Defiance City School Defiance City School District District Master Plan Presentation April 14, 2010 Presented by: Ohio School Facilities Commission Regency Construction Services, Inc.

Defiance City School District

  • Upload
    kirkan

  • View
    32

  • Download
    0

Embed Size (px)

DESCRIPTION

Defiance City School District. Master Plan Presentation April 14, 2010 Presented by: Ohio School Facilities Commission Regency Construction Services, Inc. The Past…. Exceptional Needs Program (ENP) Project in 2005 New PK-5 Elementary School 1,067 Students - PowerPoint PPT Presentation

Citation preview

Page 1: Defiance City School District

Defiance City School DistrictDefiance City School District

Master Plan PresentationApril 14, 2010

Presented by:Ohio School Facilities Commission

Regency Construction Services, Inc.

Page 2: Defiance City School District

• Exceptional Needs Program (ENP) Project in 2005– New PK-5 Elementary School

• 1,067 Students• 134,374 SF total building (123,345 SF of co-funded + 11,029 SF of LFI)

– Allowance to abate/demo four (4) existing Elementary Schools• Anthony Wayne Elementary – sold to Catholic School; repurposed • Brickell Elementary – demolished; District still owns land• Slocum Elementary – sold to City; repurposed into Municipal Court• Spencer Elementary – sold to County; repurposed into Senior Center

– Co-funded Project Cost: $22,025,045

The Past…

Page 3: Defiance City School District

• Exceptional Needs Program (ENP) Project in 2005– Projected Enrollment was 2,413 students (2009-2010)

• 1,067 students in PK-5• 570 students in 6-8• 776 students in 9-12

– Equity Rank was 251 – Local Share percentage was 41%

The Past…

Page 4: Defiance City School District

The Past…

District SavingsDistrict Savings

Page 5: Defiance City School District

The Past…

District SavingsDistrict Savings

Page 6: Defiance City School District

The Past…

District SavingsDistrict Savings

Page 7: Defiance City School District

• Equity Rank is 178• Local Share percentage is 30%• OSFC Master Plan = Enrollment + Building Assessment• Enrollment updated with October 2009 counts

– 2,816 students in 2019-2020 (+403)• 1,198 students in PK-5 (+131)• 686 students in 6-8 (+116)• 932 students in 9-12, including Career Tech (+156)

The Present…

Page 8: Defiance City School District

The Present…

School Cost to Renovate Reno/ReplaceGuideline

Right Ratio Comments

Elementary N/A N/A N/A Addition only

Middle $9,525,188 77% N/A To be Demolished or Repurposed

Junior High $10,763,824 80% 103% Building LFI is $1,543,589

High School $21,160,950 78% 87% Building LFI is $149,454

Physical building assessments conducted in November 2008

• Renovate/Replace % Guideline: If the cost of renovating a building exceeds 2/3rds the cost of building new, OSFC recommends to build new.

• Right Ratio: OSFC will co-fund up to 100% of a new building. The District is responsible for costs exceeding the 100%.

Page 9: Defiance City School District

• Master Plan Option A– Add 18,623 SF to Elementary

School– Abate/Demo Defiance Middle

School– Abate/Demo 51,777 SF of

Defiance Junior High and renovate remaining sections (1918 building and Auditorium) and add 44,729 SF

– Renovate and add 27,471 SF to Defiance High School

• Co-funded cost: $54,498,910• Project Agreement LFI: $1,693,042• District Local Share: $18,042,715• Millage: 3.8 mills• Annual Cost/$100,000 Home:

$116.68• Each additional $1 Million in LFI

is .22 Mills and $6.74 for each $100,000 Home

The Present…

Page 10: Defiance City School District

• Master Plan Option B– Add 18,623 SF to Elementary

School– Abate/Demo Defiance Middle

School– Abate/Demo Defiance High

School– Build a 243,243 SF New 6-12

School– Abate/Demo 51,777 SF of

Defiance Junior High and maintain remaining sections (1918 building and Auditorium) for non-academic instruction

• Co-funded cost: $56,949,963• Project Agreement LFI: $0• District Local Share: $17,084,989• Millage: 3.61 mills• Annual Cost/$100,000 Home:

$110.56• Each additional $1 Million in LFI

is .22 Mills and $6.74 for each $100,000 Home

The Present…

Page 11: Defiance City School District

• Other considerations – Operating Costs of multiple buildings– Land acquisition is District responsibility– Leadership in Energy and Environmental Design

(LEED) requirements for renovating schools

The Present…

Page 12: Defiance City School District

• OSFC potential offer of funding in Spring 2010• Accept

– Ballot in November 2010, February 2011, May 2011 and August 2011

– Finalize Master Plan Scope in April/May 2010– Unsuccessful in 1 year to raise Local Share = Lapsed District.

Continue to raise funds and contact OSFC for next cycle of funding. Enrollment updated and current Construction Costs applied; District goal to anticipate changes so raised Local Share is correct.

• Timing is crucial

The Future…

Page 13: Defiance City School District

• Defer– Board Resolution required– Spring 2011 offer of Funding– Ballot in November 2011, 3 more times in 2012– Changes in Construction Costs, Enrollment and

Equity Rank (local share percentage)

The Future…

Page 14: Defiance City School District

Defiance City School District Defiance City School District

Questions?