    INDIAN SCHOOL OF MINES

    Analysis of Delhi metro - Project Management

    Assignment3/16/2012

    Submitted by :-

    Rachit Tiwari

    10191

    Mineral Engineering

    Submitted to :-

    Prof. N. Das

    Department of

    Management Studies

  • 7/31/2019 Delhi Metro - Rachit

    2/11

    1 | P a g e

    WHY METRO TRAIN IN DELHI?

    Delhi, the capital city of India, is one of the fastest growing cities in the world with a

    population of 13 million as reported in the Census of India Report for the year 2000. Until

    recently, it was perhaps the only city of its size in the world depending almost entirely on

    roads as the sole mode of mass transport. The total length of the road network in Delhi has

    increased from a mere 652 km in 1981 to 1122 km in 2001 and it is expected to grow to 1340

    km in the year 2021. This increase in road length is not at par with the phenomenal growth in

    the number of vehicles on these roads in Delhi. The cumulative figure of registered private

    and government buses, the main means of public transport, is 41,872 in 1990 and it is

    expected to increase to 81,603 by the year 2011. The number of personal motor vehicles has

    increased from 5.4 lakhs in 1981 to 30 lakhs in 1998 and is projected to go up to 35 lakhs by

    2011. With gradual horizontal expansion of the city, the average trip length of buses has gone

    up to 13 km and the increased congestion on roads has made the corresponding journey time

    of about one hour. Delhi has now become the fourth most polluted city in the world, with

    automobiles contributing more than two thirds of the total atmospheric pollution. In this

    context, the decision of the Government of India to develop a mass transport system for Delhi

    providing alternative modes of transport to the passengers was most appropriate.

    DELHI METRO - Background

    The concept of a mass rapid transit for Delhi first emerged from a traffic and travel

    characteristics study which was carried out in the city in 1969. Over the next several years,

    many official committees by a variety of government departments were commissioned to

    examine issues related to technology, route alignment and governmental jurisdiction. In 1984,

    the Delhi Development Authority and the Urban Arts Commission came up with a proposal

    for developing a multi-modal transport system, which would consist of constructing three

    underground mass rapid transit corridors as well augmenting the city's existing suburban

    railway and road transport networks.

    While extensive technical studies and the raising of finance for the project were in progress,

    the city expanded significantly resulting in a twofold rise in population and a fivefold rise in

    the number of vehicles between 1981 and 1998. Consequently, traffic congestion and

    pollution soared, as an increasing number of commuters took to private vehicles with the

    existing bus system unable to bear the load.An attempt at privatizing the bus transport system

  • 7/31/2019 Delhi Metro - Rachit

    3/11

    2 | P a g e

    in 1992 merely compounded the problem, with inexperienced operators plying poorly

    maintained, noisy and polluting buses on lengthy routes, resulting in long waiting times,

    unreliable service, extreme overcrowding, unqualified drivers, speeding and reckless driving.

    To rectify the situation, the Government of India and the Government of Delhi jointly set up

    a company called the Delhi Metro Rail Corporation (DMRC) on March 5, 1995 with

    E. Sreedharan as the managing director.

    The Delhi Metro is a rapid transit system serving Delhi, Gurgaon and Noida in the National

    Capital Region of India. The network consists of six lines with a total length of

    156 kilometers (97 mi) with 132 stations of which 31 are underground. It has a combination

    of elevated, at-grade and underground lines and uses both broad gauge and standard gauge

    rolling stock. Delhi Metro is being built and operated by the Delhi Metro Rail Corporation

    Limited (DMRC). As of April 2010, DMRC operates around 130 trains daily between 6:00

    and 23:00 running with an interval of 3 to 4.5 minutes between trains. The trains have four

    coaches but there are plans to shift to six coach trains to increase capacity.

    Structure

    Chairman - Shri Navin Kumar

    Managing Director - Dr. E. Sreedharan

    Total No. of Directors - 16

    Nominee of Govt. of India5

    Mission

    To cover the whole of Delhi with a Metro Network by the year 2021.

    Delhi Metro to be of world class standards in regard to safety, reliability, punctuality,comfort and customer satisfaction.

    Metro to operate on sound commercial lines obviating the need for Government

    support.

    http://en.wikipedia.org/wiki/Rapid_transithttp://en.wikipedia.org/wiki/Delhihttp://en.wikipedia.org/wiki/Gurgaonhttp://en.wikipedia.org/wiki/Noidahttp://en.wikipedia.org/wiki/National_Capital_Region_%28India%29http://en.wikipedia.org/wiki/National_Capital_Region_%28India%29http://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/List_of_Delhi_metro_stationshttp://en.wikipedia.org/wiki/Broad_gaugehttp://en.wikipedia.org/wiki/Standard_gaugehttp://en.wikipedia.org/wiki/Standard_gaugehttp://en.wikipedia.org/wiki/Broad_gaugehttp://en.wikipedia.org/wiki/List_of_Delhi_metro_stationshttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/National_Capital_Region_%28India%29http://en.wikipedia.org/wiki/National_Capital_Region_%28India%29http://en.wikipedia.org/wiki/Noidahttp://en.wikipedia.org/wiki/Gurgaonhttp://en.wikipedia.org/wiki/Delhihttp://en.wikipedia.org/wiki/Rapid_transit
  • 7/31/2019 Delhi Metro - Rachit

    4/11

    3 | P a g e

    MASTER PLAN OF DELHI METRO-

    Phase I (1995 - 2005) Phase II (2005 -2011)

    Distance 65.10 km 53.02 km

    Corridors

    1) ShahdaraBarwala 1)Vishwa Vidhyalaya- Jahangirpuri

    2) Vishwa Vidhyalaya- Central Secretariat 2) Central Secretariat- Qutab Minar

    3) Barakhamba Road - Dwarka 3) Shahdra- Dilshad Garden

    4) Barakhamba Road - Indraprastha 4) Indraprastha- New Ashok Nagar

    5) Extension into Dwarka Sub city 5) Yamuna Bank- Anand Vihar ISBT

    6) Kirti Nagar- Mundka

    Investment Rs 6406 crores (2004 prices) Rs 8026 crores (2004 prices)

    Phase III Phase IV

    Distance 62.2 km 1) Jahangirpuri to Sagarpur West

    Corridors

    1) Rangpuri to Shahabad Mohammadpur 2) Narela to Najafgarh

    2) Barwala to Bawana 3) Andheria Mod to Gurgaon

    3) Jahangirpuri to Okhla Industrial Area Phase I

    4) Shahbad Mohammadpur to Najafgarh

    Source- RITES (2005a)

    The Delhi Metro (DM) planned in four phases is part of the MRTS. The work of Phase I and

    part of Phase II is now complete while that of phase III is in progress. The first phase of DM

    consists of 3 corridors divided in to eight sections with a total route of 65.1 kms, of which

    13.17 kms has been planned as an underground corridor, 47.43 kms as elevated corridors and

    4.5 kms as a grade rail corridor. The second phase covers 53.02 kilometers of which the

    underground portion, grade and elevated section are expected to be 8.93 kilometers, 1.85

    kilometers and 42.24 kilometers respectively. The construction of the first phase of DM was

    spread over 10 years during 1995-96 to 2004-05 while that of the second phase, which started

    in 2005-2006 is expected to be complete by 2010-11.

  • 7/31/2019 Delhi Metro - Rachit

    5/11

    4 | P a g e

    BUSINESS MODEL:-

    DMRC is confident to cover operating and maintenance costs from day one. The DMRC

    expects an internal rate of return of over 2.3 per cent from the first day of operation. DMRC

    has been able to raise cheap loans. 56 per cent of the project cost (another 30 per cent has

    come in exchange for equity from the Delhi and Central governments) has come from a JBIC

    concessional loan at an interest of only 1.8 per cent payable in 30 years with a 10-year

    moratorium. In February 1997 JBIC agreed to extend 14,760 million-yen for Phase I of the

    Project, 6,732 million yen for Phase II in March 2001 and 28,659 million-yen for Phase III.

    This means there are no outgoings for the first 10 years. And the government is giving an

    interest free subordinate loan to cover the cost of land acquisition, which constitutes 8 per

    cent of the project cost.

    The DMRC has calculated that 90 per cent of revenue (Rs.12 lakhs per day) will come from

    tickets and the remaining amount is expected to come from selling advertising space in the

    stations as well as property development. The DMRC had hired the National Council for

    Advanced Economic Research to work out a tariff plan. Insiders say the NCAER concluded

    that only 1.6 million to 1.7 million passengers would use the metro and fixed a tariff slab that

    started with Rs 5 for the first 2-km. It decided that the costliest ticket would be Rs 10 at 2001prices. At these rates, the NCAER reckoned that the project would be able to meet its

    operations and maintenance costs as well as meets its depreciation costs. Delhi Metro Rail

    Corporation is developing commercial property within and around the stations. All stations

    will have ATMs, food outlets, coffee shops, newspaper vendors etc. In addition, it is

    proposed to lease the areas around the stations for development of supermarkets, commercial

    establishments and office buildings that would act as a supplemental revenue source. A

    contract has already been signed with McDonald's and negotiations are on with Nirulas to

    open fast food counters.

  • 7/31/2019 Delhi Metro - Rachit

    6/11

    5 | P a g e

    MARKET READYNESS:-

    As cities grow in size, the number of vehicular trips on road system goes up. This necessitates

    a pragmatic policy shift to discourage private modes and encourage public transport once the

    level of traffic along any travel corridor in one direction exceeds 20,000 persons per hour.

    National Capital Territory of Delhi (NCTD), with an area of 1486 km2 has a population of

    about 15 million. Buses are the sole mode of public transport in the NCTD, which are

    inadequate and overcrowded. For want of an efficient mass transport system, the number of

    motor vehicles is around 4 million. The result is extreme congestion on Delhi roads, ever

    slowing speeds, increase in road accidents (5 persons killed and 13 injured everyday), fuel

    wastage and environmental pollution with motorized vehicles alone contributing to about two

    thirds of the atmospheric pollution.

    The mixed traffic in the city has resulted in road accidents, killing 5 persons and injuring 13

    persons a day on an average. The situation is expected to deteriorate further in the years to

    come. It was in 1970 when the Central Road Research Institute (CRRI) after an exhaustive

    study on traffic and travel characteristics of Delhi recommended a Mass Rapid Transit

    Network for the city. Since then a number of studies on the subject have been carried out like

    the Metropolitan Transport Team (MTT) of the Indian Railways, Delhi DevelopmentAuthority (DDA) and the Study Group of the Ministry of Railways. Feasibility Report on

    Integrated Multi Modal Mass Rapid Transport System of Delhi (IMMRTS) prepared by

    RITES (Rail India Technical & Economic Services) recommended the 3-component system

    comprising Rail Corridors, Metro Corridors and Dedicated Bus Way totaling 198.50 km to

    meet the projected traffic demand up to the year 2021.Implementation started when the Delhi

    Metro Rail Corporation Ltd. under the Companies Act,

    1956 was set up in May 1995. Physical work on the project started on

    October 1, 1998.

  • 7/31/2019 Delhi Metro - Rachit

    7/11

    6 | P a g e

    STRATEGIES USED IN DELHI METRO

    Funding Strategies:-

    The capital cost of Phases I and II has been estimated to be 14,430 crore (US$3.22billion) at 2004 prices. However, more recent estimates have placed the cost of construction

    at 200 crore (US$44.6 million) per kilometer. Thirty percent of the total investment for

    Phases I and II has been raised through equity capital with the Government of India (GoI)

    and Government of Delhi contributing equal shares, and approximately another 60 percent

    has been raised as either long-term or subordinate debt, through soft loans from the Japan

    Bank for International Cooperation. The rest of the investment is proposed to be recovered

    from internal revenues through operations and property development. The Metro also

    received 1,914.3 crore (US$426.9 million) as grant-in-aid from various agencies for the

    financial year ending March 2009. As of August 7, 2010, Delhi Metro has paid back an

    amount of 567.63 crore (US$126.58 million), which includes loan amount for Phase I and

    interest amounts for Phases I and II, to the Japan International Cooperation Agency (JICA).

    Revenue and profits Strategies:-

    In 2007, the Delhi Metro claimed to be one of only five metro systems in the world thatoperated at a profit without government subsidies. This was enabled by keeping maintenance

    costs to a minimum and harnessing additional revenue from advertisements and property

    development, apart from ticket sales. The Metro also generates revenue by leasing out its

    trains and stations for film shoots. Due to its increasing association with Delhi as an image of

    the city's everyday life, it has been a popular filming location for production houses, and

    several films and advertisements have been shot on board. Producers have to pay as much

    as 1 lakh (US$2,230) for every hour of filming, besides a security deposit and insurance.

    For the financial year ended March 2008, the Metro reported operating revenues of

    305.27 crore (US$68.1 million) and a profit before tax of 19.98 crore (US$4.46 million),

    which rose to 723.77 crore (US$161.4million) and 90.4 (US$20.2 million) respectively

    for the financial year ended March 2009.

    Partnership Strategy- Went for extensive experience

    http://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Equity_capitalhttp://en.wikipedia.org/wiki/Government_of_Indiahttp://en.wikipedia.org/wiki/Government_of_Delhihttp://en.wikipedia.org/wiki/Debthttp://en.wikipedia.org/wiki/Soft_loanhttp://en.wikipedia.org/wiki/Japan_Bank_for_International_Cooperationhttp://en.wikipedia.org/wiki/Japan_Bank_for_International_Cooperationhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/Japan_Bank_for_International_Cooperationhttp://en.wikipedia.org/wiki/Japan_Bank_for_International_Cooperationhttp://en.wikipedia.org/wiki/Soft_loanhttp://en.wikipedia.org/wiki/Debthttp://en.wikipedia.org/wiki/Government_of_Delhihttp://en.wikipedia.org/wiki/Government_of_Indiahttp://en.wikipedia.org/wiki/Equity_capitalhttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crorehttp://en.wikipedia.org/wiki/United_States_dollarhttp://en.wikipedia.org/wiki/Crore
  • 7/31/2019 Delhi Metro - Rachit

    8/11

    7 | P a g e

    Consulted with Pacific Consultants International from Japan for engineering matters, Korea's

    Rotem and Japan's Mitsubishi supplied the initial shipment of coaches; France's Alstom

    designed of the automatic train control system.

    Pricing StrategyDMRC has kept its fare reasonable with a minimum of Rs 6 and a maximum of Rs 24 and

    has compensated by increasing the revenue from other sources like advertisements,

    commercial exploitation of available space and consultancy services.

    Relationship Strategy- Assembled the metro carriages inBangalore and rolled them on Indian Railways track straight to the New Delhi Metro to

    avoid the conflict with Indian Railways about the kind of track to be used.

    Advertising StrategyUse of Lenticular vision technology - the picture and the projections are modified to suit the

    audience speed helping them to view the advertisements clearly.

    Customer Oriented Approach

    1) Implementation of Smart cards

    2) Feeder Bus Service

    3) Rent a cycle service in the University campus

    4) Ductile pathways and ramps to guide visually challenged people

    5) Pre Station alert Emergency Services

  • 7/31/2019 Delhi Metro - Rachit

    9/11

    8 | P a g e

    ADVANTAGES OF DELHI METRO:-

    Reduction in the number of vehicles on road

    The growth rates of registered cars, two-wheelers, three wheelers, taxis and buses in

    Delhi are calculated as 9.8, 11, 8, 5 and 7 percent, respectively using data for these

    vehicles for the period 1971-2002. To calculate the number of vehicles going off the

    road due to the introduction of MRTS the following exercise is conducted. The

    registered number of vehicles for each category of these vehicles in Delhi for the period

    2002-42 is estimated using the above mentioned growth rates.RITES (1995a) has

    reported that out of the total registered vehicles, only 28 percent of cars, 40 percent of

    two-wheelers and 65 percent of taxis and three wheelers are on the roads. It is also

    reported, depending upon the area and the density of population through which the

    Metro line passes, that only 30 percent of vehicles on road are influenced by Phase I of

    the Metro. It is further mentioned that 45 percent of cars, 70 percent of two-wheelers,

    and 25 percent of buses out of the influenced traffic are diverted to Metro. It is assumed

    that modes of transport like taxis and three wheelers are on the road by choice and

    hence they will not be diverted due to the Metro.

    Savings in fuel consumption

    There are savings in fuel consumption (inclusive of both CNG and petrol) due to the

    diversion of a part of the Delhi road traffic to Metro and reduced congestion to vehicles

    still operating on the roads. There is an inter-fuel substitution of petrol and CNG to

    electricity that could result in savings of foreign exchange and a reduction of air

    pollution. Fuel saved due to traffic diverted to the Metro is estimated given the

    estimates of diverted traffic described above and the annual run and fuel consumption

    norms of different vehicles. Table 12 provides information about the annual run and

    fuel consumption norms of different vehicles in Delhi. RITES (2005a) has estimated

    the total reduction in CNG due to the traffic of buses diverted to the Metro (Phases I &

    II) during the year 2011-12 as 39.65 million kg.

    Reduction in air pollution

    Fewer vehicles and the decongestion for the residual traffic on Delhi roads due to Metro

  • 7/31/2019 Delhi Metro - Rachit

    10/11

    9 | P a g e

    could lead to reduced air pollution. The distance saved due to decongestion is estimated by

    multiplying the time saved with the speed of a vehicle in a decongested situation. An

    estimate of the pollution reduction by a vehicle in this context could be obtained by

    multiplying the distance saved by the relevant emission coefficient for different pollutants

    for each category of vehicle. The emission coefficients for different vehicles as per the

    Euro II norms are given in Table 13. Estimates of reduction in distance traveled every day

    due to the decongestion effect are obtained for cars, two wheelers and buses as 9.18 kms,

    7.65 kms and 69.72 kms, respectively.

    Savings due to fewer accidents

    The Road User Cost Study (CRRI, 1982) later updated by Loss Prevention Association of

    India provides estimates of the cost of various accidents on road. Components like gross

    loss of future output due to death/major injury, medical treatment expenses, legal

    expenses, administrative expenses on police, insurance companies and the intangible

    psychosomatic cost of pain were included in the estimation. In the case of buses and other

    public vehicles, the loss due to lay off period and unproductive wages paid to the crew are

    also included.

    Savings in vehicular operating costs due to the decongestion effect

    Annual vehicle operating cost is substantially reduced due to the higher speed of

    vehicles and consequently lesser hours on road. It is estimated as the product of the

    residual traffic, time saved on average lead per vehicle annually and the vehicle

    operating cost per hour. According to RITES (2005b), the value of this component for the

    year 2011-12 is Rs. 15040 million.

    Savings in Capital and Operating Cost of Diverted vehicles

    Reduction in the capital and operating cost of vehicles due to the introduction of the

    MRTS is given by the product of the diverted traffic stream, the annual run and the

    VOC/V-km. The estimated value of this component for the year 2011-12 is Rs. 17677

    million.

  • 7/31/2019 Delhi Metro - Rachit

    11/11

    10 | P a g e

    WHY DMRC IS SUCCESS:-

    The Delhi Metro Rail Corporation (DMRC) is one of the four metros in the world to have

    operating profits among 135 metros globally. DMRC has been making operating profits eversince it became operational. However, in 2005-06, it earned Rs 448.93 crore, where as its

    expenditure was Rs 102.41 crore, thus making an operational profit of Rs 346.52 crore," the

    case study adds. Investment in the Delhi Metro's phase I - ended November 2006 - was Rs

    10,571 crore. The second phase, much larger in terms of size, will need much higher

    investments. The network currently is 65.1 km long and another 121 km will be added with

    Phase II. By some estimates, the project, when sanctioned eight years ago, was premised on

    expected passenger traffic of 21, 80,000 per day in the third year of operation from December2002. Today only 5, 00,000 commuters use the metro per day.

    The DMRC website states that estimated number of originating passengers per day in the

    year 2011 for Phase I and Phase II corridors will be 26,17,000. About 1,100 train trips

    operate every day with a punctuality of nearly 100 per cent, states the IIM case study.

    According to DMRC spokesperson Anuj Dayal the metro earns Rs 1 crore daily, of which Rs

    65 lakh comes from passenger fare and the rest comes through associated activities like

    property development, advertisements and displays, consultancy and others. Following

    DMRC's success, it has been asked to prepare detailed project reports for metro rail transport

    systems, both in India as well as abroad.