47
Delivering the North West Rail Link Colin Rudd, Deputy Project Director, NWRL David Polkinghorne, Design Team Leader, TJHD November 26, 2013

Delivering the North West Rail Link - Engineers Australia – constraints CHERRYBROOK CASTLE HILL NORWEST SANDSTONE KELLYVILLE CUDGEGONG SHOWGROUND

Embed Size (px)

Citation preview

Delivering the North West Rail Link

Colin Rudd, Deputy Project Director, NWRL

David Polkinghorne, Design Team Leader, TJHD

November 26, 2013

The starting point

Project overview

$8.3 billion budget

Open by late 2019

First stage of rapid transit

Artist’s impression: Kellyville Station street view

Bigger than the Harbour Bridge

Eight new railway stations

4,000 car parking spaces

A train at least every five minutes in the peak

15km twin tunnels

4km skytrain viaduct

20,000 more tonnes of steel than the Sydney Harbour Bridge.

The longest rail tunnels built in Australia. “

Artist’s impression: an underground station

More trains, more choice

Australia’s first fully-automated rapid transit rail system

Fast, safe and reliable single deck trains

Conversion and upgrade of Epping to Chatswood line

Bringing the project to life Widespread community engagement – since June 2011

Project aligned with key Government plans, Transport Master Plan

Major scope improvements made – since June 2011

Fully funded from State budget – $806m FY2013-14, $4 billion over next 4

Property acquisitions well advanced – >85% of transactions completed

EIS 1 approved September 2012 ; EIS 2 approved May 2013

Early construction works managing contractor appointed – August 2012

Tunnelling contract (TSC) awarded – June 2013

Surface viaduct and civils contract (SVC) tenders received – August 2013

Shortlist of two consortia for operations (OTS) PPP announced – May 2013

On program for the first of the TBMs in ground in 2014

State Plan

Budget Planning Transport Rail

State Infrastructure Strategy

Aligned with State strategies

The plan: Sydney’s Rail Future

The plan: delivered in five stages

Stage 1 Operational efficiencies

Stage 2 Network efficiencies

Stage 3 Rapid transit: North West Rail Link

Stage 4 Rapid transit: New harbour crossing

Stage 5 Rapid transit: Southern sector conversion

Sydney’s Rail Future & North West Rail Link Artist’s impression: Kellyville Station, aerial view

Heating and cooling in underground stations. “

Artist’s impression: Castle Hill Station

The stations Bus interchanges, taxi ranks, bicycle storage

Easy access, kiss-and-ride

Safe, well-lit environments, constant CCTV monitoring

Passenger screen doors

No timetable – just turn up and go. “

Artist’s impression

The trains Single deck, no internal stairs, three doors per carriage

1,300 capacity

Automated, modern technology

“ Clear and constant communications with customers.

Artist’s impression

Automation Safety No. 1 priority

Platform screen doors: train operations faster and safer

Constant live monitoring by expert train controllers

Artist’s impression: Cherrybrook station aerial view

Automation Clear communications

Multiple cameras and help points, inside trains and out

Staff moving through the system during the day

Australia’s first fully-automated rapid transit system.

Automation

30 years of operations

588km, 41 lines, 25 cities, 585 stations, 4 continents

Impressive safety record

Source: International Association of Public Transport, 2011 report.

Contract packages and interfaces Cudgegong

Tunnels & Station Civils (TSC)

Design & construct Driven tunnels, station excavation,

ground support

Surface & Viaduct Civils (SVC)

Epping Bella Vista Cudgegong Chatswood

Epping Bella Vista Chatswood

Design & construct Surface civil infrastructure (including viaduct), Bella

Vista to Cudgegong

ECRL existing infrastructure interface Sydney Trains operational interface at Epping & Chatswood

Operations, Trains & Systems (OTS) Partially privately financed (with substantial State contribution) – subject to VfM

Train & station operations Mechanical, electrical, signalling, train control & other systems (new and upgraded) Supply & maintain rolling stock, including maintenance facilities and control centre,

New stations construction & fit-out, civil works (including stabling and track) Overall infrastructure maintenance

Sydn

ey’s Rail Fu

ture

Po

ten

tia

l we

ster

n

ext

ensi

on

Early Works Managing Contractor Managing Contractor

Project phase and timing Artist’s impression: Rouse Hill Station, street view

Delivery scope – major civil works

Tunnelling – product requirements Geometry to suit rapid transit operations

Convenient locations for access

Shallow stations

Tunnelling – constraints CHERRYBROOK

CASTLE HILL

NORWEST

SANDSTONE

KELLYVILLE SHOWGROUND CUDGEGONG

ROAD

SHALE

BELLA VISTA

ROUSEHILL

SHALE

Topography – Hills District

Creeks, no major watercourse

Geology – 60% sandstone, 40% shale

Existing rail crossing – ECRL dive with 5m rock cover

Highways – M2, Castle Hill Rd

Buildings – Castle Towers, Norwest Business Park

Tunnelling – strategy Configuration – twin tunnels

Fire and life safety

Groundwater

Space proofing

Cross passages

Crossover cavern

Tunnelling contract $1.15 billion contract

Three portions to provide early access for OTS Contractor

Thiess John Holland Dragados joint venture

TBMs to be manufactured by NFM, headquartered in France

Completion date 2017

Awarded $1.15 Billion contract in June 2013

Australia’s most experienced tunnelling contractors

70% of Australia’s major underground infrastructure in last decade

1,200 km of tunnels world wide

Delivery of tunnelling and rail projects in metropolitan cities across the world

Thiess John Holland Dragados

We will deliver a safe, high quality and value for money rail asset, in partnership with TfNSW, on time and on budget.

TJHD: Key objective

15 km TBM tunnels

Mined tunnels and rail crossover cavern

Cross passages

Five stations: civil excavations

Two service facilities: shaft excavations

Tunnels and Station Civil scope

TBM tunnels

The design team

Design process and roles TJHD integrated design

verification

TJHD internal independent verification

TfNSW technical review

Independent certifier

Agency review

- RMS for arterial roads

- Council for local roads

- Sydney Trains for rail connection

Design Priorities

Critical equipment ordering

Day 1 24th June

TBM 12th July

Carousels, moulds & Ancillary Equipment 13th September

Segment Carriers (TSPs) 9th September Order dates

Segment Gaskets 24th September

Batch Plant September

Yard factory sheds & Gantry Cranes September

Early design/construction assessments

Rapid mobilisation of D & C Team

Segment ring build

- Type and features

- Casting methodology

- Handling methodology

TBM Capability and Features

Six segments form one ‘ring’ for tunnelling

Each segment ~ 3.75 tonnes

Total segments for TBM tunnels ~ 100,000

Total rings for TBM tunnels ~ 16,500

145,000 m3 of concrete

Concrete segment manufacture

Segment geometry

Site planning

3 x TBM Sites (Bella Vista, Showground & Cherrybrook)

1 x Station site to support mined tunnel operations (Castle Hill)

1 x Also includes a bridge (Norwest)

2 x Shaft excavations with one supporting mined tunnel (Epping & Cheltenham)

Bella Vista

Precast segment carousel plant

Segment being ‘demoulded’ using vacuum lifter

Demoulding / Vacuum lifter

Segment handling in the yard

Segments transported to tunnel

Supplied to other tunnelling sites at Showground and Cherrybrook

Precast segment transport Bella Vista

Tunnel Boring Machine (TBM) Tunnel and Station Civil Works Scope

TBM shield, with grippers

TBM tunnel cross sections

NFM Technologies Double Shielded TBM (x4)

Internal tunnel diameter ~ 6m

TBM shield length ~ 12.5m

9 backup trailers on bogies running on segments

Cutterhead with 40 disk cutters

TBM total installed power ~ 3500kW

Total weight of each TBM ~ 1000T

TBM facts and figures

Ring erection, within the tailshield

Mined tunnel - Castle Hill

Mined tunnels - Epping

Castle Hill site

Cherrybrook site