Upload
stefan-noel
View
234
Download
2
Embed Size (px)
DESCRIPTION
Project Report for Civil Eng.
Citation preview
DESIGN OF SLABS
Typically we divided the slabs into two types:
i. Roof Slab and ii.Floor Slab
In case of roof slab the live load obtained is less compared to the floor slab. Therefore we first design the roof slab and then floor slabs.
We have two types of supports. They are:
1. Ultimate support and
2. Penultimate support
Ultimate support is the end support and the penultimate supports are the in-termediate supports.
Wu x L2 Ultimate support tends to have a bending moment of 10
have W
u x L
2
12
Design of roof slab:
and the penultimate supports
It is a continuous slab on the top of the building which is also known as ter-race. Generally terrace has less live load and it is empty in most of the time except some occasions in case of any residential building. In case of office buildings it will be empty and live load act is very less.
According to the end conditions and the dimensions, the slabs are divided into 4 types. They are Roof S1, Roof S2, Roof S3 and Roof S4.
Slab
Dimensions (M x M)
Roof S1
8.62 X 3.05
Roof S2
8.62 X 3.05
Roof S3
5.78 X 3.05
Roof S4
5.78 X 3.05
10
We can observe the slab panels in the above figure and all the slabs are de-signed as one way slab for the easy arrangement of the reinforcement and ease of work.
Roof S1 and Roof S2 are the slabs with same dimensions but with different end conditions.
Roof S3 and Roof S4 are also the slabs with the same conditions as men-tioned above.
But the point to be noted is that all the Slabs have same shorter span and in the design of one way slab shorter span is of more importance. Therefore we design any two slabs with different end conditions and the remaining two slabs also follow the same design.
Design of Roof Slab S1:Calculation of Depth (D) by using modification factor:
Assume the percentage of the tension reinforcement (Pt) provided is 0.4% From IS456-2000, P38 Fig4, we get the modification factor (α) = 1.4
Required Depth (D) = rL
+ d1 a
11
Where, L
= Span
ra allowable
Ld
ratio
d1 = Centre of the reinforcement to the end fibre (= 20mm for slab) From IS456-2000, P39, Clause 24 & Clause 23.2 for continuous span we have
Span =
L = 26
Effective depth d
ra =26x1.4=36.4
3.05 x 103
Therefore, D = 36.4
+ 20 = 103.79mm say 110 mm
Effectivedepth(d)=D–d1 =110–20=90mm
Loads:Dead loads (From IS875 – Part 1):
= 2.5 KN/m2
=1x1xDx25= 110
x25 1000
= 2.75 KN/m2
= 1.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 6.75=10.125 KN/m2
Design moment: (for end panel)
Wu x L2 10.125 x (3.05)2
Mu = 10
= 10
=9.42KN-m
Terrace water proofing Selfweightoftheslab
Live loads (From IS875 – Part 2):
RoofTotal load (W) = 2.5 +2.75 + 1.5 = 6.75 KN/m2
12
Calculation of area of steel:
From IS456-2000, P96, Clause G-1.1 (b) we have
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
Or
Ast = 0.5 x fck
(1-(1-4.6 Mu
fy fck x b x d
)1/2) b x d
9.42x106 =0.87x415xAst x90x(1- 415xAst
) 20 x1000 x90
Ast = 312.4 mm2
Spacingof8mmφbars= ast x1000
=π
x82 x 1000
=160.9mm Ast 4 312.4
Therefore, Provide 8mm φ @ 150mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x110x1000=132mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=380mm 4 132
Therefore, Provide 8mm φ @ 300mm c/c.
13
Design of Roof slab S2:
Depth D = 110mm Total load (W) = 6.75 KN/m2
Limit state load (Wu) = 1.5 x 6.75 = 10.125 KN/m2
Design moment: (for intermediate panel)
Wu x L2 10.125 x (3.05)2
Mu = 12
= 12
=7.85KN-m
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
7.85x106 =0.87x415xAst x90x(1- 415xAst
) 20 x1000 x90
Ast = 256.78 mm2
Spacing of 8mm φ bars = π
x 82 x 1000
4 256.78
= 195.75mm
Therefore, Provide 8mm φ @ 190mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x110x1000=132mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=380mm 4 132
Therefore, Provide 8mm φ @ 300mm c/c.
14
Design of Roof Slab S3 is same as Roof Slab S1. Design of Roof Slab S4 is same as Roof Slab S2. Area of steel at support next to end support:
From IS 456-2000, moment = Wu x L
2
10
Total Load acting on the support (Wu) = 10.125 KN/m
10.125 x (3.05)2
Therefore, Moment = 10
= 9.42 KN-m
Calculation of Ast:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
9.42x106 =0.87x415xAst x90x(1- 415xAst
) 20 x1000 x90
Ast = 312.4 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S1 = 12
x 312.4 = 160.7 mm2
From Slab S2 = 12
x 256.78 = 128.39 mm2
Total Ast (available) = 160.7 + 128.39 = 284.59 mm2
Therefore, extra bars required for Ast = 312.4 – 284.59 = 27.81 mm2
15
Area of steel at any other interior support:
From IS 456-2000, moment = Wu x L
2
12
Total Load acting on the support (Wu) = 10.125 KN/m
10.125 x (3.05)2
Therefore, Moment = 12
= 7.85 KN-m
Calculation of Ast:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
7.85x106 =0.87x415xAst x90x(1- 415xAst
) 20 x1000 x90
Ast = 256.78 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S2 = 12
x 256.78 = 128.39 mm2
From Slab S2 = 12
x 256.78 = 128.39 mm2
Total Ast (available) = 128.39 + 128.39 = 284.59 mm2 Therefore Ast (avail-able) = Ast (required)
No need of providing extra bars.
16
Design of Floor Slab:
It is the slab in which live load is more when compared to the roof slab. In this project the slab is divided into 9 types according to the end condition and function of slab.
S1 S2 S3 S4
- Toilet and WC’s
- Office
- Office sup dept.
- Assembly hall
S5(a),S5(b) - Officechamberandwaitingchamber S6(a),S6(b) - Office
S7
S8S9(a),S9(b) - Officerschamber
- Library
- Secretary Room
17
Floor Slab
Dimensions
S1 to S5 (b)
8.62 x 3.05
S6 (a) to S9 (b)
5.78 x 3.05
DESIGN OF FLOOR SLAB (S1):Calculation of Depth (D) by using modification factor:
Assume the percentage of the tension reinforcement (Pt) provided is 0.4% From IS456-2000, P38 Fig4, we get the modification factor (α) = 1.4
Required Depth (D) = rL
+ d1 a
Where, L
= Span
ra allowable
Ld
ratio
d1 = Centre of the reinforcement to the end fibre (= 20mm for slab) From IS456-2000, P39, Clause 24 & Clause 23.2 for continuous span we have
Span =
L = 26
Effective depth d
ra =26x1.4=36.4
3.05 x 103
Therefore, D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2 Sanitary Blocks including filling = 2.5 KN/m2
18
Selfweightoftheslab =1x1xDx25= 120
x25 1000
= 3 KN/m2
Sanitary blocks public = 3 KN/m2 Corridor = 5 KN/m2
Maximum = 5 KN/m2 For Partition Wall = 1.5 KN/m2
Total load (W) = 1 + 2.5 +3 + 5 + 1.5 = 13 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 13
Live loads (From IS875 – Part 2):
Design moment: (for end panel)
Wu x L2 19.5 x (3.05)2
Mu = 10
= 10
=18.14KN-m
Calculation of area of steel:
From IS456-2000, P96, Clause G-1.1 (b) we have
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
=19.5 KN/m2
Or
Ast = 0.5 x fck
(1-(1-4.6 Mu
fy fck x b x d
)1/2) b x d
18.14x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 569.79 mm2
Spacingof10mmφbars= ast x1000
=π
x102 x 1000
=137.83mm
Ast 4
569.79
19
Therefore, Provide 10mm φ @ 130mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
DESIGN OF FLOOR SLAB (S2):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish Selfweightoftheslab
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
= 4 KN/m2 = 5KN/m2
Live loads (From IS875 – Part 2):
Office Corridor
20
Therefore, Maximum load = 5 KN/m2
For Partition wall = 1.5 KN/m2
Total load (W) = 5 +3 + 1 + 1.5 = 10.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 10.5
Design moment:
Wu x L2 15.75 x (3.05)2
Mu = 12
= 12
=12.21KN-m
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
=15.75 KN/m2
12.21x106 =0.87x415xAst x100x(1- Ast = 365.97 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
4 365.97
415xAst )
20 x 1000 x 100
= 214.61mm
Therefore, Provide 10mm φ @ 210mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
21
Area of steel at support next to end support (between S1 and S2):
From IS 456-2000, moment = Wu x L
2
10
Total Load acting on the support (Wu) = 13
+ 15.75
= 14.375 KN/m 22
14.375 x (3.05)2 Therefore, Moment = 10
Calculation of Ast:Mu = 0.87 x fy x Ast x d x (1 -
= 13.372 KN-m
fy x Ast )
fck x b x d
13.372x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 404.28 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S1 = 12
x 569.79 = 284.895 mm2
From Slab S2 = 12
x 365.97 = 182.985 mm2
Total Ast (available) = 284.895 + 182.985 = 467.88 mm2
Therefore, extra bars required for Ast = 312.4 – 284.59 = 27.81 mm2
DESIGN OF FLOOR SLAB (S3):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
22
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Design moment:
Floor finish Selfweightoftheslab
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
Live loads (From IS875 – Part 2):
Private Corridor Maximum load
For Partition wallTotal load (W) = 5 +3 + 1 + 1.5 = 10.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 10.5
Wu x L2 15.75 x (3.05)2
Mu = 12
= 12
=12.21KN-m
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
12.21x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 365.97 mm2
= 2 KN/m2
= 5 KN/m2
= 5 KN/m2
= 1.5 KN/m2
=15.75 KN/m2
23
Spacing of 10mm φ bars = π
x 102 x 1000
= 214.61mm 4 365.97
Therefore, Provide 10mm φ @ 210mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at any other interior support: (Between S2 and S3)
From IS 456-2000, moment = Wu x L2
12
Total Load acting on the support (Wu) = 15.75
+ 15.75
= 15.75 KN/m 22
15.75 x (3.05)2 Therefore, Moment = 12
Calculation of Ast:Mu = 0.87 x fy x Ast x d x (1 -
= 12.21 KN-m
fy x Ast )
fck x b x d
12.21x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 365.97 mm2
24
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S2 = 12
x 365.97 = 182.985 mm2
From Slab S3 = 12
x 365.97 = 182.985 mm2
Total Ast (available) = 182.985 + 182.985 = 365.97 mm2 Therefore Ast (avail-able) = Ast (required)
No need of providing extra bars.
DESIGN OF FLOOR SLAB (S4):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish Selfweightoftheslab
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
= 5 KN/m2
= 5 KN/m2
= 5 KN/m2
= 1.5 KN/m2
Live loads (From IS875 – Part 2):
Assembly
Corridor Maximum load
For Partition wallTotal load (W) = 5 +3 + 1 + 1.5 = 10.5 KN/m2
25
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 10.5 =15.75 KN/m2
Design moment:
Wu x L2 15.75 x (3.05)2
Mu = 12
= 12
=12.21KN-m
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
12.21x106 =0.87x415xAst x100x(1- Ast = 365.97 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
4 365.97
415xAst )
20 x 1000 x 100
= 214.61mm
Therefore, Provide 10mm φ @ 210mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
26
Area of steel at any other interior support: (Between S3 and S4)
Same as between S2 and S3
DESIGN OF FLOOR SLAB (S5 (a)):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish Selfweightoftheslab
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
= 4 KN/m2
= 2 KN/m2
= 1.5 KN/m2
Live loads (From IS875 – Part 2):
Office chamber
Private For Partition wall
Total load (W) = 2 + 4 +3 + 1 + 1.5 = 11.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 11.5
Design moment:
Wu x L2 17.25 x (3.05)2
Mu = 12
= 12
=13.372KN-m
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
=17.25 KN/m2
27
13.372x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 404.27 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
= 194.27mm 4 347.05
Therefore, Provide 10mm φ @ 190mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at any other interior support: (Between S4 and S5 (a))
From IS 456-2000, moment = Wu x L
2
12
Total Load acting on the support (Wu) = 15.75
+ 17.25
= 16.5 KN/m 22
16.5 x (3.05)2
Therefore, Moment = 12
= 12.79 KN-m
Calculation of Ast:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
28
12.79x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 385 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S4 = 12
x 365.97 = 182.985 mm2
From Slab S5 (a) = 12
x 404.27 = 202.135 mm2
Total Ast (available) = 182.985 + 202.135 = 385.12 mm2 Therefore Ast (avail-able) = Ast (required)
No need of providing extra bars.
DESIGN OF FLOOR SLAB (S5 (b)):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish Selfweightoftheslab
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
= 4 KN/m2
= 2 KN/m2
= 1.5 KN/m2
Live loads (From IS875 – Part 2):
Office chamber
Private For Partition wall
29
Total load (W) = 2 + 4 +3 + 1 + 1.5 = 11.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 11.5
Design moment: (for end panel)
Wu x L2 17.25 x (3.05)2
Mu = 10
= 10
=16.047KN-m
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
16.047x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 495.37 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
= 158.55mm 4 495.37
Therefore, Provide 10mm φ @ 150mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
=17.25 KN/m2
30
Area of steel at support next to end support (between S5 (a) and S5 (b)):
From IS 456-2000, moment = Wu x L
2
10
Total Load acting on the support (Wu) = 17.25
+ 17.25
= 17.25 KN/m 22
17.25 x (3.05)2 Therefore, Moment = 10
Calculation of Ast:Mu = 0.87 x fy x Ast x d x (1 -
= 16.05 KN-m
fy x Ast )
fck x b x d
16.05x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 495.47 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S5 (a) = 12
x 404.27 = 202.135 mm2
From Slab S5 (b) = 12
x 495.47 = 247.735 mm2
Total Ast (available) = 202.135 + 247.735 = 449.87 mm2
Therefore, extra bars required for Ast = 495.47 – 449.87 = 45.6 mm2
DESIGN OF FLOOR SLAB (S6 (a)):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
31
Selfweightoftheslab =1x1xDx25= 120
x25 1000
= 3 KN/m2
Office = 4 KN/m2 Total load (W) = 4 +3 + 1 = 8 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 8=12 KN/m2
Live loads (From IS875 – Part 2):
Design moment: (for end panel)
Wu x L2 12 x (3.05)2
Mu = 10
= 10
=11.163KN-m
Calculation of area of steel:Mu = 0.87 x fy x Ast x d x (1 -
fy x Ast )
fck x b x d
11.163x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 332.06 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
= 236.53mm 4 332.06
Therefore, Provide 10mm φ @ 230mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
32
Therefore, Provide 8mm φ @ 300mm c/c.
DESIGN OF FLOOR SLAB (S6 (b)):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
Floor finish Selfweightoftheslab
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
= 4 KN/m2
Live loads (From IS875 – Part 2):
OfficeTotal load (W) = 4 +3 + 1 = 8 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 8=12 KN/m2
Design moment: (for end panel)
Wu x L2 12 x (3.05)2
Mu = 12
= 12
=9.3025KN-m
33
Calculation of area of steel:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
9.3025x106 =0.87x415xAst x100x(1- Ast = 273.13 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
4 273.13
415xAst )
20 x 1000 x 100
= 287.55mm
Therefore, Provide 10mm φ @ 280mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at support next to end support (between S6 (a) and S6 (b)):
From IS 456-2000, moment = Wu x L
2
10
Total Load acting on the support (Wu) = 12 KN/m
12 x (3.05)2
Therefore, Moment = 10
= 11.163 KN-m
34
Calculation of Ast:
Mu = 0.87 x fy x Ast x d x (1 - fy x Ast
) fck x b x d
11.163x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 332.06 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S6 (a) = 12
x 332.06 = 166.03 mm2
From Slab S6 (b) = 12
x 273.23 = 136.565 mm2
Total Ast (available) = 166.03 + 136.565 = 302.595 mm2
Therefore, extra bars required for Ast = 332.06 – 302.595 = 29.465 mm2
DESIGN OF FLOOR SLAB (S7):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2
Library = 10 KN/m2 Total load (W) = 10 +3 + 1 = 14 KN/m2
Floor finish Selfweightoftheslab
Live loads (From IS875 – Part 2):
35
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 14 =21 KN/m2
Design moment: (for end panel)
Wu x L2 12 x (3.05)2
Mu = 10
= 10
=19.54KN-m
Calculation of area of steel:Mu = 0.87 x fy x Ast x d x (1 -
fy x Ast )
fck x b x d
19.54x106 =0.87x415xAst x100x(1- 415xAst
) 20 x 1000 x 100
Ast = 621.3 mm2
Spacing of 10mm φ bars = π
x 102 x 1000
= 126.41mm 4 621.3
Therefore, Provide 10mm φ @ 120mm c/c. Distribution steel:
Ast = 0.12% of Ag
= 0.12
x120x1000=144mm2. 1000
Spacing of 8mm φ bars = π
x 82 x 1000
=349mm 4 144
Therefore, Provide 8mm φ @ 300mm c/c.
36
DESIGN OF FLOOR SLAB (S8):
3.05 x 103
D = 36.4
+ 20 = 103.79mm say 120 mm
Effectivedepth(d)=D–d1 =120–20=100mm
Loads:Dead loads (From IS875 – Part 1):
= 1 KN/m2
=1x1xDx25= 120
x25 1000
= 3 KN/m2