84
November 2008 Engineers Ireland Geotechnical Society of Ireland Engineers Ireland Engineers Ireland - - Geotechnical Society of Geotechnical Society of Ireland Ireland Design and Construction of Metro Stations and Underground Structures to Eurocode 7 - with Case Histories David Beadman Byrne Looby Partners

Design and construction of metro stations and underground

Embed Size (px)

Citation preview

Page 1: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Engineers Ireland Engineers Ireland -- Geotechnical Society of Geotechnical Society of IrelandIreland

Design and Construction of Metro Stations and Underground Structures to

Eurocode 7 - with Case Histories

David BeadmanByrne Looby Partners

Page 2: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

ContentsContents

The Eurocodes and Eurocode 7Jubilee Line, London – North Greenwich StationJubilee Line, London – Canary Wharf StationCopenhagen Metro – Eurocode 2Copenhagen Metro – Observational Method

Page 3: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

British StandardsBritish Standards

••

Page 4: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The The EurocodesEurocodes and Eurocode 7and Eurocode 7

Page 5: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode SuiteEurocode Suite

EN 1990 Eurocode: Basis of structural designEN 1991 Eurocode 1: Actions on structuresEN 1992 Eurocode 2: Design of concrete structuresEN 1993 Eurocode 3: Design of steel structuresEN 1994 Eurocode 4: Design of composite steel and concrete structuresEN 1995 Eurocode 5: Design of timber structuresEN 1996 Eurocode 6: Design of masonry structuresEN 1997 Eurocode 7: Geotechnical designEN 1998 Eurocode 8: Design of structures for earthquake resistanceEN 1999 Eurocode 9: Design of aluminium structures

Page 6: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Structure of the Structure of the EurocodesEurocodes

EN 1990

EN 1991

EN 1992 EN 1993 EN 1994EN 1995 EN 1996 EN 1999

EN 1998EN 1997

Actions on structures

Design and detailing

Geotechnical and Seismic design

Basis of structural design

Page 7: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

ab

cd

e

f

aa National National titletitle pagepagebb National National forewordforewordcc EN EN titletitle pagepagedd EN EN texttextee EN EN AnnexAnnex(es)(es)ff National National annexannex

National version of a EurocodeNational version of a Eurocode

Page 8: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

National Annex?National Annex?

• The member states refinement of the CEN released Eurocode to reflect it’s own national practices

• Values of Nationally Determined Parameters (NDP’s)• The decisions where main text allows alternatives• The choice to adopt informative annexes• Non-contradictory complementary information (NCCI)

Page 9: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

CIRIA C580CIRIA C580

Embedded retaining walls – guidance for economic design. London 2003

Page 10: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode 7Eurocode 7

Approved by CEN on 23 April 2004.

Page 11: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Release of Eurocode to BSI by CEN

Develop National Annex Modify Existing Standards

BSI Publish Eurocode with National Annex

2 Ye

ars

Coexistence of Eurocode with British Standard

Withdrawal of British Standard

3 Ye

arsImplementationImplementation

Page 12: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Operation and ApplicationOperation and Application

Principles

• General statements and definitions for which there is no alternative.

• Requirements for analytical models for which no alternative is permitted

• Principle clauses are identified with the letter‘P’• The verb ‘shall’ is used (meaning ‘must’)

Page 13: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Operation and ApplicationOperation and Application

Application rules

• Generally recognised rules which satisfy the Principles, but alternative rules may be used.

• Verbs ‘should’, ‘may’, ‘can’ etc used

Page 14: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

ContentsContents

Section 1: GeneralSection 2: Basis of geotechnical designSection 3: Geotechnical dataSection 4: Supervision of construction, monitoring and

maintenanceSection 5: Fill, dewatering, ground improvement and

reinforcement

Page 15: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

ContentsContents

Section 6: Spread foundationsSection 7: Pile foundationsSection 8: AnchoragesSection 9: Retaining structuresSection 10: Hydraulic failureSection 11: Overall stabilitySection 12: Embankments

Page 16: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

ContentsContents

Annex A: Recommended partial factors

Annex B-J: Supplementary information

EN1997-2 Performance and evaluation of field and laboratory measurements

Page 17: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

EurospeakEurospeak

Actions (c.f. Loads)Permanent & Variable (c.f. Dead and Live)

Geotechnical action 1.5.2.1Action transmitted to the structure by the ground, fill, standing water or ground-water

Page 18: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

EurospeakEurospeak 1.5.2.71.5.2.7

Resistance• capacity ……. to withstand actions without mechanical

failure e.g. resistance of the ground, bending resistance, buckling resistance, tensile resistance

Norm• Standard – EN Euro-Norm i.e. European Standard

Characteristic• The value of a parameter to be used in design; usually

the value of an action only likely to occur with a probability of 0.02 per annum or a material property likely to be achieved with a probability of 0.95.

Page 19: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Calculations 2.4Calculations 2.4

Characteristic Values 2.4.5.2 (2)P

• The characteristic value of a geotechnical parameter shall be selected as a cautious estimate of the value affecting the occurrence of the limit state.

Page 20: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Soil ParametersSoil Parameters

Page 21: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Ultimate Limit States 2.4.7Ultimate Limit States 2.4.7

Internal failure or excessive deformation of the structure or structural elements, including e.g. footings, piles or basement walls, in which the strength of structural materials is significant in providing resistance (STR);

Page 22: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Ultimate Limit States 2.4.7 (STR)Ultimate Limit States 2.4.7 (STR)

Page 23: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Ultimate Limit States 2.4.7Ultimate Limit States 2.4.7

Failure or excessive deformation of the ground, in which the strength of soil or rock is significant in providing resistance (GEO);

NOTE Limit state GEO is often critical to the sizing of structural elements involved in foundations or retaining structures and sometimes to the strength of structural elements.

Page 24: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Ultimate Limit States 2.4.7 (GEO)Ultimate Limit States 2.4.7 (GEO)

Page 25: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Design Approach 1 2.4.7.3.4.2Design Approach 1 2.4.7.3.4.2

Check for a limit state of rupture or excessive deformation:– Combination 1: A1 “+” M1 “+” R1– Combination 2: A2 “+” M2 “+” R1

(Except for the design of axially loaded piles and anchors.)

Page 26: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode 7 Table A.3Eurocode 7 Table A.3

Page 27: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode 7 Table A.4Eurocode 7 Table A.4

Page 28: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode 7 Table A.13Eurocode 7 Table A.13

Page 29: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Ground surfaces 9.3.2.2 (2)Ground surfaces 9.3.2.2 (2)

• Ultimate limit state – level of resisting ground lowered by Δa, where Δa is, for normal levels of control:

• 10% of wall height for a cantilever or 10% of depth below the lowest support, limited to a maximum of 0.5m

• i.e. “Overdig” allowance

Page 30: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Embedded retaining wallEmbedded retaining wall

Soil strength ÷ γM(table A.4)

Combination 2 to determine toe depth (Geo) i.e. BS 8002 design

Surcharge x γF equiv. =1.3/1.0 (table A.3)

Include ‘over-dig’

Resulting section forces (BM & SF) x γF =1.0 (table A.3) – Design values.

Soil stiffness ÷ 2 (CIRIA C580)

Page 31: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Embedded retaining wallEmbedded retaining wall

Soil strength ÷ γM =1.0 (table A.4)

Combination 1 to determine section forces (Str) i.e.BS 8110 design

Surcharge x γF equiv.=1.5/1.35 (table A.3)

Include ‘over-dig’

Resulting section forces (BM & SF) x γF =1.35 (table A.3) – Design values.

Soil stiffness unfactored

Page 32: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Embedded retaining wallEmbedded retaining wall

Soil strength unfactored

Serviceability loadcase to determine deflections

Surcharge unfactored

No ‘over-dig’

Soil stiffness unfactored

Page 33: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Execution Standards 7.1(3)pExecution Standards 7.1(3)p

BS EN 1536:1999, Execution of special geotechnical works -bored piles

BS EN 12063:2000, for sheet pile walls,

BS EN 12699:2000, for displacement piles.

BS EN 14199 for micro-piles.

Page 34: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The Jubilee Line Extension, LondonThe Jubilee Line Extension, LondonNorth Greenwich stationNorth Greenwich station

Page 35: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich StationNorth Greenwich Station

• Large internal space• No internal slabs• Temporary propping of

retaining walls difficult

Page 36: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

• Box designed independently of any temporary works

London clay

Thames Gravel

Alluvium

Made Ground

30m

22m

Page 37: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

• Difficult to build station around temporary props

London clay

Thames Gravel

Alluvium

Made Ground

Page 38: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich stationConstruction sequenceConstruction sequence

• Install hard soft secant piles

London clay

Thames Gravel

Alluvium

Made Ground

Page 39: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

• Excavate outside box to 3m depth• Excavate inside to 7.5m depth• Install ground anchors

London clay

Thames Gravel

Alluvium

Made Ground

Page 40: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

• Excavate to 15.5m depth• Install prop

London clay

Thames Gravel

Alluvium

Made Ground

Page 41: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

• Complete excavation

London clay

Thames Gravel

Alluvium

Made Ground

Page 42: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

Open excavation with ground anchors

Construction of box avoided building around props

Page 43: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

Page 44: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

• Analysed with WALLAP (beam-on-springs program)• Prop load 1500kN/m (unfactored) i.e 9000kN/prop @ 6m• Measured typically 6000kN, one prop 15000kN (2500kN/m)• Note mismatch of stiffnesses - ground anchors and props

London clay

Thames Gravel

Alluvium

Made Ground

Page 45: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

North Greenwich stationNorth Greenwich station

Analysis now with factored soils, overdig, softening, minimum fluid pressure (i.e. in accordance with Eurocode 7 and CIRIA C580)

Wall is not stable

Page 46: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The Jubilee Line Extension, LondonThe Jubilee Line Extension, LondonCanary Wharf stationCanary Wharf station

Page 47: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Canary Wharf stationCanary Wharf station

Diaphragm walls installed from the base of an old dock

Page 48: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Diaphragm wallsDiaphragm walls

Dug under bentonite using a Grab or Hydrofraise

Insert reinforcement cage and concrete using tremie pipe

Page 49: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Diaphragm wallsDiaphragm walls

Typical joint detail.

Straight panels, tee panels or corner panels.

Grab length 2.8m typical.

Page 50: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Diaphragm WallsDiaphragm Walls

Reinforcement details:• Allow for the tremie pipe;• Allow for the unreinforced

area close to the CWS stop end;

• For installation, the cage must be lifted.

Page 51: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Canary Wharf station Canary Wharf station –– slot stabilityslot stability

Page 52: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The Copenhagen MetroThe Copenhagen MetroEurocode 2Eurocode 2

Page 53: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Copenhagen Metro Copenhagen Metro -- Eurocode 2Eurocode 2

Rules for Buildings

Piles require some special attention for buildability

Page 54: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Copenhagen Metro Copenhagen Metro -- Eurocode 2Eurocode 2

Analysis programs unavailable

Spreadsheets written and checked

Page 55: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Comparison of BS5400 and the Metro Specification Comparison of BS5400 and the Metro Specification

0.2mm0.25mmMaximum crack width

90mm75mmMinimum cover for structures cast against the ground

50mm35mmMinimum cover for durability for retaining wall members, as concrete cast in non-aggressive ground

fck=30N/mm2fcu=35N/mm2Concrete grade

100 years120 yearsDesign life

Metro Specification

BS5400Requirements

Page 56: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Stage 1 Install retaining wall

Stage 2 Excavate and construct roof

Stage3 Excavate and construct waling beam

Stage 4 Excavate to formation level

Top down construction sequence Top down construction sequence

Page 57: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Station crossStation cross--sectionsection

Structure hung from roof

Large fixed-end moments

Page 58: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

CrackCrack--width for concrete sectionswidth for concrete sections

Calculate crack width at cover required for durability

Page 59: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode 2 Eurocode 2 -- Crack width calculationCrack width calculation

Page 60: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Eurocode 2 Eurocode 2 -- Lapping of barsLapping of bars

Principle – not permitted to lap bars greater than 32mm diameter. (Not satisfied)

Page 61: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Bundles of equivalent diameter greater than 55mm not permitted (Application Rule)

Eurocode 2 Eurocode 2 -- Equivalent diameter of bar bundlesEquivalent diameter of bar bundles

Bundles to be considered as notional bars for purposes of crack-width calculation (Application Rule)

Page 62: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Equivalent perimeter of bundle = 40 x (2 + π) = 206mm

Number of bars in bundle:

(Assume 40mm diameter bars)

Two:

Equivalent diameter of a single bar =

56mm

Perimeter of equivalent bar = 56.6 x π = 178mm

Eurocode 2 Eurocode 2 -- Equivalent diameter of bar bundlesEquivalent diameter of bar bundles

Page 63: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Equivalent perimeter of bundle = 40 x (3 + π) = 246mm

Number of bars in bundle:

(Assume 40mm diameter bars)

Three:

Equivalent diameter of a single bar =

69.3mm

Perimeter of equivalent bar = 69.3 x π = 218mm

Eurocode 2 Eurocode 2 -- Equivalent diameter of bar bundlesEquivalent diameter of bar bundles

Page 64: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Circular sections Circular sections –– shear capacityshear capacity• Feltham I, The Structural

Engineer, June 2004

Page 65: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The Copenhagen MetroThe Copenhagen MetroThe observational method at The observational method at

Norreport stationNorreport station

Page 66: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The Copenhagen MetroThe Copenhagen MetroThe observational method at The observational method at

Norreport stationNorreport station

• Description of the project.• Construction sequence

and the observational method.

• Application• Results

Page 67: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

The Copenhagen MetroThe Copenhagen Metro

Route of the Metro

Above ground works, on embankment or viaduct.

Page 68: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

ChallengesChallenges• 100 year design life -

0.2mm crackwidth limit.• Design to Eurocodes.• First significant deep

basement construction in Copenhagen.

• Environmental standards.

• Programme constraints.• Architectural

requirements.

Page 69: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Architectural challengesArchitectural challenges

• Natural light available at platform level.

• No internal columns at platform level.

• Minimal internal propping.• Danish minimalist design details.

Page 70: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Retaining wall detailsRetaining wall details

Ground Conditions:

Made ground

Glacial till

Limestone

Page 71: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Islands Brygge

Ved Stadsgraven

Islands Brygge

Ved Stadsgraven

TBM TBM ProgrammeProgramme

Page 72: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Ved Stadsgraven

Islands Brygge

Havnegade

TBM TBM ProgrammeProgramme

Ved Stadsgraven

Page 73: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Christianshavn StationChristianshavn Station

Bottom up construction sequence with temporary props

Page 74: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Havnegade

Islands Brygge

Ved Stadsgraven

TBM TBM ProgrammeProgramme

Page 75: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Medieval BridgeMedieval Bridge

Page 76: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Norreport Station Norreport Station -- Bridge Bridge FoundationsFoundations

Page 77: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Medieval BridgeMedieval Bridge

Page 78: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Application of the observational Application of the observational techniquetechnique

Page 79: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Observation method managementObservation method management

Settlement control engineer

Comet

Retaining wall designer

Bachy Soletanche

Permanent works designer

Maunsell

Client’s representative

Cowi

Temporary works designer

Carillion

Design manager

Comet

Site manager

Comet

Page 80: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Page 81: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Excavation down to Waling BeamExcavation down to Waling Beam

Page 82: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Excavation down to Base SlabExcavation down to Base Slab

Page 83: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

Page 84: Design and construction of metro stations and underground

November 2008Engineers Ireland

Geotechnical Society of Ireland

EurocodesEurocodes