Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
DESIGN OF MULTI-STORY PRECAST
CONCRETE BUILDING
STUDENT’S NAME
1. Ahmed Kreem Mohammed
2. Hussein Shuai Shamran
3. Karar Latef Naji
SUPERVISOR
Asst.Prof. Dr.Sa'ad F.Resan
A project report submitted in partial fulfilment of the
requirements for the award of the degree of
Bachelor of Civil Engineering
Civil Engineering Department
Engineering College
University of Misan
Iraq
2017-2018
i
DECLARATION
I hereby declare that this project report is based on my original work except for
citations and quotations which have been duly acknowledged.
Signature : _________________________
Name : _________________________
Date : _________________________
ii
APPROVAL FOR SUBMISSION
I certify that this project report "DESIGN OF MULTI-STORY PRECAST
CONCRETE BUILDING"
was prepared by KRAR LATEF , AHMED KREAM and HUSSEIN SHUAI has
met the required standard for submission in partial fulfilment of the requirements for
the award of Bachelor of Civil Engineering at University of Misan.
Approved by,
Signature : _________________________
Supervisor : _________________________
Date : _________________________
iii
Specially dedicated to
my beloved mother
to my deceased father.
to my brothers
to my best freind Hussein Ali
to my teachers
iv
ACKNOWLEDGEMENTS
I would like to thank everyone who had contributed to the successful completion of
this project.I would like to express my gratitude to my research supervisor,
Asst.Prof. Dr.Sa'ad F.Resan for his invaluable advice, guidance and his enormous
patience throughout the development of the research.
In addition, I would also like to express my gratitud to my loving brother and
friends who had helped and given me encouragement......
v
DESIGN OF MULTI-STORY PRECAST CONCRETE BUILDING
ABSTRACT
The project consists of three-story classroom building of precast
structures element and this building consist of wall and hollow core
slab prestress that design with specification requirement
for load and safety according to ACI code for design wall
and PCI for design hollow core slab Iraqi Code of Loads and Powers.
vi
TABLE OF CONTENTS
DECLARATION i
APPROVAL FOR SUBMISSION ii
ACKNOWLEDGEMENTS iv
ABSTRACT v
LIST OF SYMBOLS / ABBREVIATIONS viii
CHAPTER ONE
1 INTRODUCTION 1
1.1 Background 1
1.2 Advantages of Precast Concrete Construction 3
1.3 Disadvantages of Precast Concrete 5
1.4 Applications 5
1.5 Literature Review 9
CHAPTER TWO
2 METHODOLOGY 12
2.1 prestressed hollow core slabs 12
2.2 precast wall 17
2.3 Connection 20
2.3.1 Connection details for hollow core slab system 20
2.3.2 connection wall to wall 24
2.4 Case Study 29
CHAPTER THREE
3.1 Design Prestressed hollow core slabs 40
3.2 Design of wall 48
3.3 Design of wall as deep beam 49
vii
CHAPTER FOUR
CONCLUSION AND RECOMMENDATIONS 52
REFERENCES 55
viii
LIST OF SYMBOLS / ABBREVIATIONS
A = Cross-sectional area
a = Depth of equivalent compression stress block
Aps = Area of prestressed reinforcement
bw = Net web width of hollow core slab
C = Factor for calculating steel relaxation
losses
CR = Prestress loss due to concrete creep
DL = Dead load
db = Nominal diameter of reinforcement
dp = Distance from extreme compression fiber to centroid of prestressed
reinforcement
e = Distance from neutral axis to centroid of prestressed reinforcement
Ec = Modulus of elasticity of concrete
Eci = Modulus of elasticity of concrete at the time of initial prestress
ES = Prestress loss due to elastic shortening of concrete
Es = Modulus of elasticity of steel reinforcement
f'c = Specified design compressive strength of
concrete
fci = Compressive strength of concrete at the time of initial prestress
fcir = Net compressive stress in concrete at centroid of prestressed reinforcement at
time of initial prestress
fcds = Stress in concrete at centroid of prestressed reinforcement due to superimposed
dead load
fd = Stress at extreme tension fiber due to unfactored member self weight
fpe = Compressive stress in concrete at extreme
fiber where external loads cause tension due to the effective prestress only
fps = Stress in prestressed reinforcement at nominal strength
fpu = Specified tensile strength of prestressing steel
fse = Effective stress in prestressing steel after all losses
fsi = Stress in prestressing steel at initial prestress
ix
J = Factor for calculating steel relaxation losses
k = Fraction of total load in a horizontal joint in a grout column
Kcir = Factor for calculating elastic shortening prestress losses
Kcr = Factor for calculating prestress losses due to concrete creep
Kes = Factor for calculating prestress losses dueto elastic shortening
Kre = Factor for calculating prestress losses dueto steel relaxation
Ksh = Factor for calculating prestress losses due to concrete shrinkage
LL = Live load
Mcr = Cracking moment
Md = Unfactored dead load moment
Mg = Unfactored self-weight moment
Mn = Nominal flexural strength
Msd = Unfactored moment due to superimposed dead load
P = Effective force in prestressing steel after all losses
Po = Effective prestress force at release prior to long term losses
Pi = Initial prestress force after seating losses
RE = Prestress loss due to steel relaxation
yb = Distance from neutral axis to extreme bottom fiber
yt = Used as either distance to top fiber or tension fiber from neutral axis
Chapter one introduction
10
Chapter one introduction
1
Chapter One
Introduction
1.1 Background
The concept of precast (also known as “prefabricated”) construction
includes those buildings where the majority of structural components
are standardized and produced in plants in a location away from the
building, and then transported to the site for assembly. These
components are manufactured by industrial methods based on mass
production in order to build a large number of buildings in a short
time at low cost.
The main features of this construction process are as follows:
• The division and specialization of the human workforce
• The use of tools, machinery, and other equipment, usually
automated, in the production of standard, interchangeable parts and
products This type of construction requires a restructuring of the
entire conventional construction process to enable interaction
between the design phase and production planning in order to
improve and speed up the construction. One of the key premises for
achieving that objective is to design buildings with a regular
configuration in plan and elevation. In general, precast building
systems are more economical when compared to conventional
multifamily residential construction (apartment buildings) in many
countries.
Chapter one introduction
2
Chapter one introduction
3
1.2 Advantages of Precast Concrete Construction
a) Reduced Construction Time
Precast concrete construction will save valuable time and helps to
reduce the risk of project delay and possible monetary losses.
Precast design and production of elements can be started while the
construction site is under survey or earthworks. Production are
also unaffected by weather conditions due to the controlled
environment of the casting area. Also, the usage of large precast panels
will reduce the time taken to complete the structural works. Therefore, other
trades such as painting and electrical wiring can begin work sooner.
b) High quality and aesthetical value of products
Precast products are manufactured in a casting area where critical
factors including temperature, mix design and stripping time can
be closely checked and controlled and this will ensure that the
quality of precast products are better than cast-in-situ concrete. A
huge sum of money will be saved by not having to do rectification
works. Also due to factory-controlled prefabrication environment,
many combinations of colours and textures can be applied easily
to the architectural or structural pieces. A vast range of sizes and
shapes of precast components can be produced, providing a great
deal of flexibility and offer fresher looks to the structures.
c) Greater unobstructed span
The usage of prestressed precast solutions such as the Hollow
Core slabs and Double-T beams offer greater unobstructed span
Chapter one introduction
4
than the conventional reinforced concrete elements. Having lesser
beams and columns, will provide larger open space. It is very ideal
for the construction of places of worship, warehouses, halls, car
parks, shops and offices
d) Cleaner and safer construction sites
Usage of precast elements eliminates or greatly reduces
conventional formworks and props. Precast construction also
lessens the problem of site wastages and the related environmental
problems. The prefabricated products also provide a safe working
platform for workers to work on.
e) Increased Quality of Structural Elements
Precast concrete elements produced in plants using modern
techniques and machineries. Raw materials such as concrete, sand,
and reinforcement bars are under high level of quality control.
Formworks used are of higher quality than those used at
construction sites. This allows truer shapes and better finishes in
precast components. Precast components have higher density and
better crack control, offering better protection from harsh weathers
and sound insulation.
f) Increased Durability and Load Capacity of Structural
Elements Prestressed precast concrete components have high
structural strength and rigidity, which are important to support
heavy loads. This allows shallow construction depth and long span
in structural components. Fewer supporting columns or walls
result in larger floor space, which allow more flexibility in interior
design.
Chapter one introduction
5
1.3 Disadvantages of Precast Concrete
a) The precast method of construction becomes uneconomical for
small residential construction.
b) While transportation of the precast units to larger distance it may
subject to get damage
c) Sophisticated Connection Works
The behaviour of connections determines the performance of
precast concrete structures. When assembling of precast concrete
structures, connections between precast components must be
supervised and done properly.
1.4 Applications
1.4.1 Building Structures
Chapter one introduction
6
1.4.2 Residential Buildings
1.3.1 Office Buildings
Chapter one introduction
7
1.3.2 Warehouses and Industrial Buildings
1.3.3 Parking Structures
Chapter one introduction
8
1.3.4 Stadiums/Arenas
1.3.5 Bridges
Chapter one introduction
9
1.4 Literature Review
Nowadays the precast concrete has been used extensively in many
residential and commercial construction projects. It is because of
the property of the precast concrete. It has higher durability,
thermal properties and very easy to handle and so on. Also the
quality of the precast concrete is higher as it is manufactured
under great control. But there is lack of awareness and knowledge
regarding the precast concrete in our country. This has to be
changed and more study has to be done regarding precast. The
connection details of the precast members also should be studied
well.
Sarakot Asaad Hasan, BEHAVIOUR OF DISCONTINUOUS
PRECAST CONCRETE BEAM-COLUMN CONNECTIONS,
University of Nottingham, 2011: The study investigates
experimentally and theoretically the behaviour of an internal
precast concrete beam-column connection, where both the column
and beam are discontinuous in construction terms. The aim was to
modify the behaviour mechanisms within the connection zone by
introducing a beam hogging moment resistance capacity under
dead loads and limiting the damage within the connection. This is
to offer permanent dead load hogging moments that could
counterbalance any temporary sagging moment generated under
sway loads, enhance the rotational stiffness, balance the design
requirements for the beam-end and beam mid-span moments,
provide efficient continuity across the column, and reduce the
deflection at the beam mid-span. Connection provides a hogging
Chapter one introduction
10
moment capacity under dead loads as well as under live loads.
Connection could be dealt with as an equivalent monolithic
connection under gravity loading by using the strong connection
concept. The simplified semi-rigid analysis using short stubs with
appropriate stiffnesses, reflecting the connection flexibility, was
found to give the exact solution when the stub length approaches
zero.
Patrick Tiong Liq Yee, Azlan Bin Adnan, Abdul Karim Mirasa
and Ahmad Baharuddin Abdul Rahman , Performance of IBS
Precast Concrete Beam-Column Connections Under Earthquake
Effects: A Literature Review, American J. of Engineering and
Applied Sciences 4 (1): 93-101, 2011, ISSN 1941-7020,2010
Science Publications, 2011: The main objective of this study was
to identify the most appropriate type of beam-column connections
to be introduced to precast concrete industry, particularly for
regions of low to moderate seismicity. Hence, this study presented
a comprehensive literature overview of the findings from studies
conducted to analyze and investigate the behavior of precast
concrete systems assembled with typical connections or joints
under simulated earthquake loading. The seismic performance of
precast concrete structure very much depended on the ductility
capacity of the connectors jointing each precast components,
especially at critical joints such as the beam-tocolumn connections.
It was learnt from the review that (1) hybrid post-tensioned beam-
column connection and (2) Dywidag Ductile Connector were
Chapter one introduction
11
among the most widely used connectors for precast construction in
seismic prone regions. Future refinement and research could be
carried out in order to optimize these connections to be used in
low seismicity regions. Proposed connection type should be
practical and well-accepted to avoid further impediment
of the precast system.
MULTILEVEL CAR PARK, INFOSYS, HINJEWADI, PUNE.
As per below photos, Concrete grade is M50. The precast column
are three floor height and the size is 900mm x 900mm and height
is 9.6m. Precast Beams are sitting on the corbel introduced in the
precast column. The dowel bar is embedded in the corbel while
production of column. There are sleeves provision in precast
beams. While installation of precast beams the dowel bars coming
from corbel are inserted in the beam sleeves. Elastomer pads are
used underneath of precast beams for lateral forces, rotation or
vertical movement in the columns due to seismic. These are
Dowel-pin connections
Chapter three Results and Discussion
12
Chapter Two
Methodology
2.1 DESIGN OF PRESTRESSED HOLLOW CORE
CONCRETE
2.1.1 Permissible stresses at transfer
a) Extreme fiber stress in compression ………. 0.6 f'c
b) Extreme fiber stress in tension except as permitted in (c)
…………………………………………… …………….3 √𝑓𝑐𝑖′
c) Extreme fiber stress in tension at ends of simply supported
members
……………...……………………………….. ………….6√𝑓𝑐𝑖′
2.1.2 Permissible stresses at service loads
a) Extreme fiber stress in compression due to prestress plus sustained
loads …….………………………………………….. ……...0.45f'c
b) Extreme fiber stress in compression due to prestress plus total
load ……………………………………………………… ..0.60f'c
c) Extreme fiber stress in tension in pre-compressed tensile
zone ……………………………………………………… 6 √𝑓𝑐′
d) Extreme fiber stress in tension in pre-compressed tensile zone
where deflections are calculated
considering bilinear moment-deflection
relationships………………………………………….. 12 √𝑓𝑐′
Chapter three Results and Discussion
13
2.1.4 Stresses at Transfer
When the prestressing strands are cut to apply the prestressing
force to the concrete, only the slab self weight is present to
counteract the effects of eccentric prestress. A check of stresses is
required at this point to determine the concrete strength required to
preclude cracking on the tension side or crushing on the
compression side. The concrete strength at the time of transfer
may be only 50% to 60% of the 28 day design strength.
2.1.5 Prestress Losses
1) Elastic Shortening
ES = Kes ES
Eci fcir
Kes = 1.0 for pretensioned members
Fcir = Kcir (𝑃𝑖
𝐴+
𝑃𝑖𝑒2
𝐼) -
𝑀𝑔𝑒
I
Kcir = 0.9 for pretensioned members
2) Concrete Creep
CR = Kcr ES
Ec (fcir - fcds )
Kcr = 2.0 for normal weight pretensioned members
fcds = 𝑀𝑠𝑑 𝑒
I
Chapter three Results and Discussion
14
3) Shrinkage of Concrete
SH = 8.2 x 10-6 KshEs x ( 1 − 0.06 V
S ) x (100 - RH)
Ksh = 1.0 for pretensioned members
4) Steel Relaxation
RE = [Kre - J (SH + CR + ES)]C
Total Loss = ES + CR + SH + RE
Table value J
Table Value of C
Chapter three Results and Discussion
15
2.1.6 Service Load Stresses
Tensile stress limits of between 6 √𝑓′𝑐 and 7.5 √𝑓′𝑐 are
commonly used. In special circumstances where deflections will
not be a problem and where cracking will not be of concern, the
upper limit of 12√𝑓′𝑐 can be used.
2.1.7 Design Flexural Strength
φMn ≥ Mu
φMn ≥ 1.2 Mcr
Mcr = I
yb(
P
A +
Pe
Sb + 7.5√fc
′ )
φMn = φApsfps( dp - 𝑎
2 )
fps= fpu [1- 𝛾𝑝
𝛽1 ( ρp
fpu
𝑓𝑐′ )]
γp = 0.28
ρp = 𝐴𝑝𝑠
𝑏𝑑𝑝
ωp = ρpfps
fc′
Camber and Deflection
Camber : is the upward deflection of a prestressed member and results
from the prestressing force being eccentric from the center of gravity of
the cross-section Cambers and deflections will change with time due to
concrete creep, prestress loss and other factors.
Chapter three Results and Discussion
16
Long term multipliers
Initial Camber
Camber = 𝑃𝑒𝑙2
8𝐸𝑐𝑖𝐼
Deflection = 5𝑊𝑙4
284𝐸𝑐𝑖𝐼
Chapter three Results and Discussion
17
2.2 Design of walls
Design strength
(a) ϕPn ≥ Pu
(b) ϕMn ≥ Mu
(c) ϕVn ≥ Vu
Wall thickness
Design axial strength
ϕPn = ϕ0.55f'c*Ag*[1-( 𝑘𝑙𝑐
32ℎ)2]
Chapter three Results and Discussion
18
Minimum reinforcement
Vertical reinforcement ratio
l 0.0015
Reduce to 0.0012 for bar sizes No. 16 and
fy 420 MPa
Horizontal reinforcement ratio
t 0.0025
Reduce to 0.0020 for bar sizes No. 16 and
fy 420 MP
Reinforcement detailing
For walls with h greater than 10 in., except basement walls and
cantilever retaining walls, distributed reinforcement for each direction
shall be placed in two layers parallel with wall faces in accordance with
(a) and (b):
(a) One layer consisting of at least one-half and not exceeding two-thirds
of total reinforcement required for each direction shall be placed at least
2 in., but not exceeding h/3, from the exterior surface.
Chapter three Results and Discussion
19
(b) The other layer consisting of the balance of required reinforcement in
that direction, shall be placed at least 3/4 in., but not greater than h/3,
from the interior surface.
Spacing
Spacing s of longitudinal bars in precast walls shall not exceed the lesser
of (a) and (b):
(a) 5h
(b) 18 in. for exterior walls or 30 in. for interior walls
If shear reinforcement is required for in-plane strength , shall not exceed
the smallest of 3h, 18 in , and ℓw/3
Spacing s of transverse bars in precast walls shall
not exceed the lesser of (a) and (b):
(a) 5h
(b) 18 in. for exterior walls or 30 in. for interior walls
If shear reinforcement is required for in-plane strength, s
shall not exceed the least of 3h, 18 in., and ℓw/5
Reinforcement around openings
In addition to the minimum reinforcement required at least two No. 5
bars in walls having two layers of reinforcement in both directions and
one No. 5 bar
in walls having a single layer of reinforcement in both directions shall be
providedaround window, door, and similarly sized openings. Such bars
shall be anchored to develop fy in tension at the corners of the openings.
Chapter three Results and Discussion
20
2.3 Connection
2.3.1 Connection details for hollow core slab system
Design considerations
Can transfer internal diaphragm forces
• Can be designed as structural
integrity tie Fabrication considerations
• Advantageous to have no hardware
in slab
• Beam embodiments’ must line up
with slab joints
• Accommodates variations in slab
Length Erection considerations
Design considerations
• Can transfer internal diaphragm
forces
• Can be designed as structural
integrity tie Fabrication considerations
• May increase beam reinforcement
For shallower beam
• Layout must have opposing slab
joints lined up Erection considerations
• Clean and simple
Chapter three Results and Discussion
21
Design considerations
• Can transfer internal diaphragm
forces
• Can be designed as structural
integrity tie
Fabrication considerations
• May increase beam
reinforcement For shallower beam
• Layout must have opposing slab
joints lined up Erection.
Design considerations
• Can transfer internal diaphragm
forces
• Can be designed as structural
integrity tie
Fabrication considerations
• May increase beam reinforcement
For shallower beam
• Layout must have opposing slab
joints lined up Erection
considerations
Chapter three Results and Discussion
22
Design considerations
• Can transfer internal diaphragm
forces
• Can be designed as structural
integrity tie
Fabrication considerations
• Clean and simple Erection
considerations
• Clean and simple
Design considerations
Can transfer diaphragm shear
Can provide lateral brace for beam
Potential to develop negative
moment in slabs
Erection considerations
Connection can be completed with
a follow-up crew
Lateral bracing for beam will not
be provided until keyway grout cures
Fabrication considerations
Plates in beam must align with slab
joints allowing tolerance
Chapter three Results and Discussion
23
Design considerations:
Can transfer diaphragm shear
Can be designed as structural
integrity tie
Can provide lateral brace for
wall
Consider axial force path
through slab ends
Opposing slab joints must
line up
.Design considerations
Can transfer diaphragm shear
Can be designed as structural
integrity tie
Can provide lateral brace for wall
Opposing slab joints must line up
Fabrication considerations
Clean and simple for slabs
Erection considerations
Clean and simple
Wall is not braced until grout is
placed and cured
Chapter three Results and Discussion
24
2.3.2 connection wall to wall
Chapter three Results and Discussion
25
Chapter three Results and Discussion
26
Chapter three Results and Discussion
27
Chapter three Results and Discussion
28
Chapter three Results and Discussion
29
2.4 Case Study
Chapter three Results and Discussion
30
Chapter three Results and Discussion
31
Chapter three Results and Discussion
32
Chapter three Results and Discussion
33
Chapter three Results and Discussion
34
Chapter three Results and Discussion
35
Chapter three Results and Discussion
36
Chapter three Results and Discussion
37
Chapter three Results and Discussion
38
Chapter three Results and Discussion
39
Chapter three Results and Discussion
40
Chapter Three
Results and Discussions
3.1 DESIGN OF PRESTRESSED HOLLOW CORE CONCRETE
f'c = 5000 psi
f'ci =2875 psi
fpu = 270,000 psi
Ec = 33*w1.5 *√𝑓𝑐′ = 33*(150)1.5*√5000
= 4300 ksi
Eci = 33*w1.5 *√𝑓𝑐′ = 33*(150)1.5*√2875
= 3250 ksi
Es = 28500 ksi
Properties of section
A = 259 in2
I = 3223 in4
yb = 5.00 in
yt = 5.00 in
Sb = 645 in3
St = 645 in3
wt = 270 lb/ft
DL = 68 lb/ft2
V/S = 2.23 in
bw = 10.5 in
e = 3.5 in
dp = 8.5 in
L = 7.2 m ( 23.6232 ft )
Lc = 7 m ( 22.967 ft )
D.L = 2 kn/m2 ( 41.77 psf )
L.L = 3 kn/m2 (62.65 psf )
Chapter three Results and Discussion
41
Assume prestress steel 6- 1/2"
1) Transfer Stresses
Aps = 6(0.153) = 0.918 in2
assume 5% initial loss
Po = 0.7*Aps*fpu*(1- 0.05)
Po = 0.7*0.95*0.918*270 = 164.8 k
Prestress effect
σcp = P0
𝐴 ±
𝑃𝑜∗𝑒
𝑆
σcp = 164.8
259 ±
164.8∗3.5
645
= - 0.258 ksi for top fiber
= 1.53 for bottom
Self weight at transfer point
ℓt = 50db = 50(1/2) = 25 in
Md = ( 23.6232
2∗ 1.788 −
1.7882
2 ) = 10.03 ft-k
𝑀𝑑
𝑆 =
10.03
645
= 0.186 for top fiber
= - 0.186 for bottom
Net concrete stress at transfer point
= - 0.072 ksi top
= 1.344 ksi bottom
Self weight at midspan
Md = 𝑊∗𝑙2
8 =
0.068∗4∗23.62322
8
= 18.97 ft-k
Chapter three Results and Discussion
42
𝑀𝑑
𝑆 =
18.97∗12
645
= 0.353 ksi top
= - 0.353 bottom
Net concrete stress at midspan
= - 0.095 ksi top
= 1.177 ksi bottom
Allowable stresses
Tension end = 6√𝑓𝑐𝑖′
f'ci = ( 72
6 )2 = 144 psi
tension at midspan = 3√𝑓𝑐𝑖′
does not control
compression = 0.6f'ci
f'ci = 1.344
0.6∗1000 = 2036 psi
concrete strength required at release = 2036 psi
Prestress Losses
1) Elastic Shortening
Pi = 0.7*6*0.153*270 = 173.5 k
fcir = 0.9(𝑃𝑖
𝐴+
𝑃𝑖∗𝑒2
𝐼−
𝑀𝑔
𝐼 )
= 0.9*(173.5
259+
173.5∗3.52
3223−
18.97∗3.5
3223 )
= 0.95 ksi
Es = 28500 ksi Eci= 3250 ksi
ES = 𝑘𝑒𝑠𝐸𝑠
𝐸𝑐𝑖∗ 𝑓𝑐𝑖𝑟 = 1*
28500
3250*0.95 = 8.33 ksi
Chapter three Results and Discussion
43
2) Concrete Creep
CR = kcr* 𝐸𝑆
𝐸𝑐 *( fcir –fcds )
fcds= 𝑀𝑠𝑑 𝑒
𝐼
Msd = 0.04177∗4∗23.62322
8 = 11.65 ft-k = 140 in-k
fcds= 140∗3.5
3223 = 0.152 ksi
CR = 2*28500
4300∗ (0.95 − 0.152) = 10.58 ksi
3) Shrinkage of Concrete
𝑉
𝑆 = 2.23
Use RH = 70%
SH = 8.2 x 10-6KshEs(1 − 0.06*𝑉
𝑆 )
= 8.2 x 10-6*1*28500(1 − 0.06*2.23 ) = 6.07 ksi
4) Steel Relaxation
From Table
Kre = 5000, J = 0.04
From Table
C = 0.75 for fsi/fpu = 0.7
RE = [Kre – J*(SH + CR + ES)]C
= [5000/1000 − 0.04*(6.27 + 8.74 + 7.52)] 0.75
= 3 ksi
Total Loss = ES + CR + SH + RE
Total Loss = 10.58 + 8.33 + 6.07 + 3 = 27.98 ksi
Loss% = 27.98
0.7∗270*100 = 14.8 %
Chapter three Results and Discussion
44
Service Load Stresses
Msustained = 22.9672
8*(0.068 + 0.04177)
= 7.24 ft.k/f = 86.88 in-k/ft
M Service = 22.9672
8 (0.068 + 0.04177 + 0.06265)
= 11.37 ft-k/ft = 136.44 in-k/ft
With losses = 14.8%
Apsfse = 0.7*6*0.153*270(1 – 0.148) = 147.8 k
Top fiber compression with sustained loads
ftop = 147.8
259−
147.8∗3.5
645+
86.88∗4
645 = 0.3 ksi
Permissible compression
= 0.45f′c
= 0.45(5000)
= 2.25 ksi > 0.3 ksi OK
Top fiber compression with total load
ftop = 147.8
259−
147.8∗3.5
645+
136.44∗4
645 = 0.614 ksi
Permissible compression
= 0.60f′c
= 0.60(5000)
= 3.00 ksi > 0.614 ksi OK
Bottom fiber tension
fbottom = 147.8
259+
147.8∗3.5
645−
136.44∗4
645 = 0.52 ksi
Chapter three Results and Discussion
45
Permissible tension
= 7.5√𝑓𝑐′= 7.5√5000 = 0.53 ksi
= 0.530 ksi > 0.52 ksi OK
Design Flexural Strength
φMn = φApsfps( dp - 𝑎
2 )
fps= fpu [1- 𝛾𝑝
𝛽1 ( ρp
fpu
𝑓𝑐′ )]
γp = 0.28
𝛽1 = 0.85 - (5000 −4000
1000)*0.05 = 0.8
ρp = 𝐴𝑝𝑠
𝑏𝑑𝑝 =
6∗0.153
48∗8.5 = 0.00225
fps= 270 [1- 0.00225
0.8 ( 0.00225*
270
5 )] = 258.5 ksi
a = 𝐴𝑃𝑆𝑓𝑠𝑒
0.85 =
0.918∗258.5
0.85∗5∗48 = 1.16 in
φMn = 0.918*258.5( 8.5 - 1.16
2 ) = 140.95 ft-k/slab
Wu = 1.4*(0.068 + 0.04177) + 1.7*(0.06265) = 0.26 ksf
Mu = 𝑤𝑙2
8 =
0.26∗22.9672
8 = 17.14 ft-k/ft = 68.57 in.k/slab < 140.95 0k
Check minimum reinforcement
φMn ≥ 1.2 Mcr
Mcr = I
yb(
P
A +
Pe
Sb + 7.5√fc
′ )
Apsfse= 0.7*6*41.3*(1- 0.148) = 147.8 k
Bottom compression
fbottom = 147.8
259+
147.8∗3.5
645 = 1.37 ksi
Mcr = 3223
5∗(
147.8
259 +
147.8∗3.5
645 +
7.5∗√5000
1000 )
= 1224.95 in-k
φ𝑀𝑛
𝑀𝑐𝑟 =
140.95∗12
1224.95 = 1.32 > 1.2 ok
Chapter three Results and Discussion
46
Camber and Deflection
Initial Camber
Po = 0.95*0.7*6*0.153*270 = 164.827 k
Camber = 𝑃𝑜𝑒𝑙2
8𝐸𝑐𝑖𝐼 =
164.827∗3.5∗(22.967)2
8∗3250∗3223 = 0.523"
Deflection = 5𝑊𝑙4
284𝐸𝑐𝑖𝐼 =
5∗0.068∗4∗(22.967)4∗123
384∗3250∗3223 = 0.1626"
Net camber at release = 0.523 – 0.1626 = 0.36"
Long Term Camber
At erection,
initial camber = 0.36"
Erection camber = 0.523*(1.80) – 0.1626*(1.85)
= 0.64"
Final camber = 0.523*(2.45) – 0.1626*(2.70)
= 0.84″
Deflections
superimposed dead load instantaneous deflection
Deflection = 5𝑊𝑙4
284𝐸𝑐𝐼 =
5∗0.04177∗4∗(22.967)4∗123
384∗4300∗3223 = 0.075"
Final deflection = 0.075* (3.0) = 0.225″
Instantaneous live load deflection
5𝑊𝑙4
284𝐸𝑐𝐼 =
5∗0.06865∗4∗(22.967)4∗123
384∗4300∗3223 = 0.124"
Final position
0.84 – 0.225 – 0.124 = 0.491"
Change in camber = 0.84 – 0.64 = 0.2
Sustained dead load = - 0.225
Chapter three Results and Discussion
47
Instantaneous live loads = - 0.124
= -0.149"
0.149 < 22.967∗12
360= 0.765 " ok
Chapter three Results and Discussion
48
Design of walls
Thickness of wall
h = 100 mm
Or
h ≥ 𝑙𝑐
25 =
3500
25= 140 𝑚𝑚
use h = 200 mm
1) Capacity of a Bearing Wall
ϕPn = ϕ0.55f'c*Ag*[1-( 𝑘𝑙𝑐
32ℎ)2]
ϕ = 0.65
=0.65*0.55*25000*6.2*0.2*[1-( 1∗3.5
32∗0.2)2]
= 7768 kn > 822.75 kn ok
2) Select Reinforcement
Vertical
As = (0.0012)(1000)(200) = 240 mm2/m
Horizontal spacing of vertical reinforcement
Sh,max = 𝐴𝑣
0.0012ℎ =
113.1
0.0012∗200= 470 𝑚𝑚
use 450 mm
Horizontal
As = (0.002)(1000)(200) = 400 mm2/m
Vertical spacing of horizontal reinforcement
Sv,max = 𝐴ℎ
0.0012ℎ =
113.1
0.002∗200= 282 𝑚𝑚
use 280 mm
Chapter three Results and Discussion
49
Reinforcement around openings
Use one No. 5 (16 mm) bar in both directions around window, door
Design of walls as deep beam
Wbeam = 25*1*0.2*2.8 = 14 Kn
Pu = 822.75 kn
Chapter three Results and Discussion
50
Pu = 1.2*(14/2)+(185.78)
= 194.2
RA=AD= 194.2 Kn
Max shear strength
Vu at A = RA=194.5 Kn
Assume d= 0.9 h=0.9*1000=
9000mm
Vn = 0.83* √25* 200*900= 747 Kn
ϕVn = 0.75 *747 = 560.25 Kn > 194.2 Kn
Strut BC
Fu BC = ϕFnc = ϕFce AC = ϕ(0.85 βC FC ) b Ws
βs = 1 horizontal strut
for tie AD
Fu AD = ϕ Fnt= ϕ FCe AC = ϕ(0.85 βn Fc) b Wt
βs= 0.8 (c- c - t)
Fu BC = F U AD
SO ;
Wt = 1.25 Ws
jd = 1000 - 𝑊𝑡
2 -
𝑊𝑡
2 = 1000 – 1.125Ws
Vu(1000) – Fu BC (jd) =0
194.2*1000*1000 – (0.85 βs fc )b Ws (1-125Ws)=0
Ws= 48 mm
Wt= 54 mm
Jd =1000 – 0.5*48 - 0.5*54 = 949 mm
AB = CD = √10002 + 9492 =1378.6 mm
tan θ = 949
1000
θ =43.5 > 25 ok
185.78 kn 185.78 kn
Chapter three Results and Discussion
51
Fu BC =Fu AD=194.2( 1000
949 )= 204.6 Kn
Fu AB = Fu CD = 194.2
sin 43.5 = 282 Kn
Effect stress
Fce = 0.85 βs fc = 0.85 * 0.75 *25 =15.94 MPa
S= 𝑑
5 =
900
5 =180 mm
Av = Avh=0.0025 * 200 * 180 = 90 mm2 per 180 mm
As = 𝜋
4 (10)2=78.534 * 2 =157.9 two legs
Use ϕ10 mm @ 180 mm
angle between vertical bars and strut = 90 – 43.5 = 46.5
(𝐴𝑠𝑖
𝑏𝑠) sin γ =(
157
200∗180) sin 46.5 =0.00316
angle between horizontal bars and strut = 43.5
(𝐴𝑠𝑖
𝑏𝑠) sin γ =(
157
200∗180) sin 43.5=0.003
(𝐴𝑠𝑖
𝑏𝑠) sin γ = 0.00316 + 0.003 =0.00616 > 0.003 ok
Design tie reinforcement
Fu=ϕ As Fy
As= 204.6∗1000
0.75∗410 =665.366 mm2
Ab= 𝜋
4 = (25)2=490.87mm2
NO. = 1.35 USE 2 ϕ 25
As=2 (𝜋
4) 252 = 982 mm2
Chapter four Conclusion and Rexommendation
52
Chapter Four
Conclusion and Recommendations
The use of a relatively cheaper system of construction for building
construction instead of the widely used ones, will not only have
economical benefits but also avoids the dependence on usual systems,
thereby reducing the competition in the construction industry. Precast
prestressed hollow core slab system of construction is a system, which
does not need very heavy equipment for erection, and the component
members can be produced with locally abundant construction materials.
In addition it is a precast, prestressed concrete slab system with
continuous voids provided to reduce weight and, therefore, cost and, as a
side benefit, to use for concealed electrical or mechanical runs. Primarily
used as floor or roof deck systems, hollow core slabs also have
applications as wall panels, and bridge deck units. It should be
understood that the main objective of the present study is to investigate
the advantage of pre cast prestressed hollow core slab elements for floor
slab construction, by comparing with the precast beam-block slab system.
All construction projects are designed to end up with an optimum
economy and safety. To fulfill these criteria the construction method to
be adopted should be the one with minimum total cost that satisfies the
strength requirements.A cost comparison between the two systems of
construction the hollow core slab system and the precast beam slab
system was made by designing the floor slabs of a typical four-story
building, using both systems. Based on the cost comparison, the
Chapter four Conclusion and Rexommendation
53
theoretical investigation the following conclusions
and recommendations may be drawn
1. The cost comparison shown that the hollow core slab system of
construction is faster and less expensive than the precast beam-
block slab system. The total saving obtained from the use of
system is abut 6.04% of the total construction cost of a building
using the precast beam-block slab systems. In addition to the
economical benefits gained the application of this system is
believed to solve problems associated with delays in the
construction industry, since construction delays are one of the
main causes of disputes.
2. As it can be seen from the cost comparison the saving from
construction cost component is 44% of the total saving. Higher
value of construction cost saving and hence total saving could
have been obtained if the precast pre-stressed hollow core slab
elements are designed and produced more economically
3. For the production of the precast prestressed hollow core slab
elements. it is recommended to use a minimum concrete class
C-35 and the upper surface of the slab elements should be
sufficiently roughened to create a good bond with the floor finish
cement screed or structural topping and the lower surface slab
surface should be smooth enough for final painting. The top
surface is generally prepared to receive a screed or structural
topping. Because they are cast against a steel surface, the soffits
are smooth and ready to receive a decorating finish direct without
the need for plastering.
Chapter four Conclusion and Rexommendation
54
4. During handling, transporting and erecting the hollow core slab
elements great care should be taken not to impair some structural
properties. a minimum of two-point lifting mechanism is
recommended to use .
5. For a country like Iraq application of this system of construction
not only has economical benefits but also preserves the national
resource by avoiding excessive use of formwork and scaffolding.
6. Even though there are many advantages in precast construction
there is still non responsive in untries like iraq. They still opt for
the conventional construction and consider that to be safe as the
cost of precast is slightly higher than thatof the conventional
construction.
7. Finally, it is believed that the result of this study are encouraging
and has shade light into the introduction of precast pre-stressed
slab systems in the construction industry. However, it is suggested
that further research be carried out in this area for proper
utilization of the system. It is hoped that the present study serve as
an aid for further developments and other related studies
55
8. References Book [1] PCI DESIGN HANDBOOK PRECAST AND PRESTRESSED CONCRETE ,
9. 7TH EDITION (2010)
10. [2] Building Code Requirements for Structural Concrete(ACI 318-14)
11.
12. [3] Reinforced Concrete: Mechanics and Design (6th Edition) 6th Edition
13. by James K. Wight (Author), James G. MacGregor (Author)
14. [4] Design of Reinforced Concrete, 9th Edition
15. Jack C. McCormac, Russell H. Brown
Website
[5] http://www.google.com/
16. [6] http://www.scribd.com/
17. [7] http://www.springer.com/
18. [8] http://www.slideshare.net/