14
Upgrading the Energy Grid Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Upgrading the Energy Grid

Des Cox,

Senior Co-Ordinator,

Public Planning, EirGrid

Page 2: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

110kV220kV400kV

EirGrid – Who Are We? National Electricity Transmission System Operator(TSO)

EirGrid – Who We Are Not

National Electricity Distribution System Operator(DSO) – ESBWind Farm / Renewable Energy Developer

Page 3: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

EirGrid – Roles and Responsibilities

National Electricity Transmission System Operator (TSO).

Statutory Instrument No.445 of 2000 - Article 8(1)(a)…

“To operate and ensure the maintenance of and, if

necessary, develop a safe, secure, reliable, economical,

and efficient electricity transmission system, and to

explore and develop opportunities for interconnection

of its system with other systems, in all cases with a view to

ensuring that all reasonable demands for electricity are met

having due regard for the environment.”

Page 4: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Safe, Secure, Reliable

Costs & Efficiency

Community &Environment

Page 5: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Transmission Grid

• High capacity, efficient, reliable link between

– Generation Stations

– Demand centres

– Interconnections to other systems

• Grid needs to be developed when any of these change

400 kV 220 kV 110 kV440 km 4122 km1866 km

Page 6: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

WHITEGATE

KILTOY

CATHALEEN'SFALL

TAWNAGHMORE

MOY

RICHMOND

PLATIN

CASHLAGALWAY

ENNIS

DALLOWTURLOUGH

HILL

CRANE

CARLOW

CAHIR

DOON

ANNER

BALLYDINE

GREAT ISLAND

BARRYMORE

CHARLEVILLE

BANDON

DUNMANWAY

KNOCKEARAGH

RATHKEALE

MONEYPOINT

-ON-

BRINNY

KELLIS

BUTLERSTOWN

DRYBRIDGE

DUNDALK

MEATHHILL

BELLACORICK

CASHLA

TULLABRACK

MUNGRET

MONETEEN

SOMERSET

RAFFEEN

AGHADA

GOLAGH

GILRA

STRATFORD

KINNEGAD

BALLYLICKEY

DALTON

OLDSTREET

BALLYBEG

CUNGHILL

KILLOTERANCULLENAGH

TIPPERARY

GLENLARA

MEENTYCAT

DRUMKEEN

GORMAN

NENAGH

PROSPECT

SORNEHILLTRILLICK

DERRYBRIEN

AGANNYGAL

INNISCARRA

AUGHINISH

BOOLTIAGH

WEXFORD

BALLYWATER

OUGHTRAGH

TRALEE

ARVA

MULLAGHARLIN

ARIGNA

CARRIGADROHID

COOLROE

TRABEG

MARINA

PORTLAOISE

IKERRIN

TONROE

TARBERT

NAVAN

KNOCKUMBER

SHANKILL

CROSSHARTNETT’S

MACROOM

RATRUSSAN

THORNSBERRY

TRIEN

LETTERKENNY

CASTLEFARM

SEALROCK

GARROW

CLOON

DUNGARVAN

SLIGO

CARRICK

BALLYCUMMIN

TYNAGH

BINBANE

LISDRUM

LOUTH

ATHY

THURLES

COOKSTOWN

RB

BLAKE

FASSAROE

INCHICORE

POLLAPHUCA

FINGLASCOLLEGE

PARK

RINAWADE

CORDUFF

HUNTSTOWN

GLASMORE

NORTH WALLPOOLBEG

SHELLYBANKS

IRISHTOWN

DUNFIRTH

BALTRASNA

BALGRIFFIN

BARODA

DUNSTOWN

FLAGFORD

SHANNON

DRUMLINE

ATHLONE

MALLOW

CASTLEBAR

WATERFORD

KILKENNY

MULLINGAR

MONREAD

ARKLOW

SRANANAGH

CORDERRY

GLANLEE

LISHEEN

CLASHAVOON

DERRYIRON

COOMAGEARLAHY

CLONKEEN

CLIFF

CUSHALING

NEWBRIDGE

KILBARRY

SHANNONBRIDGE

LANESBORO

AHANE

ARDNACRUSHA

LIMERICK

KILLONAN

KNOCKRAHA

CORRACLASSY

GORTAWEE

WOODLAND

MAYNOOTH

KILTEEL

CARRICKMINES

TANDRAGEE

STRABANE

OMAGH

DUNGANNON

COLERAINE

LOGUESTOWN

LIMAVADY

MAGHERAFELT

TAMNAMORE

KILROOT

MOYLE INTERCONNECTOR

RATHGAEL

NEWTOWNARDS

BALLYNAHINCH

NEWRY

BANBRIDGE

KELLS

BALLYMENA

CREAGH

ANTRIM

DRUMNAKELLYWARINGSTOWN

COOLKEERAGH

BALLYLUMFORDLARNE

LISAGHMORE

LISBURN

CASTLEREAGH

ENNISKILLEN

KR

B

BC

CG

DG

PW

HT

FINAGHY

GG

CREDEN

• Government 40% target for renewables

• 4,000 MW of wind generation in Gate 3

• Balanced Regional Development

• Renewable and Conventional Generation

• Competitive Market

• Interconnection

• Sustainable Economic Development

Page 7: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Governing Context “The major investment underway in the high voltageelectricity transmission system under EirGrid’s Grid25Programme is the most important such investment inIreland’s transmission system for several generations.While the Government does not seek to directinfrastructure developers to particular sites or routesor technologies, the Government endorses, supportsand promotes the strategic programmes of theenergy infrastructure providers, particularly EirGrid’sGrid25 investment programme across the regionsand reaffirms that it is Government policy and in thenational interest, not least in the current economiccircumstances, that these investment programmesare delivered in the most cost efficient and timelyway possible, on the basis of the best availableknowledge and informed engagement on theimpacts and the costs of different engineering

solutions.” (July 2012)

Page 8: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

The Challenge of Grid Development

Page 9: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Grid 25 Initiatives

Page 10: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

2015 – Review of our Approach to Consultation

Page 11: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

2015 – Review of our Approach to

Tourism, Equine, and Agriculture

Page 12: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

2015 – Your Grid, Your Views, Your Tomorrow

• Explains the need for and drivers of grid development.

• These factors are the context for a broader discussion about how we should respond to these needs.

• 3 Strategy Statements:

- “Open engagement and inclusive consultation with local communities and stakeholders will be central to EirGrid’s approach to network development”

- “All practical technology options will be considered for network development”

- “The network will be optimised to minimise requirements for new infrastructure

Page 13: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Conclusions:

PUBLIC PLANNINGEirGrid

Policy

LawPrecedent

Process

Economics (Cost Effective) Community &

Environment

Politics Technical (Engineering)

Page 14: Des Cox, Senior Co-Ordinator, Public Planning, EirGrid

Thank You

Q&A

[email protected]