Upload
prashant-kumar
View
249
Download
3
Tags:
Embed Size (px)
DESCRIPTION
APPAREL INTERNSHIP DOCUMENT ON DELAY ANALYSIS REPORT AND SMED
Citation preview
NATIONAL INSTITUTE OF FASHION TECHNOLOGY
INTERSHIP REPORT COMPANY: HHEC of India Ltd., 31 - 32, Guindy Industrial Estate, Chennai, Tamilnadu.
AN EFFORT BY: NEELKANTH PASHUPATI SINHA PRASHANT KUMAR TARUN PARGAI
B.F.Technology (Apparel Production)Semester -7(Batch 2009 - 2013)
1
Acknowledgment
Our sincere gratitude to our mentor Mr. Amit kumar Anjanee (Assistant Professor) DFT, for his support, guidance and encouragement. We are very thankful to H.H.E.C, Chennai for entrusting us to do our internship with them. We are indebted to thank, Mr.K. Venkataraman (Senior Manager), Mr.K. Paneerselvam (Assistant Marketing Manager), Mr. Manohar (Marketing Executive) , Mr.R.Laxminarayanan(consultant) for their information, guidance and support.
We would like to thanks to our course coordinator Mr. Samuel Wesley (Associate Professor) DFT, for her special support.
I would like to thank each of my batch mates for support and co-operation.
2
COMPANY HIERARCHY
3
General Manager
Production Manager
Quality Manager
Quality Incharge
Line checker
Unit incharge Sampling Incharge Cutting Incharge
Sampling supervisor
Cutting supervisor Unit supervisor
Stitching supervisor
Packing supervisor
Packing incharge
COMPANY PROFILE
HHEC , a Govt of India Ministry of Textile company has an exhaustic range of Indian handicrafts , indian handlooms , Indian decoratives , Indian gifts , Indian antiques , leather decoratives , gems and jewellery , Garments , wrought iron handicrafts . We at HHEC ensure the quality and genuiness of the product .HHEC's Garment division has a modern factory in Chennai (Madras) located at the Industrial Estate, Guindy (Madras). It manufactures and exports apparel made of cotton, silk and cotton/nylon for men, women and children. Its strength is in casual wear of cotton fabrics. It has separate quality assurance wing, which takes care of online quality control (In cutting room and sewing room) as well as final quality audit before releasing garments for pressing and packing. The fabric inspection wing takes care of quality control before releasing fabrics for cutting.
Fabrics that are used for makingGarments
Quality of the Fabric Items
COTTON
Light Medium weight in yarnDyed like 40s x 40s, 2/60s x 40s,2/40s x 20s, 2/80s x 2/60s,Seersucker, 80s mull, cambric,Bubbled batik, Kalamkari,Patchwork fabric, printed, Dobby& Jacquard. Heavy weight-Twill, Drill, Flannel, 2/10s x 6s
Mens, Ladies &Childrenswear
Like Shirts,Blouses, pants, Shorts,Tops,Dresses, etc.,
SILK
Filature x Filature, Filature x Dupion,Taffeta, tussar, Matka,Muga.
4
S.NO PARAMETER VALUE MAINTAINED
1FLOOR AREA OF EACH FLOOR
2 FIRE EXTINGUISHERS
DISTANCE BETWEEN
EACH, NOT MORE THAN
50 FT.
3HEIGHT OF LIGHT FROM THE
SEWING MACHINE1.3 METERS
4ANGLE OF THE CHROMIUM
REFLECTORS45° TO 60°
5POWER OF EACH ENERGY
EFFICIENT TUBE LIGHT28 WATTS.
6 HEIGHT OF THE FLOOR 24 FT( 6.6 METERS)
7 URINALS6 FOR MEN(1 urinal per 30),
8 FOR FEMALE(1 per 20)
8 AISLE SPACES42 INCHES( 3.5 FT or 1.06
MTS)
9DISTANCE BETWEEN CUTTING
TABLES4.5 FT (1.37 MTS)
10DISTANCE BETWEEN EACH
SEWING LINE4 FT( 1.21 MTS)
12 WINDOWS LOCATED ON THREE
SIDES OF WALLS
5
Non-Sewing Machines
SL
No.
Description Make Model
1 Snap Button Toniy T1808
2 Button Pull Tester Presto
3 Button Wrapping St-9 Loiva
4 Placket Cutting Nagashing NS94
5 Collar notcher Nagashing NS91
6 Collar Turning Nagashing NS44
7 Collar Turning Nagashing NS81
8 Cuff Turning Nagashing NS46
9 Cuff Turning Nagashing NS85
10 Thread Winding Toniy TI3900
11 Cloth Drilling Eastman CD3
12 Cutting Eastman 629X/BLUE STRECK
13 Round Knife Cutting Eastman EC 45
14 End Cutter Sulee 360
15 End Cutter Nagashing NS71
16 Band Knife Oshima OB900A
6
Sewing Machinery Details:
224 Single Needle machines and special machines like, lockstitch button stitching, Front placket Multineedle sewing machine, Elastic attaching Multineedle machine, Keyhole buttonholing machine, Feed –off the arm, Double needle, blind stitch hemming machine, 5 thread overlocking machine. Also special attachments of suisei brand like pin tucking attachment, Ruffler attachment, Spaghetti attachment for loop making, bias binders, straight binders. etc.,
7
ACTIVITIES OF A MERCHANDISER
8
SAMPLING
MERCHANDISING
PRODUCTION PLANNING DEPT.
FABRIC MAIN STORE
FABRIC SUB-STORE
CUTTING DEPARTMENT
SEWING SECTION
FINISHING
QUALITY
PACKAGING SHIPMENT
TRIM STORE
Design/Sampling
Fabric
Accessories
Testing
Production
Quality Check
Documentation
Shipping/Forwarding
MARKETING MERCHANDISING
Main functions of marketing merchandising are:
Product development
Costing
Getting Purchase Orders
It brings the order, develops the product, and does the costing. It has a direct access to
the Buyer.
PRODUCT MERCHANDISING
This is from sourcing to finishing that is from first sample to onwards, the product
merchandising work starts and ends till the shipment
PACKAGE FILE
It consist of following reports
1. List of orders pasted on the left hand inside cover of the file.
2. Tech pack.
3. CAD marker-costing and factory
4. RMR-order wise and summary chart
5. Trim pro forma invoices from the supplier.
6. Confirmation of the trim
9
7. Order chart from the buyer
8. P.O. copies from the buyers
9. Fabric “order confirmations” with approved fabrics swatches
10. Hard copy of all incoming and outgoing crucial and important mails that may
be required for future references (buyer related)
11. Mills fabric reports-checking, testing
12. Internal fabric reports-checking, testing
13. Buyer approved-
a. Trim card
b. Shade bands
c. Wash swatch/wash mocks
d. Embroidery/printing
14. Packing list
Sampling Department
WORKING PROCEDURES 1. The package file is received from the merchandiser and the copies of it are
handed over to the sampling manager, CAD in charge, sampling technician and
the sampling QA in charge.
2. The pattern request is received from the merchandiser by the sampling manager
for the following samples:
Fit sample
PP sample
Size set sample
Top sample
Types of samples
Proto sample
It is made of out raw fabric. It is the first sample send to the buyer to check the fit of
the garment. It is also known as development sample.
Design sample
All the designs are implemented in the garment in order to look the appearance and the
design of the sample to the buyer.
10
Size set sample
All the sizes of a particular style are stitched is stitched and send to buyer. The buyer
checks the grading in this sample.
3 samples are made.
Every sample contains a review sheet and spec sheet .
4 proto sample of each size are made and 1 is send to-
Buyer.
Merchandiser
Vendor
Sampling section.
Pre-salesman sample
3. Generally the above 3 sample are not asked for by most of the buyers. Hence the
next sample is made after the proto sample, is the pre-salesman sample.
4. Then samples are made to check the samples whether they are proper for the SRC
5. 3 samples are made.
6. These samples are sent to the buyer for the buyer for approval.
7. The sampling section also calculates the Thread Consumption. This is done using
the meter. The meter is attached to the sewing machine and the garment is stitched.
The meter gives the amount of thread consumed (in mtr).
8. They also calculate the thread using the measuring method. They stitch a meter
length. Then the thread is ripped off and the length measures.
9. They then prepare the Thread Consumption Report. This report contains the details
– Type of stitch, Stitching length, SPI, Consumption per mtr. This is filled for all the
stitches in the garment.
10. The weekly plan is then generated based on the requisition received from the
merchandiser and it is handed over to the sampling coordinator, CAD in charge,
merchandiser and the sampling QA in charge.
11. The pattern cum sample requisition is given to the sampling coordinator by the
sampling manager for manual patterns as per the buyer requirements.
11
12. The CAD in charge receives the package file from the sampling coordinator and
after discussion with the sampling manager and the technician the package file copy
is handed over and discussed with the concerned pattern maker.
13. The pattern maker after discussing with the technician makes the patterns
according the details in the package file and hand over the patterns to the CAD in
charge.
14. The patterns along with the cutting plan are then handed over to the sampling
coordinator who in turn hands them over to the cutters.
15. The requisition is raised for the fabric and accessories by the sampling coordinator
and given to be signed by the sampling manager.
16. According to the weekly plan prepared by the sampling manager for the tailors and
cutters, their individual targets are fixed.
17. The feeding helpers do the loading as per the requisition of accessories and fabric
to the cutters and tailors
18. Cutting and stitching of samples is then started.
12
PRODUCTION PLANNING AND CONTROL DEPARTMENT
WORKING PROCEDURES
The senior coordinator of the PPD receives the order booking from the GM
merchandising through mail. It has the following details in it:
style #
quantity
delivery date
fabric in-house data
accessories in-house data
The operation breakdown (OB) of the particular style is received from the IE
department to fix the final inspection (FI) dates, the sample collected from the
concerned merchandiser is studied with the OB and the CMD is checked for
machines.
13
RECEIVING ORDER BOOKING
GENERATE FACTORY PLANNING
GENERATE PCD PLAN
GENERATE LINE PLAN
GENERATE FINISHING PLAN
GENERATE HOURLY PRODUCTION REPORT
DISCUSS WITH UNIT
Based on the order booking, factory planning is generated as per the delivery date
and copied to the following:
GM merchandising
Merchandiser
FABRIC STORE DEPARTMENT
The basic functions of the fabric store are:
Storage and Segregation of Fabric for production.
Storage of dead stock.
Maintain basic stock.
Co-ordinate fabric flow between cutting, processing, and audit department.
Coordination between the Suppliers, Fabric processing, audit and cutting
Department.
Maintain account and documents in order to ensure regular flow of fabric and
no shortage.
Report maintained in the fabric department.
Maintain inspection reports.
Physical Testing & Inspection:
Fabric is inspected by using a 4 point system. It is a projection of total defects based
on the total number of defects found during inspection of a sample as a basis for
acceptance/rejection criteria. In this point inspection system penalty points are
assigned base on the standard fault.
There is only manual inspection. In 4 point system 40 points are acceptable.
For minor defect cross sticker is place for identification
For major defect part changed sticker is place for identification
Point assign for the 4 point system
Fault Size Point Assigned
0 to 3 inches 1
3 to 6 inches 2
6 to 9 inches 3
9 & above 4
14
Upto 40 points are acceptable
The common defects observed are:
Fabric uneven width Slub
Foreign yarn Stain
Missing yarn Knot
Reed mark Selvedge thickness
Fabric shade Fabric design
Cuts Thickness
Trims department
Infrastructure:
Racks
Issuing table
Fire extinguisher
Tube light
Fan
Trims available in trim department:
Threads
Tissue paper
Clip, PVC Patti
Poly bag, single and
master polybag.
Buttons-14,16,18
Carton, gum tape
Main label
Wash care label
Barcode label
Zipper-6 ½,3 ½,4 ½,5 ½,11
½,17,18 and 19
Taps
Needles-DB*5=14and18,
DB*5=16,
15
DB*17=14(button hole).
Process Flow
First the trims store in-charge receives the PO copy. This PO copy contains
various details such as the PCD Date, Sample Date, PCD Sample, Prototype
Sample, Order chart, RMR.
The trim store in-charge takes out only the Raw Material Status Report (RMR).
This report gives the details as to the which trims are to be received, the
consumption per garment, the required quantity, the quantity ordered, the
quantity received and the balance left to receive.
There are 2 parts to the trims store.
o Stitching Part
o Packing Part
When the trims are received, the trim unit checks them and makes an Inward
Challan. In the quantity ordered, 3% extra is always added as for wastage
considerations.
Maintain a Daily Status Report of the trims that are issued from the main store
and the balance left yet to receive.
The inspection of the trims and accessories is done in the main unit itself.
Hence, when the trims are received, they are only stored and issued to the
production at the trims store.
However, for buttons counting is done. Inspection is done in case of Labels and
Shrinkage test for Elastic.
Out of the 1 roll or 1 box, 100 labels are inspected for defects or damages.
o If 4 defects are found, it is accepted.
o If 5 or more defects are found, then another 100 are checked.
If 4 defects are found, it is accepted.
If 5 or more than 5 defects are found, then the entire lot is rejected.
In case of 100 labels,
o 40 defective are acceptable
o 50 are unacceptable
o And 40-50 are in the decision making process.
16
There are many types of labels that are used in the production:
o Main Label – has the buyer’s name and logo
o Content Label – contains the content of the fabric
o Size Label – size of the garment is specified
o Wash care Label – has the wash care instructions for the garment
Shrinkage (%) = [After wash – Before wash)/before wash] * 100
In case there different shades in the buttons that are received, all the different
shades of the buttons are stuck too in the chart.
This chart goes to the merchandiser for the approval. The merchandiser signs
the chart and sends back. The shades of the buttons (if present) are then
approved form the buyer and signed.
The rest of the trims are not inspected. After this inspection, a meeting is held
between the trim store head, Industrial Engineer Department head, Production
coordinator and the cutting department head.
In this meeting it is decide as to which colour and style has to be cut first for
production. This is decided on the trims that are received. As to for which style
and colour the trims are available for production.
This is taken by the feeding helper who maintains a register called the Cutting
Book. All the details of the slip are copied into this book, except the Shrinkage.
The helper also fills in the time..
The trims and accessories are then issued to the required dept as per the
required qty.
There is no fixed method of Issuing System followed here. The trims as and
when received are kept together (mixed up). While issuing any of the stored are
issued.
After every 2-3 days the stocks are checked.
The trims store also maintains Bin Card. These bin cards were found hanging
by the racks that store the trims. Every section in the rack had an individual bin
card containing all the details.
The bin card contains the details of the trims that are being stored in the rack,
how much is issued and the balance. Details – Date, Received Qty, Date, Line
no., issued qty, Balance.
Inspection for the selected trims & accessories
17
Sl.No ITEM PARAMETERS
CHECKED
TOLARANCE
1. Sewing thread Shade no. NIL
Ply NIL
type NIL
2. Button Line no NIL
type NIL
No of holes NIL
colour NIL
3. Zipper type NIL
1. length NIL
Type of puller NIL
colour NIL
2. Cartons Size +1”-1/2”
No of ply NIL
Printed matter NIL
CUTTING DEPARTMENT
18
Objective of cutting room:
Cost control
Cutting methods
Process Flow:
Defect management
Spreading techniques
Material handling
19
Merchandiser sends the cutting details desample
Numbering
Marker planning done and Fabric consumption calculated
Spreading and cutting
Panel checking (Top, middle, bottom)
ok
Pilot run
ok
Bulk run
Maintaining Min using book
TICKETING /BUNDLING
SEND FOR SEWING
MANUAL SPREADING AND CUTTING
First a layslip is given from the minusing department. Minusing department gets
the total quantity which has to be cut and the ration of the sizes in which marker
planning is made, then as the pieces are cut they keep on subtracting that quantity
from the minusing book. Mainly the cut order planning is done.
After spreading 1 or 2 ply of a lay, QC checks for the length, width, face side, and
shade variation of the fabric.
When QC comes through any defect a sticker is pasted there and a brown sheet is
placed so that that part can be recognised easily for recutting,
Then the manual marker or plotted marker is placed over the lay and with straight
knife patterns are cut.
NUMBERING
After the panels are cut, according to the size and shade bundles of parts of the
garment are made which contain 20 pieces of each parts and each part of a garment
are given the same ticket number.
After numbering the parts of the garment in the bundle are counted and recorded in
the cutting check list.
FUSING
After numbering the parts which has to be fused is send to the fusing incharge
where they are fused.
Before fusing the temperature, time, and pressure is evaluated by using viline
fusing tape. After fusing the parts are send for bundling. And then stored in parts
bank.
Observation Suggestion
20
Difference between the actual and standard spreading time.
Spreading techniques should be practiced by the operator.
Only big left over pieces are reused
.
Waste pieces should be given to recycling industry
Out of 3 fusing machine only 2 machines are functional.
Machine should be repaired to reduce the time consumed.
SEWING DEPARTMENT
21
PROCESS FLOW
22
MERCHANDISING PRODUCTION DEPARTMENT
CUTTING DEPARTMENT
TECHPACK, SEALED SAMPLES, PATTERN
ESTIMATED OPERATION BULLETIN
CUT (FABRICS, PANELS)
SEWING SECTION
SIZE SET
PRE-PRODUCTION MEETING
FINAL OPERATION BULLETIN
BATCH SETTING
PILOT RUN
BULK PRODUCTION
PRODUCTION MANAGER, MERCHANDISER SAMPLING,
CUTTING, QUALITY PLANNING, BUYER REPRESENTATIVE
WORKING PROCEDURE IN SEWING FLOOR
Once the Order gets confirmed for a particular style the planning department comes in
to action. It planned in well advance that which unit is going for Production as well as
the Quantity.
Then Factory Manager, decides the batch size, number of Batches and daily target to
be achieved by the each batch. Other details such as no of stitches/inch at different
areas, measurement for different sizes, placement of trims etc are finalized and
standardized at the sampling stage.
Report maintained by Sewing Department
Daily production report
Hourly production report
Monthly labour report
Batch order completion
Batch planning file
Cutting loading book
Time and motion study
Purchase order sheet
Manpower report
Quality Check
Quality check at Sewing Department conducted at two stages of production.
1. Inline quality check
2. End-line quality check
Inline inspection is done after every critical operation. This are----
Collar end
Sleeve and cuff end
Front end
Collar attaching
Side seam (feed of arm)
End of the line inspection is done after the last operation.
23
The following reports are made after the quality checking.
In line Inspection Report
End line Inspection Report
QC Report
AQL Report
INSPECTION:
The buyer recommends the suppliers to have an Independent Quality Assurance team
responsible for quality control (internal audits). The team should be separated from
the production team and under the direction of ownership, or fully independent.
It is important that an internal quality control (audit) is done before offering the
order for buyer inspection.
Suppliers who use subcontractors for production must have their own QC's working
at the subcontractors. It is the supplier's responsibility to make sure that the
subcontractor follows all buyer quality standards and requirements.
INTIAL INSPECTION:
It is important that the QC team carries out initial inspections after a trial cutting of
100 -500 pieces covering all sizes and colours. This is to ensure conformance to
requirements. This inspection is very important in order to get a smooth running
production. At this stage it is still possible to find and solve problems without
causing any major disturbance in the production.
Information about an order's planned production start and finish is to be given to the
buyer office.
INLINE INSPECTION:
The purpose of this inspection is to confirm that during the early stages of
production, the agreed manufacturing specifications are being followed. The
approved counter sample, and its duplicates, must be present at all stages of
production. Information regarding style, measurements, accessories etc must be
available for everyone. All problems identified during inline inspections, must be
corrected immediately by the supplier and must not be present at the time of the next
buyer’s QC inspection.
24
The goods must be inspected and records must be kept after each major stage
during production e.g.
Cutting: parts and panels size conformance, fabric or knit defects.
Pre-assembly: general workmanship, appearance and measurements e.g.
Stitching, linking, collars, sleeves, position of pockets.
Assembly: general workmanship, appearance and measurements e.g.
stitching, linking, pockets, zippers, position and fastening of buttons and
rivets, buttonholes.
Finishing/pressing: overall workmanship, pressing appearance and
measurements.
MAINTENANCE IN SEWING FLOOR
Maintenance manager generates the reports from the complaint register for the
following things:
Recurrence of the problem
Efficiency of mechanics
Total break down time
Line wise break down
Machine wise break down
For the above system each factory is provided with mechanics, 1 Needle boy and 2
Helpers.
Reports to be made by this department:
A daily maintenance report which should include
Collective break down report
Needle consumption for the day
Spares consumed for the day
Machinery serviced on floor for the day
Corrective actions taken
Machinery movement report (monthly)
Idle machine report (weekly)
Folders and attachments report
OBSERVATION
25
Observation SuggestionOperator idle time is high. This is due to lack of feed from the previous operation.
This can be reduced by further improving the operator allocation.
Material flow can be improved further. This will reduce the chances of bottlenecks.
This can also be improved by the proper operator allocation i.e. following the skill matrix of operator’s job and the no. of operators are needed to be assigned.
External disturbances such as gossips, calling operator for any other work, operator movement form one table to another etc are need to reduce.
External disturbances can only be reduced by setting rules and regulations. Individual table should have their own set of instruments.
It has been observed that operator face doubts regarding the style variation. So to clear these doubt they have to move to the line supervisor. Thus the SAM increases.
The operators need to be clear about the style and if possible the charts displaying the sewing procedure can be made available in the sewing line.This will reduce the SAM and may help in increasing the quality garment.
FINISHING DEPARMENT PROCESS FLOW
FINISHING PROCESS
26
1. the garments are loaded into the button holing section and the approved sample
is checked for the following:
Button hole, button placement, eyelet placement etc.
Thread runs
No of buttons
Two / Four hole buttons
2. Production targets are given to individual operators and pieces are checked
randomly every hour. In case of defective pieces, they are returned to the batch
for alteration and are kept a track of.
3. After button hole and button attach, the feeding helper loads the pieces into the
trimming section.
4. The no. of pieces loaded is entered into the loading register.
5. All trimmers are given individual targets. In case of any defects, the pieces are
returned to the batch for alteration, darners. The pieces then go for flat ironing
after which the button closing is done and the extra button is attached.
6. After this, the pieces go for final check and presentation check. In the final
check, the pieces are checked on the outside starting from one point and ending
at the same. In the presentation check, the pieces are checked for the overall
look of the garment-the fall, alignment of the plackets etc.
7. After this the pieces undergo measurement check where the garments are
checked for compliance with the measurements in the buyer’s spec sheet.
8. After the measurement check the pieces go for a final pressing, tagging,
polybag packing and carton packing (size-wise or color-wise as per the buyer’s
requirement).
Once the cartons are open ed the following has to be checked
Count the no of pcs as per the ratio.
Poly bags
Hangers
Folding
27
Ironing
Size, Main & wash care labels.
Price tags
Extra buttons
Measurements
Quality
EQUIPMENTS
No. of tables - 30
Types of machine in finishing room:
Collar pressing machine, no. of machine Waistband pressing machine, no. of machine Folding machine, no. of machine Pressing machine, no. of machine
INSPECTION AND MEASUREMENT (TIGHTEN INSPECTION)
1.5 A.Q.L% 2.5 A.Q.L%
CONSIGNMENT LOT SIZE
SAMPLE SIZE
ACCEPTED REJECTED ACCEPTED REJECTED
1-50 8 0 1 0 151-90 13 0 1 0 191-150 20 0 1 1 2151-280 32 1 2 2 3281-500 50 2 3 3 4501-1200 80 3 4 5 61201-3200 125 5 6 7 8
Observation Suggestion
The finishing unit has much more capacity than actual. This can be said on the basis that the full area is still not utilized and the industry is using the
Utilization of full area will provide for better movement area and disposing of the unused equipments and waste would give better working conditions.
28
older process for finishing.
\
APPAREL INTERNSHIPHHEC
GUINDY INDUSTRIAL ESTATE
29
PROJECT ON
“ANALYSIS OF DELAY FACTORS IN SEWING FLOOR AND SOLUTION”
Analysis of delay factors in sewing floor and solution.
Synopsis
Scope: It will provide a solution to minimize the delays, identify and rectify the
problems which comes in sewing department.
OBJECTIVES
30
The main objective is to study the operator activities in garment industry and the
percentage of distribution of operations and to analyse the personal and delay
allowance by observing the operations by:
Developing a system to minimize/control the delay that were found
Find out the accurate% of time loss Identify concern factors and contribution of each of them and analysis them
statically. How to increase the efficiency to achieve daily target
Factors
Sewing Operator Productivity & Earnings.
Sewing Operator Morale.
Manufacturing Through-put Time.
Products Produced may Require Greater Inspection.
Capacity planning is an operations strategy which has been considered as a means of
estimating their capacity and do things better, thus improving their efficiency. By
optimally utilising the existing capacity there is a chance to improve their efficiency
and actually grow without necessarily investing a huge sum of money.
The export oriented apparel manufacturers make goods on a make to order basis rather
than on a make to sell strategy as a result there can not be over stocking of goods
which has to be liquidated at a lower price later. However there can be frequent issues
of idle capacity or shortage of capacity exist .In the whole process the manufacturer
must ensure the timely shipment of goods to the buyer or customer.
Aspects of capacity
1. Capacity depends on the interaction of various resource constraints, such as
equipment, labour availability, storage space etc.
2. Capacity is mix dependent, so capacity should be expressed in terms of aggregate
measures.
31
3. Capacity is technologically based; an estimate of capacity implies some assumption
about the technology used.
4. Capacity is dynamic, in that as a manufacturing facility gains experience in
producing something, and discovers and removes successive bottlenecks; its total
capacity tends to expand with time, even without major new investments.
5. Capacity may not be sustainable because normally when stated as so many units
could have many meanings.
For example it could mean the average output per month or the maximum achievable
output for the period, or the best performance actually achieved in the past.
1. Capacity is storable, for instance maintaining excess equipment (to allow
regular. Maintenance) or excess labour (to fill in for missing employees) is a
form of stored capacity.
Standard Allowed Minute is used to measure task or work content of a garment. This term is widely used by industrial engineers and production people in the garment manufacturing industry. For the estimation of cost of making a garment SAM value plays a very important role. In past scientists and apparel technicians did research on how much time to be allowed to do a job when one follows standard method during doing the job. According to the research study minute value has been defined for each movement needed to accomplish a job. Synthetic data is available for each movements.
General Sewing Data (GSD) has defined set of codes for motion data for SAM calculation. There is also other methods through which one can calculate SAM of a garment with out using synthetic data or GSD. Both method has been explained in the following.
Method Used'predetermined time standard' (PTS) code are used to establish 'Standard Time' of a garment or other sewing products.
Step 1: Select one operation for which you want to calculate SAM.
Step 2: Study the motions of that operation. Stand by side of an operator (experienced one) and see the operator how he is doing it. Note all movement used by the operator in doing one complete cycle of work. See carefully again and recheck your note if all
32
movement/motion are captured and correct. (for example motions are like - pick up parts one hand or two hand, align part on table or machine foot, realign plies, etc.)
Step 3: List down all motion sequentially. Refer the synthetic data for TMU (Time measuring unit) values. For synthetic data you can refer GSD (without licence use of GSD code prohibited but for personal use and study one can refer GSD code and TMU values) or Sewing Performance Data table (SPD). Now you got TMU value for one operation (for example say it is 400 TMU). Convert total TMU into minutes (1 TMU=0.0006 minute). This is called as Basic Time in minutes. In this example it is 0.24 minutes.
Step 4: Standard allowed minutes (SAM) = (Basic minute + Bundle allowances + machine and personal allowances). Add bundle allowances (10%) and machine and personal allowances (20%) to basic time. Now you got Standard Minute value (SMV) or SAM. SAM= (0.24+0.024+0.048) = 0.31 minutes.I like to refer you an article Secret Behind Calculation of Machine Time in SAM for better understand of SAM calculation.
Method 2 - Through Time Study:Step 1: Select one operation for which you want to calculate SAM.
Step 2: Take one stop watch. Stand by side of the operator. Capture cycle time for that operation. (cycle time – total time taken to do all works needed to complete one operation, i.e. time from pick up part of first piece to next pick up of the next piece). Do time study for consecutive five cycles. Discard if found abnormal time in any cycle. Calculate average of the 5 cycles. Time you got from time study is called cycle time. To convert this cycle time into basic time you have to multiply cycle time with operator performance rating. [Basic Time = Cycle Time X performance Rating]
Step 3: Performance rating. Now you have to rate the operator at what performance level he was doing the job seeing his movement and work speed. Suppose that operator performance rating is 80%. Suppose cycle time is 0.60 minutes. Basic time = (0.60 X 80%) = 0.48 minutes
Step 4: Standard allowed minutes (SAM) = (Basic minute + Bundle allowances + machine and personal allowances). Add bundle allowances (10%) and machine and personal allowances (20%) to basic time. Now you got Standard Minute value (SMV) or SAM. SAM= (0.48+0.048+0.096) = 0.624 minutes.
Method 3 - Through Videography:Step 1: Select one operation for which you want to calculate SAM.
33
Step 2: Take one camera. Stand by side of the operator. Capture video for that operation. (cycle time – total time taken to do all works needed to complete one operation, i.e. time from pick up part of first piece to next pick up of the next piece). Take video for connsecutive five cycles. Discard if found abnormal time in any cycle. Calculate average of the 5 cycles. Time you got from time study is called cycle time. To convert this cycle time into basic time you have to multiply cycle time with operator performance rating. [Basic Time = Cycle Time X performance Rating]
Step 3: Performance rating. Now you have to rate the operator at what performance level he was doing the job seeing his movement and work speed. Suppose that operator performance rating is 80%. Suppose cycle time is 0.60 minutes. Basic time = (0.60 X 80%) = 0.48 minutes
Step 4: Standard allowed minutes (SAM) = (Basic minute + Bundle allowances + machine and personal allowances). Add bundle allowances (10%) and machine and personal allowances (20%) to basic time. Now you got Standard Minute value (SMV) or SAM. SAM= (0.48+0.048+0.096) = 0.624 minutes.
Advantages of videography
1. Videography helps us to retain the data captured.2. Video can be used for further study.3. Comparative study can be done more efficiently.4. Rating can be done separately after time study.
COST ESTIMATION OF A GARMENTIn the clothing manufacturing, supplier gives final manufacturing cost to buyer prior to order confirmation. For that factory prepares cost sheet estimating costs in different cost heads. Cost heads like Fabric, Trims and Packing materials, Labor cost and Overheads.
At costing stage, supplier only get one sample of the garment and specification of fabric and trims for the reference. For raw material cost suppliers directly take price quote from fabric and trim suppliers. For labor cost it is very important to estimate as near as it will be during actual production.
The scientific method for estimating CM (Cut and make) cost of a garment involves following steps
Determine SAM of the garmentCalculate average line efficiency andDirect labor cost per minute
How to calculate the minute cost of the operator
Formula:
34
Labor cost per minute = (Monthly salary of an operators/Total minutes available in the month)
Suppose,Operator monthly salary is INR 5000.00Total available capacity per month (in minute) = 26 working days*8 hours/day*60=12,480 minutes
So, per minute cost of the direct labor = 5000/12480 = 0.4006 INR
Formula for the projected labor cost per piecesCM cost = (SAM of the garment * Minute cost of the labor)/Line efficiency(%)
If Sewing SAM is 15 minutes and line perform at 50% efficiency then estimated garment make cost = 15*0.40/50% =12 INRAnd Cutting SAM is 2 minutes and cutting room perform at 50% efficiency then estimated cutting cost = 2*0.40/50%=1.6 INR
So, Total estimated CM cost of the garment = (12.00+1.60) = 13.60 INRFollowing above formula easily one can estimate garment CM cost and use it for the product costing.
Line output varies depending on the line efficiency. When a line performs at lower efficiency than standard (100%) line will produce less units in a day compared to what line could make at 100% efficiency. But factory spends same amount of money as salary whether line perform at 100% efficiency or less. So, per unit cost will increase when line performs at lower efficiency
Purpose and Objectives of the project
The purpose of this project is to examine the delay factors and find solution
for the given lines.
The specific objectives arising from the overall purpose are to:
To investigate the factors affecting the throughput time and causes responsible
for delays in production.
35
To investigate and document factors influencing the capacity utilisation
decisions.
Road Map
Study the existing layout and Infrastructure of the two lines.
Study the absenteeism pattern.
Figure out the operator behaviour and existent working trends.
Analyse the result.
Working methodology:
Calculation of existing floor space and its utilization.
Study the allocation of existing human and material resources and its
utilization.
Possible capacity if working at stated efficiency.
Data collection from productivity
Statistical analysis of collected data
Comparison of data and process
Finding the error in the available process and system
Developing step by step method to eliminate these errors.
Delay factors:
Absenteeism
Operator idleness(waiting on work)
Many machines in a line are not in use
Restricted movement area
Attachment not ready
Machine breakdown
Bottleneck
36
No feeding for cutting department
Idleness in presence of work
Poor flow of operation
Uneven distribution of work
Absenteeism
Absenteeism is the most occurring and major cause responsible for the delay in
production and the major cause for absenteeism is the location of the company and the
employment pattern.
The company is located in Guindy and is surrounded by IT companies hence, the
operators tend to move out for comparatively easy jobs and only the operators who
want to earn more stay at the factory and hence they are less punctual as compared to
other factories.
Operator idleness
Operator idleness is persistent due to waiting on work as work is not fed to the
operators working at faster rate whereas some operators are very slow and need
training to cope with the skilled workers.
Unused machines are left idle in the line
Unused machines should be removed or corrected as it consumes time for
transportation and restrictes the movement area.
Restricted movement area
Restricted movement area helps in adding on to the throughput time as more time is
taken in transportation and workers cannot move freely.
Attachment not ready
Machine breakdown
Bottleneck
No feeding for cutting department
37
Idleness in presence of work
Poor flow of operation
Uneven distribution of work
Factor due to shortcoming of management:
Control of operation
Line balancing
Quality control
Batch layout
Maintenance
Delay due to control of operations:
Delay due to absenteeism
Idleness
Poor performance
Rework/alteration
Types of production losses:
Unavoidable losses
Avoidable losses
Unavoidable losses
Machine setup time
Some material handling
Personal fatigue time
Inspection and instruction to operator
Delay allowance like –bobbin change, needle change
Avoidable losses
Response time for system balancing
Reduction in size of bottleneck operation
38
Frequently m/c breakdown
Excessive material handling
Late start, early stops, low speed
Break down maintenance
Work content and delays
Basic work content: Basic work content is irreducible time theoretically required to
produce one unit of output.
Work content means the amount of work “contained in” a given product or process
measured in man hours or machine hours.
Total work content: The total of basic content and excess time due to basic content and
excess time due to defects in design or specification of the products or the time due to
inefficient method of manufacture or operation.
Time due to inefficient method of manufacture or operation.
DELAYS: Delays is the time for which the worker or machine or both are idle due to
shortcoming of management or the workers.
STRENGTHING THE PRODUCTIVITY ACTIVITY CAN HELP IN
REDUCING THE LEAD TIME SIGNIFICANTLY:
Ensuring availability of raw material details and construction details by means
of sample requisition checklist.
Problem at the sampling stage should be recorded.
Industrial engineering department should work out exact requirement of exact
requirement of work aids for critical operation before a new style is loaded on
production floor.
WORK STATION AND DESIGN
The workstation design affects the production rate efficiency and the accuracy with
which an operation can be performed.
39
The work station not only needs space for the workers and the machine there are
plenty of other items which are also needs accommodation.
For the movements of material handling
Easy access to safety stops in case of emergency
Easy access to machine for inspection
Lubrication
Maintenance
Repair
Easy for machine installation
It will easy for the gap between the machines for smooth operation.
Movement of the operator to the centre table would be easy.
TOTAL WORK CONTENT AND DELAY
BASIC WORK CONTENT
Total work cont of product
Design complication of product Lack of standardization Excessive product variety
Work content added
Ineffective planning Lack of raw materials Ineffective batch setting Wrong method inefficient methods Poor production control Poor maintenance
40
DELAY CAUSE, RESPONSIBILITIES AND SUGGETIONS
S.NO OBESERVATION CAUSES RESPONSIBILITIES SUGGESTIONS1. Very high
associated timeUnskilled operators and Less no of helpers
Lesser availability of labour as the industry is located in an urban area.
Attachements and pre sewing operations should be completed before being fed for sewing.
2. Operator idleness Operators indiscipline Ineffective time management,Due to m/c breakdown, bad flow of material.
Supervisor, operator and production team.
No skill matrix and operation bulletin is referred by supervisor.
3. Bottleneck Ineffective line balancing, due to operator performance.
Supervisor and operator
Skilled operators should be placed, operation bulletin and skill matrix should be followed.
4. Uneven distribution of work
Some operators are over burdened while some sit idle
Production planning work distribution should be done evenly on the basis of skill matrix.
5. Machine breakdown
Unplanned maintenance, wrong handling of machine by operators.
Maintenance department, operator
Instructions should be given for Autonomous maintenance.
6. Line balancing 1 Many machines are not working. _
Unused machines should be removed so the movement area will increase and production flow would be better.
41
7. Absenteeism Operator dissatisfaction, work pressure, no motivation, work environments
Factory working condition, supervisor and HR involvement
Motivation should be given to them.
8. Line balancing 2 Unorganized production flow
Production planning Bundle handling time could be reduced.
Average garment production per day Quality is directly prepositional to the production so quality would be
maintained for the better production.
42
OBESERVATION OF A-LINE DURING SHIRT PRODUCTION
IDLE TIME
The average idle time between back centre stitch and pocket batch placket is =
Average thread breakage time= The idle average time between pocket making stitch and pocket double
needle is = Wastage of time during loss of electricity= Material flow delay time due to pass of material= Idleness during presence of work= Absenteeism= Machine breakdown time= Operator idealness =
43
CONCLUSION
For every production delay factors are the major reason for the low production of a garments. Effective planning is important to minimise the delay factors. It should me minimise by the better management, like due to low efficiency and
high absenteeism line balancing get affected and due to improper line
balancing lots of waiting time involved in the line, one operator
low efficiency will be the reason of whole line down production.
44
PROJECT ON:
Analysis on the Company’s Style Changeover Process with respect to SMED Method.
45
Single Minute Exchange of Die (SMED)
Single Minute Exchange of Die (SMED) is one of the lean tools for reducing waste in a manufacturing process. It provides a rapid and efficient way of converting a manufacturing process from running the current product to running the next product. This rapid changeover is essential to reduce production lot sizes and thereby improve flow which is a 'Lean' aim. It is also often referred to as Quick Changeover (QCO). The phrase "single minute" does not mean that all changeovers and start-ups should take only one minute, but that they should take less than 10 minutes (in other words, "single digit minute").
Steps of SMEDTheoretically SMED is defined in four steps:
1. Suppress useless operations2. Work together3. Simplify fittings and fasteners4. Suppress adjustments and trials
Note: These steps are non-sequential.Steps 1 and 2 focus on organizational improvement; steps 3 and 4 focus on
design improvement. SMED methodology can be easily defined in six steps. Practically high quality of analytical ability and devotion is required to follow the steps. It consists of :
Observing the current changeover process
Identifying internal and external activities
Converting activities from internal to external set up
Increasing efficiency of the remaining internal activities
Optimizing the start up time
Increasing efficiency of external activities
There are series of activities which should be performed before changeover to reduce the set up time. All these activities are important and should be performed timely by the responsible person. These activities can be divided in three phases:
Planning Phase: The activities in this phase are essential prerequisite to the activities of preparatory phase.
46
Preparation Phase: The activities in this phase involve completion of external activities.
Operating Phase: The activities in this phase involve execution of changeover.
Planning Phase Line Plan:
Planning of line plan should be done in a manner that loading of upcoming style will occur four days after receiving updated line plan. Loading of styles similar to previous running styles in the respective lines helps in achieving quicker changeover and better productivity.
Operation Bulletin:
Operation Bulletin of upcoming style should be revised on the basis of line plan by IE 3 days prior to style loading. Operation Bulletin developed at sampling room should be crosschecked with the reference sample by IE executive and updated for required changes. After finalizing operation bulletin, Machine layout should be developed by IE Executive.
Mock Sample:
Supervisor should be informed about upcoming style, on the basis of line plan, 3 days prior to style loading, to prepare the mock sample. It is the replica of upcoming style in terms of design details. The purpose of mock sample preparation is to make supervisor acquainted with all the operations. It is beneficial as it helps in early identification of:
Critical operations
Necessary templates.
Method details
Preparation of mock sample should be completed on the same day.
Machine Plan:
Machine Plan preparation is a fundamental planning tool for SMED. It involves internal and external element segregation for new style by comparing operation bulletin of old and new style. It should be prepared 3 days prior to loading.
It is a record of: Operation Type
Machine Type (Segregated as internal/external)
Machine Number
SPI
47
Required Settings
Critical/External Independent Operation
Additional Operator/Helper
Status Check:
Status of Cutting, Outsourcing and Trims should be checked by the supervisor 3 days prior to loading of new style and related issues should be discussed in Internal PPM. It is necessary to check the status of all the inputs in advance, to prevent off standard time arising due to waiting for raw material inline.
Internal Pre Production Meeting:
Internal PPM should be held 2 days prior to style loading, after completion of preliminary activities (OB, Mock sample & Status check). The purpose of Internal PPM is to discuss new style in advance to anticipate problems and their respective measures. The duration of PPM should be less than 10 minutes. Internal Pre Production Meeting is not mandatory for repeat styles. Internal PPM is held in the presence of:
Production Manager
Quality Head
Floor In-charge
Maintenance Head
Supervisor
Preparatory Head
Internal PPM involves discussion on following topics: Mock Sample: Sample prepared by supervisor should be checked by
Quality Head and CTP (Critical to Production) operations should be discussed.
Cutting and Trim status: Cutting and outsourcing status issues should be discussed and Production Manager should be held responsible to get them sorted. Trim status issues should be communicated to merchandising department by Production Manager.
48
Quality Specifications: CTQ (Critical to Quality) operations and PP comments are discussed by Quality Head. Any changes in the specifications from the reference sample should also be conveyed.
Machine, Folder and Attachment Status: Requirement for any new folder, attachment or machine for new style, analyzed during machine plan preparation, is also discussed by IE in the meeting. The order should be placed for the same after crosschecking with maintenance department on the same day.
Template Preparation: QC should discuss about templates required.
Operator Allocation Plan: Based on the machine plan Floor In-charge will decide operator allocation. Only discussion for operator allocation at critical operations is held in the meeting.
A PPM report should be documented in the meeting by Industrial Engineer and concerned issues are solved by the responsible persons. Machine plan is handed over to maintenance department in the Internal PPM. All the concerns regarding upcoming style are discussed and solved in Internal PPM.
Preparation Phase….External Machine Setting:
External machines should be set by the mechanic according to the machine plan. The settings should be complete a day prior to loading of new style.
Machine setting includes: Gauge change
Folder/ Presser Foot change,
Needle addition /removal
SPI adjustment
Programming
The stitch quality should be approved by Quality Checker. After completion of machine setting the machine should be tagged indicating the line and style for which the machine is set.
Preparatory Section Status:
Preparatory Section status should be checked by supervisor one day prior to style loading and problems should be discussed with preparatory head and solved to get timely loading.
49
Template Preparation:
Patterns should be issued by supervisor one day prior to style loading. The number of patterns should be checked and requirements of any other pattern should be communicated to CAD/ Sampling room immediately. The templates should be prepared by supervisor and approved by QC.
Day of Changeover:
Inline LoadingTrims Issue: Trims like threads, zippers labels, buttons etc. should be issued at least 2 hours
before old style ends at first operation. Cut part loading: Cut part loading should also be done at the same time. It should be checked by
feeding helper while loading if all the parts are present. Parts coming from preparatory section should be counted before loading so that any missing parts can be communicated to preparatory section at the earliest. Early inline loading is necessary to reduce the off standard time.
Start of Independent Operations:
Presence of Floor In-charge, Supervisor, QC and Mechanic is necessary during complete changeover.
Manual operations:
Manual operations such as ironing and marking should start before the succeeding operation ends to create enough WIP at the first operation.
External Independent Operations:
External Independent operations, as the name suggests, are independent of the style running in the line, so these can be started before completion of old style. It helps in creating enough WIP and reducing off standard time as all the trials can be done outside the line.
Operating Phase..Start of Dependent Operations:
When the operation of old style ends, the machine settings for new style should be done by the mechanic inline. The operation should be demonstrated by supervisor to operator and the operator should start the operation
Procedure for starting operation of new style:
Internal Machine Setting by Mechanic according to specifications.
Operation Demonstration by Supervisor.
50
First piece by the Quality Check.
Machine setting, if required.
Operation performed by operator.
Quality Check for the complete bundle.
For initial operations bundle check for initial 5-10 bundles should be done by QC in-charge, so that no faulty piece is passed to the next operation. The close attention given to quality at critical operations helps to improve the quality of work performed leading to reduced off standard time. If quality is not consistent even after checking of 10 bundles then the operation should be analyzed by supervisor to identify the root cause of problem and solve.
Style Change Analysis
Style change analysis report should be documented for each style by IE person to analyze the problems faced during the changeover. All the problems faced during style analysis should be discussed in the style review meeting which will be held a day after completion of changeover.
\
51
Road Map:
Observing the current changeover process
(The observation is done with resemblance to SMED Method)
Status Sheet
Dated : 6th july,2012 Style no: 5AC21008Buyer: Buyer Phase type: Planning Phase
Table no : (i)
Serial No Activity Name Yes No1. Size set Sample prepared
2. Operation Bulletin
3. Line plan
4. Machine Plan
5. Status Check(Cutting, Outsourcing and Trims)
6. Outsourcing completed
7. Trims ready
Note: The activities shown are needed to be finished 3 days before the style change
52
Status Sheet
Dated : 7th july,2012 Style no: 5AC21008Buyer: Orvis Phase type: Planning Phase (Activities Pending)
Table no : (ii)
Serial No Activity Name Yes No1. Operational bulletin
2. Line plan
3. Machine plan
Planning Phase(activities to be finished)
Serial No Activity Name Yes No4. Pre-production meeting
5. Revision operation Bulletin
6. Revision Line plan
7. Revision Machine Plan
8. Size set approved
9. Fabric issued for cutting
10. Cutting started
Note: The activities shown are needed to be finished 2 days before the style change
53
Status Sheet
Dated : 8th july,2012 Style no: 5AC21008Buyer: Orvis Phase type: Preparation Phase
Activities Pending
Table no : (iii)
Serial No Activity Name Yes No1. operation Bulletin
2. Line plan
3. Machine Plan
4. Pre-production meeting
5. Revision operation Bulletin
6. Revision Line plan
7. Revision Machine Plan
8. Size set approved
9. Cutting started
( Activities To Be Finished On 8th July)
Serial No Activity Name Yes No14. Cutting buffer ready
15. External machine setting
16. Preparatory Section Status as required
17. Template preparation
Note: The activities shown are needed to be finished 2 days before the style change
54
Status Sheet (Scheduled day for the style changeover)
Dated : 9th july,2010 Style no: 5AC21008Buyer: Orvis Activities Pending
Table no : (iv)
Serial No Activity Name Yes No1. Preproduction meeting
2. operation Bulletin
3. Line plan
4. Machine Plan
5. Size set ready
6. Fabric issued for cutting
7. Revision operation Bulletin
8. Revision Line plan
9. Revision Machine Plan
10. Size set approved
11. Fabric issued for cutting
12. Cutting started
13. Cutting buffer ready
14. External machine setting
15. Template prep.
Note: The activities shown are needed to be finished before the day of style change
55
Since the scheduled styled is not inserted in the line the table for the activities needed to happen is not shownThe activities are shown that are needed to be finished before the style change.Here, it can be clearly noticed that 64.3% activities are still unfinished. But since the required cannot be finished on schedule ,it was decided to insert the another style which was supposed to finish in one day as only 281 pieces were needed to be completed. But 281 pieces cannot be finished with the line of capacity 500 pcs(actual 320 pcs) perday!!So the work extended for one more day extra
Status Sheet (Actual day for the style changeover)Dated : 12th july,2010 Style no: 5AC21008Buyer: Orvis Phase Type : Operational Phase
Table no : (v)
Serial No Activity Name Yes No Remarks1. Line plan Line Planning is
based on experiences 2. Machine Plan Also machine
Planning is based on experiences
3. Size set ready
4. Fabric issued for cutting
5. Pre-production meeting
6. Revision operation Bulletin
7. Revision Line plan
8. Revision Machine Plan
9. Cutting buffer ready
10. External machine setting
11. Template preperation
Note: The activities shown are needed to be finished before a day of scheduled style change
Serial No Activity Name Yes no Remarks12. Trims issued(2hr
prior)13. Cut part loading
56
The efficiency of the company improved by eliminating wastage of time.
Observation Poor flow of operation and bundle handling.
Reason Unorganized set-up of machines.
Solution If the unused machines are removed or setup at another place, it would help in-
Results Setting up a line ( production system).
Better bundle handling and less wastage, unwanted stains could be prevented.
Would give better visibility to management employes and bring in discipline.
Would reduce wastage of time by atleast an hour or two as it is prevelant in the company.
Ease of flow of bundles as no one needs to carry the sewn parts – just pass on to the next.
Waiting for work and hence, idleness could be abolished to an extent.
57
Observation Very high througput time. ( 15 ladies tops in 8 hours by 6 operators ).
Reasons Slow work by in experienced operators, attachments not ready, enough workers
not available.
Solution If the work shall be divided on the basis of operator skill matrix, then the
production can be increased. For example – if we divide the work content as, unskilled operators make
attachments and fusing ready and then pass it on the experienced operators, who would be given the stitching operations will result in more production.
The operators should be encouraged or tempted to work more to earn more, it will help the company to save its electricity bill by achieving higher targets in less time.
Observation Too much time wastage in thread breakage and needle breakage.
Reason Due to lack of routine maintenance and check up, while some machines are old
and hence more problem occur in old machines.
SolutionAutonomous maintenance
Operators can be given instructions about lubricating and tightening of any loose screws on their own after the end of the day or routine maintainance can be adopted.
Results The machine will run for longer time than now.
The machines will run more efficiently and smoothly, hence, resulting in less thread breakage and needle breakage.
58
/’
59