Upload
digger797
View
19
Download
0
Embed Size (px)
DESCRIPTION
The legacy of suspended wells
Citation preview
THE LEGACY OF
SUSPENDED WELLS
Derek Saward
Head, Environmental Management Team
DECC OGED, 02 October 2013
In 2012, DECC Licensing Exploration and Development (LED) initiated a review to update the inventory of open-
water suspended wells on the UKCS
O&GUK convened a industry workshop in June 2012 to discuss the inventory and how to prioritise the
abandonment of suspended wells
DECC took an action from the workshop to review the available information and write to industry to encourage
the development abandonment programmes
In view of the environmental issues relating to suspended wells, it was decided that DECC Offshore Oil
and Gas Environment and Decommissioning (OGED)
should take this work forward
BACKGROUND
To encourage industry to develop a risk-based programme / campaign to
abandon legacy open-water
suspended wells
AIM
DECC OGED reviewed the existing information provided by DECC LED
Following its review, OGED wrote to operators early in 2013 to seek additional information, to facilitate a risk
assessment broadly based on the output of the
industry workshop
There were challenges reconciling LED legacy data against current well ownership, indicating that suspended wells receive little attention during asset
transfer processes
There was a very good response rate, with the qualification that some of the responses did not
provide complete information
DATA COLLECTION
RISK ASSESSMENT
Criteria Risk Factor
Potential for re-use / abandonment plans No clear plans for reuse (appraisal or development)
or abandonment of the wells
Well suspension category Category type 3 & 4 (using O&G UK well
suspension and abandonment guidelines)
Hydrocarbons Hydrocarbon type (Oil>Condensate>Gas)
Natural flow to surface
High pressure and/or high temperature
Well status Leaking or damaged
Confirmed degradation of barriers
Outwith design life (>25 years)
No recent inspection / survey (>5 years)
Environmental factors Water depth (>300 m or >1,000 m)
Environmental sensitivity
Fishing activity
Safety zone or proximity of infrastructure
Information quality Complete and relevant information not provided
RESULTS - E&A WELLS
100
13
42 19
55
7
52
2 1
Need more info./action required
Already abandoned
Abandonment planned 2013 - 2015
Category 1
Planned re-use
Producer
Well in safety zone
Close to other infrastructure
Serving another purpose
Total 291 wells
SUSPENDED E & A WELLS
SHUT-IN PRODUCTION WELLS
RESULTS - SHUT-IN WELLS
Total 349 wells
49
10
39
2 9
240
Need more info./action required
Category 1
Planned re-use
Abandonment planned 2013 - 2015
Abandoned / Producing
Well in safety zone
Suspended
Open-water E&A
Wells and Shut-in
Production Wells
on the UKCS
100 E&A wells and 49 shut-in production wells
requiring further action
These wells fell into three categories:
Lack of information
Operator didnt provide any firm plans for re-use or abandonment
Risk factor, e.g. hydrocarbon / reservoir type, well status (leakage, degradation of barriers, outwith
design life, etc.) and environmental factors
RESULTS - FURTHER ACTION
27 E & A wells and 2 production wells where industry needs to provide additional information,
or they will be placed in highest risk category
31 E & A wells and 14 production wells with no planned re-use where industry needs to provide
Plugging and Abandonment (P&A) proposals, or
they will be placed in highest risk category
42 E & A wells and 33 production wells considered to be at risk, and industry needs to undertake P&A operations in the short term.
SUMMARY
Suspended E&A
Wells and Shut-
in Production
Wells on the
UKCS
If P&A is required in the short term, operators are required to develop abandonment
programmes, initially targeting the at risk wells
Industry should:
Explore opportunities for joint abandonment programmes for wells in same area
Maximise vessel / rig availability
Mitigate costs
DESIRED OUTCOME
If there are no obvious concerns, new applications for suspension will receive approval for a maximum of 5 years
After 5 years, extension applications must be supported by acceptable inspection / survey information or proposals
After 5 years, extension applications will trigger request for risk assessment information (i.e. the information recently
collected for the legacy wells)
DECC OGED will undertake a risk assessment and, if the outcome is satisfactory, recommend that continuation of the
suspension should be approved
If the risk assessment highlights potential issues, operators will be required to submit firm proposals to P&A the well
before the continuation of the suspension is approved
DECC OGED will contact operators annually to update the inventory of suspended wells and review the risk assessment
FUTURE POLICY
QUESTIONS?