71
Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Stormwater Management Concept Plan Review Checklist Applicant: Applicant's Representative: Contact Name: Contact Name: Phone Number: Phone Number: Email: Email: A. General Project Information S = Satisfactory U = Unsatisfactory N/A = Not Applicable Item S U N/A Comments 1. Address and legal description of site 2. Vicinity map 3. Project narrative a. Purpose of project b. c. d. 4. 5. Incentive Standards a. Redevelopment b. Brownfield redevelopment c. d. Vertical density e. TOTAL VOLUME CREDIT (Up to 0.75 inches): 6. I. Non-structural practices a. Better Site Design b. Natural area conservation/restoration A completed application and stormwater management concept plan shall be submitted for each development subject to the management ordinance. The stormwater management concept plan shall be reviewed according to the following criteria. Impact of development on site hydrology and stormwater Description of stormwater management system Rationale for selection of stormwater treatment practices Evidence of hotspot runoff that may require pretreatment or enhanced High density (>7 units per Mixed use and transit-oriented development Type of stormwater management

dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Embed Size (px)

Citation preview

Page 1: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Stormwater Management Concept Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

Email: Email:

A. General Project InformationS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Address and legal description of site2. Vicinity map3. Project narrative

a. Purpose of projectb.

c.

d.

4.

5. Incentive Standards

a. Redevelopmentb. Brownfield redevelopmentc. High density (>7 units per acre)d. Vertical densitye.

TOTAL VOLUME CREDIT (Up to 0.75 inches):

6.I. Non-structural practices

a. Better Site Designb. Natural area conservation/restoration

A completed application and stormwater management concept plan shall be submitted for each development subject to the stormwater management ordinance. The stormwater management concept plan shall be reviewed according to the following criteria.

Impact of development on site hydrology and stormwater qualityDescription of stormwater management systemRationale for selection of stormwater treatment practices

Evidence of hotspot runoff that may require pretreatment or enhanced treatment

Mixed use and transit-oriented development

Type of stormwater management practices planned for site

Page 2: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

c. Sheet flow to vegetated filter stripd. Sheet flow to conservation areae. Impervious area disconnection

II. Structural practicesa. Stormwater pondb. Stormwater wetlandc. Filtrationd. Infiltratione. Bioretentionf. Water quality swaleg. Permeable Pavementh. Regenerative Stormwater Conveyancei. Rainwater harvestingj. Vegetated roofg. Grass swale

III. On-lot practicesa. Impervious disconnectionb. Rain gardenc. Soil-amended filter pathd. Rainwater harvestinge. Other:

B. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

a. Catchmentsb. Drainage areas & flowpathsc.

d.

e. Stream reachesf. Proposed channel modifications

3. Predominant soil types4.

5.

6. Floodplain/floodway limits7. Development setbacks

a. Stream buffersb. Stormwater pond/wetland buffersc. Building setbackse. Property line setbacks

Existing and proposed topography (minimum 2-foot contours or local standard)

Existing and proposed stormwater management system

Stormwater management practices: types identified and adequate surface area allocated on plan

Proposed drainage and maintenance access routes and easement locations

Existing land cover/land use and proposed limits of disturbanceResource protection areas (e.g. sensitive streams, wetlands and lakes)

Page 3: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

f. Well setbacksg. Septic system setbacks

8.

9.

C. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

3.

4.

D. Permit Approval and DocumentationS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a.

b.

c. Dam safety permitd. Floodplain/floodway construction permite. Other Type of permit:

2. Site visit and field verification

E. Better Site Design (BSD) & Smart Growth SupplementS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1 Site Layout BSD Techniques

a.

b. Amount of grading minimizedc.

d.

e.

Existing and proposed roads, buildings and other structuresExisting and proposed utilities and utility easements

Preliminary spreadsheet/calculations for 1-inch performance standard

Preliminary stormwater management practice sizing calculationsPreliminary analysis of potential downstream impacts of projectDrainage area to stormwater practice(s) within recommended range for selected practice type(s)

Status of other applicable local, state and federal permits

Construction stormwater discharge permitState/federal permit for stream and wetland impacts

Pre-development natural drainage pathways, soil characteristics, topography, and vegetative cover identified

Steep slopes (as locally defined) left in natural conditionOpen space and other natural areas preservedBuffers provided on intermittant streams and wetlands

Page 4: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

f.

g. Street Length Minimizedh.

i. Stream crossings minimizedj.

k.

l.

m.

2.

a.

b.

c. Urban forestry, tree preservationd. Green roofs

3

a. Shared parking used b. Structured parking usedc.

d.

e. Compact car spaces providedf.

g.

Additional Comments:

Floodplains for intermittant streams left in natural condition

Street width and ROW width are minimum allowed

Cul-de-sacs alternatives selected (hammerhead, loop road)Cul-de-sac diameter is minimum allowedGrass swales used in lieu of curb & gutterMinimize driveway lengths/widths or use shared driveways

Site Layout Techniques for Infill/Redevelopment (component of local Smart Growth policies)

Setbacks and/or height restrictions reduced for efficient use of spaceTransit, pedestrian, and bicycle access & facilities

Parking Lot BSD & Smart Growth Techniques

Pervious parking for overflow and/or regular spaces (w/ optional stormwater storage below)

Minimum number of parking spaces provided

Parking lot designed to sheet flow to vegetated areas

Parking lot graded toward landscaped islands, perimeter landscaping, and/or bioretention

Page 5: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation
Page 6: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Stormwater Management Design Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

Email: Email:

A. General Project InformationS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Address and legal description of site2. Vicinity map3. Project narrative

a. Purpose of projectb.

c.

d.

4.

5.I. Non-structural practices

a. Better Site Designb. Natural area conservation/restorationc. Sheet flow to vegetated filter stripd. Sheet flow to conservation areae. Impervious area disconnection

II. Structural practicesa. Stormwater pondb. Stormwater wetlandc. Filtrationd. Infiltratione. Bioretentionf. Water quality swaleg. Grass swale

III. On-lot practicesa. Impervious disconnection

Impact of development on site hydrology and stormwater qualityDescription of stormwater management systemRationale for selection of stormwater treatment practices

Evidence of hotspot runoff that may require pretreatment or enhanced treatmentType of stormwater management practices planned for site

Page 7: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

b. Rain gardenc. Soil-amended filter pathd. Rainwater harvestinge. Other:

B. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.a. Catchmentsb. Drainage pathsc. Stormwater management practicesd.

e.

f. Stream reachesg. Proposed channel modifications

3. Predominant soil typesa. Location of soil borings (if applicable)

4.

a.

b.

5.

6. Floodplain/floodway limits7. Development setbacks

a. Stream buffersb. Stormwater pond/wetland buffersc. Building setbacksd. Property line setbackse. Well setbacksf. Septic system setbacks

8.

9.

10.

a.

Existing and proposed topography (minimum 2-foot contours)Existing and proposed stormwater management system

Drainage and access routes and easementsMaintenance access routes meet acceptable design standards

Existing land cover/land use and proposed limits of disturbance

Infiltration facilities located outside of limits of disturbanceVegetated filter strip and conservation areas outside of limits of disturbance

Resource protection areas (e.g. sensitive streams, wetlands and lakes)

Existing and proposed roads, buildings and other structuresExisting and proposed utilities and utility easementsErosion and sediment control plan (NOTE: Full ESC checklist not provided here)

Infiltration areas not used as sediment basins during construction

Page 8: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

b.

c.

d. Tree save areas consider root zonee.

f.

11. Landscaping plana.

b.

c.

12. Maintenance O&M plans provided

C. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a. Drainage areas and design pointsb.

c. Curve number assumptionsd. Flow paths and times of concentratione.

f.

g. Total runoff volumes 2.

a. Drainage areas and design pointsb.

c. Curve number assumptionsd. Flow paths and times of concentratione.

Plans clearly indicate how sediment will be prevented from entering stormwater management system during construction

Cleared area minimized by clearing only areas that must be graded

Tree save areas to be marked in the fieldLimit of disturbance to be marked in the field

Planting plan meets acceptable design standards and/or planting plan prepared by certified professional

Planting instructions, schedule and details includedDams and principal spillways kept free of woody vegetation

Pre-development hydrologic/hydraulic analysis (show methodology and supporting calculations)

Land use, soil type and impervious cover assumptions

Summary of design storms analyzed (applicable as per local code)Peak runoff rates (applicable as per local code)

Post-development hydrologic/hydraulic analysis (show methodology and supporting calculations)

Land use, soil type and impervious cover assumptions

Summary of design storms analyzed (applicable as per local code)

Page 9: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

f.

g. Total runoff volumes for 1" rainfall3.

a. Treatment Volume, Tvb.

c.

d.

e.

f. Other4.

a.

5.

a.

6.

a.

7.

8. Dam breach analysis (if applicable)9. Flood study (if applicable)10.

D. Construction SpecificationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

E. Construction SequenceS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments

Peak runoff rates (applicable as per local code)

Calculations for relevant stormwater design criteria

Channel protection volume, Cpv (applicable as per local code)Groundwater recharge volume, Rev (applicable as per local code)Overbank flood protection volume, Qp (applicable as per local code)Extreme flood protection volume, Qf (applicable as per local code)

Stormwater management practices sized to reduce 1" rainfall

Results of runoff reduction analysis in WV Design Compliance Spreadsheet

Hydraulic analysis of conveyance system and inlet and outlet structures

Velocity of discharge from practice infalls and outlet

Outlet rating curves and stage-storage-discharge relationships for storage facilities

Compliance with post-development peak discharge requirements

Analysis of potential downstream impacts of project

Supporting structural calculations (if applicable)

Consistent with project plans: stormwater practice plan, profile, and cross-section details providedSpecified materials and installation procedures meet acceptable design standards

Page 10: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

1.

2.

F. Permit Approval and DocumentationS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Certification of registered professional2. Certification of owner3. Date of approval:

a. Record of all major permit decisions4.

a.

b.

c. Dam safety permitd. Floodplain/floodway construction permite. Other Type of permit:

5. Performance bond/guarantee6. Necessary legal agreements

a. Easementsb.

E. Better Site Design (BSD) & Smart Growth SupplementS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1 Site Layout BSD Techniques

a.

b. Amount of grading minimizedc.

d.

e.

f.

g. Street Length Minimizedh. Stream crossings minimized

Soils beneath infiltration facilities not compacted during constructionContributing drainage area to be stabilized prior to conveying runoff to filtering or infiltration practices

Approved stormwater management concept plan

Status of other applicable local, state and federal permits

Construction stormwater discharge permitState/federal permit for stream and wetland impacts

Maintenance agreement(s) (w/ O&M plans)

Pre-development natural drainage pathways, soil characteristics, topography, and vegetative cover identified

Steep slopes (as locally defined) left in natural conditionOpen space and other natural areas preserved Buffers provided on intermittant streamsFloodplains for intermittant streams left in natural condition

Page 11: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

i.

j.

k.

l. Cul-de-sac center is landscapedm. No sidewalks on cul-de-sacsn.

o.

p.

q. Driveway length minimized2.

a.

b.

c. Urban forestry, tree preservationd. Green roofs

3

a. Shared parking used b. Structured parking usedc.

d.

e. Compact car spaces providedf.

g.

Additional Comments:

Street width and ROW width are minimum allowedCul-de-sac alternatives selected (hammerhead, loop road)Cul-de-sac diameter is minimum allowed

Grass swales used in lieu of curb & gutterSidewalks on one side for low-traffic roadsShared driveways used if this minimizes IC

Site Layout Techniques for Infill/Redevelopment (component of local Smart Growth policies)

Setbacks and/or height restrictions reduced for efficient use of spaceTransit, pedestrian, and bicycle access & facilities

Parking Lot BSD & Smart Growth Techniques

Pervious parking for overflow and/or regular spaces (w/ optional stormwater storage below)

Minimum number of parking spaces provided

Parking lot designed to sheet flow to multiple pointsParking lot graded toward landscaped islands, perimeter landscaping, and/or bioretention

Page 12: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation
Page 13: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Sheet Flow to Conservation Area - Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

Email: Email:

Key QuestionsItem X Comments

1. Sheet flow drainage areaa. All perviousb. Includes impervious

2. Type of conservation areaa. Forestb. meadow/brushc. Other ________________________

3. Conservation area protects:a. Streamb. Lake or pondc. Other ________________________

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a. Limits of existing natural areab. Average slope of natural areac. Root zones for specimen treesd.

e. Location of fencing and signagef. Restoration plan, if applicable

If a conservation area is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Plan view depicts the boundaries of the conservation area relative to existing and proposed features. And includes the following:

Type, size, and condition of existing vegetation

Page 14: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

2.

a. Pervious areas: max flow length ≤ 150’b. Impervious areas: max flow length ≤75’

3.

a. Flows are in sheet flowb.

4. Detailsa. Permanent fencing requirementb. Permanent signage

5.

a.

b.

c.

6.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Calculation of the amount of credit is shown

a.

2.

3. Design for engineered level spreader

a. Calculations for Tv peak dischargeb. Length of level spreader rigid lip

C. Construction SpecificationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

Plan view depicts the limits of the contributing drainage area:

Drainage map shows flow paths to the conservation area

Level spreaders provided at the end of outfalls or channels discharging to the conservation area

Erosion and Sediment control plan shows limit of disturbance, with no disturbance to occur in the conservation area

Sediment controls are located upstream of the natural area to be preserved

Temporary construction fencing protects natural areaTemporary construction signage at boundaries of natural areaLandscaping plan shows restoration planting specifications, if applicable

Area is not double counted with other credits

Conservation area meets requirements for size, slope, and existing condition

Specifications clearly state that no disturbance is to occur in the conservation area

Page 15: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

2.

D. Permit Approval and DocumentationS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

Additional Comments:

Sequence of construction indicates that the contributing drainage area must be stabilized before flows can be routed to conservation area

Conservation Easement in place that specifies conservation area to be maintained in natural condition

Page 16: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Sheetflow to Vegetated Filter Strip - Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

Email: Email:

Key QuestionsItem X Comments

1. Sheet flow drainage areaa. All pervious areab. Includes impervious areas

2. Filter Strip's existing conditiona. Forestb. Prairie/grasslandc. Other _________________________

3. Required Filter Strip width: ______________

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

3.

a. Pervious areas: max flow length ≤ 150’b. Impervious areas: max flow length ≤75’

4. Soils are delineateda. Design includes soil amendmentsb.

5. Detailsa. Level spreader (if applicable)

If sheet flow to a vegetated filter strip is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Plan view depicts the boundaries of the filter strip relative to proposed drainage featuresRunoff enters filter strip as sheet flow or has a level spreader

Plan view depicts the limits of the contributing drainage area:

Plan includes soil amendment quantity and incorporation depth

Page 17: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

6.

a.

b.

7.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Calculation of the amount of credit is shown

C. Construction SpecificationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

D. Permit Approval and DocumentationS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Filter strip is in place and stabilized

Additional Comments:

Erosion and sediment control plan shows limit of disturbance

Sequence of construction shows filter strip being installed after contributing drainage area has been stabilized

Temporary or permanent protective matting or fabric to help establish vegetation

Landscaping plan provides stabilization specifications and notes

Sequence of construction indicates that the contributing drainage area must be stabilized before flows can be routed to the filter strip

Specifications clearly state that no disturbance is to occur in the buffer

Page 18: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Impervious Area Disconnection Credit - Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

Email: Email:

Key QuestionsItem X Comments

1. Type of impervious area disconnecteda. Rooftopb. Parkingc. Other

2.

Compensatory device type:a. Infiltrationb. Rainwater Harvestingc. Rain gardend. Other _________________________

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a.

b.

If impervious area disconnection is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Compensatory practice needed to help disperse flows from impervious area -- Include compensatory device if flow path through pervious area is less than 40 feet (or local standard); see separate checklist for particular practice

Plan sheet shows a receiving pervious area (e.g. vegetated channel, swale, grass strip) downgradient from the impervious area to be disconnected

For rooftop disconnection, the locations of the downspouts are shown; downspouts are not connected to the storm drain system

For surface impervious area disconnection, no barrier (e.g. curb) is present

Page 19: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

c.

d.

e.

2.

a.

3. Detailsa. Level spreader (if applicable)b. Compensatory device (if applicable)

4. Landscaping plana.

b.

5.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Calculation of the amount of credit is shown

a.

2.

a.

b.

c.

The disconnection flow path through the pervious area receiving runoff is a delineated OR a compensatory device is shown

The average slope of the pervious area receiving runoff is ≤2% or ≤5 with turf reinforcement

The soil type of the pervious area receiving runoff is appropriate (A, B, or C) and is not highly erodible

Drainage map shows flow paths to the pervious area receiving runoff

Level spreaders provided at the end of outfalls or channels

Specifies maximum compaction for the receiving pervious areaSpecifies soil amendment and topsoil requirements if necessary

Erosion and sediment control plan shows flows from the impervious area diverted until pervious area is stabilized (possible exception for rooftop runoff if silt fence or other ESC measures are in place)

Area is not double-counted with other credits

Disconnected drainage area does not exceed the maximum

For rooftop disconnection, the rooftop impervious area to a single disconnection does not exceed 1,000 sq. ft.

For non-rooftop impervious area disconnection, the impervious drainage area longest flow path ≤ 75 ft. (e.g., sheet flow condition)

If compensatory practice is used in pervious area, device has adequate surface area and volume as per the individual practice specifications

Page 20: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

C. Construction SpecificationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

Additional Comments:

Sequence of construction indicates that the pervious area must be stabilized before flows can be routed to the area

Page 21: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Infiltration/Filtration/Bioretention Practice Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

E-mail: E-mail:

Key Questions Item X Comments

1. Type of facility (check all that apply)a. Bioretentionb. Water Quality Swalec. Urban Bioretentiond. Residential Rain Gardene. Infiltration Practicef. Filtration Practice

2. For Bioretentiona. Standard design (Level 1)b. Infiltration design (Level 2)c. Extended filtration design (Level 2)

3. Facility Locationa. Open to Surfaceb. Underground

4. Filtration Mediaa.b. Sandc. Bioretention Soil Mixd. Peate. Other

5. Hydraulic configurationa. On-line facilityb. Off-line facility

6. Type of pretreatment facilitya. Separatte pretreatment cellb. Sedimentation chamber/maholec. Grass channel

If an infiltration or filtration facility (including bioretention) is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

No filtration media (e.g., stone reservoir only)

Page 22: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

d. Grass filter stripe. Gravel or stone flow spreaderf. Gravel diaphragmg. Other Type of pretreatment facility:

7. If designed for infiltration (e.g., no underdrain OR infiltration sump below underdrain):a.

b.

c. Field-measured rate:

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a.

b.

c.

d.

e.

2. Detail view of pretreatment facilitya. Inlet details, materials and elevationsb. Inlet protection (rip rap or other)c. Outlet details, materials and elevations

3. Cross-section view of treatment facilitya. Existing and proposed elevationsb.

c.

d.

4.

Evidence of hotspot runoff which may prevent infiltration; check use of liner for hotspot conditions.

Soil boring logs and infiltration testing report providedField-measured infiltration rate of 0.5 to 4 inches/hour

Facility contours shown in plan view on stormwater management and/or grading plan

Site slope does not exceed 3:1 (bioretention) or 4:1 (infiltration)

Flow length is maximized; no short-circuiting between inlet(s) and outlet

If off-line facility, flow diversion structure location & design shown (details, materials, elevations)

Facility meets building foundation setback requirements (see "Feasibility Criteria" for applicable specification)

Facility meets drinking water well setback requirements (typically 100')

Side slopes do not exceed 3:1 (bioretention) or 4:1 (infiltration)Plan shows depth and composition of underdrain, choker, and soil media layers; check Level 1 and 2 required depths

Ponding depth does not exceed maximum allowable (18" for bioretention)

Details for riser/outlet structure (if applicable)

Page 23: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

a. Materialsb. Elevationsc.

d.

e.

f.

5. Observation well(s) provided (infiltration)6. Embankment/berm details and elevations7. Landscaping plan

a.

b.

8. Signagea.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

3.

4.

5.

Additional Comments:

For filtration practices: details, materials and elevations for underdrain system

For bioretention & filtration practices: Cleanouts provided for underdrain system

Principal spillway equipped with removable trash rackDetail for trash rack(s) includes material, dimensions, size of openings

Vegetation suited to the hydrologic regime

Landscaping plan contains required elements

Signage provided for high visibility projects

Facility sized according to relevant design criteriaPretreatment facility sized according to relevant design criteriaFacility designed to dewater within maximum allowable drawdown time (48 hours for infiltration and/or infiltration sump in underdrain)

Geotechnical report or other source indicates depth to groundwater and bedrock. Minimum separation distance of 2' between bottom of practice and seasonal high water or bedrock (bioretention and infiltration)

Analysis of stable conveyance downstream from practice

Page 24: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation
Page 25: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation
Page 26: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Permeable Pavement Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

E-mail: E-mail:

Key QuestionsItem X Comments

1. Type of facility (check all that apply)a. Standard design (Level 1)b. Infiltration design (Level 2)c. Infiltration sump design (Level 2)

2. Pavement Typea. Pervious concreteb. Porous asphaltc. Concrete grid paversd. Permeable interlocking concrete paverse. Other:

3. External drainage area?a. Yes. Ratio:b. No

4. Pretreatment (if landscaped/turf areas in drainage area)a. Yes. Type:b. No

5. If designed for infiltration (e.g., no underdrain OR infiltration sump below underdrain):a.

b.

c. Field-measured rate:

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

If permeable pavement is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Evidence of hotspot runoff which may prevent infiltration; check use of liner for hotspot conditions.

Soil boring logs and infiltration testing report providedField-measured infiltration rate > 0.5 inches/hour

Page 27: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Item S U N/A Comments1.

a.

b.

c.

d.

2. Detail view of pretreatment facility (if applicable)a. Inlet details, materials and elevationsb. Inlet protection (rip rap or other)c. Outlet details, materials and elevations

3. Cross-section view of permeable pavementa. Existing and proposed elevationsb.

4. Observation well(s) provided (infiltration)5. Signage

a.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

3.

4.

5.

Facility contours shown in plan view on stormwater management and/or grading plan

Pavement section bottom slope is flat (infiltration) or almost flat (0.5% if using underdrain)

External drainage area (if present) is delineatedFacility meets building foundation setback requirements (see "Feasibility Criteria" for applicable specification)

Facility meets drinking water well setback requirements (typically 100')

Plan shows depth and composition of filter layer, reservoir layer (with or without underdrain and/or infiltration sump), pavement

Signage provided for high visibility projects

Facility sized according to relevant design criteriaDesign accounts for anticipated structural load Facility designed to dewater within maximum allowable drawdown time (48 hours for infiltration and/or infiltration sump in underdrain)

Geotechnical report or other source indicates depth to groundwater and bedrock. Minimum separation distance of 2' between bottom of practice and seasonal high water or bedrock

Analysis of stable conveyance downstream from practice for large flows

Page 28: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Additional Comments:

Page 29: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation
Page 30: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Grass Swale Credit - Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

Email: Email:

Key QuestionsItem X Comments

1. Grass Swale Designa. Grass swale (use this checklist)b.

c. Other

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2. Runoff enters the swalea. Sheet flow along the lengthb.

c. Channel bottom width is 2 to 8 ftc. Side slopes are 3:1 or flatterd.

e.

2.

3. Detailsa. Channel cross section & profileb.

If a grass swale is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Water Quality Swale (use Bioretention checklist)

Grass swale locations are marked on the plan sheet

Concentrated flow through curb cuts or pipes

Channel longitudinal slopes are 2% or lessChannel longitudinal slope is steeper than 2% with check dams

Drainage map shows flow paths to the grass swale

Erosion control blanket or turf reinforcement mat (if applicable)

Page 31: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

4. Landscaping plana. Seed specificationsb.

5.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Calculation of the amount of credit is shown

2. Peak discharge calculations for the Tv3.4. Tv depth is ≤ 4 inches 5. Swale 2-year velocity is non-erosive 6.

7. Swale 2-year velocity is non-erosive

C. Construction SpecificationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

Additional Comments:

Topsoil or soil amendment specificationsErosion and sediment control plan shows

flows diverted around the swale until the swale & contributing drainage area are stabilized

Tv velocity is ≤ 1 ft/s

10-year flow is within the swale with adequate freeboard

Sequence of construction indicates that the grass swale must be stabilized before flows are routed to them

Page 32: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name: Location:

File Number:Date of Submittal:

Reviewer:Date:

Rainwater Harvesting Practice Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

E-mail: E-mail:

Key Questions Item X Comments

1. Location of storage tank (check all that apply)a. Undergroundb. Above-groundc. Indoorsd. On rooftope. Other

2. Uses of rainwater (check all that apply)a. Potable Use:b. Non-Potable Use:

3. Secondary runoff reduction practice (if applicable)a. Bioretentionb. Infiltrationc. Grass Swaled. Stormwater Wetlande. Permeable Pavementf. Other Type:

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1. Plan view of stormwater management plan

a. Shows footprint location of cisternb. Shows conveyance system to cisternc. Adequate setbacks from utilitiesd. Shows outlet point(s)

If a rainwater harvesting facility is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Page 33: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

2.

a.

b.

c.

d.

3. Profile view of rainwater systema.

b.

c.

4.

a. Specificationsb. Elevationsc. Protections against freezing in place

5.

6.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2. Year-round use verified3. Drawdown volume computed (if applicable)4. Adequate hydraulic head where necessary

5.

6.

7. Sizing of secondary practice (if applicable)8.

Additional Comments:

Detail view of conveyance, pretreatment, and cistern

Location of inlet, outlet, air gap,pump, etc.Filter sizing appropriate for drainage area - minimum 95% filter efficiency

Screening over open ports to keep out pestsMaterials for cistern, includes access for maintenance

Existing elevations/contours and proposed inverts of system components shown

At least 1.5% slope from downspouts to cisternAdequate slope from cistern to outfall of overflow

Details for pumping/distribution system, including additional filtration

Details for outlet protection and/or secondary practiceRainwater system design and components comply with local codes

Cistern Design Spreadsheet completed and runoff reduction credit calculated.

Only rooftop in contributing drainage area, unless approved by locality

For underground system, vehicle loading limits shown on plan - signage in place if no loading allowed.

Analysis of stable conveyance downstream from practice

Page 34: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation
Page 35: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name:

Location:

File Number:

Date of Submittal:

Reviewer:

Date:

Vegetated Roof Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

E-mail: E-mail:

Key QuestionsItem X Comments

1. Type of vegetated roof (check all that apply)a. Extensive - shallow soilb. Intensive - deep soilc. Other Type:

2. Type of plant cover (check all that apply)a. Sedumsb. Shrubsc. Treesd. Other Type:

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a. Location of drainsb.

c.

d.

2.

If a vegetated roof is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Footprint of vegetated roof shown in plan view on stormwater management and building plan

Flow paths from drainage layer to roof drain shownLocations of roof access, and walkways for maintenance2-foot vegetation-free zone around perimeter (recommended)

Profile view shows pitch of roof - some pitch required for drainage, but maximum 25% pitch

Page 36: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

3.

a. Appropriate roof decking material Type:b. Type:

c. Insulation layer (if applicable)d. Root barrier Type:e. Type & Depth:

f. Filter fabric - needled, non-woveng. Minimum 4" of growing media Depth:

4. Details for growing mediaa. Organic matter content not above 20%b.

c.

5. Details for roof drainsa.

b.

c.

6. Landscaping plana.

b.

7.

8.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

2.

3.

Cross-sectional view of vegetated roof with all layers

Appropriate waterproofing layer material

Drainage layer - synthetic or inorganic material

Maximum water holding capacity of 30%If trees present, depth of growing media at least 4 ft.

Flashing 3" above soil surface around drains located adjacent to growing media

Adequate number of roof drains NOT adjacent to growing mediaDrainage layer adequate enough to convey water to downspouts without excessive ponding on roof.

Plant types that can survive harsh conditions, appropriate to relevant hardiness zone

Number and species of plants listed on plan.

Design and setbacks in conformance with local building codesDesigns in conformance with ASTM International Vegetative (Green) Roof Standards.

Structural capacity conforms to ASTM E-2397 guidelines or other approved method

WV Site Design Spreadsheet completed to show amount of credit

Vegetated roof "sized" to manage the 1" rainfall

Page 37: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Additional Comments:

Page 38: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

Project Name: Location:

File Number:Date of Submittal:

Reviewer:Date:

Stormwater Wetland Plan Review Checklist

Applicant: Applicant's Representative:

Contact Name: Contact Name:

Phone Number: Phone Number:

E-mail: E-mail:

Key QuestionsItem X Comments

1. Type of stormwater wetland (check all that apply)a. Stormwater wetland basin (Level 1)b.

c.

d. Other Type:

2. Type of pretreatment facility (check all that apply) Pretreatment must be provideda. Sediment forebayb. Other Type:

3.

4.

a.

A. Project PlansS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a.

If a stormwater wetland is included in the project plans, the stormwater management design plan shall be reviewed according to the additional criteria provided below.

Stormwater multi-cell wetland or pond/wetland combination (Level 2)Subsurface gravel wetland (Modified Level 2)

Temperature-sensitive waters located downstream of wetland

Soil boring logs and geotechnical report provided

Evidence that a pond liner is required due to underlying geology (e.g. karst topography, sand)

Stormwater Wetland contours shown in plan view on stormwater management and/or grading plan

Length-to-width ratio and/or flow path ratio is at least 2:1 for Level 1 designs or 3:1 for Level 2 designs

Page 39: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

b.

c. Curvilinear shoresd.

e.

f.

g.

2.a.

b.

c.

3. Detail view of pretreatment facilitya. Inlet details, materials and elevationsb. Inlet protection (rip rap or other)c.

4. Details for riser/outlet structurea. Materialsb. Elevationsc.

d.

e.

f.

g. Structural details for concrete risersh.

i.

5. Details for barrel (outlet pipe)a. Barrel materials, elevations, dimensions

b.

c. Joint sealant specifications

Flow length is maximized. Berms or baffles provided to lengthen flow path if necessary

4' - 6' wide aquatic bench provided around forebays & micropoolsFor Level 2: Microtopography in pond results in varied water depths For Level 2: Multiple cells with mean depth less than 1 foot Emergency spillway located in excavated area, not in fill

Profile view of pretreatment facility and stormwater wetland with existing and Profile location is marked on

plan viewWater surface/ponding elevations for design stormsCore trench, anti-seep collars, riser, low-flow orifice, barrel shown

Outlet details, materials and elevations

Riser/outlet structure located within embankmentPrincipal spillway equipped with removable trash rackDetail for trash rack(s) includes material, dimensions, size of openingsCleanouts provided for pond drain system

Low flow orifice provided and meets or exceeds minimum orifice size (3 in. or local standard)

Low flow orifice adequately protected from clogging (e.g. reverse slope pipe, trash rack)

Anti-seep collar details (if applicable) includes dimensions, material, reinforcement

Page 40: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

d.

e.

f. Outlet protection (rip rap or other)6. Embankment/berm details and elevations

a.

b.

c.

7. Landscaping plana.

b.

B. Design ComputationsS = Satisfactory U = Unsatisfactory N/A = Not Applicable

Item S U N/A Comments1.

a.

b.

c.

2.a. Maximum of 4' depth in forebay(s)b.

c.

d.

3.

Barrel outfall details, materials and elevationsEmergency overflow structure/spillway details, materials and elevations

Embankment/berm slopes do not exceed maximum allowable (max. allowable slope: __________ )

Embankment/berm top width meets or exceeds minimum allowable (min. allowable top width: ____________ )

Allowable soils specified for embankment and core trench

No woody vegetation on embankments constructed of fill material Vegetation suited to the normal pool water depths

Wetland permanent pool and available storage volume sized according to WV Stormwater Manual

For Level 2: Design Volume of wetland is 1.5 x Treatment VolumeFor Level 2: Wetland surface area greater than 3% of contributing drainage area.

Hunt Water Balance equation performed to size minimum depth of permanent pool

Pretreatment facility sized and designed according to WV Stormwater Manual

Depth transitions to 1' at entrance to wetland cellSize of forebay(s) is proportional to total inflow to wetlandForebay includes metered rod for monitoring sediment accumulation

Drain system capable of draining wetland pool within acceptable drawdown time

Page 41: dep.wv.govdep.wv.gov/WWE/Programs/stormwater/M… · XLS file · Web view · 2013-06-09SW Wetland Vegetated Roof Rainwater Harvesting Grass Swale ... Specified materials and installation

4.

Additional Comments:

Difference between high water level (detention storage) and normal water level does not exceed 12"