Upload
hoangkhuong
View
230
Download
0
Embed Size (px)
Citation preview
By Gan Cheng Chian,
Bekaert Singapore Pte Ltd
Design and application of fibre reinforced concrete floor and tunnel
linings with 3D, 4D & 5D steel fibres
Steel fibre reinforced concrete for segmental lining 3
Typical cage reinforcement for precast segmental lining
Steel fibre reinforced concrete for segmental lining 4
STEEL FIBRES REINFORCED CONCRETE (SFRC) for precast segmental
lining
Steel fibre reinforced concrete for segmental lining
Technical Advantages
• High impact resistance.
• Multidirectional reinforcement
• No damages at Edges and corner due to the spalling forces
•Post fire durability superior to rebar
• Fire protection in combination with micro –polypropilene fibre
•DURABILITY IMPROVEMENT
Economical Advantages
• Increase of productivity, time saving
• Reduction of repair cost of damage segments
• Elimination of storage and positioning of reinforcement cages.
• Use of automatic dosing and dispensing equipment linked to the control
panel of the batching plant.
Advantages of Dramix Steel Fibre in Segmental Lining
Steel fibre reinforced concrete for segmental lining 6
Dramix® fibres are made from prime quality hard
drawn steel wire to ensure high tensile strength and
close tolerances. CE LABEL system 1
A hooked end which slowly deforms during
pull-out is generally considered as the best
form of anchorage.
The glueing of the fibres into bundles
guarantees quick and easy mixing for a
homogeneous distribution
Dramix RC-80/60-BM especially designed for
precast Segment
Length = 60 mm
Diameter = 0.75 mm
L/d = 80
TS = min. 1550 Mpa
RC-80/60-BM
BEKAERT PROPOSAL
Steel fibre reinforced concrete for segmental lining 7
Segmental lining design procedure
Demolding
Stacking
Transport
& Placing
Service
Bending
Tension
Compression
Impact
Shrinkage &
Temperature
Effects
Acting forces
Steel fibre reinforced concrete for segmental lining 8
Voice of Designer
Load Case Rebar Steel FibreGround loading O.K O.K
Handling and stacking O.K O.K
Bolting O.K O.K
Erection O.K O.K
Grout Pressure O.K O.K
Ram Loading ? O.K
Application of SFRC is possible by selecting a static system for the tunnel ring
in such a way that there is minimal stress from bending moments.
Steel fibre reinforced concrete for segmental lining 9
SFRC ONLY : Hi-Perform
Combined solution: low amount of rebars for critical
bending moment + SF : High Perform
Combined solution : low amount of rebars for bursting+SF
Extreme Network
PRECAST SEGMENT : DURABILITY FIRST REQUIREMENT IN EACH CASE
Rebars(No amount decrease) +
Steel Fibre (min fibre dosage):
Extreme Network
RC80/60BM REMAINS THE REFERENCE PRODUCT
Steel fibre reinforced concrete for segmental lining 10
QA/QC Testing – EN14651 Beam Testing – Design values
Dramix®
Segmental Linings Coming Soon
1.Klang Valley MRT Line 1 Malaysia – 3600tons RC-80/60-BM based on 9.3km of twin tunnels
– Supplying 50% - on-going.
2.Klang Valley MRT Circle Line Malaysia – 30km of twin tunnels – Approx. 12000tons RC-
80/60-BM based on Line 1 – 1st Qtr 2014 start bidding
3.Klang Valley MRT Green Line Malaysia – 7km of twin tunnels – Approx. 2500tons RC-80/60-
BM based on Line 1 – 3rd Qtr 2014 start bidding
4.Thomson Line MRT Singapore – 3km of twin tunnels – Approx. 1200tons RC-80/60-BM –
Waiting for award
5.Shatin to Central Link C1107 Hong Kong – 400tons RC-80/60-BN – Waiting for award
6.Tuen Mun to Chek Lap Kok Link Hong Kong – 6000tons RC-80/60-BN – Bidding now
7.Tokyo Outer Ring Road Concrete Segments – 42000tons ZP306 – Start end-2013
8.Linear Tokyo to Nagoya Maglev Concrete Segments – 52500tons RC-65/40-CN – Start 2015
9.Jakarta Metro – Planning Stage
10.Bangkok Metro – Planning Stage
Steel fibre reinforced concrete for segmental lining 12
Deflection (mm) =0.46 =1.31 =3.00 =2.15
QA/QC Testing – BS14651 Beam Testing – Design Values
Inner tunnel lining:
Crack control
Durability
Slope stabilisation Retaining wall
Steel Fibre Reinforced Shotcrete
Mesh Reinforced Shotcrete
Shotcrete consumption is high due to:
•irregular rock surface
•filling up voids
•high rebound on the mesh wires
Steel Fibre Reinforced Shotcrete
17
Mesh Reinforced Sprayed Concrete
Design Information Required
•Thickness of concrete
•Concrete quality
•Size of mesh
•Spacing of rock bolts
Steel Fibre Reinforced Shotcrete - SFRS Design Consideration
18
Fiber Reinforced Sprayed Concrete
Design Proposal
•Proposed concrete thickness
•Proposed steel fibre type & dosage
•Proposed concrete quality
•Proposed performance criteria
SFRS Design Consideration
19
1 mesh reinforced layer versus fibre reinforced sprayed concrete layer
Design of 1 mesh reinforced layer
SFRS Design Consideration
21
Double mesh reinforced layer versus fibre reinforced sprayed concrete layer
Design of 2 mesh reinforced layer
SFRS Design Consideration
22
Double mesh reinforced layer versus fibre reinforced sprayed concrete layer
Design of steel fibre reinforced sprayed concrete layer
SFRS Design Consideration
23
Efnarc toughness classification:
500 J: min. requirement; rock; small diameter tunnel
700 J: standard; less good rock
1000 J: high ductility for bad soil condition
500mm
600mm
500mm600mm
100x100mm
F
deflection
25mm
loa
d
QA/QC Testing – EN14488-5 Panel Testing – Design Values
Some Shotcrete case references in SEA
1. San Roque tunnel – Shotcrete (Philippines)
2. Bakun HPPE – Shotcrete (Philippines)
3. Bakun Hydro Power Project – Shotcrete (Malaysia)
4. Pergau Hydropower – Shotcrete/Cast Lining (Malaysia)
5. Mandai Cavern – Shotcrete (Singapore)
6. Marina MRT line – C825 – Shotcrete/Precast Segments (Singapore)
7. MRT Circle Line – C852 – Shotcrete (Singapore)
8. Deep Tunnel Sewerage System – T02, T04 & T06 – Shotcrete (Singapore)
9. Tanggari Hydropower and Sinkarak Hydropower - shotcrete (Indonesia)
10. Theun Hinboun Hydropower – Shotcrete (Laos)
11. Miri water transfer tunnel – Inner concrete lining (Malaysia)
12. Hai Van Pass Road Tunnels – Shotcrete (Vietnam)
13. Hai Van Pass Railway Rehabilitation Tunnels – Shotcrete (Vietnam)
14. MRT Circle Line – C856 – Shotcrete/Precast Segments (Singapore)
15. Nam Ngum 2 Hydropower Project – Shotcrete (Laos)
16. Jurong Rock Caverns – Shotcrete/Cast Lining (Singapore)
17. Ambuklao & Binga Rehabilitation – Shotcrete (Philippines)
18. Pahang Selangor Raw Water Transfer Tunnel – Shotcrete (Malaysia)
19. Peusanggan Hydropower Project – Shotcrete (Indonesia)
SFRC Floor Design Considerations
- Slab-on-grade • WHEEL LOADS – VEHICLE MODELS
• RACK LOADS – RACKING LAYOUTS & HEIGHTS
• LINE LOADS – BRICK WALL THICKNESS & HEIGHTS
• UNIFORMLY DISTRIBUTED LOADS – GIVING FALSE RESULTS
• SUBBASE INFORMATION
• JOINT INFORMATION – DISTANCE, SAWCUTS & DOWELS
• CONCRETE QUALITY
• SOG 10000sqm x 0.16m x 15 = 24tons
- Slab-on-piles • WHEEL LOADS – VEHICLE MODELS
• RACK LOADS – RACKING LAYOUTS & HEIGHTS
• UNIFORMLY DISTRIBUTED LOADS
• PILE SIZE & SPACINGS
• CONCRETE QUALITY
• SOP 10000sqm x 0.2m x 30 = 60tons
26
5D, 4D & 3D Fibre types
31
Perfect anchorage
+ Ultra high tensile
+ Ductile wire
3DDra
mix
®D
ram
ix®
4DDra
mix
®
5DDra
mix
®
Perfect anchorage
Ductile wire
Ultra high
tensile
5D, 4D & 3D Fibre types
32
Pull out
Max. force at high elongation of the wire
Similar slip pattern but for the at a substantially
higher level
*Comparison between a 3D – 4D – 5D with the same length and diameter
Max. force is utilized, no slip
5D, 4D & 3D Fibre types
33
Beam test
33
Bending hardening
Biggest gain in fR3
Biggest gain in fR1
fR1 => SLS design fR3 => ULS design
CMOD
Combislab
- Project info • Date of execution : 2013
• Location : Belgium, Brussels
• Contractor : CFE
• Owner : ELIA
• Outdoor restraint ground slab (Pond)
Project Reference
ELIA at Brussels (Belgium) - Pond
- Technical solution • Fibre type : Dramix® 4D 65/60BG
• Dosage : 35 kg/m³
• Additional reinforcement : Ø10mm / 150 mm (top)
• Slab thickness : 300 mm
• Concrete quality : C30/37
• Design based on a restraint shrinkage
- Benefits • Cost saving : ≈ 0,00 EUR (time saving not included)
• Time saving : because the shape is complicated
• Water-tight (wk = 0,30 mm)
Combislab
- Project info • 06/02/2014
• Sydney Australia
• ADCO Construction
• Australia Post
Project Reference
Australia Post
- Technical solution • Dramix® 4D 65/60BG
• 25 & 30 kg/m3
• SL81 (7.6ɸ @ 100) & SL91 (8.6ɸ @ 100)
• 150mm & 230mm
• C32/40
• 15,000m2
• 25 tonne post load. Client required NO opening
joints – all fully tied.
- Benefits • 15,000m2 completed in 8 pours over 9 days
• Alternative Post Tensioned option would not
have been completed in time for handover
CombiSlab
- Include picture here - Project info
• Nov 2013
• NZ
• Fonterra
Project Reference
Fonterra, joint free truck wash roadway
- Technical solution • Dramix 4D 65/60BG
• 25kg/m3
• Top steel; 10mm bars, 120mm c/c
• 180mm
• C40/50
• Joint free, watertight roadway
- Benefits • This solution reduced the conventional
reinforcing by about 50pc; from two layers of
bar to one layer
CombiSlab
- Project info • January 2014
• NZ
• Conslab
Project Reference
Panalpina saw cut free yard slab
- Technical solution • Dramix 4D 65/60BG
• 20kg/m3
• Top mesh; 6.3mm wires at 150mm c/c
• 150mm
• C40/50
• External saw cut free panels, 30 x 30m
- Benefits • This solution was used to remove the cost
and risk associated with maintaining and
repairing saw cut joints
CombiSlab
- Project info • February 2014
• Australia, Sydney
• Australia Post
Project Reference
Loading dock, joint free
- Technical solution • Dramix 4D 65/60BG
• 25kg/m3
• Top mesh; 7.6mm wire at 100mm c/c
• 150mm
• C32/40
• Joint free restrained loading dock
- Benefits • This solution was used to remove the cost
and risk associated with maintaining and
repairing saw cut and movement joints
CladRack foundation
- Project info • Date: September 2013
• Location: Kingdom Saudi Arabia, Jeddah
• Contractor: RCR Flooring
• Owner: SIBCO
• Hyder Consultant approved Bekaert design
Project Reference
SIBCO Pepsi Mega Plant
- Technical solution • Dramix® 4D 65/60BG )
• 30 kg/m3
• Top mesh (5,24cm²/m), bottom only along
the perimeter (d=12mm/150mm)
• 700mm
• C30/37
• Bigger panels sizes due to thinner slab
- Benefits • Cost saving : 22% =185.000 €
• Time saving : 370 hours
• Fast anchorage (as all columns with
chemical anchors
CladRack foundation
Project Reference
Schenker logistics
- Project info • Date: 2013
• Location: Zwevegem - Belgium
- Benefits • Seamless strip at loading docks
• Increased productivity in handling
• Reduced maintenance costs
62
Contact
Bekaert Singapore Pte Ltd
3 Church Street
Level 8 Samsung Hub
Singapore 049483
T +65 97859171
www.bekaert.com/building
Bekaert is always near you