Page 1 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
Design and Access Statement
for Access for All Footbridge at
Stratford-upon-Avon Railway Station
Station Road Stratford-upon-Avon Warwickshire
CV37 6PL Physical Site Assessment
The existing railway station dates from 1859 and originally formed part of the Great Western
Railway network. The station was originally a 2 platform through line. This was expanded to the
current 3 platform configuration in the late 19th Century at which time the buildings on
platform 2 were demolished and the existing footbridge, dated 1891, was added for access
between platforms.
The station continued as a through line until 1976 from which time it has served as a terminus. The
station is located adjacent to the embankment forming the Alcester Road bridging over
the tracks to the south. The existing station is viewed in the round, from above via the
Alcester Road, from its eastern approach along Station Road and the new residential
properties proposed to be constructed there, from the north within the station car park
and from the west, across the tracks, from the supermarket car park. The plan below
illustrates the existing site arrangement.
Page 2 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
The station buildings are located to the east of the tracks and typical of their time
predominantly dating from 1859 and retaining many original features but also having
undergone numerous modifications. They are single storey red brick with extensive timber
clad, steel framed, dagger boarded canopies to both rail and non-rail elevations and buff
brick features to window and door openings.
View from Alcester Road View from Station Road approach
View from station car park View looking south to the footbridge and station building
View of cranked double stair to island platform View of the footbridge from the Platform 1 access
The track arrangement and bridge over the Alcester Road result in an asymmetrical
platform arrangement with platform 1 extending further south than the island platforms 2 and 3
which themselves extend further t o t h e north. The station building is located east of the
Page 3 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
View of platforms looking north, platform 1 on the right
View of platforms looking south, Platform 1 with canopy and station building on the left, Alcester Road bridge in centre of
shot.
Page 4 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
track on the southern end of platform 1 with the existing footbridge circa 10m to its north.
Access to platforms 2 and 3 is gained only from platform 1. This is predominantly by way of
the existing footbridge although a grade track (barrow) crossing also exists to the north of
the platforms. These forms of access do not comply with current Network Rail station standards
for step free access nor do they meet the requirements of the Equality Act 2010.
The existing footbridge, which is dated 1891, is a metal riveted structure with roof
arranged with stairs to half landings at mid-height, with the stairs continuing up to the deck
level at ninety degrees to the initial rise from the half landing. The Western end of the
bridge has stairs up to the half landing from both North and South, whilst the Eastern
(station building) end of the bridge has stairs only from the South; these serve the main
desire line pedestrian flows, as all passengers using the bridge will wish to enter and leave
the station to the South (station building) side of the bridge, whilst passengers on the
island platforms could be to either side of the bridge. The bridge is narrow and without lift
access.
The bridge has some heritage value, and has been well maintained with a recent major
refurbishment by Network Rail in order to maintain its traditional appearance and to
preserve its structural integrity.
Platform 1 to the north of the footbridge is largely open with lighting, signage, passenger
information and 2 covered cycle storage facilities. It is bounded to the east (car park) by a
steel railing fence. The island platforms 2 and 3 to north and south of the footbridge are
similarly largely open with lighting, signage, seating, advertising hoardings and, to the north
of the footbridge, a covered waiting shelter. Both platforms include some planting.
Platform 1 currently serves Birmingham and London routes. The island platforms serve both London routes and specials services such as steam or heritage trains which run on an ad-hoc basis.
Position of Stratford-upon-Avon Station in the Rail Network
In the period 2011-12 Stratford-upon-Avon station accounted for 855,000 originating or terminating passenger journeys1. This figure is an increase of approximately 210,000 passenger journeys since 2009/10; representing a roughly 30% growth in patronage in just 2 years, and demonstrating the importance of the Station as a gateway to the Town for residents, commuters and tourists alike.
It is also important to note that in the last 10 years the number of journeys made on the national rail network using a Disabled Persons Rail Card has increased by 165%2; the need for an accessible footbridge at the Station is becoming increasingly important if Stratford-upon-Avon is to be a fully accessible railway station.
1 ORR, Estimate of Station Usage Data, 2011-12, http://www.rail-
reg.gov.uk/upload/xlsx/station_usage_estimates_1112.xlsx
2 ATOC, Train Companies Praised at New Accessibility Forum, http://www.atoc.org/media-centre/latest-press-releases/2012/11/08/train-companies-praised-at-new-accessibility-forum-100765/
Page 5 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
Planning Policy
The application is accompanied by a separate Planning Statement outlining how the proposed development accords with local and national transport, accessibility and rail safety policies.
Introduction to the Development
As noted above, the existing station facilities do not meet the accessibility needs of station
users in a suitable way for access to the island platforms 2 and 3. As part of the wider
Network Rail Access For All (AfA) nationwide 10 year programme to improve accessibility
to key stations on the rail network, Warwickshire County Council are supporting the proposal to
provide step-free access to the island platforms.
AfA is aimed at providing easier access within station sites for wheel chair users, people
with mobility issues, parents with pushchairs, assistance dogs and passengers with heavy
or awkward luggage with the provision of automatic lifts and improved staircases when compared
to the existing.
In response to the historic nature of the existing station building and footbridge together
with the arrangement of canopies and platforms, the development proposes a new
separate lift, stair and bridge construction, with the new span being c.15m to the north of
the existing.
Involvement The scheme has been subject to a widespread consultative process with demonstrated
support from:
The local public;
Station users;
Statutory authorities (Warwickshire County Council, Stratford District Council &
Centro);
Network Rail;
London Midland; and
Chiltern Railways.
Evaluation The need for the development has been identified through the N e t w o r k R a i l Access for All programme and the Warwickshire 3rd Local Transport Plan and the proposals are in keeping with the existing station use and support the consolidation and expansion of public transport patronage to the Stratford-upon-Avon area. The scheme proposals responds to contemporary user needs and is in accordance with the station owner and operator
Page 6 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
obligations under the Equality Act 2010 and their duty of care for the safe use of the station facility.
View of station building showing brick detailing Trackside frontage of station building with timber
and canopy dagger-board canopy over
DESIGN
Site Analysis The existing station and surroundings are typical of their age with a substantial, single
storey red brick station building, timber and steel canopies and metal framed footbridge.
The site is served by a dedicated access road, Station Road, from the main Alcester Road
which leads to a dedicated surface car park fronting the station building.
Page 7 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
It should be noted that the view from the east will shortly change with the construction of
the new Station Road and residential housing on the site of the former Cattle Market.
However, the new footbridge should provide little visual intrusion into this development,
being as it is within the footprint of the station itself. It should also be noted that the view
from the north, towards the station, is limited to that from the car park as the area is
surrounded by industrial units with little public access.
The station buildings and footbridge are concentrated to the south of the station site
responding to the primary site access (blue arrow above) with pedestrian access/ egress
to platforms through the station building and the gap between building and footbridge
(yellow arrows above).
Blue badge parking is located adjacent to the existing bridge, less than 30m from the
proposed position of the new lift shaft towers. This will help those who are unable to walk
long distances to cross between platforms and their parked car.
Consideration of Alternative Options
1. Do Nothing
The simplest and easiest option which would result in no impact to the fabric,
appearance or structure of the existing station site would be to do nothing. However, this
would not solve the Equality Act 2010 accessibility issues at the station that are
presented by the stepped footbridge and barrow crossing. This option was therefore not
taken further.
2. New Bridge at Southern End of Station
Analysis of the existing station identified at an early stage that the introduction of
lift, stair and new bridge a t t h e s o u t h e r n e n d o f t h e p l a t f o r m s
would be incompatible with the existing functions, form and historical context of
the station building and canopies. It was therefore decided that the existing
station buildings would remain unaltered by the proposal.
3. Adaptation of the Existing Bridge to Accept Lifts
Investigation work was undertaken to determine if lifts could be added to the existing
stepped footbridge (as had occurred at a number of other stations in the West Midlands
e.g. Dorridge) however there were a number of shortcomings identified with the
option to adapt the existing bridge to introduce lift access. These being the
narrowness of the bridge span and stairs, steepness of the stairs and the cranked
form of the double landing staircase design. The structural framework needed to achieve
the necessary clearances over the platform edge and track, from the new lift shafts and
the existing bridge, would have cost more than a new standalone bridge. In addition:
A new temporary bridge would be required to enable passengers to cross between
platforms whilst construction work was being undertaken;
Page 8 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
The visual form of the existing bridge would have become unrecognisable on
completion of the work.
4. Swing Bridge
A swing bridge between platforms at the southern end of the station was briefly
investigated to provide an at-grade crossing that did not permanently obstruct the
passage of trains to and from the head-shunt under the Alcester Road bridge. However,
this option was rejected by Network Rail on operational and railway safety grounds.
5. Relocated Barrow Crossing
A relocated barrow crossing at the southern end of the station platforms was also
considered (as this is outside of the day to day operations of the station). However this
was also rejected on railway safety grounds but also did not meet the objectives of
providing a unassisted crossing facility between platforms.
Use To retain the defining heritage assets of the site, to meet Network Rail standards for
stepless access within railway stations, to meet the needs of the Equality Act 2010 and to
respond to the site and building constraints the development proposes a new separate
structure consisting of a lift and stairs to both platform 1 and the island platforms 2 and 3
with an open bridge span.
Layout
The new bridge is proposed to be located to the north of the existing footbridge. This location will
minimise the extra distance that users of the bridge will need to travel – especially bearing in mind
that those users who require step-free access are those least able to move a greater distance than
necessary. Indeed, Chapter 2 Part (20) of the Equalities Equality Act 2010 makes the following
provision:
Page 9 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
“… where a physical feature puts a disabled person at a substantial disadvantage in relation to a
relevant matter in comparison with persons who are not disabled, to take such steps as it is
reasonable to have to take to avoid the disadvantage”.
Accordingly, a location as close to the existing footbridge as practicable is required to ensure that disabled or mobility impaired persons are not put at a disadvantage by having to travel much further than an able bodied person in order to use cross between platforms via the new bridge.
In addition, this location has been determined following consideration of the following factors:
A position at the South end of the existing station building is not viable, as it is not possible to construct any structure in front of the existing station building, opposite the south end of the island platforms, due to the need to maintain a clear platform for a minimum distance from the operational railway.
A number of consultation responses highlighted concerns that the new bridge could impact on the visual appeal of the station if located too close to the existing structure.
The existing platform lighting levels at the station needs to be taken into account in the
location of the bridge to ensure that there are no contrasts in lighting level that could pose a
security or safety hazard;
Moving the bridge further down the platform to the north would result in the loss of a
number of mature trees that exist between Platform 1 and the station car park; if located
significantly further to the north, it would also impact on the visibility of the network signals
from the train driver’s viewpoint, especially for short formation trains, when stopped at the
designated places on the platforms. Relocating signals and/or relocating the designated
train stopping points is not considered a viable option due to knock-on implications.
The new bridge will impinge on 3 car parking spaces (due to the width of the lift shaft); in the
proposed location, the bridge will sit next to the relocated bicycle shelter; and
The proposed location is approximately 30m from the blue badge parking within the station car park, thus minimising the amount of distance passengers have to travel if using this facility. This is an important consideration because one of the eligibility criteria for a blue badge is that holders are unable to walk unaided for more than 50m.
All trains stop to the South of the existing bridge towards the South end of the platforms; as nearly all trains from Stratford-upon-Avon are four carriages or shorter, nearly the entire length of the train is normally to the South of the bridges. Locating the new bridge further to the North on the platforms will therefore require users to travel this extra distance both to reach the bridge, and to return to reach the trains at the island platforms.
This l o c a t i o n will therefore offer the most convenient access for users whilst retaining the
station defining heritage assets.
Page 10 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
To comply with Network Rail guidance for the design of vertical circulation the b a s e o f
t h e new l i f t t o w e r structure will be located 5m from the base of the existing stairs.
The gap between bridge spans, new to existing, will therefore be circa. 15m. This spacing
will provide safe access and maximum convenience for the user whilst protecting the
identity of the existing station and bridge.
Amount And Scale Of Development
To meet user demand the proposed new lifts will have a capacity of 16 persons requiring a lift shaft
plan dimension of 2,425mm square. The bridge span itself will provide a clear pedestrian
width of 2,000mm and will have a vertical clearance from top of track to underside of bridge
of 5.1m, in accordance with national Network Rail standards to allow for possible future
electrification of the line. It should be noted that this requirement was also stipulated by
Network Rail in the design of the new Stratford Parkway Station footbridge.
This will result in the underside of the new bridge being higher than the existing by circa.
900mm. Similarly and to meet station usage, the stairs will have a clear width of 1600mm
with base, intermediate and top landings to meet accessibility guidelines and Network Rail
standards. Both stairs and bridge will be uncovered. All will be based upon Network Rail
standards to achieve full accessibility to the island platforms.
The height of the lift towers is also dictated by the requirement to have sufficient space above the
lift car to install manual hoisting equipment to raise or lower the lift car in the event of power
failure of maintenance requirements.
This design brief therefore dictates a scale and size of development to provide bridge
clearance over track and lift overrun above the bridge deck level. Stylistically the options
for this brief have been investigated through the standard NR design, a contemporary
option and a heritage option. These are illustrated below.
Page 11 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
Option 1: Standard Network Rail Design Standard NR bridge, lift and
stairs. Red brick base to 3m
above platform with
composite grey metal
cladding above. Painted
steel bridge span and stairs.
Monopitched roof to lift
shafts. View from the north with
form of existing bridge visible
behind.
Option 2: Contemporary Bridge Design Contemporary bridge, lift
and stairs. Red brick base
to underside of bridge,
steel bridge deck with clear
glazed sides. Lift shafts
formed with flat panel
stainless steel cladding and
flat roof. View from the north with
form of existing bridge
visible behind.
Option 3: Heritage Bridge Design Heritage bridge, lift and
stairs. Red brick cladding
throughout with buff brick
detailing mimicking the
existing station building.
Painted steel bridge span
with colours matching
existing footbridge. Timber
dagger-board canopies over
lift exits and pyramid standing
seam roofs to lift shafts. View from the north with form
of existing bridge visible
behind
Page 12 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
Consultation
The three design approaches illustrated above were displayed for public consultation.
Public response demonstrated a clear and substantial preference for the heritage design
approach complimenting the existing station design.
The developed design is illustrated below.
As Existing:
View south from platform
1 looking back at the
existing footbridge with
station building beyond
As Proposed: View of the evolved design
proposal illustrating the
use of materials, forms
details and colours to
harmonise with the
existing station buildings
Page 13 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
Appearance
Following the public exhibition at which alternative bridge designs were illustrated, including a
standard Network Rail design, a Heritage based design and a contemporary modern design (as
illustrated above), feedback received strongly supported a Heritage design. As such, a Heritage
design has been developed for this proposal.
The design draws upon the original station materials of red facing brick with buff brick details
to doors and windows, dark grey zinc pitched roofs, timber dagger-boards to canopies,
painted to colour match the existing dagger-boards, and distinctive 2 colour paint
scheme to the steel bridge structure, colour matched to the colours of the existing
bridge, to create a harmonious whole across new and existing structures.
Weather protection to lift entry and exit is provided by way of canopies to all levels. At
platform level these are lightweight glass cantilevered off the lift shaft to reduce posts and
impediment at platform level. In the more visible location to the top of stairs these are
pitched roofs with painted dagger-board details and ridge finial to reflect the existing bridge
and station canopies.
Materials The materials proposed are shown on the Appendix to this Statement
Landscape Landscape works are restricted to the necessary improvement of pedestrian paving to the base of
the proposed stairs and lift entrances at platform level. No other landscape works to the station will be carried out as they are outside the remit of the Access for All funding package.
Access The application site is a railway station, with excellent access by train; access by bus will be
improved to enable bus routes to stop opposite the station building, instead of on Alcester Road,
on completion of the redevelopment of the former Cattle Market site. Access to the station site by
foot and bicycle from Stratford-upon-Avon town centre is excellent. There is also a newly
expanded car park adjacent to the station, with Blue Badge parking spaces close to the access to
the station platforms and the base of the new bridge.
The development provides for improved accessibility within the existing station to meet
Network Rail best practice guidance through the AfA scheme of works to provide step free
access within the station to all platforms. As such the proposal will provide significantly
improved access within station sites for wheel chair users, people with mobility issues,
parents with pushchairs, assistance dogs and passengers with heavy or awkward luggage as
well as for all other general users, with the provision of automatic lifts and improved staircases
in accordance with AfA best practice.
Page 14 | Stratford-upon-Avon Railway Station AfA Footbridge Design and Access Statement
The lifts will be operated by means of a call button and intercom system, connected to the station ticket office during opening hours and to the Centro control room otherwise, which will ensure that the use of the lifts is monitored and secure for users, and available at all times that access to and from the island platforms is required. This will greatly reduce the risk of vandalism to the lifts and bridge but also will provide an emergency call facility in case of incident when the lift is in use.
Conclusion
This Design & Access statement has set out how the context of the site and its surroundings have been taken into account through the design process and how the design of the proposed development has responded to both the constraints and opportunities identified. The process has involved meaningful consultation with local residents and other informed stakeholders. The views expressed through this process have influenced the development of the scheme, particularly in terms of the Heritage Style of the bridge and its location on the station platform. The illustrative plans which accompany the proposals represent the product of a successful balancing of the site assets and constraints, to achieve a development which is both sustainable and deliverable. It is considered that the proposed Stratford Town Station Access for All Footbridge consists of a
high quality design which is appropriate to the site context with safe and inclusive access for
pedestrians, and especially the mobility impaired, and those with luggage / pushchairs etc. Its
provision will ensure that Station forms a world-class gateway to Stratford-upon-Avon for many
years to come.