1
SHERATON HELIOPOLIS EXTENTION PROJECT Date: 11 -9- 2006 To: Mr: Zikar Masroua (Project Director) From : Khaled Metwaly (HSE Manager) Subject: Unsafe welding machine Dear, sir With reference to above subject, I would like to inform you that: there are at our site sup contractor DEPA co, zone (J) level (-9) using unsafe welding machine. This causing to taking place electrical shock. Please we need to resolve this problem as soon as possible to prevent any hazards inside the site. . Yours Sincerely, …………………………………… HSE Manager / Khaled Metwaly

DEPA 11-9-2006

Embed Size (px)

Citation preview

SHERATON HELIOPOLIS EXTENTION PROJECT

Date: 11 -9- 2006

To: Mr: Zikar Masroua (Project Director)

From : Khaled Metwaly (HSE Manager)

Subject: Unsafe welding machine

Dear, sir With reference to above subject, I would like to inform you that: there are at our site sup contractor DEPA co, zone (J) level (-9) using unsafe welding machine. This causing to taking place electrical shock.

Please we need to resolve this problem as soon as possible to prevent any hazards inside the site. .

Yours Sincerely,

……………………………………

HSE Manager / Khaled Metwaly