42
DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE Andrew Burr MA(Cantab), ACIArb, FFAVE(Master) ArbDB Chambers Silver Shemmings LLP London

DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

Embed Size (px)

Citation preview

Page 1: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE

Andrew BurrMA(Cantab), ACIArb, FFAVE(Master)

ArbDB ChambersSilver Shemmings LLPLondon

Page 2: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

2

1. Delay and disruption: some attempted definitions

Comparative terms

No intrinsic qualities

Completion dates

Causes and effects of each other

Page 3: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

3

2. Introduction

•Walter Lilly and Company Limited v Mackay,[2012] EWHC 1773 (TCC), per Akenhead J

•Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TRC), per Ramsey J

Page 4: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

4

3. Apportionment concurrency and progressagainst the contract programme

3.1 The English and Welsh way: Walter Lilly and Company Limited v MacKay [2012] EWHC 1773 (TCC)

JCT standard form of BC 1998 edition: almost 30 months delay; 234 EoTs requested with 196 EoTs going unanswered; evaluation in judgment depended upon Lilly’s design responsibilities and of the defects

Who has the responsibility to pay up?

• Defects claim almost totally unsuccessful

• Further payment of £2.3 million (plus costs) and EoTs awarded to the date of practical completion (PC)

• Unclear contractual allocation of design responsibility

Page 5: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

5

Apportionment, concurrency and progress against the contract programme

EoT:

1. Look at what the contract stipulates

2. Look at relevant evidence; actual facts and expert advice (minus any theoretical possibilities)

3. If delay results from two or more effective causes, one entitling the contractor to an EoT as a relevant event, EoTshould be granted (an “all or nothing” approach)

4. The central question = CAUSATION

Page 6: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

6

Apportionment, concurrency and progressagainst the contract programme

Based upon:

• Principle that these are relevant events that would otherwise amount to an act of prevention; unfair not to award an EoT in such circumstances

• The “straight contractual approach”; clause 25 of JCT stated nothing about apportionment if the contractor is partially responsible for delay

Page 7: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

7

Apportionment, concurrency and progressagainst the contract programme

How to assess causation in relation to delay?

1. Criticality

1. Generally, not the last item of work but what delays this

2. Snagging? Only if excessive

2. Prospective and retrospective analysis

1. Should come to the same conclusions

2. Prospective: requires a “critical path programme” (CPP) (absent in this case from 2007)

3. Cross-checking (in absence of a CPP):

1. Month-month review of probable delays

2. Cross check with facts (factual analysis)

Page 8: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

8

Apportionment, concurrency and progress against the contract programme

• Amended JCT 80 contract (construction of a hotel in Bristol) employer, (City Inn) dismissed design team and contractor, Shepherd claimed 11 week EoT to the completion date.

Is there an entitlement to EoT, if the architect's instructions which caused delays were concurrent with delays arising from matters which were the contractor' s responsibility?

3.2 The Scottish way: City Inn v Shepherd [2010] CSIH 68

Page 9: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

9

Apportionment, concurrency and progress against the contract programme

Elements of relevance for the decision:

• Principles of calculation of EoTs

• Critical path analysis

• Causation in law when there are concurrent events

Page 10: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

10

Apportionment, concurrency and progress against the contract programme

Lord Drummond Young:

• Thorough examination of the construction process supported by expert witnesses

• Mere critical path analysis approach not possible in the case at hand (eg because of lack of full electronic records from the contractor)

• “Where there is a true concurrency between a relevant event and a contractor default, in the sense that both existed simultaneously, regardless of which started first, it may be appropriate to apportion responsibility for the delay between the two causes.”

Page 11: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

11

Apportionment, concurrency and progress against the contract programme

Inner House of the Court of Session, Scotland (majority) held

• Where two concurrent causes are operative, one being a relevant event and the other being an event for which the contractor is responsible, the certifier should approach the matter in a fair and reasonable manner and apportion the delay between the causes unless one is dominant.

Page 12: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

12

Five Hudson principles for the evaluation of a delay claim

1. Is there a relevant event which is likely to cause / has caused delay as a result of which completion of the work is likely to be / has been delayed?

2. Application of common sense

3. Discretion of the decision maker as to the choice and use of evidence

4. Is the cause dominant?

5. In case of concurrent events, neither of which is dominant

Discretion of the decision maker to apportion the delay by applying the principles of fairness and reasonableness

Apportionment, concurrency and progressagainst the contract programme

Page 13: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

13

4. Assessment of causation

• Mirant• City Inn• Allocation of responsibility by expert witnesses of opinion• DDCCS

Page 14: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

14

5. Time at large and the prevention principle

• Honeywell = sub-contractor, responsible for the security and communication installations at Wembley

• Multiplex = main contractor

Did Multiplex mismanage the project? Did this mismanagement release Honeywell from its

obligations to complete the project within the period foreseen in the sub-contract?

Multiplex v Honeywell [2007] EWHC 447 (TCC)

Page 15: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

15

Time at large and the prevention principle

Honeywell’s line of argument:

• Prevention principle

• Failure by Multiplex to provide adequate programming data deprived Honeywell of the possibility to give proper notices or particulars of delay ( condition of the right to an EoT)

• Gaymark Investments v Walter Construction (no liquidated damages for delay, even though no EoT could be given)

Page 16: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

16

Time at large and the prevention principle

Jackson J (as he then was):

• Prevention principle not applicable, since the contract allowed Multiplex to grant EoTs for “acts of prevention”

• Sub-contractor is only expected to give notices when practicable and if there is requisite knowledge

• Contractual terms requiring the contractor to give prompt notice of delay should be preserved, regardless of the other party complicating matters

Page 17: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

17

6. Notice as a condition precedent

• Contractor had to work towards certain phases of the project to achieve target service availability dates (TSAD) • Contractor had to give notice if it could not achieve a TSAD within 20 business days of the delay event• Contractor served a TSAD notice of delay due to asbestos (containing a claim for EoT and damages)• Contract provided for an obligation of the contractor to comply with a 20 day deadline for notice of “works compensation event” (WCE) such notice was not served

Education 4 Ayrshire v South Ayrshire Council [2009] CSOH 146

Page 18: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

18

Notice as a condition precedent

• Cautionary tale for contractors entering into contracts requiring a strict formal process in order to obtain time and money

• Determination of the meaning and effect of a condition precedent clause by a Scottish Court (= clause regularly used in FIDIC and NEC contracts to prevent contractors claiming an EoT, or additional payment unless they provide written notice of the delay event, within a prescribed time limit):

Page 19: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

19

Notice as a condition precedent

Decision: • Strict and clear contractual requirements for relief (including WCE notice)• Non compliance with these requirements leads to loss of right to extra time and payment

Decision is in line with previous cases (eg Steria Limited v Sigma Wireless Communications Limited): no interference by the courts in cases of clear and unambiguous contractual requirements

Page 20: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

20

7. The valuation of damages for prolongation

• Claim for damages for breach of contract /negligence

Is a recovery of prolongation costs for the period during which it was alleged that the project encountered delays from the abandonment of the surcharged scheme and the later design and construction of piled foundations possible?

What is the critical delay to the completion of a project in the case of a negligent foundation design?

Costain v Haswell [2010] TCLR 1

Page 21: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

21

The valuation of damages for prolongation

• Experts from both parties agreed on delays to foundations causing critical delays due to one of the affected structures being on the critical path at the time

• Unanimity between experts as to a common methodology to assess delay (using time impact analysis), the baseline programme as well as as-built data

• Differences between the experts on how the agreed methodology should apply

Page 22: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

22

The valuation of damages for prolongation

Deputy High Court Judge Richard Fernyhough QC in the TCC:

• Design had failed to produce the intended result

Negligence

• Criticism of both experts:

- Failure to undertake an analysis of a specific period

- Failure to consider what effect the foundation delays actually had on follow-on activities and other structures

- Failure to investigate whether Costain could have mitigated or negated the initial delays by later events.

Page 23: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

23

The valuation of damages for prolongation

Held:

• Recovery of prolongation costs for the whole project requires the demonstration that the delay relied upon in fact led to an overall delay to the completion of the project as a whole, not due to other reasons

• Since there were other delays caused by United Utilities as well as Costain, there was no justification for Costain recovering all its costs in maintaining the site

• The extent of critical delay can only be determined retrospectively once the works are completed

Page 24: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

24

The valuation of damages for prolongation

Clause 26 JCT:

• Contractor informs architect of losses/expenses incurred or likely to be incurred

• which, under the contract terms, will not be reimbursed

• which, will materially affect the progress of Works

• Architect agrees that works will be materially affected

• Architect shall instruct a quantity surveyor to quantify the loss/expense

• AS LONG AS...

Walter Lilly and Co Limited v Mackay [2012] EWHC 1773 (TCC)

Page 25: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

25

The valuation of damages for prolongation

Conditions:

• Provisions of 26.1.1ff. of the JCT contract are followed• Timely application • Provision of factual supporting details and evidence

-> But what does this entail? • Common sense fact-fact approach• Consider knowledge available to Architect and their involvement in the project • Put architect in reasonable position

This can be retrospective, or prospective

Page 26: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

26

The valuation of damages for prolongation

“Global” and/or “total” loss claims:

“These are not terms of art or statutorily defined terms...What is commonly referred to as a global claim is a contractor’s

claim which identifies numerous potential or actual causes of delay and/or disruption, a total cost on the job, a net payment from the employer and a claim for the balance between costs

and payment which is attributed without more and by inference to the causes of delay and disruption relied upon”

Akenhead J

Page 27: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

27

The valuation of damages for prolongation

Principles:

• Contractor must prove delays occurred and caused it to incur loss on the balance of probabilities

• No need to show that it is impossible to prove cause and effect in the normal way

• Any condition precedent clauses re notification are complied with

• No established method of proof for such claims

Evidentiary difficulties:

• Contractor must show that loss has been incurred would not have been incurred in any event

• They had a sufficiently well-priced tender which would have made a net return

Page 28: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

28

The valuation of damages for prolongation

Not all, or nothing:

• If the claim includes an event, not caused by the employer, this does not wipe out the claim

• It all depends upon the impact of such events

• A deduction can be made from the global claim total for such individual events (ie in a claim for £1M with an underpriced £50K item, that 50K item is deducted)

However:

• No need for such a claim, if it is possible to find the actual cost attributable to individual events

• Possible, even if contractor is responsible for the inability to disentangle individual events

Page 29: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

29

The valuation of damages for prolongation

The facts:

• Contract was a “complete mess” on the administrative side

• Insufficient design from the outset and no sufficient allocation of this responsibility to WLC

• Multiple variations

• “Hopelessly late provision of instructions and information”

• Lack of unity and certainty between owner and designers

• Allowed for certain losses/expenses to be claimed as a global claim

Page 30: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

30

The valuation of damages for prolongation

Head office overheads and profit:

1. Contractor can recover the above as a result of owner-caused delay

2. Contractor must prove, on balance of probabilities, that if there had not been delay, it would have won tenders for other projects which would produce a profitable return or contributed to head office overheads

3. Emden/Hudson formula are useful methodologies for calculating number 2 above

4. There need be certainty that the loss or expense has been incurred because of a clause 26 delay.

Page 31: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

31

8. Global and/or total costs claims

• Impossibility of proving cause and effect

• Lilly

Page 32: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

32

9. Head office overheads and profit

• Proof that the contractor would otherwise have successfully won other contracts

• Clause 26 relevant event

Page 33: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

33

10. Material breach: programming

Material breach for the purpose of termination: failure to provide a rev 4 programme?

Hudson on Building and Engineering Contracts (8-056 to 8-058):

• Facts of the case

• Consequences of termination

• Importance attached to the type of breach

• Actual circumstance of the breach

• Commercial consequences of the breach

Here: time of completion = important aspect of the project

Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC)

Page 34: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

34

Material breach: programming

• Contractor’s inability to provide a “rev 4 programme”

• Five principles derived from Hudson

Page 35: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

35

11. Obligation to proceed regularly and diligently

West Faulkner Associates v London Borough of Newham [1992] 71 BLR 1

• Contractor obliged to do both

• Regularly: “With sufficient way of men, materials and plant to have physical capacity to progress works substantially in accordance with contractual obligations”

• Diligently: “Physical capacity must be applied industriously an efficiently with successful progress towards contractual obligations”

Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC)

Page 36: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

36

Obligation to proceed regularly and diligently

• West Faulkner Associates definitions

• Vivergo v Redhall

Page 37: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

37

Obligation to proceed regularly and diligently

Facts:

Vivergo claims Redhall breached this obligation by:

• Inadequate resourcing of critical path works to DET

• Lack of productivity

• Lack of programming

• Poor labour management and supervision

• Poor material controls and site management

Ruled: in breach of productivity and programming obligations because of a lack of a proper programme. This gave rise to a notice under 43.2(b) of the Contract.

Page 38: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

38

12. Notices

• Unilateral notices:

• Construe against the relevant objective contextual scene

• Meaning as understood by the reasonable recipient

• Purpose of notice is relevant to its construction

• Sufficiently clear and unambiguous

In addition, default and termination notices:

• Must be reasonably connected in content and time

• Notify the default

• Indicate seriousness, or link to clause 43.2

Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC)

Page 39: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

39

Notices

Facts:

• No explicit clause 43.2 reference > valid in the background context, or improperly construed?

• Not specific and unambiguous enough in the three notices

• The reasonable recipient of the letter would...not know that it had to take steps to remedy a default within 14 days to avoid termination

• Fourth notice: contained a sufficient link to a clause 43.2 notice BUT only with regard to one aspect of the claim

• Not consider that it can be construed as giving clear and unambiguous notice that Redhall had to take other steps

Page 40: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

40

13. Opinion evidence

Walter Lilly v DMW [2012] EWHC 1773 (TCC)

Expert witnesses

“Persons of this description though in English law confounded with witnesses and not without advantage treated as such, are in fact a sort of assistant to the Judge and treated as such by Roman law. The expert witness is in quite a special position. He is an assistant in the determination of truth. He is a purveyor of information on which decisions are arrived at, and to the truth and validity on that information his professional credit and reputation are pledged”

Attributed to Jeremy Bentham

Page 41: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

41

Opinion evidence

Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC)

How an expert’s approach can help assess delay and disruption, which leads to breach?

• Use common programme and factual information

• Aware of each other’s approach

Problems:

• Lack of coherent reasoning and analysis

Page 42: DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND · PDF fileDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE ... damages for delay, even though no EoT could be given)

42

Thank you for your attention!

[email protected]

[email protected]