Design and Built-A4

Embed Size (px)

Citation preview

  • 7/27/2019 Design and Built-A4

    1/2

    BPP( Borang PelaksanaanProjek )

    Project Brief

    Ceiling Cost

    JKR - HOPT,HODT (Ar,C&S, M+E,QS)

    Site visit

    Verification of site/

    problems

    For direct nego only

    Prepare Q-plan/ shedule ofimplementation

    Contractor to submit list of

    consultants for JKRapproval

    Checking/Enquiring scopeof works

    Completeness/comprehensiveness ofbrief

    Receive Appointment letter &

    Project

    Brief from MOH

    Appoint Project teamHOPT + HODT

    Issue Letter of Intent to

    contractor

    (appointed by Treasury)

    Confirm project brief KKM + JKR

    Duration depends on

    size and complexity of

    projects.

    1 week

    4-10 weeks

    1

    2

    3

    4

    1 week

    1

    2

    3

    4

    Technical requirement Ar,

    C&S, M&E, QS, MedicalEquipment ,ICT, base onfinalised project brief.

    Prepare concept design

    Ar, Medical Planner, C&S,M&E,QS, MedicalEquipment, ICT

    Technical evaluation

    Financial Evaluation

    For Direct Nego, activitydatais done at this stage

    Activity Data interactionJKR,KKM + End User +specialists

    Formulation of Pre Bid.Document

    Issue Pre-Bid document

    to contractor/ contractors

    Contractor to prepare Technical+ Financial proposal submit to

    JKR

    4-8 weeks

    6-8 weeks

    Concept Design

    will take 2-3

    months)

    5

    6

    7

    JKR evaluate Contractor

    /Contractors

    Proposal

    Layout Floor Plan and Activity

    Data interaction

    6-8 weeks

    8-16 weeks

    8

    9

    5

    6

    7

    8

    9

    DESIGN AND BUILT WORK PROCESS(Direct Negotiation and Tender)

    LAMPIRAN B

  • 7/27/2019 Design and Built-A4

    2/2

    Activity DatainteractionJKR,KKM + EndUser + specialists

    4- 6 weeks

    10 LOI to Contractor

    Activity Data interaction11

    11

    Between Government(JKR,KKM,EPU,Treasury) and Contractor

    Project Director (PD)Pengarah Caw. KerjaKesihatan

    Coordination of alldisciplines involved atthis stage is veryimportant

    Const. Plan (C-Plan)

    Site meetings

    Const. Auditing

    Mock-up inspection

    Calibration

    Const. /shop /as builtdrawings.

    Change committee

    NCR

    Evaluation report andPrice Negotiation

    Treasury Approval

    Delegation of power - Minister of

    Works to JKR Director General

    4- 6weeks

    1-2 weeks

    12

    13

    14

    1-2 weeks12

    13

    14

    Issue Letter of Award to

    Contractor

    2 weeks

    Construction 24-36 weeks

    15

    16

    16

    Room inspection

    M&E equip / system

    C&S Equip/ system

    Medical Equipment

    ICT

    Inventory counting For

    all Medical Equipment Key lebelling

    Defect Rectification

    Plan PreventiveMaintenance

    Meetings

    After 2 yearsmaintenance

    Defects rectified

    Testing and commissioning

    - Issue CPC from JKR.

    - CF from Local Authority

    2-3 months17

    182- 6 weeks

    Handing Over Project

    to KKM

    Defect Liability/ Maintenance

    Period24 weeks20

    19

    Issue Certificate of Making Good

    Defect (CMGD) to Contractor21

    17

    18

    20

    19

    21