Upload
duongngoc
View
219
Download
0
Embed Size (px)
Citation preview
Massachusetts Water Resources Authority
Deer Island Treatment Plant“Heat First-Power Second” CHPHeat First-Power Second CHP
Daniel O’Brien, PEDeputy Director OperationsDeputy Director, Operations
NBP WebcastSeptember 22, 2010
1
Massachusetts Water Resources Authority
Presentation Outline
• MWRA Background • Overview of Deer Island• Energy Use Profile
S lf G ti & E S i I iti ti• Self-Generation & Energy Savings Initiatives• Current CHP Scheme• Future CHP Modifications• Future CHP Modifications• Questions
2
Massachusetts Water Resources Authority
MWRA Background
• Independent Public Authority – created in 1985
• Wholesale Provider of Water and Sewer Services
• Service Population – 2.2 million (42% of State)
• 61 Communities receive some form of service• 61 Communities receive some form of service
• Centralized wastewater treatment at Deer Island
3
Massachusetts Water Resources Authority
4
Massachusetts Water Resources Authority
D I l d T t t• Deer Island Treatment Plant
• 2nd Largest Wastewater gTreatment Plant in the United States
• Built on 150 Acres• Built on 150 Acres
• Treatment Capacity:– Maximum
• 1.27 Billion Gal/Day
– Avg. Daily Flow365 Million
5
• 365 Million Gal/Day
MWRA – Leading by Example
• As a leading environmental agency, MWRA has been striving to meet the goals established in Governor Patrick’s Executive Order 484 (April 2007)g ( p )
• Goals include:• Overall Reduction of Energy Consumptiongy p• Increase Renewable On-site Energy Production (30% by 2020)• Purchase of Renewable Energy
• Original 1988 design already had similar goals
66
Self-Generated Renewable Energy
• MWRA self-generated over 40% of it’s energy demand in FY10 from D I l d R bl E tDeer Island Renewable Energy assets
– Digester gas heat supply
– Digester gas STG electricityDigester gas STG electricity
– Hydro electricity
– Wind
– Solar
• Deer Island Renewable Energy assets generated over 16% (35M• Deer Island Renewable Energy assets generated over 16% (35M kWh/yr) of MWRA’s total electricity demand (215M kWh/yr) in FY10
– Or 22% of Deer Island total electricity demand (164M kWh/yr)
77
Self-Generation & Energy Savings Initiatives
8
Deer Island Electricity
ELECTRICITY USAGE BY PROCESS AREA
Pumping – 30%
Secondary – 30%
Residuals 14%Residuals – 14%
Primary – 12%
Thermal – 8%
S pport Facilities 6%
99
Support Facilities – 6%
Massachusetts Water Resources Authority
Overview of DI Facilities
• Deer Island – 365 mgd (avg); 1270 mgd (peak)• Pure Oxygen Secondary Plant• Primary:Secondary Sludge Ratio – 65:35• Thickening Gravity Thickeners & Centrifuges• Thickening – Gravity Thickeners & Centrifuges• Egg-shaped Digesters – 12 units at 3 mg each• Detention 15-21 days; VS Destruction 65% (avg)Detention 15 21 days; VS Destruction 65% (avg)• Gas Utilization – 98-99%; Production – 185,000 scfh• Sludge Production – 105 dry tons per day
10
Deer Island – Aerial View
11
Deer Island – Site-Specific Factors
Site-Specific Factors Impacting Decisions
• Remote Site – Limited Access• Constrained Site – Little Open Space• Power Plant Complex – Tight Interior Layout
N S l f N t l G (P bli O iti )• No Supply of Natural Gas (Public Opposition)• Sale of power to grid prohibited by supplier contract• Air Emissions Permit• Air Emissions Permit• Noise Restrictions
12
Residuals Complex – Egg-Shaped Digesters
DIGESTER GAS
Current Utilization 98-99%Thermal ValueThermal Value• 5 MG ($10-15M/yr)
El t i it P d tiElectricity Production• 28M kWh/yr ($2.8M/yr)
MA RPS - Renewable Energy Certificates• > $500k/yr
13
y
Digester Gas Utilization – 2003-2010
Digas Beneficially Utilized at the Deer Island Thermal Power Plant
90%
100%
50%
60%
70%
80%
lized
20%
30%
40%
50%
% U
til
0%
10%
Jul-03 Nov-04 Mar-06 Aug-07 Dec-08 May-10
14
Digester Gas Utilization – 2008-2010
Digas Beneficially Utilized at theDigas Beneficially Utilized at the Deer Island Thermal Power Plant
90%
100%
60%
70%
80%
ized
20%
30%
40%
50%
% U
tili
0%
10%
Jul-08 Oct-08 Jan-09 Apr-09 Aug-09 Nov-09 Feb-10 Jun-10
15
CHP – Original Design Concept
Original Design Concept• Dedicated power cable to local supplier – base power• On-site availability of digas to fire dual-fuel boilers• High-pressure boilers to meet thermal load• STG to generate electricity• CTGs (Pratt Whitney) to provide backup power• CTGs (Pratt-Whitney) to provide backup power• STG sized to provide add’l power if needed
16
Boilers – Existing Installation
• Installed - 1998• Model - Zurn (2)• Rated Capacity – 150,000 #/HR each
A O t t 70 000#/HR• Average Output – 70,000#/HR
17
STG – Existing Installation
• Installed - 1998• Model - Demag Deval• Rated Capacity – 18 MW• Average Output – 3.2 MW
18
BP STG – New Installation
• Installed – 2011(planned)• Model - Siemens• Rated Capacity – 1.2 MW• Expected Output – .5 MW• Cost $2 2M• Cost - $2.2M
19
STG Production – 2003-2010
STG Production at the Deer Island Thermal Power Plant
4 50
5.00 6,000
3.00
3.50
4.00
4.50
atio
n, M
W
4,000
5,000
Gas U
tiliz
1.00
1.50
2.00
2.50
STG
Gen
era
1,000
2,000
3,000
zed, KSC
FH
0.00
0.50
Jul-03 Nov-04 Mar-06 Aug-07 Dec-08 May-100
,
Steam Generator Output Gas Used at Thermal Power Plant*
20
STG Production – 2008-2010
STG Production at the Deer Island Thermal Power Plant
4.00
4.50 250
2.50
3.00
3.50
00
atio
n, M
W
150
200
Gas U
tiliz
1.00
1.50
2.00
STG
Gen
era
50
100
zed, KSC
FH
0.00
0.50
Jul-08 Oct-08 Jan-09 Apr-09 Aug-09 Nov-09 Feb-10 Jun-100
21
Steam Generator Output Gas Used at Thermal Power Plant*
Existing CHP Issues
• Actual conditions differed from design projections• Sludge (and therefore digas) production much less• Both power and thermal demand less• Treatment Plant full build-out was reduced• STG full output requires lots of supplemental fuel• STG full output requires lots of supplemental fuel• Some ancillary support equipment undersized
22
BP STG – Planned Modifications (winter mode)
23
BP STG – Planned Modifications (summer mode)
24
Dump & Vacuum Condenser – Existing & Future
• Original Installation – 1998 (tube bundle replaced 2004)• Model - Katema Heat Transfer
• New Installation – 2011• Model – TBD• Cost - $2.8M
25
Expected Benefits of Modifications
• Overall STG Output Increased• Expected Increase – 5.4M KWH/YR (20%)
$• Estimated Annual Savings - $540,000• Boiler efficiency increased (hotter feedwater)• Less wasted steam• Less wasted steam• More flexibility for seasonal heat load swings• Payback Period – 6-8 yearsPayback Period 6 8 years
26
Self-Generation – Current & Future (Annual)
• Deer Island – Total Power Demand – 166M kWh• Purchased Power – 127M kWh (76%)
• Existing STG – 28 5M kWhExisting STG 28.5M kWh• Future BP STG – 5.4M kWh
E i ti CTG 5 2M kWh• Existing CTG – 5.2M kWh• Existing Hydro – 6.0M kWh
• Existing Wind & Solar – 2.3M kWh• Future Wind & Solar – 3.5M kWh
2727
Massachusetts Water Resources Authority
Thank You
Contact Information - Daniel O’Brien, [email protected]
617-660-7680(Questions will be taken once all presentations have
been completed)
28