmental and social issues associated with mine tailings

deposition and water management are the main reason why a holistic approach is required

for the selection of the tailings storage facilities (TSF) in mining projects. In this article,

two copper mines with similar throughputs and minable reserves are selected and it is

shown that despite their similarities, the selected tailings disposal schemes are different.

Both of these mines are located in Iran and they are both part of the Iranian National

III- 35

Page 36: Design Optimization of Bauxite Residue Dam in Connection with

Copper Company (NICICO) expansion plan. The environmental conditions in the region

are the reason why water management and conservation is of crucial importance in both of

these projects. The mines covered in this paper are the Taft mining complex and the Dareh

Alou mine – both open cut copper mines in central Iran.

Due to water scarcity in the region and the cost of water, the client instructed that at least

paste thickening should be utilized for tailings dewatering. Also, due to the complexities

and problems associated with pumping of slurry, the client was reluctant to use slurry

pumps and requested the minimization of slurry pumping in both projects.

2. BASIS OF DESIGN

2.1. Tailings Dewatering and Transportation

Various dewatering methods are adopted in the mining industry for the main purpose of

water recovery. Another advantage of dewatering the tailings is the fact that if water is

removed from the tailings the potential for storing the tailings in a stack with steeper

angles would become more viable. In the mining industry, the most common dewatering

facility is the thickener, which covers a wide range of forms from “conventional”

thickeners with the lowest underflow solid concentration, to “high-rate”, “high density”and

finally “paste” thickeners with the highest underflow solid concentration. Generally the

capital cost and also the operation costs of thickeners increase as the underflow solid

concentration increases.

Another less common dewatering technique is filtration. In general, there are two main

types of filter systems, pressure or vacuum filters. Usually vacuum filters are more

mechanically demanding and require intensive maintenance. On the other hand, pressure

filters use hydraulic or mechanical forces to apply the required pressure. Due to the

adverse impact on vacuum filters of the elevation of the sites (1600~2400 m), pressure

filters have been assumed to be more viable in these studies.

Typical effluent solid concentrations that can be achieved from each of the dewatering

technologies are presented in Table 1.

Table 1.Typical Slurry Concentrations for Copper Tailings

Case Solid Concentration

(%)

Un-thickened tailings slurry ex concentrator 20-25% w/w

High rate thickener underflow 50-54% w/w

Paste thickener underflow 60-64% w/w

Cake from pressure filters 75-80% w/w

Typically, as the solid concentration of the tailings increases, the Rheological properties

change. A typical tailings slurry rheogram is presented in Figure 1.

III- 36

Page 37: Design Optimization of Bauxite Residue Dam in Connection with

Figure 1. Typical Rheograms for Copper Tailings Slurry at Various Concentrations

As the solid concentration of slurry increases, the volumetric flow rate decreases, but at the

same time, the required energy for slurry transportation usually increases. This required

energy could be in the form of potential energy in the case of gravity transportation of

slurry or required pump head. Thus, the combination of tailings dewatering and tailings

transportation system should be optimized. Gravity slurry transportation could take place

in slurry channels or pipelines with various types and shapes.

In the case of filtered tailings, the product is no longer a liquid and typically is referred to

as “cake” which requires solid handling techniques. Such techniques are usually more

expensive than fluid transportation and requiremore sophisticated equipment.

2.2. Tailings Storage and Return Water

Tailings with lower solid concentration, deposit in the TSF with a flatter beach slope which

usually results in higher embankments. On the other hand, tailings slurry that is thickened

sufficiently will not segregate, i.e. there will be no hydraulic sorting of particle sizes when

it is deposited sub-aerially on a beach, and will form a planar slope for a given percent

solids, which is referred to as the “stacking” of thickened tailings. The form of the stack

can be as a cone on flat terrain and is called Central Thickened Discharge (CTD) or as

Down-Valley Discharge (DVD) if the discharge is down-slope to a retaining embankment.

Based on the methods proposed by Pirouz and Williams (2007) and Fitton (2006),

prediction of the beach slopes has been undertaken. The beach slope for sub-aerial

deposition (i.e. not underwater deposition) of non-segregating tailings slurry is a function

of particle size distribution, mineralogy – expressed by specific gravity, clay content,

particle angularity – rheology, and flow rate. Most of these parameters are fixed for a

given ore type and mineral recovery process, but rheology and flow rate are variable. A

typical tailings particle size distribution curve is presented in Figure 2.

III- 37

Page 38: Design Optimization of Bauxite Residue Dam in Connection with

Figure 2. Typical particle distribution curve for Copper Tailings

If the tailings are even further dewatered and “cake’ is produced, then they can be

deposited with steeper slopes, which could decrease the overall footprint of the TSF.

However, filtered tailings require more sophisticated and more expensive deposition and

spreading methods.

It is obvious that as the solid concentration of tailings increases, less water remains in the

deposited tailings which would result in production of less bleed water and typically less

return water from the TSF. Bleed water together with the surface run off that is generated

in the TSF area are usually returned back to the concentrator. This is called “return water”.

3. TAFT MINING COMPLEX

The Taft mining complex comprises two copper mines; Aliabad and DarehZereshk,

respectively 58 and 62 km south-west of Yazd city. Both the Aliabad, and

DarehZereshkmine sites are located on sloping planes surrounded by hills, grading up to

steep mountainous terrain at RL 2470m. The location of the concentrator is proposed at

approximately 1.5 km north of DarehZereshk village, which is immediately upstream from

the pit in the same floodway valley. On the other hand, the preferred location for the TSF

is in lower, flatter terrain, approximately 35 km to the south of the concentrator location at

RL 1600m, this would give an overall average slope of 25 m/km. This is in desert area

with minimum environmental and social impacts.

The total throughput at the concentrator is 7 Mtpa which comprises of 4 Mtpa from

DarehZareshk mine and 3 Mtpa from Aliabad mine over the 20 years of mine operation.

This equates to generation of 140 Million tons of dry tailings.

The TSF location is in an arid region with an average of 100 mm/year of precipitation and

3,800 mm/year of pan evaporation with low humidity.

III- 38

Page 39: Design Optimization of Bauxite Residue Dam in Connection with

The average required fresh water for the two cases of paste thickening and filtration is

estimated at 387,200 m3/month and 169,200 m

3/month respectively.

In this study,central thickened discharge (CTD) and tailings filtration (Dry Stacking)

schemes have been investigated at the TSF location. For the CTD option three tailings

dewatering and transportation options including paste thickening at the concentrator and

paste thickening at the TSF plus the option of high rate thickener at the concentrator and

paste thickener at the TSF have been investigated. In the case of the filtration option, the

best arrangement was proven to be a high rate thickener at the concentrator and filtration at

the TSF location.

In the CTD option an overall earthwork of approximately 2Mm3 would be required mostly

in low bunds around the perimeter of the TSF and a central tailings delivery pipe ramp.

Thickened tailings is predicted to be stacking in the TSF at maximum slope of 3%. The

overall plan of the TSF for the CTD is presented in Figures 3.

Figure 3.TSF plan for CTD case for Taft mine

In the filtration option it is assumed that the “cake” stacks in a steeper angle but in order to

prevent erosion, the face of the stack is planned to be covered by mine waste. For the

Transportation of “cake’ to the TSF location various options including trucks and conveyor

belt were examined and conveyor belt is proven to be more cost effective. Also the

distribution of tailings in the TSF is undertaken by stacking equipment instead of trucks.

The overall plan of the TSF for the filtration option is presented in Figures 4.

III- 39

Page 40: Design Optimization of Bauxite Residue Dam in Connection with

Figure 4.TSF plan for filtration case for Taft mine

In the case of transportation of un-thickened tailings to the TSF location, the required

energy gradient for the tailings pipeline (NS 750mm steel pipe) is estimated at 6.7 m/km,

for the transportation of partially thickened tailings from high rate thickener underflow (NS

500 mm steel pipe) an energy gradient of 8.7 m/km is estimated to be required and in the

case of transportation of paste the required energy gradient is 42 m/km (NS 400 mm steel

pipe).

A cost estimate and analysis have been undertaken with prices at 2011 rates, and a rate of

return equal to 8%. The result of the costs estimate is presented in Table 2.

Table 2.Cost Estimation Results at Taft TSF

Option CAPEX

(USD)

OPEX

(USD/year)

NPV

(USD)

Paste thickener at concentrator 202M 10.9M 283M

High rate thickener at

concentrator and Paste at TSF

166M 4.3M 169M

Paste thickener at TSF 160M 5.6M 175M

Filtration 280M 11.2M 320M

On this basis, the equivalent cost of tailings deposition in the least expensive CTD option

and the filtration option are $2.4/ton and $4.6/ton respectively.

The net present value of the cost of fresh water supply in the case of CTD is estimated at

$135M while the cost of fresh water supply for the filtration option is estimated at $25M.

By including these costs in the total evaluation, the net present value of the total costs at

the CTD option is $304M,and$345M for the filtration option.

4. DAREH ALOU MINE

III- 40

Page 41: Design Optimization of Bauxite Residue Dam in Connection with

Dareh Alou mine is located approximately 4 km north west of Gerdootan village, which

lies about 23 km north east of the town of Rabor in Kerman province. Dareh Alou mine

site is located on a sloping plane in a valley that is surrounded by hills, grading up to steep

mountainous terrain. The surface elevations of the proposed pit are generally between 2800

and 2900 m above sea level. Since this is a green field project the location of the

concentrator was selected in conjunction with the tailings deposition options study. As the

result five contractor locations with various ore transportation options have been

investigated together with the tailings and water management study. The result of the

study indicated that the best concentrator plant location was at RL 3050m at a distance of

approximately 2.5km from the preferred TSF location.

A number of different TSF site locations were also investigated, and the results of initial

these investigations suggested that only one TSF site was worthy of further studies. The

tailings disposal management method at the selected site is a Central Thickened Discharge

(CTD) system. Two embankments are required for this site. Embankment 1 (South West

Embankment) is a 44 m high embankment. Embankment 2 (North East Embankment) is 80

m high. The total volume of required embankment construction is 7.2 Mm3 which will be

constructed in various stages. Tailings will be delivered to the center of the TSF on an

earthfill pipeline ramp that would be extended during the life of the mine. The thickened

tailings, similar to Taft CTD case, is predicted to be stacked at a maximum beach slope of

3%. As mentioned earlier this is the maximum beach slope at the top of the stack and

gradually reduces as it gets closer to the bottom of the stack and the embankment. There

are very few social issues associated with the location of the TSF.

The total throughput at the concentrator is 7 Mtpa with a life of mine of 20 years which

would result in production of 140 Million tons of dry tailings. An overall plan of the TSF

in this study is presented in Figures 5.

Figure 5. TSF plan for Dareh Alou mine

Tailings pipeline energy requirement at conceptual study stage was assumed to be similar

to those of the Taft project.

III- 41

Page 42: Design Optimization of Bauxite Residue Dam in Connection with

Precipitation at the location of the TSF is not as low as for the Taft project with, an average

annual rainfall of 251mm/year. Also, the amount of pan evaporation is not has high as that

in Taft, and is recorded at 1,930 mm/year.

In the Dareh Alou project, water is not as scarce as at Taft, and based on previous

experience, it is anticipated that filtration would not be attractive, hence three tailings

dewatering and transportation options were investigated. These options included; paste

thickening at the concentrator location, paste thickening at the TSF location plus the option

of a paste thickener at the TSF and a high rate thickener at the concentrator.

Similar to the Taft project in cost estimate and analysis, 2011 rates are used with a rate of

return equal to 8%. The result of the cost estimateis presented in Table 3.

Table 3.Cost Estimation Results at Dareh Alou TSF

Option CAPEX

(USD)

OPEX

(USD/year)

NPV (USD

Paste thickener at concentrator 143M 3.6M 122M

High rate thickener at

concentrator and Paste at TSF

148M 5.3M 189M

Paste thickener at TSF 143M 3.9M 123M

On this basis, the lowest annual equivalent cost of tailings depositionis $1.8/ton.

As mentioned earlier, since the availability of water at Dareh Alou was not as problematic

as for the Taft project, and also, since all the proposed options present the same amount of

fresh water requirement, the cost of water supply and transportation have not been included

in the study.

5. DISCUSSIONS

In the Taft project the TSF, regardless of the type of deposition, is located in flat terrain in

an arid area. The distance between the concentrator location and the TSF is long enough

that the extra cost of additional high rate thickeners could be compensated by the savings

in the reduced size of tailings and return water transportation. On the other hand, the

elevation difference between the concentrator and the TSF was such that gravity flow of

the partially thickened tailings (underflow from a high rate thickener) was viable. On this

basis, and if the cost of water is excluded, the central thickened discharge would present

the lowest net present cost. However, water scarcity is severe, so much so that sufficient

water may simply not be available at all. In this case, the only remaining tailings

deposition option would be tailings filtration. In the case of tailings filtration, in order to

reduce the cost of tailings and water transportation, utilization of high rate thickeners at the

concentrator is suggested. If the environmental and social constraints were removed, some

saving in the filtration option could be achieved by moving the TSF location closer to the

concentrator.

In the case of the Dareh Alou project, the distance between the concentrator and the TSF is

such that transportation of un-thickened tailings to the paste thickener adjacent to the TSF

is the most effective option. Also, despite that fact that relatively large embankments

would be required in the Dareh Alou project, thickening the tailings could still provide

III- 42

Page 43: Design Optimization of Bauxite Residue Dam in Connection with

benefits in reducing the construction cost by adopting a CTD scheme. This is made

possible due to the special topographical conditions at the Dareh Alou TSF site.

6. CONCLUSIONS

The conclusions that are derived from these studies are as follows:

There is no single answer for tailings and water management projects. Each project

is unique and thorough, specific study is required.

Factors that may have significant impact on the preferred tailings and water

management projects are; site topography, environmental constraints, climate

conditions, social sensitivities, distance from the concentrator and tailings

properties.

With increasing importance of water saving and scarcity, filtration gets more and

more attention, and there are cases in which filtration may become the viable option

if the cost of supply and transportation of fresh water is included in the study.

If the TSF is far enough away from the concentrator, two stages of dewatering

might be the most viable option.

With advancements in thickening technologies and based on the recent researches

and understanding of the beach slope, stacking of thickened tailings in the Central

Thickened Discharge and Down Valley Discharge options provide the most viable

options.

In some cases the clients prefer to select the option with lower up-front capital cots.

This is usually to be able to overcome the cash flow problems prior to the

commissioning of the plant.

ACKNOWLEDGEMENT

The authors wish to express their gratitude for the support and cooperation of the managers and

engineers at NICICO’s integrated water master plan technical office, ATC Williams and Middle

East Water and Environment.

REFERENCES

Pirouz, B and Williams, P. (2007):“Prediction of Non-Segregating Thickened Tailings

Beach Slope – A New Method”. Proceedings of the 10th International Seminar on Paste

and Thickened Tailings, Fremantle, Western Australia.

Fitton, T.G. and Bhattacharya, S.N. (2006):“Tailings Beach Slope Prediction. A New

Rheological Method”.International Journal of Surface Mining, Reclamation and

Environment. Vol. 20, 93, pp 181-202.

III- 43

Page 44: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Comparison of tailings dams dynamic response in case of central and

downstream method of construction

Ljupcho Petkovski, Professor, PhD, BSc. Civ. Eng. Ss. Cyril and Methodius University, Civil Engineering Faculty in Skopje, Republic of Macedonia

[email protected]

Stevcho Mitovski, MSc., BSc. Civ. Eng. Ss. Cyril and Methodius University, Civil Engineering Faculty in Skopje, Republic of Macedonia

ABSTRACT: The tailings dams are complex engineering structures, composed of: initial (starter) dam, sand dam, deposit pond, drainage system, water conveyors for cleared water conduction and structures for protection in case of incoming external water. The tailings dams along with the enormous volume of sediment’s lake are structures with highest potential hazard for the surrounding. A numerous tailings dams had a break or suffered enormous displacements during past earthquakes. Namely, the first main reason for tailings dam break is overflow, while the second is the action of earthquakes, causing tailings dams break at around 17% of the total number of breaks. The aim of this research is to contribute on the understanding of tailings dams behavior on action of strong earthquakes, by comparison analysis of the seismic response of the tailings dam constructed by different construction method. In this paper are presented results and conclusions from the comparison analysis (tailings dams alternatives with central and downstream method of construction) of the dynamic response of tailings dam no. 4 of lead and zinc mine Sasa, located in the north-east part of Republic of Macedonia. This region, as part of the Western Balkan, is seismic active area with maximal intensity of VIII-th degree for the expected earthquake for return period T = 1,000÷10,000 years, magnitude M ≈ 6.5, and peak ground acceleration PGA ≈ 0.35 g in case of Maximum Credible Earthquake. The analyzed tailings dam, currently at design stage, is planned with dam crest width of 5.0 m, downstream slope of 2.7 and height of 79.0 m measured from the tailings dam crest to the downstream toe.

Keywords: tailings dams, dynamic analysis.

1. INTRODUCTION

The tailings dam, imposing large volume of deposit pond, are structures with highest potential hazard on the environment. The similarities between tailings dams and convectional embankment dams (creating water reservoirs) have contributed many of the procedures and techniques at designing, construction and maintenance of the embankment dams to be applied also at tailings dams, thus improving their safety. But, numerous reports on accidents at tailings dams in the last three decades worldwide and also in Republic of Macedonia, are indicating on the ascertainment that structural (Petkovski L., Tančev L., Mitovski S., 2007;, Petkovski L., Tančev L., Mitovski S., 2013), dynamic (Daghigh Y., ..., 2005. Petkovski L., Paskalov T., 2003; Petkovski L., 2005), hydrologic

III- 54

Page 45: Design Optimization of Bauxite Residue Dam in Connection with

and hydraulic safety is not secured by same strictness – as for embankment dams (Wieland M., Malla S., 2002; Seid-Karbisi M., Byrne P.M., 2004; Petkovski L., Tančev L., 2003). If we take in consideration following facts for the tailings dams: (1) there is no terminal control on the dam quality by applying the procedure of “first filling of the reservoir”, (2) there is no bottom outlet on eventual reservoir emptying and (3) in case of eventual dam break, beside the human victims and material damage, there is also a lasting degradation of the environment in the downstream valley. This requires the strictness for estimation of the tailings dams safety to be on higher level, compared with conventional dams.

The purpose of this study is to contribute to the understanding of the tailings dams behavior, constructed by different methods, caused by earthquake action. In this paper are presented the results and conclusions of the comparative analysis of the dynamic response in time domain (Salehi D., Mahin Roosta R., 2005; Matsumoto N., ..., 2005.) of the tailings dam Sasa no. 4, according to alternative construction methods – central and downstream method. In composition of the tailings dams of mine Sasa, M. Kamenica, located in north-eastern part of Republic of Macedonia, along the valley of Saska river, up to now are constructed 4 tailings dams, by application of the downstream method of construction (Petkovski L., Ilievska F., 2010.08). Currently, is active deposit pond no. 3-2, for which creation is constructed downstream tailings dam no. 3-2 with designed level of 975.0 masl. In order to use all available space along Saska river in the future service period of mine Sasa (after 2016), the following basic parameters of the tailings dam no. 4 are adopted: (а) crest elevation 952.0 masl, (b) deposit lake elevation 950.0 masl and (c) location of the dam site axis – most downstream from dam no. 3-2, limited in order all civil engineering structures to be placed in the zone of urban coverage of mine Sasa.

By such choice of parameters the downstream slope of tailings dams no. 4 is at vicinity of settlement. Due to the vicinity of the settlement (downstream from the zone of tailings dams no.4), in order to protect the inhabitants more efficiently from the air pollution, it is necessary to start the cultivation process of the tailings dams downstream slope as soon as possible. The initial thoughts for the alternative with downstream method of construction, as mostly acceptable solution from ecological point of view, are rejected, due to the very active earthquake region and this type of method obtains lowest seismic resistance of the structure. Therefore it is analyzed alternative differencing from the so far practice of downstream construction, apropos applying the method of central advancement of the sand dam. At such alternative, by embedding the rock material (from mine excavation) in the downstream shell, the final downstream slope can be formed practically in the same time with the raising of the dam crest elevation. It will enable in the initial stage of the dam construction to start the cultivation of the downstream slope, much more favorable from ecological point of view, compared with the alternative on downstream advancement of the sand dam. Namely, at downstream method of construction of the dam, by advancing in skew layers, the cultivation can start after the completion of the service period, apropos after the reaching of the final dam crest and last skew layer on the downstream slope. Therefore two alternatives are envisaged: (a) alternative no. 1 - downstream method of construction (proved as safe solution in the previous 4 tailings dams) and (b) alternative no. 2 – modified central method of construction. If the structural analysis confirms that alternative no. 2 poses the required safety and even if it is more expensive (at reasonable amount), then it will be adopted as most favorable solution, due to the possibility of faster cultivation of the downstream slope, apropos securing more acceptable level of inhabitants protection from air pollution.

III- 55

Page 46: Design Optimization of Bauxite Residue Dam in Connection with

2. REPRESENTATIVE CROSS SECTION FOR STRUCUTRAL ANALYSIS AND AUTHORITATIVE MATERIAL PARAMETERS

The tailings dams cross section with maximal dimensions is adopted as representative section for dynamic analysis. For this section are foreseen several approximations, contributing on simplification of the numerical experiment, and not decreasing the analysis safety. The cross section simplification is done with the following:

i. The rock foundation is composed of gneiss at around 100 times higher deformable properties compared with the deposit (and also to the materials in the tailings dam), and in the analysis is treated as non-deformable and rigid boundary condition.

ii. The river bed deposit has variable depth, at around 27 m upstream of the dam (in near by of the upstream toe), 25 m at tailings dam site axis (dam crest) and 23 m in near by of the downstream toe of the sand dam.

iii. The river deposit will be cut in the initial dam axis by plug with depth of 8 m and bottom width of 3 m, thus securing the required casual seepage strength in the alluvium.

iv. The initial dam will be constructed as symmetrical homogeneous dam, made of graphite shale, with drainage blanket in the downstream toe, crest width of 3 m, crest elevation at 906.0 masl (due to securing of reserved volume in case of flood with return period of 20 years) and slope m = 1.5.

v. The sand dam will be created up to elevation 952.0 masl, (2.0 m above deposit lake), with crest width of 5 m, and slopes: upstream m1=1.5 (alternative no. 1) and downstream m2 = 2.7 (for both alternatives).

vi. The influence of the deposit lake (up to elevation of 950.0 masl) and the river deposit upstream of the dam site will be analyzed at section of 100.0 m upstream of the dam site, and the influence of the river bed deposit will be analyzed at section at around 40 m downstream of the downstream toe of the sand dam.

In such a way is prepared the idealized cross section for the dynamic analysis. The heterogeneous composition of the tailings dams is modeled by 6 different materials, fig. 1 and fig. 2.

Figure 1. Representative cross section for downstream method of construction (1) alluvium, (2) initial dam of shale, (3) tailings sand and (4) sludgein the deposit lake.

1

2

34

884.4

952.0950.0

906.0

882.0 873.0888.4879.4 874.6

Distance [m]

0 50 100 150 200 250 300 350 400

Ele

vatio

n [m

]

840

865

890

915

940

965

III- 56

Page 47: Design Optimization of Bauxite Residue Dam in Connection with

Figure 2. Representative cross section for central method of construction (1) alluvium, (2) initial dam of shale, (3) tailings sand, (4) sludgein the deposit lake, (5) mix of tailings sludge and sand and (6) rock from mine excavation.

The adoption of the strength, deformable and water impermeable properties of the materials is based on number of terrain and especially laboratorial testing (three axial and oedometar testing). The adopted values for the geomechanical parameters, applied as input data in the analysis, are systemized in Tab. no. 1.

Table 1. Basic geomechanical parameters of the materials.

no. dim. 1 2 3 4 5 6

material

gravel shale tailings

sand tailings sludge

mix sludge-sand

mine rock

element foundation initial dam lake lake dam γspec kN/m3 26.5 27.0 32.0 31.0 31.5 32.0γdry kN/m3 19.0 19.2 18.0 15.0 16.5 20.0n 0.283 0.289 0.438 0.516 0.476 0.375

ω < ωsat % 8.0 8.0 10.0 15.0 12.0 8.0γsat kN/m3 21.8 22.0 22.3 20.1 21.2 23.7γ kN/m3 20.5 20.7 19.8 17.3 18.5 21.6φ o 37.0 31.0 32.0 15.0 20.0 33.0c kN/m2 0.0 15.0 0.0 5.0 2.0 0.0

k_s m/s 2.0E-05 1.0E-07 2.0E-06 2.0E-07 7.0E-07 1.0E-05Ko(φ) = 0.40 0.48 0.47 0.74 0.66 0.46ν(Ko) = 0.28 0.33 0.32 0.43 0.40 0.31

Mv compr kN/m2 37,000 35,000 30,000 22,000 25,000 40,000

3. INPUT DATA FOR THE DYNAMIC ANALYSIS

The analysis of the dynamic stability of the tailings dams Sasa is elaborated in accordance with the current standards on aseismic designing in Republic of Macedonia. In accordance with geographic coordinates of the location of the dam site of tailings dam Sasa – M. Kamenica, by seismological maps of Republic Macedonia, the dam is in moderate seismically active area. The maximal intensity of the expected earthquake at the location, according to MKS-64, for return period T = 1,000÷10,000 years is VIII degrees. In accordance with the scales on comparison of the earthquake intensity and magnitude, for

1

2

34 5

6

952.0950.0

906.0

878.0873.0

917.0

884.0 880.4 877.0

910.0902.5

895.0887.5

Distance [m]

0 50 100 150 200 250 300 350 400

Ele

vatio

n [m

]

840

865

890

915

940

965

III- 57

Page 48: Design Optimization of Bauxite Residue Dam in Connection with

earthquake intensity of VIIIth degree corresponds magnitude M ≈ 6.5. By research of the dependence between the earthquake magnitude “M” and peak ground accelerations (PGA) for the wide region, where Republic of Macedonia belongs, if it is case of rock medium and attenuation of the seismic action on distance from the epicenter at around 5 km, it can be assumed Maximum Credible Earthquake (MCE) – strongest possible earthquake, to be PGA ≈ 0.35 g. In accordance with Euro Code 8, (Eurocode 8, 2003; Wieland M., 2003), the time lasting of the earthquake excitation is in dependence of the PGA, and is adopted rounded at ± 5 s, and the vertical component of the acceleration is adopted at 2/3 оf the horizontal. In this analysis, for MCE with PGAX = 0.35 g, the time lasting is adopted t=25 s, and the vertical component is PGAy = 0.23 g. In line with the advanced practice (ICOLD 1989), the dynamic analysis in time domain is analyzed with several accelerograms: (а) synthetic – according to the norms in Macedonia (Paskalov T., Zelenović V., 1986), and (b) realistic scaled earthquakes – El Centro, 1940, Ulcinj, 1979. In the following are presented results of the dynamic response of the tailings dams, at action of synthetic earthquake (SIMQKE 1997) – generated according to the norms in Macedonia, fig. 3.

Figure 3. Time history (accelerogram) of the horizontal acceleration component for MCE earthquake with t2 = 25 s, PGAx2 = 0.35 g, Z2_MAC (synthetic, MK-norms)

In the analysis is applied equivalent linear model (Geo-Slope QUAKE/W, 2007), where shear modulus Gmax [kPa] is in dependence of mean effectives stress σ'm [kPa], according to the equation no.1:

= ( ) (1)

Exponent "n" in this relation increases by deformation increscent, and for materials in composition of the tailings dams is adopted n = 0.5. Modulus "K" for calculation of the maximal value of the shear modulus "Gmax", is elastic parameter, and therefore is not directly dependable of the strength parameters of the local materials (cohesions and internal friction), is estimated according to the following two procedures: First procedure for estimation of "K" regards the reference data (Kramer S.L., 1996.) according to the geomechanical description of the materials and numerous empiric relations (Salehi D., Mahin Roosta R., 2005) in dependence of the material type and compaction – expressed by coefficient of porosity, after authors: Kokusho and Esashi, 1981; Hardin and Black, 1968; Seed and Idriss, 1970. By the second procedure for calibration of "K" are used dependences between: (a) distribution of the mean effective stresses in internal part of the tailings dams from initial stress state, (b) registered values of the propagation velocities of the transversal seismic waves in the internal part of the tailings dam, obtained with refraction geophysical measurements (Aleksovski D, 2003.), and (c) empirical dependence between velocities of the transversal waves and elastic parameters of the materials, in accordance with the equation no. 2:

-0.4

-0.3

-0.2

-0.1

0.0

0.1

0.2

0.3

0.4

0 5 10 15 20 25

t [s]

Acc

[g]

PGA z2_mac

III- 58

Page 49: Design Optimization of Bauxite Residue Dam in Connection with

= ( / ) (2)

The approximate non-linearity and non-elasticity of the dynamic parameters of the local materials (fig. 4) is assumed according to the properties of the materials and experience dependences taken over from technical literature in domain of geotechnical earthquake engineering – by dynamic testing of materials: clay, sand, gravel, alluvium and crushed stone by the authors: Seed (1986), Idriss (1990), Vucetic and Dorby (1991), Kokusho (1980), and Tanaka (1987), as well and with comparison with the material parameters from dynamic testing of the tailings dams (Seid-Karbisi M., 2005).

Figure 4. Reduction of shear modulus G/Gmax and increase of damping ratio DR in dependence of the cyclic shear strains CSS

4. RESULTS OF THE DYNAMIC ANALYSIS

The dynamic response of the tailings dams, by application of equivalent linear analysis, is displayed by acceleration accelerograms (fig. 5 and 6) and response spectra of the accelerations (fig. 7 and 8) in the upstream edge of the dam crest, node with coordinates X=97.5m, Y=952 m.

Figure 5. Absolute horizontal acceleration, alternative no. 1 a[g]÷t[s], Z2_МАC, with PCA=0.447g

G /

Gm

ax R

atio

Cyclic Shear Strain (%)

0

0.2

0.4

0.6

0.8

1

0.001 1000.01 0.1 1 10

1

2

3

4

5

6D

ampi

ng R

atio

Cyclic Shear Strain (%)

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.001 1000.01 0.1 1 10

X-A

ccel

erat

ion

(g)

Time (sec)

-0.1

-0.2

-0.3

-0.4

0

0.1

0.2

0.3

0.4

0.5

0 10 20 30

III- 59

Page 50: Design Optimization of Bauxite Residue Dam in Connection with

Figure 6. Absolute horizontal acceleration, alternative no. 2 a[g]÷t[s], Z2_МАC, with PCA=0.574g

Figure 7. Response spectra for alternative no. 1, Sa[g]÷t[s], for DR=0.05, for acceleration in horizontal direction, Z2_MAC, in the foundation and in the crest

Figure 8. Response spectra for alternative no. 2, Sa[g]÷t[s], for DR=0.05, for acceleration in horizontal direction, Z2_MAC, in the foundation and in the crest

The estimation of the permanent deformations during excitation, caused by the internal dynamic forces, is done by application of Newmarks’ analysis (Geo-Slope SLOPE/W 2007; Paskalov T., 1985; Petkovski L., 2007.). In this analysis, based on the stability factor and dynamic internal forces, for each time period of the dynamic excitation, is calculated the mean acceleration for the total potential sliding body and dependence of the stability factor in function of the acceleration is determined. In case where the stability factor equals F=1.0, acceleration of fracture or creep is obtained. In case when the mean acceleration exceeds the creep acceleration, the mass would slide (fig. 9 and fig. 10).

X-A

ccel

era

tion

(g)

Time (sec)

-0.2

-0.4

-0.6

0

0.2

0.4

0.6

0 10 20 30

X-S

pect

ral A

ccel

erat

ion

(g)

Period (sec)

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

0 0.5 1 1.5 2

X-S

pect

ral A

ccel

erat

ion

(g)

Period (sec)

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

1.8

2

0 0.5 1 1.5 2

III- 60

Page 51: Design Optimization of Bauxite Residue Dam in Connection with

Figure 9. Time history of permanent displacements for critical sliding surface for alternative no .1, Z2_MAC, Xdisp = 0.381 m

Figure 10. Time history of permanent displacements for critical sliding surface for alternative no .2, Z2_MAC, Xdisp = 0.183 m

5. CONCLUSION

The engineering estimation on the degree of endangerment of the tailings dams in dependence of the value and geometry of the permanent displacement is based on the value of deformations at sand dam crest. Finally, at tailings dams no. 4 of mine Sasa, an earth sand dam, an uncontrolled emptying of the deposit lake would appear when: (1) the critical sliding surface of the slope (area with highest permanent displacements caused by earthquake), passes at least 2 m below the crest and if the value of the displacement is bigger than the crest width (b = 5 m) and/or (2) the settlements are bigger than the height from crest (952.0 masl) to the highest elevation of sludge in the lake (950.0 masl), apropos bigger then h=2.0 m.

The mechanism conditioning sliding of the downstream slope of the sand dam results from increase of the shear stresses at action of the dynamic inertial forces during earthquake action. If these stresses, in some zones, exceed the material shear resistance (most often in relatively shallow sliding surfaces), cause deformations, so the cumulative effect of these deformations is permanent deformation during the seismic excitation caused by increase of the tangential stresses. From the analysis of the dynamic stability of the downstream slope of the dam, at action of MCE, Z2-MK, it can be noticed that minimal value of the stability factor only in few cases is less then F=1.0. So at action of catastrophic earthquake small permanent displacements will appear (caused by increase of the shear stresses), that would be manifested as longitudinal cracks along the crest (or the slope) of the sand dam. These displacements, for action of earthquake Z2-MK, for alternative no. 2 (with downstream

Def

orm

atio

n

Time

0

0.1

0.2

0.3

0.4

0 10 20 30

Def

orm

atio

n

Time

0

0.05

0.1

0.15

0.2

0 10 20 30

III- 61

Page 52: Design Optimization of Bauxite Residue Dam in Connection with

construction method) are 38.1 cm, and for alternative no. 2 (with central construction method) has a value of 18.3 cm.

In the dynamic analysis is done approximate calculation of the displacements in the dam due to additional compaction of the stresses redistribution for the local materials – exposed on cyclic action. The maximal settlement from these displacements, for action of earthquake Z2-MK, for alternative no. 1 (with downstream construction method) is 66.4 cm, and for alternative no. 2 (with central construction method) has a value of 24.2 cm.

At earthquake action is possible appearance of liquefaction in the water saturated zones of the tailings sand in the dam (at eventual plugging of the drainage structure), by increase of the pore pressure up to dPw = 94.4 kPa (for alternative no. 1), and dPw = 12.1 kPa (for alternative no. 2) for action of earthquake Z2-MK. But, composition of the cross section of the tailings dams, conditioned by the adopted technology of advancement of the sand dam (in downstream direction) enables to attain the stability of the downstream slope, at action of the excess pressure at the liquefiable material – directly after the earthquake action. By the slow hydrodynamic process of dissipation of the excess pressure in the pores of the tailings sand (till the once again establishment of the initial steady regime), some displacements in the dam body can be expected, The maximal settlement by these displacements, at action of earthquake Z2-MK, for alternative no. 1 (with downstream construction method) is 37.4 cm, and for alternative no. 2 (with central construction method) has a value of 42.4 cm.

The general conclusion from the dynamic analysis of tailings dams Sasa no. 4 with crest elevation 952.0 masl would be that heterogeneous medium, with adopted geometry and distribution of the materials, possess the required seismic resistance, and there is no disruption of the dynamic stability of the sand dam – not during the earthquake excitation, nor immediately after its termination. By the displacements caused from catastrophic earthquake (value of 141.9 cm for alternative no. 1 or 84.9 cm for alternative no. 2) the height of 2 m is not exceeded (from dam crest 952.0 masl till the highest elevation of the tailings sludge in the lake at 950.0 masl), so there is no risk for rapid leakage of the sludge from the deposit lake.

REFERENCES

Aleksovski D., (2003). „Defining of dynamic properties of the materials for embankment dams by geophysical testing in natural scale“, PhD dissertation, IZIIS, Skopje

Daghigh Y., Davoudi M.H., Shokri A.(2005) "Nonlinear dynamic analysis of earth dams using Diana code: (a case study in Alavian dam)", 73rd Annual Meeting of ICOLD, Tehran, IRAN, Paper No.:160-W4,

Eurocode 8, (2003), Design of structures for earthquake resistance, Doc CEN/TC250/SC8/N335, DRAFT No 6, Brussels

Geo-Slope QUAKE/W, 2007."Dynamic modeling", Geo-Slope SLOPE/W 2007. "Stability analysis", GEO-SLOPE International Ltd., Calgary, Alberta, Canada

ICOLD (1989), Selecting Seismic Parameters for Large Dams, Guidelines, Bulletin 72, Committee on seismic aspects of dam design,

Kramer S.L., (1996). "Geotechnical Earthquake Engineering", Prentice Hall, New Jersey, USA

Matsumoto N., ..., (2005). "Analysis of strong motions recorded at dams during earthquakes", 73rd Annual Meeting of ICOLD, Tehran, IRAN, Paper No.: 094-W3

III- 62

Page 53: Design Optimization of Bauxite Residue Dam in Connection with

Paskalov T., (1985). "Earthquake induced deformations on earth-fill and rock-fill dams", International Journal "Soil Dynamics and Earthquake Engineering", Vol.4m No.1, CML Publications, UK, p35-42

Paskalov T., Zelenović V., 1986., "Normative of technical standards for design and computation of engineering structure in seismic areas", Belgrade

Petkovski L., (2005). “Dynamic Analysis of a Rock-filled Dam with Clay Core“, International Conference IZIIS 40 EE-21C, Skopje/Ohrid Macedonia, Proceedings, CD-ROM

Petkovski L., (2007). “Seismic Analysis of a Rock-filled Dam with Asphaltic Concrete Diaphragm“, 4th International Conference on Earthquake Geotechnical Engineering, Thessaloniki, Greece, CD-ROM;

Petkovski L., Ilievska F., (2010.08) “Comparison of Different Advanced Methods for Determination of Permanent Displacements of Tailings Dams in Earthquake Condition“, 14th Europian Conference on Earthquake Engineering, Ohrid, R.Macedonia, paper #1511, CD-ROM;

Petkovski L., Paskalov T., 2003. “Comparison of Dynamic Analyses of Embankment Dams by Using Lumped Mass Method and Finite Element Method“, International Conference in Earthquake Engineering - Skopje Earthquake - 40 Years of European Earthquake Engineering, Skopje, Ohrid, R.Macedonia, Proceedings, CD-ROM

Petkovski L., Tančev L., 2003. “Dynamic Analysis of a Rock-filled Dam with Geosynthetic Screen”, International Conference in Earthquake Engineering - Skopje Earthquake - 40 Years of European Earthquake Engineering, Skopje, Ohrid, Republic of Macedonia, Proceedings, CD-ROM,

Petkovski L., Tančev L., Mitovski S., (2007). “A contribution to the standardization of the modern approach to assessment of structural safety of embankment dams", 75th ICOLD Annual Meeting, International Symposium “Dam Safety Management, Role of State, Private Companies and Public in Designing, Constructing and Operation of Large Dams”, St.Petersbourg, Russia, Proceedings p.66, CD-ROM

Petkovski L., Tančev L., Mitovski S., (2013) "Comparison of numerical models on research of state at first impounding of rockfill dams with an asphalt core", International symposium, Dam engineering in Southeast and Middle Europe - Recent experience and future outlooks, SLOCOLD, Ljubljana, R.Slovenia, ISBN 978-961-90207-9-1, Proceedings, 106-115

Salehi D., Mahin Roosta R., (2005). "Evaluation of different methods for dynamic stability analysis of embankment dams", 73rd Annual Meeting of ICOLD, Tehran, IRAN, Paper No.:063-W4,

Seid-Karbisi M., (2005). "Seismic stability of embankment dams", 73rd Annual Meeting of ICOLD, Tehran, IRAN, Paper No.: 113-W4

Seid-Karbisi M., Byrne P.M., (2004). “Embankment dams and earthquakes”, Hydropower & Dams, Issue Two

SIMQKE 1997, manual of computer program for simulation of acceleration time-history of synthetic earthquakes, from target response spectrum

Wieland M., (2003). "Seismic Aspects of Dams", General Report of Question 83, ICOLD, Montreal, Canada

Wieland M., Malla S., (2002), “Seismic Safety Evaluation of a 117 m High Embankment Dam Resting on a Thick Soil Layer”, 12th European Conference on Earthquake Engineering, London, Paper Reference 128

III- 63

Page 54: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Assessment of static and seismic stability of

Kumtor’shdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkj

f fffffjfjjfkkfjjj

Kumtor’s gold mine tailings dam

2(14pt)

in Kyrgyz Republic

B.A. Chukin & R.B. Chukin Institute of Geomechanics and Development of Mineral Resources (IGDMR), Bishkek, Kyrgyz Republic

[email protected]

ABSTRACT: Kumtor gold mine is situated in the Kyrgyz Republic in Central Tien Shan Mountains at an altitude 4000 meters in permafrost area. Construction and exploitation of the tailings dam was started in

1995. In 1999 the displacement of the dam to downstream side was detected. The dam height was

20 meters. Analysis of monitoring data showed that displacement took place in ice rich loamy layer in the foundation on 4 meters depth. To stop the displacement the decision was made to excavate

loamy layer beyond downstream and change it by construction shear key made of macro

fragmental soil. The depth of shear key was 5 meters. In the following the monitoring data showed

that tailings dam continue to move on underlying soils. The additional geological investigation was done. It showed that more solid soils were located on the depth from 10 to 12 meters. Numerical

modeling of the dam was made in FLAC codes. The methodology of displacement stoppage was the

same. Rheological parameters of the soils in numerical model calibrated on the basis of back analysis. Forecast calculations were made to 2016 when the dam height would be 42.7 meters.

Also the assessment of seismic stability was made with consideration of layered foundation.

Calculation in FLAC codes showed the influence of soils condition. Peak ground acceleration was increased. Worked out measures to stop the tailings dam displacement was accomplished in the

period from 2006 to 2010. The new monitoring data of displacement confirm the efficient of the

taken actions.

1. INTRODUCTION

1.1. Overview

The tailings dam is located in the bed of Ara-Bel River. Water of the river was redirected

around the tailings dam through upper bypass canal with returning to the former bed below

the dam. The tailings dam was designed with filling method of wastes lying. Dam filling

was started in 1995. The dam is raised by stages to the downstream side. The dam body is

filled with macro fragmental soil. The upstream and downstream sides are formed with

gradient 1:3. There is impervious screen with the length 100 meters which is lying along

the upstream and the bottom of reservoir. It’s made of polyethylene film of high density

with thickness 1.5 millimeters. General view of the dam is shown in Figure 1.

III- 64

Page 55: Design Optimization of Bauxite Residue Dam in Connection with

Figure 1. Kumtor tailings dam

1.2. Description of the Problem

In 1998, holes for installation inclinometers were drilled. At that time maximum height of

the dam was 20 meters. Data of field observations showed that dam was moving to

downstream side. Allocation of horizontal offset showed that displacement was caused by

ice rich loamy layer in the foundation. In order to stop displacement the decision was made

to remove loamy layer beyond downstream side and change it by construction of shear key

from macro fragmental soil. In 2003, works for arrangement of shear key were performed.

At that time dam height was 24.7 meters. Trench for shear key with depth 5 meters and

slope ratio 1:1 had a length about 20.5 meters. Shear key depth was determined on the

basis of analysis of horizontal offsets with consideration for meter long incut in soil which

had no any displacement. Cantledge with 5 meters height was dumped on the shear key.

Soil for organization of shear key, cantledge and dam body was selected from one pit. In

the following the data of field observations showed that the measures which had been done

did not lead to stoppage of the dam displacement. Temporary group of experts from

Canadian consulting firm BGC Engineering INC and IGDMR was created to solve this

problem. The following are results of IGDMR. Tailings dam numerical model was

performed in FLAC codes as a creep model. Regulatory requirements acting in Kyrgyz

Republic about assessment of stability based on the value of factor of safety. In this case

the factor of safety was calculated after creep modeling had been finished.

2. NUMERICAL MODELING

2.1. Design and Calibration of Numerical Model

Numerical modeling was performed using the program FLAC (Itasca 2011). The important

stage of numerical modeling is selection of soil model, describing the relation between

creep deformation and relaxation of stress. In the result of analysis of different models for

description of rheological processes in soil, Norton’s power law dependence was selected.

Stress-strain analysis with consideration of rheological processes was based on the

comparison of calculated displacements and monitoring data. Monitoring of displacement

was made on the basis of inclinometers. Figure 2 (a) describes observed displacements

according to inclinometer INC98-1 in period from 21.12.01 to 13.08.05.

III- 65

Page 56: Design Optimization of Bauxite Residue Dam in Connection with

Figure 2. (a) INC98-1 inclinometer data; (b) allocation of deformation shift in loamy layer

The depth in meters from the dam crest is on vertical axis and total displacements in meters

are on horizontal axis. The figure shows that the most intense displacements occur between

22 meters and 24 meters marks. Original ground level corresponds to 20 meters mark.

Loamy layer has a various width from 6 to 10 meters. The largest deformation shift is

observed in upper part of it within the limits of 2 meters. The roof of loamy layer is

situated at a depth of 2 meters from ground surface. All shift indexes above this mark are

virtually the same. That means that the dam body and two meters of natural soil above the

loamy layer have lesser deformation shift. In order to find out on which depth and with

what intensity deformation happens, schedule of inclinometer knees was built relative to

each other and provided on Figure 2 (b). This figure shows that the largest deformation

shift is registered at a depth from 2.5 to 4 meters (mark 22.5 - 24 meters). The most

deformable layer has width about 1.5 meters. Below 4 meters (mark 24.0 meters)

deformation shift drops evenly. Formation of rheological model is based on separation of

calculated rheological layers within the limits of whole loamy layer with a capacity of 9

meters. In view of the fact that shifts in loamy layer occurred before installation of INC98-

1, it is necessary to try to restore accumulated shifts from the beginning of the dam

construction. Difference in shifts between layers defines by the value of deformation and

this is the most important for assessment of resistance. Figure 3 provides restored shifts in

Figure 3. Horizontal displacement of loamy layers at depth from 2.0 to 4.5 meters based on INC98-1

(a) (b)

III- 66

Page 57: Design Optimization of Bauxite Residue Dam in Connection with

separated layers of loamy layer on the basis of monitoring data. The results of layer shift

approximation with coefficient of determination R2 = 0.995 are also showed at Figure 3.

Layer shift at the stage of the dam upbuilding during the period from 1999 to 2005 occur in

a linear fashion. Model calibration was carried out by variation of rheological parameters

А and n according to Norton’s method. In this case n parameter is considered as constant

and equal 3. The most exact approximation of the results was obtained by rheological

model consists of six calculated layers which are provided on Figure 4. Figure 5 displays

comparison of calculated displacement and observation data according to INC98-1 to 2004

inclusively. The calculation data matched well with monitoring data obtained on basic

shifting layers, situated at a depth 22.5, 23.0 and 23.5 meters. Calibration test of 2004 was

associated with the fact that in 2008 shifts have some departure from linear fashion.

Figure 4. Calculated layers of dam foundation for 2004

Figure 5. Comparison of numerical results with monitoring data according to INC98-1 for 2004

The correction of А index in the middle layer in 2004 allowed reaching the optimal

approximation. In view of the fact that the last model hadn’t correction of A index, it can

believed that all the following calculations have prognostic character.

2.2. Forecast of Displacement and Stability Assessment

The construction of the dam will be finished in 2016. Figure 6 displays the results of

horizontal displacement forecast by layers according to INC98-1 for 2016 inclusively.

Loamy layer, outspreading under the dam body and shear key of 2003 cannot be removed.

FLAC (Version 6.00)

LEGEND

19-Jan-13 13:49

step 33360

Creep Time 2.8383E+08

Table Plot

21-22 m inc98-1

22.5 m inc98-1

23.0 m inc98-1

23.5 m inc98-1

24.0 m inc98-1

24.5 m inc98-1

21.0 m * #3

22.0 m * #4

22.5 m * #5

23.0 m * #6

23.5 m * #7

24.0 m * #8

24.5 m * #9

5 10 15 20 25 30

(10 ) 07

0.500

1.000

1.500

2.000

2.500

3.000

3.500

4.000

(10 )-01

JOB TITLE : Correlation X-disp Inc98-1 2004

IGDMR

Kyrgyz Republic

III- 67

Page 58: Design Optimization of Bauxite Residue Dam in Connection with

The key feature in character of horizontal displacement allocation is that the shifts in

loamy layer under the dam areas continue, and shifts in areas where it was removed stop.

Figure 6. Forecast results of horizontal displacements of the layers for 2016

Figure 7 provides total horizontal displacement for the end of 2016. The largest horizontal

offsets concentrated in the area where loamy layer cannot be removed. In this area total

horizontal offsets to the end of 2016 are less than 80 centimeters. In the area where loamy

layer was removed and shear key was built, horizontal offsets are less than 20 centimeters.

It points to the fact that stopping measures for dam shifting caused by rheological

processes in loamy layer are effective. The question how to calculate factor of safety for a

Figure 7. Horizontal displacement for the end of 2016

a model of geotechnical object with rheological processes remains open. For evaluation of

overall stability we use the following method. The main differential characteristic from

early performed calculation of dam stability is that now we take into account alteration of

soils strength properties for loamy layer from deformation shift value, obtained as a result

of rheological process modeling. In other words, stability of the dam is evaluated with

consideration of time effect. The basis of coefficient of stability calculation has two

principal points:

If a structure is a subject to continuous rheological processes, then the moment of

beginning of stability loss will be defined not by time rheological processes

duration, but formation of surface of failure, along which soil reached critical

deformation;

FLAC (Version 6.00)

LEGEND

19-Jan-13 14:12

step 72156

Creep Time 6.6226E+08

Table Plot

21-22 m inc98-1

22.5 m inc98-1

23.0 m inc98-1

23.5 m inc98-1

24.0 m inc98-1

24.5 m inc98-1

21.0 m * #3

22.0 m * #4

22.5 m * #5

23.0 m * #6

23.5 m * #7

24.0 m * #8

24.5 m * #9

10 20 30 40 50 60

(10 ) 07

1.000

2.000

3.000

4.000

5.000

6.000

7.000

(10 )-01

JOB TITLE : Correlation X-disp Inc98-1 2016

IGDMR

Kyrgyz Republic

FLAC (Version 6.00)

LEGEND

19-Jan-13 14:12

step 72156

Creep Time 6.6226E+08

-2.103E+02 <x< 2.843E+02

3.683E+02 <y< 8.630E+02

X-displacement contours

0.00E+00

1.00E-01

2.00E-01

3.00E-01

4.00E-01

5.00E-01

6.00E-01

7.00E-01

8.00E-01

Contour interval= 1.00E-01

Boundary plot

0 1E 2

3.750

4.250

4.750

5.250

5.750

6.250

6.750

7.250

7.750

8.250

(*10 2̂)

-1.750 -1.250 -0.750 -0.250 0.250 0.750 1.250 1.750 2.250 2.750

(*10 2̂)

JOB TITLE : X-disp 2016

IGDMR

Kyrgyz Republic

III- 68

Page 59: Design Optimization of Bauxite Residue Dam in Connection with

As rheological processes of deformation shift in different points of structure are

various, overall stability of structure shall be calculated on the basis of deformation

shift distribution with determination of areas where deformation reached limit

values.

Zaretskiy points out that for soils there is a critical strain of form alteration. On the basis of

experiments with sand clay for Nurekskaya dam strain intensity was about 14%. This

circumstance for assessment of resistance upon calculation of creeping was realized as

follows. If it’s necessary to evaluate stability of the dam in certain period of time, then we

define the area in loamy layer, in which the amount of deformation reached limit value.

The limit value of deformation shift is 13%. This value was selected as the smallest among

all values provided in literary sources. It is accepted that this area doesn’t resist to shifting.

In this area strength properties cohesion and friction angle are set to zero. Special function

was developed in FISH programming language for exact area separation where soil doesn’t

resist shifting and maximum deformation reached value of 0.13. Figure 8 (a) provides

picture of maximum deformation shifts for 2016. The largest deformation shifts

concentrated in loamy layer. Figure 8 (b) as an example, describes friction angle

distribution for the same geometry after the function was used. After that we used standard

procedure for factor of safety calculation proposed by Dawson and Roth 1999. The

minimum factor of safety value is 1.36 for 2016 dam body. Note that shear-strain rate

contours doesn’t have exit to free surface and doesn’t form closed region.

Figure 8. (a) Maximum deformation shifts; (b) friction angle distribution

Kyrgyz Republic is a seismic active country. Seismic stability assessment of the dam was

based on dynamic theory. It was made on the basis of calculated deformations analysis.

The limit state of the dam is characterized by the presence of damage (vertical crest

displacement, cracks etc.) which can lead to disturbance of the dam with following

overflow of the pulp. We selected two criteria of seismic stability. The first criterion is

vertical dam crest displacement. Vertical crest displacement during earthquake must not

exceed reserve between the crest and the level of the water in upstream. The second

criterion is connected with shear-strains. This criterion is based on comparison of limit

shear-strains and shear-strains which evolving in dam body during earthquake. The

formation of surface of failure is related with the increase of plastic shear-strain increments

to value 2 – 5 %. Slope failure occurs when surface of failure cross the dam body and has

an exit to slope face. Thus, for overflow of the pulp this exit should be on upstream under

the water level. The earthquake motion is considered to occur when the reservoir level is at

fool pool. Pore-pressure calculation is important part, it determine pore-pressure

distribution on the upstream side of the dam and in the soils corresponding to the reservoir

elevation. Figure 9 displays the pore-pressure distribution and phreatic surface location

FLAC (Version 6.00)

LEGEND

19-Jan-13 14:14

step 72156

Creep Time 6.6226E+08

-6.927E+01 <x< 2.077E+02

4.772E+02 <y< 7.541E+02

Max. shear strain increment

0.00E+00

5.00E-02

1.00E-01

1.50E-01

2.00E-01

2.50E-01

Contour interval= 5.00E-02

Extrap. by averaging

Boundary plot

0 5E 1

5.000

5.500

6.000

6.500

7.000

7.500

(*10 2̂)

-0.250 0.250 0.750 1.250 1.750

(*10 2̂)

JOB TITLE : ssi 2016

IGDMR

Kyrgyz Republic

FLAC (Version 6.00)

LEGEND

19-Jan-13 16:29

step 72156

Creep Time 6.6226E+08

-8.630E+01 <x< 2.188E+02

4.712E+02 <y< 7.763E+02

friction

0.000E+00

1.500E+00

2.400E+01

3.500E+01

3.800E+01

4.400E+01

4.500E+01

Boundary plot

0 5E 1

5.000

5.500

6.000

6.500

7.000

7.500

(*10 2̂)

-0.500 0.000 0.500 1.000 1.500 2.000

(*10 2̂)

JOB TITLE : Friction 2016

IGDMR

Kyrgyz Republic

(a) (b)

III- 69

Page 60: Design Optimization of Bauxite Residue Dam in Connection with

through the dam and foundation at steady state. The area where the dam was built

according to the confirmed “Map of seismic zoning of Kyrgyz Republic” classified as zone

Figure 9. Pore-pressure distribution and phreatic surface

with 8 points of intensity and repeatability 1 earthquake per 500 years. In the reports on

feasibility study of the project there is an analysis of Kumtor mine seismic ground motion.

This analysis based on methodology of evaluation of such factors as location of active

faults and their parameters and distance from these faults and construction site. As a result

peak ground acceleration for seismic analysis has a value 0.3g. For understanding the

influence of weak ice rich loamy layer on seismic stability the modeling of the foundation

was made. On the first stage the deconvolution analysis that is performed to obtain the

appropriate input motion was made without weak layer. On the second stage weak layer

was set. The dynamic simulation was made with three strong motions, one local

(Suusamyr) and two global (Kobe, CapeRio). The results of simulation with Kobe strong

motion earthquake are described further. It has duration 40.88 seconds and several high

peaks. The soil conditions of the dam foundation lead to dynamic amplification. Peak

ground acceleration increased from 0.3g to 0.34g. Also the character of frequencies was

changed. The Figure 10 displays acceleration time histories on the surface with (black line)

and without (red line) weak loamy layer. The Figure 11 displays power spectrum of

accelerations in three different locations of the model. For the better reading power

spectrum was converted from FLAC to Excel. Red line indicates power spectrum of input

Figure 10. Acceleration time histories on the surface of the foundation

Kobe acceleration. The dominant frequency is approximately 0.6 Hz, the highest frequency

component is less than 8 Hz, and the majority of the frequencies are less than 6 Hz. The

blue line is a power spectrum of acceleration on foundation surface. The highest frequency

FLAC (Version 7.00)

LEGEND

20-Feb-13 22:21

step 359600

Flow Time 7.0497E+07

3.155E+02 <x< 8.489E+02

3.357E+03 <y< 3.890E+03

Pore pressure contours

0.00E+00

1.00E+05

2.00E+05

3.00E+05

4.00E+05

5.00E+05

6.00E+05

7.00E+05

8.00E+05

Contour interval= 1.00E+05

Phreatic surface

Contour interval= 5.00E-01

Minimum: 0.00E+00

Maximum: 5.00E-01

Boundary plot

0 1E 2

3.400

3.500

3.600

3.700

3.800

(*10 3̂)

3.500 4.500 5.500 6.500 7.500

(*10 2̂)

JOB TITLE : PP and PS S2 2013

LSGO

FLAC (Version 7.00)

LEGEND

26-Feb-14 19:45

step 706397

Flow Time 7.0497E+07

Dynamic Time 4.0880E+01

3.152E+02 <x< 8.489E+02

3.357E+03 <y< 3.890E+03

Original Surface

Y-axis :

31 X acceleration( 358, 44)

X-axis :

100 Dynamic time

5 10 15 20 25 30 35 40

-2.000

-1.000

0.000

1.000

2.000

3.000

JOB TITLE : Acc_WI

LSGO

Kyrgyz Republic

FLAC (Version 7.00)

LEGEND

26-Feb-14 19:44

step 326299

Dynamic Time 4.0880E+01

3.155E+02 <x< 8.489E+02

3.340E+03 <y< 3.874E+03

HISTORY PLOT

Y-axis :

5 X acceleration( 151, 44)

X-axis :

1 Dynamic time

5 10 15 20 25 30 35 40

-2.000

-1.000

0.000

1.000

2.000

JOB TITLE : Acc_WO

LSGO

Kyrgyz Republic

III- 70

Page 61: Design Optimization of Bauxite Residue Dam in Connection with

is 0.6 Hz and the second peak is 3.6 Hz. The black line is power spectrum of acceleration

on the crest of the dam. The highest frequency is 0.6 Hz and the second peak is 2.8 Hz.

Displacement of the dam after 40.88 seconds is primarily concentrated along upstream

slope. This is shown in the Figure 11. The maximum displacement is 50 centimeters.

Figure 10. Power spectrum of accelerations

Downstream side has a less value of the displacement due to the shear key efficiency.

Figure 11. Horizontal displacement contours

Figure 12 shows the plot of horizontal (green line) and vertical (blue line) displacements of

the crest. The maximum value of horizontal crest displacement is 42 centimeters and

vertical 3.3 centimeters. The value of maximum shear-strain occurred during seismic

loading is stored with special FISH function. The Figure 13 displays the maximum shear-

strain increment contours after 40.88 seconds. The maximum value of shear-strain is 50%

in weak loamy layer. This level of deformations shows that loamy layer reached the limits

and it doesn’t resist shifting anymore. The result of calculation showed that the condition

of slope failure, when the formed surface of failure crossed the dam body and had an exit

on slope face did not happen. None of the selected criteria of dam failure took place.

Seismic stability of the dam was confirmed.

FLAC (Version 7.00)

LEGEND

20-Feb-14 13:03

step 565409

Flow Time 7.0497E+07

Dynamic Time 2.3950E+01

3.152E+02 <x< 8.489E+02

3.357E+03 <y< 3.890E+03

X-displacement contours

-4.00E-01

-3.00E-01

-2.00E-01

-1.00E-01

0.00E+00

1.00E-01

2.00E-01

3.00E-01

4.00E-01

5.00E-01

Contour interval= 1.00E-01

Boundary plot

0 1E 2 3.400

3.500

3.600

3.700

3.800

(*10 3̂)

3.500 4.500 5.500 6.500 7.500

(*10 2̂)

JOB TITLE : X-Disp

LSGO

Kyrgyz Republic

III- 71

Page 62: Design Optimization of Bauxite Residue Dam in Connection with

Figure 12. Crest dam displacement

Figure 13. Maximum shear-strain increment contours after 40.88 seconds of seismic loading

REFERENCES

Ye.N. Bellendir, D.A. Ivashintsov, D.V. Stefanishin, O.M. Finagenov, S.G. Shulman

(2003): Probabilistic Methods of Assessment of Reliability of Soil Hydro-

Engineering Structures, St. Petersburg, Russia Federation.

C. Lomnitz and E. Rosenblueth (1976): Seismic Risk and Engineering Decisions, New

York, USA.

L. Suklje (1976): Rheological Aspects of Soil Mechanics, London, UK.

J.K. Zaretskiy and V.N. Lombardo (1983): Static and Dynamic of Soil Dams, Moscow,

USSR.

Seed, H. Bolton, and I. M. Idriss (1970): Soil Moduli and Damping Factors for Dynamic

Response Analysis, California, USA.

Seed, H. B., and I. Idriss (1969): Influence of Soil Conditions on Ground Motion During

Earthquakes, Journal of Geotechnical Engineering Division, ASCE, Vol. 95, pp. 99-

137, California, USA.

K.Ishihara (2006): Soil Behaviour in Earthquake Geotechnics, Tokyo, Japan.

L.H. Mejia and E.M. Dawson (2006): Earthquake deconvolution for FLAC, 4th

International FLAC Symposium on Numerical Modeling in Geomechanics, Itasca

Consulting Group, Inc., Minneapolis, USA.

International Commission on Large Dams (ICOLD) (1995): Tailings Dams and Seismicity,

Bulletin 98, 21-43 pp.

FLAC (Version 7.00)

LEGEND

27-Feb-14 13:03

step 706397

Flow Time 7.0497E+07

Dynamic Time 4.0880E+01

3.152E+02 <x< 8.489E+02

3.357E+03 <y< 3.890E+03

HISTORY PLOT

Y-axis :

52 reldispx (FISH)

53 reldispy (FISH)

X-axis :

100 Dynamic time

5 10 15 20 25 30 35 40

0.000

0.500

1.000

1.500

2.000

2.500

3.000

3.500

4.000

(10 )-01

JOB TITLE : Crest_Disp

LSGO

Kyrgyz Republic

FLAC (Version 7.00)

LEGEND

27-Feb-14 13:00

step 706397

Flow Time 7.0497E+07

Dynamic Time 4.0880E+01

3.152E+02 <x< 8.489E+02

3.357E+03 <y< 3.890E+03

EX_10 Contours

0.00E+00

1.00E-01

2.00E-01

3.00E-01

4.00E-01

5.00E-01

Contour interval= 1.00E-01

Boundary plot

0 1E 2

3.400

3.500

3.600

3.700

3.800

(*10 3̂)

3.500 4.500 5.500 6.500 7.500

(*10 2̂)

JOB TITLE : Max_ssi

LSGO

Kyrgyz Republic

III- 72

Page 63: Design Optimization of Bauxite Residue Dam in Connection with

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6

TH , 2014

Geotechnical Performance Evaluation of Sediment Dam

A Case Study on Fiona Dam at PT Vale Indonesia Tbk

Wiyatno Haryanto PT Vale Indonesia Tbk, Sorowako, Indonesia

[email protected]

Anom Prasetyo PT Vale Indonesia Tbk, Sorowako, Indonesia

ABSTRACT: This paper is intended to evaluate geotechnical performance of Fiona Dam as a sediment dam in terms of stability against seismicity since water filling stage until operational period. The dam is

located in the area of the mining operations of PT Vale Indonesia Tbk at Sorowako, East Luwu

Regency, South Sulawesi Province, Indonesia, constructed to impound solids of waste material (disposal) and also act as filter function before the mine effluent released to the downstream

waterbody. In this review, the analyses are referring to the detailed engineering design, survey &

monitoring serial data, seismicity calculation, and previous geotechnical site investigation report

through simulation and data analysis approaches.

Keywords: Sediment dam, solids of waste material, seismicity, peak ground acceleration (PGA),

geotechnical slope stability.

1. INTRODUCTION

The main purpose of the Fiona Dam construction as a sediment impoundment is to

containment of solids of fine-grained sediments or waste materials (disposal) by allowing

surface water passing the dam body (overtopping and seepages) and released to the

waterbody as mine effluent that must be complying with an environment quality standard

as regulated by Government of Republic of Indonesia, Ministry of Environment in

PERMEN-LH No.9/2006 regarding effluent quality standard of nickel ore mining industry

at eleven parameters such as TSS (total suspended solid), Cr+6

(chromium hexavalent),

Crtotal (total chromium), and some other metal minerals. [Blank line 10 pt]

Solid particles is derived from the operation of a nickel processing plant, mining face,

disposal, slag dump, revegetation and some exposed area in Anoa Hill in which transported

by surface runoff. Through the dam structure, sediment load transported by runoff contains

of suspended solid and floating particles shall be settling in the reservoir, thus clean water

shall be passing the dam structure with the whole parameters comply with the environment

quality standard. [Blank line 10 pt]

III- 73

Page 64: Design Optimization of Bauxite Residue Dam in Connection with

Fiona Dam had been constructed in End of 2001, located on the position of 2°35’13” South

Latitude and 121°25’30” East Longitude with maximum elevation head about 22 m height,

design capacity 13,000,000 m3 with probable maximum flood 632 m

3/s, flood level on elv.

+396 m amsl and catchment area about 18.6 km2, dedicated to serve mining activities in

life of mine until 2035. The dam structure is categorized as rock-fill dam with drainage

core ripped slag and geotextile filter in front of core face. The dam crest is on elv. +397 m

amsl, 12 m width, 185 m length, upstream slope 40%, downstream slope 10%, and

spillway level on elv. +395 m amsl and 100 m width with flow capacity about 250 m3/s.

[Blank line 10 pt]

Layout of Fiona Dam is shown in the figure below; all of water effluents from mining

activities are trapped by some sediment ponds such as Diana Pond, Delaney Pond, and

Anoa Pond to settling solids before released to the reservoir. [Blank line 10 pt]

Figure 1. Aerial Photograph of Fiona Dam and Vicinity

[Blank line 10 pt]

Figure 2. Crest and Spillway of Fiona Dam

[Blank line 10 pt]

III- 74

Page 65: Design Optimization of Bauxite Residue Dam in Connection with

Figure 3. Downstream Slope of Fiona Dam

[Blank line 10 pt]

Figure 4. Water Reservoir of Fiona Dam

[Blank line 10 pt]

[Blank line 10 pt]

2. DETAILED ENGINEERING DESIGN [Blank line 10 pt]

To evaluate technical performance of Fiona Dam referred to as a sediments dam; material

specification, detailed drawings, and standards are referring to technical report explained

below. [Blank line 10 pt]

2.1. Material Specification [Blank line 10 pt]

Fiona Dam is a rock-fill dam without impermeable core layer, constructed with rocky

material taken from quarry area consisting of peridotite rocks. Borrow material location is

relatively close to the dam site. Due to the dam is not equipped with impermeable core

layer, geotextile drainage is acting to replace it and as filter of granular particles passing

into the dam body. Material specification of the dam body is described below:

III- 75

Page 66: Design Optimization of Bauxite Residue Dam in Connection with

� Riprap rock material is specified as selected boulder hard rock (size 450 mm, 600 mm

up to 1,000 mm), placed at upstream and downstream slope face as protection against

wave, abrasion, and scouring.

� Filter layer consists of three (3) vertical filter layers located in centerline of the dam

made of graded rock passing 40 mm, 300 mm and 150-450 mm. The filter layer surface

is coated with a fabricated geotextile filter layer to avoid fine materials passing into the

drainage layer that can decreases drainage capacity (clogging), thus clean water will

flow out of the dam body.

� Drainage core ripped slag material placed both on centerline and downstream shoulders

of the dam body, has function to drain water seepage from the dam body.

[Blank line 10 pt]

2.2. Detailed Drawing [Blank line 10 pt]

Detailed drawing of Fiona Dam is shown in the following cross section below.

Horizontal Drainage Ripped Slag

Fi lter Geotextil e

Maxi mum Water Level

Drainage Core Ripped Slag

Rockfill Ri prap

Jointed Peridotite

Horizontal Distance

0 20 40 60 80 100 120 140 160 180 200 220 240

350

360

370

380

390

400

410

420

430

0 20 40 60 80 100 120 140 160 180 200 220 240

Act

ua

l E

lev

ati

on

350

360

370

380

390

400

410

420

430

Figure 5. Detailed Drawing of Fiona Dam

[Blank line 10 pt]

The original base floor as bearing layer is a slightly weathered and jointed peridotite rock

with consistency hard to very hard. The dam body structure is laid on floor level from elv.

+375 m until reaching top crest on elv. +397 m. At centerline of the dam body, a drainage

core ripped slag covered by filter geotextile are constructed layer by layer reaching elv.

+395 m. A horizontal drainage ripped slag of 2 m thickness are constructed sloping down

parallel to final downstream slope. [Blank line 10 pt]

2.3. Geotechnical Parameter [Blank line 10 pt]

Geotechnical parameters are modeled in drained condition as critical state since water level

at front face higher and influencing stability of the dam body. The geotechnical parameters

are shown in the following Table 1. [Blank line 10 pt]

Table 1. Geotechnical Parameter of Respective Materials

Material Specification

Bulk Unit

Weight

Friction

Angle Cohesion

(kN/m3) (degree) (kPa)

Jointed Peridotite Rock 27 33 10

Rock-fill Riprap 26 38 20

Drainage Core Ripped Slag 25 33 0

Horizontal Drain Ripped Slag 25 33 0

III- 76

Page 67: Design Optimization of Bauxite Residue Dam in Connection with

3. SEISMICITY [Blank line 10 pt]

Seismicity in the Indonesian Archipelago is quite high and about 10% of the whole

seismicity in the world. The epicenters were abundant in the young tectonic belt between

the continental shelf of South Asia and Australia. The belt starts from Sumatra-Java-Banda

turned to the northward through Sulawesi and Philippines. Generally, shallow epicenters

and its position are concentrated in western part of Sumatra, southern and eastern part of

Java, Banda Trench, western part of Papua and some territory between North Sulawesi,

Halmahera and Philippines. [Blank line 10 pt]

As we know Indonesia is prone to earthquakes, as it is the convergence of the Euroasia, the

Indo-Australia, the Pacific, and the Philippine Tectonic Plates. Fiona Dam that located in

Sulawesi Island is part of Pacific Tectonic Plate lines and Philippine Plate that's why

identification and evaluation of seismic hazard is very important for the dam design. [Blank line 10 pt]

There are several active fault systems on the Sulawesi Island including Matano Fault that

leads towards the bottom of Lake Matano adjacent to Fiona Dam. Sorawako that located

on the shores of the Lake Matano is a place where some frequent small earthquakes

emerge every few months. Thus, we have to careful in determining seismic coefficient for

the dam design. [Blank line 10 pt]

3.1. Determination of Peak Ground Acceleration [Blank line 10 pt]

In pre-design stage, determination of peak ground acceleration (PGA) for Fiona Dam on

horizontal direction is using some sources such as Indonesian Earthquake Study (1981),

NGDC/USGS Earthquake Catalogue (1999), and Golder Associates (1996). Results of the

peak ground acceleration (PGA) probability of Fiona Dam which is based on some sources

are mentioned above can be seen in Table 2. [Blank line 10 pt]

Table 2. Peak Ground Acceleration, PGA (g)

Source Return Periods (Years)

20 100 200 475 1000 2000

IES 1981 0.07 g 0.18 g 0.23 g 0.28 g 0.33 g 0.40 g

NGDC/USGS 1999 0.08 g 0.16 g 0.21 g 0.28 g 0.36 g 0.44 g

Golder 1996 0.03 g 0.18 g 0.28 g 0.39 g 0.48 g 0.58 g

Vale 2013 0.47 g 0.59 g 0.78 g

[Blank line 10 pt]

Calculation of maximum credible earthquake (MCE) is also based on Indonesian

Earthquake Study (1981), NGDC/USGS Earthquake Catalogue (1999), Golder Associates

(1996), which can be seen in Table 3 below. [Blank line 10 pt]

Tabel 3. PGA of Maximum Credible Earthquake

Source MCE PGA

Mean Mean + 1 T

IES 1981 M 7.9 @ 60-70 km

NGDC/USGS 1999 M 7.5 @ 60 km 0.12 g 0.20 g

Golder 1996 M 7.5 @ 10 km 0.43 g 0.73 g

Vale 2013 M 7.1 @ 10 km 0.37 g

[Blank line 10 pt]

III- 77

Page 68: Design Optimization of Bauxite Residue Dam in Connection with

The probability calculation result shows that among sources are relatively similar. In line

with the earthquake calculation results on Balambano and Karebbe Dam in which using

sources from Golder (1996), then seismic design for Fiona Dam is also using Golder

(1996) as well. Earthquake design for Fiona Dam is recommended for the earthquake

periods of 400 years related to design basis earthquake (DBE) refer to Golder (1996) in

which the PGA is 0.36 g. [Blank line 10 pt]

3.2. Seismic Hazard Analysis [Blank line 10 pt]

PT Vale Indonesia Tbk in cooperation with Bureau of Meteorology, Climatology, and

Geophysics (BMKG) headquartered in Jakarta had accomplished Sorowako Seismic

Hazard Analyses in 2013. Sixteen in-situ micro-tremor tests were conducted in Fiona Dam

to obtain resonance frequency, amplification factor, and seismic susceptibility index. The

test results show that Fiona Dam dominantly has low seismic susceptibility index ranging

from 0.29 – 9.70 with resonance frequency between 1.9 – 9.3 Hz and amplification factor

low to medium (A < 6). These values indicate that the ground profile of Fiona Dam and

vicinity is relatively stable. [Blank line 10 pt]

Response spectra at the bedrock around Fiona Dam with return period of 475 years (equal

with 10% probability) and probability of exceedance 50 years (T = 0 second), peak ground

acceleration (PGA) is ranging from 0.44 – 0.49 g; response spectra at the bedrock with

return period 950 years (equal with 5% probability) and probability of exceedance 50 years

(T = 0 second), peak ground acceleration (PGA) is ranging from 0.55 – 0.62 g; and

response spectra at the bedrock with return period 2,475 years (equal with 2% probability)

and probability of exceedance 50 years (T = 0 second), peak ground acceleration (PGA) is

ranging from 0.74 – 0.83 g. [Blank line 10 pt]

[Blank line 10 pt]

4. DAM STABILITY ASSESSME NT [Blank line 10 pt]

Slope stability analyses both at upstream and downstream dam slopes and risk assessment

are conducted to obtain safety factor and risk matrix of Fiona Dam in case of failure in

which applied seismic loads modeled as pseudo static loads that represented with the peak

ground acceleration (PGA). [Blank line 10 pt]

4.1. Stability at Upstream Slope [Blank line 10 pt]

Pattern of critical slip failure for various seismic loads at upstream slope of the dam is

shown in the Figure 6 below. The slip failure is started from centerline of the dam crest

crossing a drainage core ripped slag until toe of rock-fill riprap with safety factor 2.231

(0.0 g), 1.859 (0.1 g), 1.602 (0.2 g), 1.401 (0.3 g), 1.250 (0.4 g), 1.129 (0.5 g) and 1.031

(0.6 g). [Blank line 10 pt]

Safety factor of upstream slope is lower than downstream slope due to the slope steeper. [Blank line 10 pt]

III- 78

Page 69: Design Optimization of Bauxite Residue Dam in Connection with

Horizontal Distance

0 20 40 60 80 100 120 140 160 180 200 220 240

350

360

370

380

390

400

410

420

430

0 20 40 60 80 100 120 140 160 180 200 220 240

Act

ua

l E

lev

ati

on

350

360

370

380

390

400

410

420

430

Figure 6. Pattern of critical slip failure at upstream slope

[Blank line 10 pt]

4.2. Stability at Downstream Slope [Blank line 10 pt]

Critical slip failure pattern at downstream slope of Fiona Dam can be seen in the following

Figure 7. The slip failure is started from centerline of the dam crest as crossing a drainage

core ripped slag and rock-fill riprap then penetrating a jointed peridotite rock as original

base floor with respective safety factor various 4.513 (0.0 g), 3.153 (0.1 g), 2.533 (0.2 g),

2.120 (0.3 g), 1.834 (0.4 g), 1.624 (0.5 g) and 1.484 (0.6 g). [Blank line 10 pt]

Horizontal Distance

0 20 40 60 80 100 120 140 160 180 200 220 240

350

360

370

380

390

400

410

420

430

0 20 40 60 80 100 120 140 160 180 200 220 240

Act

ua

l Ele

va

tio

n

350

360

370

380

390

400

410

420

430

Figure 7. Pattern of critical slip failure at downstream slope

[Blank line 10 pt]

[Blank line 10 pt]

Table 3. Resume of Safety Factor based on Seismic Load

Geotechnical Stability at

Factor of Safety based on Seismic Load (PGA)

0.0 g 0.1 g 0.2 g 0.3 g 0.4 g 0.5 g 0.6 g

Upstream Slope 2.231 1.859 1.602 1.401 1.250 1.129 1.031

Downstream Slope 4.513 3.153 2.533 2.120 1.834 1.624 1.484 [Blank line 10 pt]

III- 79

Page 70: Design Optimization of Bauxite Residue Dam in Connection with

Geotechnical Stability at the Dam Body based on Seismic Load

0.50

1.00

1.50

2.00

2.50

3.00

3.50

4.00

4.50

5.00

0.0 g 0.1 g 0.2 g 0.3 g 0.4 g 0.5 g 0.6 g

Seismic Load (Peak Ground Acceleration, PGA)

Fact

or

of

Safe

ty

FoS of the Upstream Slope FoS of the Downstream Slope Minimum FoS

Figure 8. Geotechnical Stability at the Dam Body with various Seismic Loads (PGA)

[Blank line 10 pt]

[Blank line 10 pt]

5. SUMMARY AND RECOMMENDATION [Blank line 10 pt]

Fiona Dam is located on low seismic susceptibility index zone that means relatively stable

in geotectonic terms. Based on slope stability analyses as summarized in Figure 8 above,

upstream and downstream slope of Fiona Dam with seismic loads for peak ground

acceleration (PGA) 0.45 g indicates that the dam body structure is in stable condition in

which the calculation results of respective safety factors more than 1.2 or meets

requirement. It means that Fiona Dam structure is expected having service life until 50

years with probability of exceedance 10%. [Blank line 10 pt]

Especially for upstream slope with peak ground acceleration (PGA) 0.49 g, safety factor is

ranging 1.0 – 1.2, it means the upstream slope is still in critical condition. Intensive

monitoring mainly soon after earthquake incident should be done to observe prior signs

before failure. [Blank line 10 pt]

At the dam crest and downstream slope, land clearing should be routinely conducted to

clean wild vegetation and bushes growing on it as well as trash in front of the spillway to

avoid any clogging and blocking in the spillway structure. [Blank line 10 pt]

[Blank line 10 pt]

ACKNOWLEDGEMENT We would like to express our grateful to Mr. H Basri Kambatu as Senior General Manager of

Mines & Exploration Department who has given encouragement during writing this paper, Mr.

Yusram Rantesalu as General Manager of Mine Engineering who has given direction and positive

feedback, and also colleagues BMKG who had conducted seismic study in Sorowako area. [Blank

line 9 pt]

[Blank line 9 pt]

III- 80

Page 71: Design Optimization of Bauxite Residue Dam in Connection with

REFERENCES [Blank line 9 pt]

Bemmelen, R.W. Van. (1949): The Geology of Indonesia, Martinus Nijhoff The Hague,

Batavia, Indonesia.

Hamilton, W. (1979): Tectonic of the Indonesian Region, Geological Survey Professional

Paper 1078, Washington, United States of America.

Irsyam, Masyhur, et all. (2010): Summary of Study Team Indonesia Earthquake Map

Revised 2010, Ministry of Public Work, Jakarta, Indonesia.

Simandjuntak, T.O., et all. (1991): Geology of Malili, Ministry of Energy and Mineral

Resources, Geological Research and Development Center, Bandung, Indonesia.

____________________ (2009): Final Report of Dam Evaluation and Stability Analysis,

PT. Indra Karya (Persero) Wilayah – I Jawa Timur, Malang, Indonesia.

____________________ (2013): Seismic Hazard Analysis at Sorowako and Vicinity Area,

Bureau of Meteorology, Climatology, and Geophysics (BMKG), Jakarta, Indonesia.

III- 81