Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Offshore Decommissioning ConferenceFairmont Hotel, St Andrews8th October 2014
Delivering The Future Together:
Nigel Jenkins, Chief Executive
Delivering the Future
Together
Nigel Jenkins
CEO Decom North Sea
Delivering
DNS, Members, Stakeholders :
Streamlined Decom Template
ECE
EIA
ITF Outputs
Market Intelligence
Streamlined Decommissioning programme
Lessons Learnt (With DECC and O&GUK)
Standard Contracts
Multiparty Well P&A Cost Reduction
Mattresses
Listening to
Members
Open Space
Consultations
Member
Surveys
Facilitated
Sessions
Workshops
Face to Face
Meetings
Project Ideas
Prioritised Projects
Delivering:
help us deliver the projects industry needs
The Future
Summary of Activity
Insert Here Slide 1 1 from the Drop Box: Can it be made smaller in “Mbits”?
File 2 here
Slide 3 here
Slide 4.
So What Does That Mean For Specific Operators?
Summary of ActivityOperators current expectations are being outlined, however scopes
are sometimes not firm and still subject to change/approval.
Conoco Phillips:
Removal of 10 platforms in the Ekofisk field complete
Last topside removed 2014, onshore disposal into 2015
Next removal campaign: pre-planning started
P&A of 23 wells starting in Q4 2014
3-4 Topsides to remove, preparing for tender process
4-5 Substructures to remove, preparing for tender process
Onshore Disposal preparing tender process
ExxonMobil
Jotun B under consideration for removal
Activity in the Norwegian Sector
Statoil
Gullfaks SPM loading buoys dismantling and disposal ongoing
TOGI manifold disposed at Stord
H7 platform from German sector removed and disposed (for Gassco)
B11 platform from German sector removal underway (for Gassco)
Ekofisk 2/4S jacket offloaded at Stord for dismantling and disposal (for Gassco)
Huldra – under consideration for removal
BP
Ekofisk 2/4G (Valhall RP) equipment removal and topsides being prepared for removal.
Bridge removed in 2014.
HOD and Old Valhall (QP, PCP, DP) forecast removal 2017-2020
Talisman:
Decommissioning of YME Gamma MOPUStor forecast 2015-2016
Gyda – engineering down & preparation for removal 2018//2019
Activity in the Norwegian sector
Schiehallion/Loyal
regulatory approval obtained in June 2013
offshore removal & onshore disposal is underway of subsea
pipelines and production flowlines etc.
Don
expected start date of 2015/16 – subsea flowlines, injection
equipment, control umbilicals and manifolds etc.
Miller
removal of ~28,000 tonnes topsides scheduled for 2016
removal of ~18,000 tonnes six leg jacket scheduled for 2017
overall completion by end 2018
Activity in Central & Northern
North Sea
Three fixed steel jacket platforms (Brae Alpha, Brae Bravo & East Brae)
85 platform drilled wells to P&A
87kT topsides to remove; 33kT sub-structures to remove
Three subsea tiebacks (Central Brae, West Brae & Braemar)
19 subsea drilled wells to P&A
1000 T manifolds, templates and structures to remove
75 km flowlines, 38 km umbilical's, 195 km of pipelines, 57 km submarine cables
Decommissioning Activities
Project team established; Compliance activities on-going
Studies in support of Decommissioning Programme
Drill cuttings piles survey and sampling
Brae Alpha drilling rig reactivated – completion Q1 2014
Pilot well plug and abandonment to commence (3 – 4 wells) – completion Q1 2015
Brae Bravo / East Brae rig recertification study to commence Q1 2015
Activity in Central & Northern North Sea
Brae Field Decommissioning Programme
BRENT Field:
4 Platforms (Alpha, Bravo, Charlie, Delta), 3GBS, 1 Steel Jacket.
PreDecom Programme Study being finalised, robust stakeholder engagement
ongoing.
Finalising DECC Submissions
P&A complete on Delta, ongoing on Bravo, 57 of 142 complete.
Engineering Down Delta prior to single lift
Onshore working closely with Able, Quay Upgrading ongoing
Contracts with:
Allseas (lift), Able (onshore disposal),
WGPSN (decom services), Baker Hughes (Conductor Cutting/Removal, Archer
(drilling services).
Activity in Central & Northern
North Sea
Activity in Central & Northern North Sea
Quad 9 UK Sector, Leadon:
Decommissioning Programme complete and submitted to DECC, Public
Consultation now complete
Programme and Environmental Statement submitted
Preparation/engineering for well P&A ongoing (18 wells),
Subsea Structures (3x300Te) and bundles remain in place
Awaiting DECC response to programme.
Removal of controls equipment, concrete mattresses, infield jumpers and tree
spools has commenced.
No topsides;
FPSO was relocated in 2006.
Onshore recycling/disposal contract in place and items recovered to date
recycled
Maersk Oil have a DSV on-hire for 365 days in 2014, which has allowed
decommissioning works to commence at Leadon. Decommissioning of both drill
sites on Leadon field under consideration
Activity in Southern North Sea
Planning for decommissioning projects:
Markham ST-1 (6 wells 1,250Te topsides / 1,000Te jacket)
Stamford (Sub-sea Tree)
Rose
Audrey 7X
Bains
Forecast timetable: 2014-2017
Potential for A-field:
Ensign
4-legged Steel jacket NUI4 wells slots, 2
production wells 1 SS tie-back
Alison, Ann, Annabel
5 production wells
Export to TGT via LOGGS & WD
Audrey A (WD)
Steel Jacket NUI
8 Production wells
Export to TGT via LOGGS
Audrey B (XW)
Steel jacket NUI
4 production wells – no longer exporting
Activity in Southern North Sea
Viking & LOGGS Satellites
• DECC Submissions for 3 – 7 programmes in 2015/17
• plus corresp. studies/EIA/stakeholder-engagements
• Well P&A
• 4 wells abandoned out of 34-well initial tranche
• to be later followed by a further 104 wells
• >20 pipelines being flushed/decommissioned in 2015/2016
• expectation of limited need for pipeline retrieval/recovery
• Removal of 6 –16 platforms commencing Q3/Q4 2015
• Tender process ongoing
• Lift preparation commencing Q2 2015
• Onshore recycling/disposal of 6–16 structures
• Tender process commencing.
Summary of Forecast Activity
Circa 40 programmes in progress
Circa 60 further programmes under discussion
The Future:Framed by the Wood Review and the Scottish
Government TVA Report
New Regulator Action A25:
A new single decommissioning forum responsible for delivering significant
decommissioning cost reduction, promoting innovation & great cooperation,
jointly led by the new regulator and industry
Be more ambitious in what it seeks to achieve
Set a radical target to reduce cost
Work with the supply chain
A26: Technology
A27: No premature decommissioning
A28: Late Life Business Models
A29: Game changing decommissioning concepts
The Wood Review
Government and the new Regulator should play a central role in developing a
strategic approach to decommissioning with the aim of minimising decommissioning
costs to the operators and the taxpayer and achieving the maximum economic
extension of field life.
A clear strategy is required to mobilise investment by the supply chain to ensure that
technology, capability and capacity is in place, and that the TVA from
decommissioning expenditure is optimised.
To minimise the cost to both operators and the taxpayer, consideration should be
given to encouraging a pipeline or cluster of decommissioning projects – creating
economies of scale, sharing knowledge and techniques.
Scottish Independent Commission:Maximising TVA Report
Together?Collaboration delivering real business benefit
Moving from talking to working to deliver tangible benefits
DNS Projects
DECC Initiatives
PLUG
O&GUK Work Groups
Already Delivering to the Wood Review/TVA Agenda
But: Initiative Overload?
Together!
The Future of TogetherFewer, Focussed Initiatives 80:20
Coordination, Collaboration, Streamlining
“Best Person for the Job”
Focus on Delivering meaningful outputs
Panel Session…
Delivering the Future Together