"We Manage to Succeed" Description of Project - Advanced Technology Building This project involves the new construction of an advanced technology building (approximately 55,000 SF) on the campus of Victor Valley Community College. It also includes a new bridge and associated sitework. Site preparation includes removal of asphalt paving, concrete paving, concrete curb, site clearing and grading. It also includes excava- tion of basement and imported backfill. Site development includes asphalt paving, con- crete paved fire lane, concrete paving, con- crete curb, concrete ramp, site drainage, site lighting, allowance for land- scaping and maintenance, concrete retaining wall, metal guardrail, metal handrail, concrete stairs and railing, road markings, exterior sign- age, concrete seat and mis- cellaneous accessories. Site utilities includes domes- tic and fire water, site gas distribution, meter and seis- mic shut-off valve, sewage, central plant well water and chilled water distribution, temporary cooling tower con- nection, main normal power feeders, telecommunication feeders and trade demolition, including protection and rerouting of existing lines. Concrete includes reinforced concrete column bases, wall footings, and elevator pit. It also includes reinforced concrete columns, retaining walls, slab on grade, concrete curb, equipment pads, concrete topping and finish, concrete stairs and architectural concrete topping at deck surface. Masonry include reinforced concrete block. Steel includes steel framing, metal decking, metal fascia, metal guardrail and miscellane- ous metals. It also include metal stairs and railings, and elevator pit ladder. Wood and plastic includes plywood sheathing, base cabinet, wall cabinet, knee space and countertops. Thermal and moisture protection includes wa- terproofing, rigid insulation, batt insulation, built-up roofing, metal tile roofing, walkway pads, cant strip, cover flashing, metal gutter, metal coping, roof hatch, caulking and sealant. Doors and windows includes exterior aluminum framed windows with insulated glazing, interior aluminum win- dows and glazing, aluminum glazed doors, metal doors, slid- ing glass door, revolving door, wood door, and roll-up door. Finishes include partitions of metal furring, metal stud fram- ing, gypsum board, gypsum board sheathing, and shaft liner. Finishes of carpet, ce- ramic tile, vinyl composition, sheet vinyl, quarry tile, con- crete sealer, carpet tile, carpet mat, column cover, acoustical tile and paint. Specialties include corner guards, toilet parti- tions, toilet and bathroom accessories, grab bars, mirrors, shelving, markerboards, interior signage, fire extinguisher and cabinets, tele- phone enclosure and shelf, entrance mat, pro- jection screens, display case, horizontal blinds, receptionist desk and access flooring. Plumbing includes sanitary fixtures and rough- in, backflow preventor, condensate drainage, water heater (gas and electric), industrial cold water, gas distribution and surface water drain- age, including elevator drainage.

Description of Project - Advanced Technology Building June 06 report... · Description of Project - Advanced Technology Building ... lighting, allowance for land- ... Description

Embed Size (px)

Citation preview

"We Manage to Succeed"

Description of Project - Advanced Technology Building

This project involves the new construction of an advanced technology building (approximately 55,000 SF) on the campus of Victor Valley Community College. It also includes a new bridge and associated sitework.

Site preparation includes removal of asphalt paving, concrete paving, concrete curb, site clearing and grading. It also includes excava-tion of basement and imported backfill.

Site development includes asphalt paving, con-crete paved fire lane, concrete paving, con-crete curb, concrete ramp, site drainage, site lighting, allowance for land-scaping and maintenance, concrete retaining wall, metal guardrail, metal handrail, concrete stairs and railing, road markings, exterior sign-age, concrete seat and mis-cellaneous accessories.

Site utilities includes domes-tic and fire water, site gas distribution, meter and seis-mic shut-off valve, sewage, central plant well water and chilled water distribution, temporary cooling tower con-nection, main normal power feeders, telecommunication feeders and trade demolition, including protection and rerouting of existing lines.

Concrete includes reinforced concrete column bases, wall footings, and elevator pit. It also includes reinforced concrete columns, retaining walls, slab on grade, concrete curb, equipment pads, concrete topping and finish, concrete stairs and architectural concrete topping at deck surface.

Masonry include reinforced concrete block.

Steel includes steel framing, metal decking,

metal fascia, metal guardrail and miscellane-ous metals. It also include metal stairs and railings, and elevator pit ladder.

Wood and plastic includes plywood sheathing, base cabinet, wall cabinet, knee space and countertops.

Thermal and moisture protection includes wa-terproofing, rigid insulation, batt insulation, built-up roofing, metal tile roofing, walkway pads, cant strip, cover flashing, metal gutter, metal coping, roof hatch, caulking and sealant.

Doors and windows includes exterior aluminum framed windows with insulated glazing, interior aluminum win-dows and glazing, aluminum glazed doors, metal doors, slid-ing glass door, revolving door, wood door, and roll-up door.

Finishes include partitions of metal furring, metal stud fram-ing, gypsum board, gypsum board sheathing, and shaft liner. Finishes of carpet, ce-ramic tile, vinyl composition, sheet vinyl, quarry tile, con-crete sealer, carpet tile, carpet mat, column cover, acoustical tile and paint.

Specialties include corner guards, toilet parti-tions, toilet and bathroom accessories, grab bars, mirrors, shelving, markerboards, interior signage, fire extinguisher and cabinets, tele-phone enclosure and shelf, entrance mat, pro-jection screens, display case, horizontal blinds, receptionist desk and access flooring.

Plumbing includes sanitary fixtures and rough-in, backflow preventor, condensate drainage, water heater (gas and electric), industrial cold water, gas distribution and surface water drain-age, including elevator drainage.

"We Manage to Succeed"

Description of Project - Advanced Technology Building

Heating, ventilating and air conditioning in-cludes gas fired boiler, thermal expansion and circulation, hydronic distribution, air handling units, including split heat pumps and fancoil units, sound attenuation, terminal VAV reheat boxes, air distribution supply, return and ex-haust ductwork, underground concrete en-cased ductwork, diffusers, registers and grilles, DDC controls and instrumentation, testing and balancing, and unit ventilation exhaust.

Electrical includes main normal power distribu-tion, machine and user convenience power, lighting and power specialties, telephone/data including conduit and cable, centralized clocks, A/V security conduit only and fire alarm sys-tem.

Fire protection includes complete automatic wet sprinkler system.

"We Manage to Succeed"

Site plan - Advanced Technology Building

"We Manage to Succeed"

Site plan - Advanced Technology Building First floor plan

"We Manage to Succeed"

CONTRACTORS - Advanced Technology Building

Contract Number/Bid Package Contractor Contract Amount

Bid Package No. 01 Grading Sitework $644,929.00

Prime Vance Corporation

Bid Package No. 02 General Construction $3,395,000.00

Prime T.B. Penick & Sons

Bid Package No. 03 Structural Steel $1,489,610.00

Prime KCB Towers

Bid Package No. 04 Doors, Frames, & Hardware $162,760.00

Prime EJ Enterprises

Bid Package No. 05 Painting $101,000.00

Prime Simmons & Wood

Bid Package No. 06 Specialties $94,732.00

Prime Inland Empire Architectural Specialties

Bid Package No. 07 HVAC $1,541,856.00

Prime Air-Ex Air Conditioning

Bid Package No. 08 Plumbing $652,322.00

Prime Pro-Craft Plumbing

Bid Package No. 09 Electrical $1,469,000.00

Prime RDM Electric

Bid Package No. 10 Glazing $850,844.00

Prime E & R Glass Contractors

Bid Package No. 11 Flooring $76,048.00

Prime Continental Flooring

Bid Package No. 12 Masonry $862,930.00

Prime Nibblelink Masonry Bid Package No. 13 Plaster & Gypsum Board $685,585.00 Prime Caston Plastering & Drywall

Bid Package No. 14 $52,400.00

Prime Inland Pacific Tile

Ceramic/Quarry Tile

"We Manage to Succeed"

CONTRACTORS - Advanced Technology Building

Contract Number/Bid Package Contractor Contract Amount

Bid Package No. 15 Roofing $400,000.00

Prime Bell Roof Company

Bid Package No. 16 Acoustical Ceilings & Insulation $305,647.00

Prime Elljay Acoustics

Bid Package No. 17 Casework $139,000.00

Prime Lozano Caseworks

Bid Package No. 18 Sheet Metal $551,000.00

Prime United Contractors

Bid Package No. 19 Hydraulic Elevator $154,900.00

Prime RVH Constructors

Bid Package No. 20 Fire Sprinklers $117,500.00

Prime United Automatic Sprinklers

Bid Package No. 21 Landscaping $253,100.00

Prime Worthington Construction

Bid Package No. 22 Access Flooring $247,000.00

Prime Partition Specialties

"We Manage to Succeed"

Schedule - Advanced Technology Building

The construction of the Advanced Technology Building consists of several phases; grading, fencing, foundation, building frame construction, systems installation, landscaping, and finishes. Next 30 Days The following tasks will be starting within the next thirty days. They are also shown on a calendar that follows. The entire schedule is also included. SITEWORK

Install U/G Irrigation Connection 7/03/06 U/G Utilities Completed 7/07/06 Sat/Sun - Connection To Exist Systems [Min. Interruption] 7/10/06 Clear & Grub 7/12/06 Adv. Tech. Bldg. Pad Survey @ West 7/17/06 Excavate Footings @ West 7/18/06 Adv. Tech. Bldg. Pad Survey @ East 7/18/06 Excavation For U/G Conc. Tunnel 7/19/06 Frp U/G Mechanical D/B Concrete Tunnel 7/24/06

Form/Reinf Footings @ West 7/25/06

"We Manage to Succeed"

Pictures are taken frequently during construction. The following pages represent activities that took place during the month of June 2006. Photos are taken on a digital camera and then transferred to CD-ROM for archiving. At the completion of the project, the CD-ROM (s) will be transmitted to the Maintenance and Operations Department for future reference. Besides creating a visual diary of the construction activities, they serve as a reference for future work that may need to be done. Locations of utilities, valves, clean-outs, storm drain trenches, and grading activities are typically cataloged. By utilizing the latest technology in monitoring the projects, Cal K-12 assures that the information will be accessible when the next modernization or upgrades are performed at campuses throughout the District. The pictures included in this report are representative and are not the full measure of pictures taken.

Photos - Advanced Technology Building

"We Manage to Succeed"

Site plan - Advanced Technology Building

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

"We Manage to Succeed"

Photos - pre construction pictures

July 2006Sunday Monday Tuesday Wednesday Thursday Friday Saturday

1

2 3 4 5 6 7 8

9 10 11 12 13 14 15

16 17 18 19 20 21 22

23 24 25 26 27 28 29

30 31

GENERAL CONDITIONS, 412 daysINSTALL U/G ELECTRICAL / FIBER OPTICS, 15 days

GENERAL CONDITIONS, 412 daysINSTALL U/G ELECTRICAL / FIBER OPTICS, 15 days

U/G UTILITIES COMINSTL U/G IRRIGATION CONN, 3 days

GENERAL CONDITIONS, 412 daysSAT/SUN - CONN TO EXIST SYSTEMS [ CLEAR & GRUB, 3 days

GENERAL CONDITIONS, 412 daysADV. TECH. BLDG. EXCAVATE FOOTINGS @ WEST, 5 days

ADV. TECH. BLDG. EXCAV FOR U/G CONC. TUNNEL, 3 days

GENERAL CONDITIONS, 412 daysEXCAVATE FOOTINGS @ WEST, 5 days FORM/REINF FOOTINGS @ WEST, 10 days

FRP U/G MECH D/B CONC TUNNEL, 25 days

GENERAL CONDITIONS, 412 daysFORM/REINF FOOTINGS @ WEST, 10 daysFRP U/G MECH D/B CONC TUNNEL, 25 days

ID Task Name % Start Finish

1 Advanced Technology Building 4% 4/17/06 12/13/07

2 NOTICE TO PROCEED 100% 4/17/06 4/17/06

4 INST TEMP FENCING/POWER/TOILETS/SIGNAGE 90% 4/17/06 4/19/06

3 MOBILIZATION 100% 4/20/06 4/28/06

5 INDEPENDENT UTILITY SURVEY [BID PKG 1] 80% 4/20/06 4/21/06

6 ATTEND PRE-DEMO WALK-THRU w/ARCHITECT 100% 4/21/06 4/21/06

8 SAWCUT EXIST. CONC / SITE DEMO 80% 4/24/06 5/5/06

123 INSTALL U/G SEWER & MH's 90% 5/8/06 6/2/06

127 INSTALL STORM DRAINS, CB'S & DRAINS 80% 5/8/06 6/2/06

128 INSTL U/G COLD WATER / FIRE WATER & APPURT. 80% 6/5/06 6/30/06

168 INSTALL GAS LINE/SHUT-OFF VALVES 95% 6/5/06 6/23/06

35 INSTALL U/G ELECTRICAL / FIBER OPTICS 0% 6/19/06 7/7/06

169 INSTL U/G IRRIGATION CONN 75% 7/3/06 7/5/06

120 U/G UTILITIES COMPLETED 90% 7/7/06 7/7/06

7 SAT/SUN - CONN TO EXIST SYSTEMS [MIN. INTERUPTN] 80% 7/10/06 7/11/06

9 CLEAR & GRUB 90% 7/12/06 7/14/06

12 ADV. TECH. BLDG. PAD SURVEY @ WEST 0% 7/17/06 7/17/06

17 EXCAVATE FOOTINGS @ WEST 0% 7/18/06 7/24/06

48 ADV. TECH. BLDG. PAD SURVEY @ EAST 0% 7/18/06 7/18/06

49 EXCAV FOR U/G CONC. TUNNEL 0% 7/19/06 7/21/06

53 FRP U/G MECH D/B CONC TUNNEL 0% 7/24/06 8/25/06

20 FORM/REINF FOOTINGS @ WEST 0% 7/25/06 8/7/06

24 POUR CONC FOOTINGS @ WEST 0% 8/8/06 8/10/06

26 CMU STARTER WALLS @ WEST 0% 8/11/06 8/24/06

28 BACKFILL FOR SOG @ WEST 0% 8/25/06 8/30/06

54 BACKFILL & COMPACT 0% 8/28/06 9/1/06

11 INST U/S ELECTRICAL @ WEST 0% 8/31/06 9/13/06

13 INST U/S PLUMBING @ WEST 0% 8/31/06 9/13/06

16 INST U/S FIRE WATER @ WEST 0% 8/31/06 9/13/06

22 FORM/REINF SLAB ON GRADE @ WEST 0% 8/31/06 9/20/06

18 EXCAVATE FOOTINGS @ EAST 0% 9/4/06 9/8/06

19 FORM/REINF FTGS @ EAST [Incl Basement/Elev Pit] 0% 9/11/06 9/22/06

31 INSTALL VAPOUR BARRIER @ WEST 0% 9/14/06 9/15/06

40 POUR SOG @ WEST 0% 9/21/06 9/22/06

23 POUR CONC FOOTINGS @ EAST 0% 9/25/06 9/27/06

25 CURE & PROTECT SOG @ WEST 0% 9/25/06 9/29/06

27 CMU STARTER WALLS @ EAST 0% 9/28/06 10/11/06

30 FRP CIP COLUMNS @ WEST 0% 10/2/06 10/6/06

34 INST STR STEEL COLUMNS @ WEST 0% 10/2/06 10/6/06

43 INSTALL CMU WALLS I @ WEST 0% 10/2/06 10/27/06

29 BACKFILL FOR SOG @ EAST 0% 10/12/06 10/17/06

10 INST U/S ELECTRICAL @ EAST 0% 10/18/06 10/31/06

14 INST U/S PLUMBING @ EAST 0% 10/18/06 10/31/06

15 INST U/S FIRE WATER @ EAST 0% 10/18/06 10/31/06

A

Victor Valley Community CollegeAdvanced Technology Building

Full Schedule Page 1 of 5

ID Task Name % Start Finish

21 FORM/REINF SOG @ EAST [Incl. Basement/Elev Pit] 0% 10/18/06 11/7/06

36 INST STRUCT. STEEL BEAMS/TRUSSES @ WEST 0% 10/30/06 12/1/06

41 INST STEEL DOOR FRAMES @ WEST 0% 10/30/06 11/3/06

51 INSTALL CMU WALLS II @ WEST 0% 10/30/06 11/24/06

32 INSTALL VAPOUR BARRIER @ EAST 0% 11/1/06 11/2/06

39 POUR SOG @ EAST [Incl. Basement] 0% 11/8/06 11/9/06

58 CURE & PROTECT SOG @ EAST 0% 11/9/06 11/16/06

38 WELD STR STEEL @ WEST 0% 11/13/06 12/15/06

44 INSTALL CMU WALLS I @ EAST 0% 11/17/06 12/14/06

59 FRP CIP COLUMNS @ EAST [Incl Basement] 0% 11/17/06 11/30/06

60 FRP BASEMENT CONC RET WALL I 0% 11/17/06 12/14/06

64 INST STR STEEL COLUMNS @ EAST 0% 11/17/06 11/23/06

45 INST HI/LO ROOF METAL DECK @ WEST 0% 12/4/06 12/15/06

61 INST BASEMENT MASONRY 0% 12/15/06 1/11/07

62 FRP BASEMENT CONC RET WALL II 0% 12/15/06 1/11/07

46 INST PLYWD SHEATHING OVER RIGID INSUL'N @ WEST 0% 12/18/06 12/29/06

89 DROP HANGERS/PIPE SPRTS THRU MTL DECK [WEST] 0% 12/18/06 1/12/07

57 INST WALL/CEILING FRAMING @ WEST 0% 1/1/07 1/26/07

47 ROUGH-IN PLUMBING @ WEST 0% 1/8/07 2/2/07

50 ROUGH-IN FIRE SPRINKLER @ WEST 0% 1/8/07 2/2/07

52 INSTALL CMU WALLS II @ EAST 0% 1/12/07 2/8/07

68 INST METAL DECK OVER BASEMENT 0% 1/12/07 1/18/07

75 INST STRUCT. STEEL BEAMS/TRUSSES @ EAST 0% 1/12/07 2/8/07

83 INST STEEL DOOR FRAMES @ EAST 0% 1/12/07 1/18/07

55 INST BLDG INSULATION @ WEST 0% 1/15/07 1/26/07

56 INSTALL DOOR FRAMES @ WEST 0% 1/15/07 1/26/07

70 POUR/CURE CONC OVER MTL DECK 0% 1/19/07 1/25/07

33 ROUGH-IN ELECTRICAL @ WEST 0% 1/22/07 2/16/07

37 ROUGH-IN LOW VOLT ELECTRICAL @ WEST 0% 1/22/07 2/16/07

42 ROUGH-IN MECH/HVAC @ WEST 0% 1/22/07 2/16/07

73 FRP BASEMENT STAIRS 0% 1/26/07 2/22/07

80 WELD STR STEEL @ EAST 0% 1/26/07 3/1/07

84 INSTALL GLASS BLOCK WALLS 0% 1/26/07 2/1/07

94 HANG DRYWALL @ WEST 0% 1/29/07 2/23/07

85 INST HI/LO ROOF METAL DECK @ EAST 0% 2/16/07 3/1/07

97 TAPE & FINISH DRYWALL @ WEST 0% 2/26/07 3/23/07

77 INST METAL STAIRS 0% 3/2/07 3/8/07

87 INST PLYWD SHEATHING OVER RIGID INSUL'N @ EAST 0% 3/2/07 3/15/07

98 DROP HANGERS/PIPE SPRTS THRU MTL DECK [EAST] 0% 3/2/07 3/29/07

115 INST FLASHING & SHT MTL 0% 3/2/07 3/22/07

117 INST ROOF ACCESS HATCHES 0% 3/2/07 3/8/07

129 INST EQUIPMENT PLATFORMS 0% 3/2/07 3/8/07

78 INST STL RAILINGS/HANDRAILS 0% 3/9/07 3/15/07

125 INST MOD. BUILT-UP ROOFING SYSTEM 0% 3/9/07 3/29/07

A

Victor Valley Community CollegeAdvanced Technology Building

Full Schedule Page 2 of 5

ID Task Name % Start Finish

99 INST WALL/CEILING FRAMING @ EAST 0% 3/16/07 4/12/07

105 ROUGH-IN PLUMBING @ EAST 0% 3/23/07 4/19/07

106 ROUGH-IN FIRE SPRINKLERS @ EAST 0% 3/23/07 4/19/07

108 INST BLDG. INSULATION @ EAST 0% 3/30/07 4/12/07

109 INSTALL DOOR FRAMES @ EAST 0% 3/30/07 4/12/07

130 INST ROOFTOP HVAC EQUIPMENT 0% 3/30/07 4/5/07

159 INST MET-TILE ROOFING AT HIGH ROOF 0% 3/30/07 4/12/07

101 ROUGH-IN ELECTRICAL @ EAST 0% 4/6/07 5/3/07

102 ROUGH-IN LOW VOLT ELECTRICAL @ EAST 0% 4/6/07 5/3/07

104 ROUGH-IN MECH/HVAC @ EAST 0% 4/6/07 5/3/07

158 INST ROOF PROT WALK PADS 0% 4/6/07 4/10/07

167 RESUME SITEWORK 0% 4/12/07 4/12/07

184 START WALKWAY - BRIDGE 0% 4/12/07 4/12/07

111 HANG DRYWALL @ EAST 0% 4/13/07 5/10/07

160 INST GUTTERS & DOWNSPOUTS 0% 4/13/07 4/26/07

173 INST EXT STAIRWELL FTGS / STAIRS @ EAST 0% 4/13/07 5/24/07

185 TEMP FENCING, POWER, TEMP FACILITIES 0% 4/13/07 4/17/07

186 SUB-EXCAV & COMPACT @ FTGS 0% 4/18/07 4/26/07

112 TAPE & FINISH DRYWALL @ EAST 0% 4/27/07 5/24/07

132 INST EXT. PLASTER @ SOFFIT 0% 4/27/07 6/7/07

166 INST EXT. STEEL PIPE GUARD RAIL 0% 4/27/07 5/10/07

187 EXCAVATE WALKWAY FTGS. 0% 4/27/07 5/1/07

188 INST FORMS / REBAR @ WALKWAY FTGS 0% 5/2/07 5/4/07

174 INST SITE WALLS @ STAIRWELLS [EAST] 0% 5/4/07 6/14/07

189 POUR WALKWAY FTGS. 0% 5/7/07 5/7/07

190 FORM / REBAR CONC SUPPORT WALLS/COLS. 0% 5/8/07 5/28/07

161 INSTALL DOWNSPOUTS 0% 5/11/07 5/17/07

163 INST EXTERIOR LIGHTING 0% 5/11/07 5/17/07

191 ROUGH - ELECTRICAL 0% 5/15/07 5/17/07

165 INST EXTR BLDG. SIGNAGE 0% 5/18/07 5/22/07

162 INSTALL METAL LOUVER 0% 5/23/07 5/29/07

67 INST CERAMIC/QUARRY TILES 0% 5/25/07 6/21/07

76 INSTALL WINDOWS/GLAZING I 0% 5/25/07 6/14/07

114 INST GLAZED ALUM CURTAIN WALLS 0% 5/25/07 6/14/07

116 SET EXT HOLLOW MTL FRAMES 0% 5/25/07 6/7/07

121 INST ELEVATOR DR FRMS / HYDR. / GUIDE RAILS 0% 5/25/07 6/14/07

124 INST ROLL-DOWN DRS 0% 5/25/07 5/31/07

192 POUR / STRIP CONC SPRT WALLS/COLS. 0% 5/29/07 6/1/07

164 INST EXTERIOR PAINT/ANTI-GRAFFITTI 0% 6/1/07 6/14/07

193 BACKFILL & COMPACT @ WALKWAY FTGS 0% 6/4/07 6/7/07

72 INSTALL EXT/INT DOORS 0% 6/8/07 6/21/07

118 INST ENTRANCES & STOREFRONTS 0% 6/8/07 7/5/07

170 INST U/G HYDRONIC PIPE [TO END OF NEW ACCESS RD] 0% 6/8/07 7/5/07

194 DELIVER & STAGE W/W STR. STEEL 0% 6/8/07 6/12/07

A

Victor Valley Community CollegeAdvanced Technology Building

Full Schedule Page 3 of 5

ID Task Name % Start Finish

195 ERECT/INSTALL WALKWAY STR. STEEL 0% 6/13/07 7/3/07

63 PAINT / WALL COVERINGS I 0% 6/15/07 7/12/07

93 INSTALL WINDOWS/GLAZING II 0% 6/15/07 7/12/07

175 BACKFILL & COMPACT 0% 6/15/07 6/28/07

69 FINISH PLUMBING 0% 6/22/07 7/19/07

74 INST HARDWARE 0% 6/22/07 7/5/07

66 INST ACOUSTIC CEILING GRID 0% 6/29/07 7/12/07

131 FINE GRADE 0% 6/29/07 7/5/07

196 INST WALKWAY METAL DECKING 0% 7/4/07 7/10/07

119 INST AUTO SLIDING DRS 0% 7/6/07 7/12/07

133 ON-SITE CONC CURBS/RAMPS/FLATWORK (WEST) 0% 7/6/07 8/16/07

134 INSTALL IRRIGATION 0% 7/6/07 8/2/07

171 INST U/G HYDRONIC PIPE II [TO CNTRL PLNT] 0% 7/6/07 8/16/07

197 INST AREA DRAINS & PLUMBING 0% 7/11/07 7/12/07

79 FINISH ELECT/ FIXTURES/SWITCHBRD 0% 7/13/07 8/16/07

81 FINISH FIRE LIFE SAFETY & TELECOM DEVICES 0% 7/13/07 8/16/07

82 FINISH MECH / HVAC 0% 7/13/07 8/16/07

86 FINISH FIRE SPRINKLERS 0% 7/13/07 8/2/07

126 INST GLASS RAILINGS @ BASEMENT 0% 7/13/07 7/19/07

137 INST COMP CIP COLUMN CAPITALS 0% 7/13/07 7/26/07

198 POUR CONC OVER WALKWAY DECK 0% 7/13/07 7/17/07

199 FRAMING / HR BACKING @ W/W SIDE WALLS 0% 7/18/07 7/31/07

71 TOILET PARTITIONS & ACCESS. 0% 7/20/07 8/2/07

136 INSTALL LANDSCAPING 0% 7/20/07 8/16/07

200 CONT. ROUGH ELECTRICAL 0% 7/20/07 7/24/07

201 INST W/W LATH & PLASTER 0% 8/1/07 8/21/07

172 U/G UTILITIES COMPLETED II 0% 8/16/07 8/16/07

176 ON-SITE CONC CURBS/RAMPS/FLATWORK (EAST) 0% 8/16/07 9/27/07

65 PAINT / WALL COVERINGS II 0% 8/17/07 9/13/07

88 ENERGIZE BLDG. 0% 8/17/07 8/21/07

177 INST AC PARKING LOT BASE 0% 8/17/07 8/23/07

181 INSTALL EXTR GUARDRAILS / HANDRAILS 0% 8/17/07 8/23/07

182 INST EXTR SIGNS/ID DEVICES 0% 8/17/07 8/23/07

140 TEST MECH/HVAC SYSTEMS 0% 8/22/07 8/28/07

141 TEST ELECTRICAL SYSTEMS 0% 8/22/07 8/24/07

202 INST SHT METAL COPING/EXP & SEP JTS 0% 8/22/07 8/28/07

107 INST ACOUST. CEILING TILES [LOW CEILING] 0% 8/24/07 9/6/07

135 INST TECTUM CEILING TILES [HIGH CEILING] 0% 8/24/07 8/30/07

178 INST AC PAVING @ PARKING LOT 4 0% 8/24/07 8/30/07

203 INSTALL WALKWAY HANDRAILS 0% 8/29/07 8/31/07

204 INST FIN ELECTRICAL/LIGHT FIXT. 0% 8/29/07 8/31/07

205 INST W/P FINISH TRAFFIC COATING 0% 9/3/07 9/7/07

91 INSTALL CARPET / CT / CM & BASE 0% 9/7/07 10/4/07

92 INSTAL RES/SHEET VINYL FLOORING 0% 9/7/07 9/13/07

A

Victor Valley Community CollegeAdvanced Technology Building

Full Schedule Page 4 of 5

ID Task Name % Start Finish

206 INST WALKWAY PAINT & SEALERS 0% 9/10/07 9/14/07

145 INST PROJECTION SCREENS 0% 9/13/07 9/20/07

103 INSTALL CASEWORK 0% 9/14/07 10/11/07

138 INST RAISED ACCESS FLRING 0% 9/14/07 10/11/07

144 INS ELEVATOR CAB / FIN CONN / ACTIVATE 0% 9/14/07 9/27/07

207 COMPLETE WALKWAY - BRIDGE 0% 9/14/07 9/14/07

100 FINISH CARPENTRY 0% 9/21/07 10/4/07

142 INST RECESED ENTRANCE MATS 0% 9/21/07 9/24/07

143 INST REVOLVING DR @ WEST ENTRANCE 0% 9/25/07 10/1/07

179 INST AC FIRE ACCESS RD BASE [EAST] 0% 9/28/07 10/4/07

147 INST DISPLAY CASES 0% 10/4/07 10/11/07

152 INST MARKER BOARDS 0% 10/4/07 10/11/07

95 INSTALL INT. SIGNAGE 0% 10/5/07 10/11/07

96 INST FIRE EXT CABS/UNITS 0% 10/5/07 10/11/07

148 INST MISC SPECIALTIES 0% 10/5/07 10/11/07

150 INST CORNER/END GUARDS 0% 10/5/07 10/9/07

151 INST MOTORIZED ROLER SHADES 0% 10/5/07 10/11/07

153 PROJECT CLOSE-OUT/WARRANTIES 0% 10/5/07 11/8/07

154 RECORD DOCS/O&M MANUALS 0% 10/5/07 11/8/07

155 IN-SERVICE DISTRICT STAFF TRAINING 0% 10/5/07 11/8/07

180 INSTALL AC PAVING [EAST] 0% 10/5/07 10/11/07

90 TEST & BALANCE HVAC 0% 10/12/07 10/18/07

139 INSTALL STRIPING [ALL AREAS] 0% 10/12/07 10/18/07

110 PUNCHLIST 0% 10/19/07 11/8/07

149 INSTL WHEEL BUMPERS 0% 10/19/07 10/22/07

183 SITE WASH-DOWN 0% 10/23/07 10/24/07

146 SITEWORK PUNCHLIST 0% 10/25/07 10/31/07

122 FINAL INSPECTION 0% 11/9/07 11/15/07

156 COMPL'N M/S [Excl. Holidays/Ordinal Sch.] 0% 11/13/07 11/13/07

157 HOLIDAY ALLOWANCE [APPL. TO ORDINAL SCH] 0% 11/16/07 12/13/07

113 PROJECT COMPLETION 0% 12/13/07 12/13/07

A

Victor Valley Community CollegeAdvanced Technology Building

Full Schedule Page 5 of 5

"We Manage to Succeed"

Photos - Progress shot at bridge location

"We Manage to Succeed"

Photos - Progress shot view of music building

"We Manage to Succeed"

Photos - Advanced Technology Building

Silt bed in excavation for bridge footings in lake

"We Manage to Succeed"

Photos - Advanced Technology Building

Slurry encasement

"We Manage to Succeed"

Photos - Advanced Technology Building

Start of 4160V power change over

"We Manage to Succeed"

Photos - Advanced Technology Building

Start of basement over excavation

"We Manage to Succeed"

Photos - Advanced Technology Building

Start of electrical duct bank

"We Manage to Succeed"

Photos - Advanced Technology Building

Storm drain between ATB and Music Building

"We Manage to Succeed"

Photos - Advanced Technology Building

Storm drain in fire road

"We Manage to Succeed"

Photos - Advanced Technology Building

Storm interceptor to lake

"We Manage to Succeed"

Photos - Advanced Technology Building

‘T’ and valves on city water

"We Manage to Succeed"

Photos - Advanced Technology Building

Thrust block on city water beside Art Building

"We Manage to Succeed"

Photos - Advanced Technology Building

Upgraded electrical encasement

"We Manage to Succeed"

Photos - Advanced Technology Building

Weekend pull of new power feeder