19
DUBLIN INSTITUTE OF TECHNOLOGY Decant Strategy Moving to the Central and East Quads Rev: 1.8 Status: Draft - For Review 19 April 2018

Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DUBLIN INSTITUTE OF TECHNOLOGY

Decant Strategy Moving to the Central and East Quads

Rev: 1.8

Status: Draft - For Review

19 April 2018

Page 2: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

Contents

1.0 Introduction ...................................................................................................................................3

Objective........................................................................................................................................3

2.0 Planning and Management of Decant ............................................................................................3

Governance ....................................................................................................................................4

3.0 High Level Decant Programme and Timelines .............................................................................6

4.0 Decant Communication Strategy ...................................................................................................7

5.0 De-clutter Strategy .........................................................................................................................7

6.0 Staff Decant ...................................................................................................................................7

Staff accommodation/destination ..................................................................................................7

Preparation of Staff to decant ........................................................................................................7

7.0 Equipment and Consumables Decant ............................................................................................8

Condition Assessment of equipment for decant ............................................................................8

Delivery of new equipment ...........................................................................................................8

Equipment Decant Warranty issues ...............................................................................................8

Decant cost benefit analysis ..........................................................................................................8

Equipment labelling .......................................................................................................................9

8.0 Consumables Decant .....................................................................................................................9

Decant of consumables ..................................................................................................................9

9.0 Access to Buildings .......................................................................................................................9

10.0 ICT Decant ....................................................................................................................................9

11.0 Risk Assessment: impact on academic function ............................................................................9

12.0 Disposal of Obsolete Equipment and Surplus Consumables ...................................................... 10

13.0 Appendices ................................................................................................................................. 10

Prepared by DIT Campus Planning Office: [email protected]

Page 3: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

Abbreviations:

CJV Construction Joint Venture company (formerly referred to as the PPP Co)

DIT Dublin Institute of Technology

DPM Decant Project Manager

DPT Decant Project Team

GDA Grangegorman Development Agency

LTTC DIT Learning, Teaching and Technology Centre

MPB Migration Project Board

MPT Migration Project Team

NDFA National Development Finance Agency

PPP Public Private Partnership

SLT DIT’s Senior Leadership Team

Page 4: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

3

1.0 Introduction

The relocation of Dublin Institute of Technology (DIT) operations to new premises at DIT Grangegorman

is among the most significant moves in the history of the Institute. This document sets out the strategy for

decant of staff, equipment, consumables and other items from their present locations to the East and Central

Quads at Grangegorman. This decant will be undertaken by the Construction Joint Venture (CJV) element

of the Eriugena group as part of the Public Private Partnership (PPP) being undertaken to design, build,

finance and operate the East and Central Quads. The procurement and construction of this project are

managed by the National Development Finance Agency (NDFA) on behalf of the State. This relocation

has a number of facets:

Several buildings will be decanted into two new buildings

Some moves are from long established locations whilst others are from recently occupied buildings

Approximately half of DIT’s teaching activities will relocate

Several different schools, with a wide variety of differing needs, must be accommodated.

Consequently, it is necessary to plan to decant the current locations and move in an agreed systematic

manner. It is essential that all staff are involved and fully informed of this process. DIT has extensive

experience of relocation, having undergone a number of significant relocations in the last 10 years, e.g.

decant of Head Office from Pembroke Street to Rathmines in 2007, of Zhivago building to Bolton Street

and Linenhall 2010, of Mountjoy Square/Portland Row to the Cluster Buildings at Grangegorman 2014

and more recently the planning and implementation of the move from Rathmines to Park House. In all of

these relocations, a systematic strategy was devised and implemented. Lessons were learned on each of

these occasions and these are incorporated into this strategy.

Objective

The purpose of the strategy is to ensure a smooth and efficient relocation from the current buildings to the

PPP Quads in Grangegorman minimising, where possible, disruption to the academic functions of DIT.

The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works

relating to the relocation of staff, equipment and consumables.

Appendix A shows the locations from which each of the Schools will move in 2020 to the Central and East

Quads.

2.0 Planning and Management of Decant

The decant will be undertaken and completed by the CJV. Planning and management of the DIT input to

the decant will be led by a Decant Project Team (DPT) comprising membership from the DIT Campus

Planning Team, the Migration Project Teams (MPT), the Estates Office, Information Services, Human

Resources, Procurement and Finance. Using the experience of the previous moves, this group will plan the

project, establish the resources required to complete the project, initiate the relevant actions to achieve the

project tasks, monitor progress and report to the DIT Migration Project Board (MPB). As DIT will be

providing input into the CJV contract, it is important to note that the overall project is managed by the

NDFA and that DIT’s role is a supporting one to the CJV.

The relevant Colleges/Schools/Units that will relocate to the East and Central Quads are currently engaged

in the planning for this move through the East and Central Quad MPTs. As the workload is anticipated to

Page 5: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

4

increase substantially in the 12 months in advance of the relocation, The MPB will provide support through

a Decant Project Manager (DPM) who will drive and implement the project from DIT’s perspective. At the

discretion of the MPB, this may be a directly employed project manager or a resource similar to the

Rogerson Reddan project management facility employed by DIT for the 2014 move.

Once this DPM is appointed, it is expected that the CJV will liaise closely with him/her to ensure that the

relocation proceeds with the minimum disruption to DIT’s provision of its educational programmes.

Governance

At a planning and management level, the decant project will overseen by the DPT, This team will report to

both the PPP Project Board (through DIT’s Campus Planning office) and directly to DIT’s Migration

Project Board (MPB).

At local level, each College/School/Unit will be required to nominate a Decant Subgroup, to internally

manage the decant process. One of the members of this group should be nominated as the group leader to

act as its contact point for the decanting process. This person must have the authority to make technical

equipment decisions in specific spaces.

The governance structure for this decant is shown below in Figure 2.

Figure 1: Governance Structure for the Decant.

Page 6: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

5

The key deliverables at each level in this structure are as follows:

Level Deliverables Subsequent Actions & Approvals

Decant

Project

Team

High Level Decant Programme Provide programme to all parties

Monitor progress and report to MPB

Specialist Equipment Report Provide to SLT for funding decision

Decant Communication Strategy Approval by MPB

Support MPTs and HR in implementation

Declutter Strategy Approval by MPB

Support MPTs in implementation

Existing Equipment Report Provide to NDFA/CJV

Decant

Subgroup

Condition survey of items to be

relocated

Provide report to MPT

MPT to alert MPB of cost consequences

Cost benefit analysis of moving

large items

Provide report to MPT

MPT to alert MPB of cost consequences

Risk Assessment identifying:

Safety risks in moving

equipment/consumables

Analysis of potential impact on

academic function

Provide to MPT who will assess suggested

control measures and further action required

Finalised list of items to be

relocated

Provide report to MPT

MPT to alert MPB of cost consequences

MPB to approve spending final list of new items

Provide finalised report to MPM

Document showing agreed

timing of availability of items to

be decanted

Provide to Decant Project Manager

Decant

Project

Manager

Ongoing monitoring report of

project progression

DPM maintains ongoing communication with

CJV to ensure operational readiness

Equipment commissioning sign

off procedure

DPM sets up, implements and manages the

process for procurement, receipt and

commissioning of new Specialist Educational

Equipment

DPM sets up, implements and manages the

process for receipt and commissioning process of

existing Specialist Educational Equipment

DPM provides verification that all equipment is

delivered, installed and commissioned in

accordance with appropriate requirements

CJV Construction Project Programme DPT develops and updates high level decant

programme

Detailed Decant Programme CJV and DPM coordinate decant tasks

Page 7: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

6

In addition, the MPTs have a number of key responsibilities, including (but not limited to):

• Allocation of financial resources for the purchase of new specialist educational equipment

following that SLT decision on the level of such funding

• Escalation of appropriate actions to the MPB without delay

• Ensuring that all of the identified Decant Subgroups are constituted in time to undertake their

assigned tasks

• Providing leadership in cooperation with the DPM in the purchase, delivery, installation and

commissioning of specialist educational equipment

• Providing support to staff and students to ensure full cooperation in the decant process.

An initial stakeholder mapping exercise has been undertaken to establish clarity in terms of the roles and

responsibilities and a detailed assessment of deliverables. Relevant staff have been setting out the

individuals which are Responsible, Accountable, Consulted and Informed (i.e. the RACI process – see

figure 2 below) in relation to the various tasks involved in the Decant.

The developed RACI matrix is shown as Appendix B. It is intended that this document will identify all of

the relevant issues to be taken into account in the relocation, thereby providing certainty of the process for

the CJV, the DIT schools and support units, the staff of DIT and the GDA.

R Responsible

- Who is/will be doing this task? - Who is assigned to work on this task?

A Accountable

- Who has the authority to take decisions? - Who deals with the outcome?

C Consulted

- Who must be consulted before a decision is made or action is taken?

I Informed

- Who must be informed of actions, decisions and progress

Figure 2. RACI Process

3.0 High Level Decant Programme and Timelines

To plan the work to be undertaken in the decant, a high level programme, identifying tasks to be undertaken,

estimated durations, sequence and dependencies, will be developed in draft form by the DPT with input

from the Decant Subgroups. It will then be refined in consultation with NDFA and the CJV, prior to its

issue as a working programme. The programme will be a live document, subject to revision where

necessary as the construction phase of the project develops. The programme will allow appropriate periods

of time for preparation of the equipment to be moved and for compilation of appropriate documentation.

This will become the monitoring tool for the management of DIT aspects of the decant.

Page 8: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

7

Once the Decant Programme is developed, staff briefings will be undertaken by the DPT to ensure that all

DIT staff are aware of the key milestone dates on the programme and of the obligations on staff themselves

to prepare for the decant. Staff will be notified that rigid adherence to the programme will be essential.

4.0 Decant Communication Strategy

Development of the Decant Communication Strategy will be undertaken by the DPT, with input from the

Decant Subgroups, the DIT Public Relations Office and the DIT Human Resources office. Communication

of details of the decant will be responsibility of the Decant Subgroup Leaders. The strategy document will

also be posted on the DIT website at http://www.dit.ie/grangegorman/information-for-staff/relocation/.

Presentations to staff on the Strategy will be provided by DPT on a systematic basis with the relevant

Colleges/Schools/Units.

5.0 De-clutter Strategy

Over several years, staff has gradually accumulated items that are no longer necessary for the delivery of

DIT’s programmes. The relocation provides DIT staff an opportunity to bring with them only the items that

are necessary and required for their current and future teaching and research. Unrequired or out of date

items should not be relocated. In addition, the teaching technology that will be available provides a unique

opportunity to maximise the use of digital material and to move away from older methods of lecturing

(involving the extensive use of paper). DIT staff will receive assistance to digitise their teaching materials

in the time between November 2018 and February 2020. A strategy document will be developed by the

Decant Project Team with input from various DIT units, such the DIT Learning, Teaching and Technology

Centre (LTTC) and will draw heavily on the experiences of staff moving in September 2014. The strategy

will have been fully developed by November 2018 and its delivery will become part of the migration

process.

6.0 Staff Decant

Staff members will be relocated to their new locations on a date which will be derived from the CJV

construction programme and will be discussed with the relevant staff several months in advance of the date.

Staff accommodation/destination

Each staff member moving to the new facility will be assigned a workstation with a coded reference. Again,

this will be notified to the staff member in advance of the move date.

Preparation of Staff to decant

The CJV will provide each staff member be given a maximum of ten boxes (400x300x300mm) for their

effects. Staff must ensure that their belongings are appropriately labelled and packaged. The CJV will then

deliver these effects to the staff member’s new workstation in the East and central Quads. Computers will

be separately moved.

It is important that staff in general when moving their effects have due consideration of the DIT de-clutter

strategy. Staff must only pack what will be required in the new location. Further personal effects not

required at the new location should be removed by staff as such items are likely to be disposed of when the

old buildings are being prepared for handover to the new owners.

Page 9: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

8

7.0 Equipment and Consumables Decant

The decant of equipment and consumables is essential for the smooth operation of the Grangegorman

facilities. There are several different types of equipment which will be moved by the CJV. To prepare for

the move, the DPT will first categorise equipment (initial categorisation attached as Appendix C) and

identify equipment under each category (Appendix D – Equipment Relocation Schedule).

The Decant Subgroups will assess the current condition of each item to ensure that the benefit of moving

the equipment exceeds the cost of its relocation and to verify its fitness for purpose in the new building.

Only such equipment that is deemed fit for purpose in the new building will be relocated. A Health &

Safety risk assessment (which will form part of that referred to later in Section 11) will form part of this

process and the outcome of the exercise will be to identify a definitive list of the equipment to be relocated.

These assessments will inform the compilation of the final list of equipment to be decanted. The DPM will

inform the CJV where there are specific issues associated with movement of equipment. The equipment

Relocation Schedule will show the dates that relocation can take place and confirm by signature that the

item will be ready to move on the date identified.

By identifying each item under a specific category, the Decant Subgroup will provide details of how the

equipment will be physically presented for CJV on move day, e.g. in relation to serviced items with

water/electrical/vent connections etc., Equipment connected to services will be isolated and disconnected

by CJV prior to moving.

On arrival in the new location, the CJV will reconnect relevant equipment to services such as water,

electricity, gas, air, extraction, etc.

Condition Assessment of equipment for decant

If equipment is damaged during the move DIT’s pre-move assessment will show that it was in working

order and that it was fit for purpose when it left our premises. The outcome of the pre-move assessment

will be noted against each item on the final list of equipment to be relocated. If the CJV wishes to witness

this assessment, this will be facilitated by the Decant Project Manager.

Delivery of new equipment

In cases where Group 6 or Group 4 FF&E is unsuitable for transfer to the new location, it will be replaced

with new Group 3 FF&E. Installation and calibration of such items will be carried out by the supplier with

access being granted by the CJV. This process will be managed by the DPM in consultation with and

agreement with the CJV.

Equipment Decant Warranty issues

Some equipment may void its warranty if not moved by a specialist procedure. It will be necessary to

identify such equipment to the CJV in the condition assessment exercise.

Decant cost benefit analysis

A cost benefit analysis of moving large items equipment will be carried out by the Decant Subgroups and

presented to the MPTs and the DPT. In this analysis, certain large items of equipment may be identified as

so difficult to move that their relocation is not economical.

Page 10: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

9

In such circumstances, the MPT will alert the Migration Project Board of the outcome of the analysis and

seek instructions on how to proceed.

Equipment labelling

All equipment to be moved will be appropriately identified or labelled by the Decant Subgroup to assist

the CJV in moving it to the appropriate location. Once this is done, the CJV will pack the equipment as

appropriate, move it and unpack it at its new location. Care must be taken to ensure that all items are packed

in accordance with the manufacturers/suppliers recommendations. Where appropriate, equipment that is

relocated must have its new location recorded in the DIT Asset Register. This is an internal DIT issue that

will be managed by the DIT Estates Office.

8.0 Consumables Decant

Decant of consumables

Academic, Professional, Management and Support Staff should aim to run down stocks of materials as

much as possible in advance of the move. This will lower transport costs. The Decant Subgroup will inform

the CJV with a definitive list of the amount of consumables to be moved and any associated hazards, at a

date to be agreed with the CJV.

9.0 Access to Buildings

The CJV will relocate equipment that has been identified by DIT Colleges, Schools and Units. As the CJV

will not be familiar with the equipment or aware of the layout of DIT buildings, it will be essential that

there will be access to all appropriate rooms on the day of the equipment removal. The coordination of this

process between DIT personnel and the CJV will be one of the duties and responsibilities of the DPM. In

the event that an existing building requires alterations to remove specific equipment, DIT will carry out

such work in advance of the removal.

10.0 ICT Decant

The only ICT equipment to be decanted will be a number of desktop PCs and 3rd party printers that will be

assessed for fitness for purpose closer to the time of the move. These will be relocated using the process

described in Section 7 above, with Information Services being the relevant Decant Subgroup.

11.0 Risk Assessment: impact on academic function

Each Decant Subgroup is obliged to carry out a Risk Assessment. This should include an "analysis of

potential impact on academic function" e.g. if certain items are required to move early, how will it impact

on the delivery of education services? Will the potential early movement of certain larger items impact on

exam schedules etc.? A short risk identification workshop will be arranged in Autumn 2018 and

Page 11: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

10

contingency arrangements will be established where necessary. Particular contingency measures may be

required where a building requires alteration to facilitate the movement of a large item of equipment.

12.0 Disposal of Obsolete Equipment and Surplus Consumables

All obsolete and worn out equipment or surplus consumables in existing buildings will be disposed of in

accordance with the appropriate DIT guidelines and public sector regulations for such items. This task will

be undertaken by the DIT Estates Office following services commencement in the new buildings.

13.0 Appendices

These are in draft form and will be subject to further development

A. Central and East Quad Schools – Locations and Affiliations

B. RACI template

C. Categories of equipment to be relocated

D. Equipment Relocation Schedule

Page 12: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

i

Appendix A

Central and East Quad Schools: Locations and Affiliation

Location School College Affiliation Location 2016

Central Quad

Physics Sciences & Health Kevin Street

National Optometry Centre (This Centre is incorporated into the School of Physics)

Sciences & Health Kevin Street/New Bride Street

Chemical & Pharmaceutical Sciences Sciences & Health Kevin Street

Mathematical Sciences Sciences & Health Kevin Street

Biological Sciences Sciences & Health Kevin Street

Food Science & Environmental Health Sciences & Health Cathal Brugha Street

Computing Sciences & Health Kevin Street

Culinary Arts & Food Technology Applied Arts & Tourism Cathal Brugha Street

Hospitality Management & Tourism Applied Arts & Tourism Cathal Brugha Street

Electrical and Electronic Engineering Engineering & Built Environment

Kevin Street

East Quad

Dublin School of Creative Arts* Applied Arts & Tourism Grangegorman

Music & Drama Applied Arts & Tourism Chatham Row/Clarendon Row

and Rathmines

Languages, Law & Social Sciences** Applied Arts & Tourism Languages from Kevin St and Cathal Brugha

St. Social Science in Grangegorman.

Media Applied Arts & Tourism Aungier St, Grangegorman (Photography)

* The Printing element of the Dublin School of Creative Arts is based in Bolton Street and will not

be relocating to Grangegorman in 2020.

** The Social Science element of this School in based in Grangegorman. The Languages element

associated with the Tourism programmes in Cathal Brugha St/Sackville Place will relocate in

2020. The remaining Law and Languages elements, currently located in Aungier St and Kevin St

respectively, are not relocating to Grangegorman in 2020.

Page 13: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

ii

Appendix B RACI Template

Existing Equipment

(Group 6)

DIT Decant

Leadership

Decant Subgroups Staff

/Students

Decant Support Non DIT

R: Responsible

A: Accountable

C: Consulted

I: Informed

Project Deliverable

DIT

Sen

ior

Lea

der

ship

Tea

m

Mig

rati

on

Pro

ject

Bo

ard

Cen

tral

Qu

ad M

PT

Eas

t Q

uad

MP

T

Dec

ant

Pro

ject

Tea

m

Dec

ant

Pro

ject

Man

ager

Co

lleg

e o

f E

ng &

BE

Co

lleg

e o

f A

rts

& T

ouri

sm

Co

lleg

e o

f S

cien

ces/

Hea

lth

Sch

Mu

sic

& D

ram

a

Sch

Cre

ativ

e A

rts

Sch

Med

ia

Sch

Lan

g,

Law

So

c S

cien

ces

Sch

Cu

lin

ary

Art

s

Sch

Ho

spit

alit

y M

gt

& T

our

Sch

Ele

ctri

cal/

Ele

ctro

nic

En

g

Sch

Bio

log

ical

Sci

ence

s

Sch

Ch

em a

nd

Ph

arm

a S

ci

Sch

Co

mp

uti

ng

Sch

Fo

od

Sci

/En

v H

ealt

h

Sch

Mat

h S

cien

ces

Sch

Ph

ysi

cs

DIT

IC

T S

erv

ices

Aca

dem

ic S

taff

mo

vin

g

Ad

min

/su

pp

ort

mo

vin

g

Stu

den

ts U

nio

n

Sta

ff U

nio

ns

Cam

pu

s P

lan

nin

g

DIT

Est

ates

DIT

Pu

bli

c A

ffai

rs o

ffic

e

HR

Fin

ance

Pu

rch

asin

g

LT

TC

ND

FA

GD

A

CJ

V

1. Develop RACI Matrix A C C C I I I I I I I I I I I I I I R I C C

2. Nominate members of Decant

Project Team

I A R R I C C C I I I I I I I I I I I I I I I I I I C I R R R R I I I

3. Compile Draft Equipment

Report for SLT for funding

decision

AR C C C C C C C C C C C C C C C C C

4. Confirm New Educational

Equipment Funding Envelope

AR I I I I I I I I I I I I I I I I I I I I I I I I

5. Allocate available funding to

Colleges

A R R I I I I I I I I I I I I I I I I I I I I

6. Compile Finalised Equipment

Report

A A C R R R R R R R R R R R R R R R R R I I

7. Review and refine list of

categories of equipment to be

moved

I I I AR C C C C C C C C C C C C C C C C C I I I C C I I

8. Identify equipment under each

category from FF&E schedules

I I I A R R R R R R R R R R R R R R R R R C C C C I I

9. Assess condition of existing

equipment

I A A C R R R R R R R R R R R R R R R R R C C I I I I

10. Establish alteration works to

be carried out to facilitate

relocation of equipment

I I I I I I C C C C C C C C C C C C C I C AR

Page 14: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

iii

Group 6 (Continued) DIT Decant

Leadership

Decant Subgroups Staff

/Students

Decant Support Non DIT

R: Responsible

A: Accountable

C: Consulted

I: Informed

Project Deliverable

DIT

Sen

ior

Lea

der

ship

Tea

m

Mig

rati

on

Pro

ject

Bo

ard

Cen

tral

Qu

ad M

PT

Eas

t Q

uad

MP

T

Dec

ant

Pro

ject

Tea

m

Dec

ant

Pro

ject

Man

ager

Co

lleg

e o

f E

ng &

BE

Co

lleg

e o

f A

rts

& T

ouri

sm

Co

lleg

e o

f S

cien

ces/

Hea

lth

Sch

Mu

sic

& D

ram

a

Sch

Cre

ativ

e A

rts

Sch

Med

ia

Sch

Lan

g,

Law

So

c S

cien

ces

Sch

Cu

lin

ary

Art

s

Sch

Ho

spit

alit

y M

gt

& T

our

Sch

Ele

ctri

cal/

Ele

ctro

nic

En

g

Sch

Bio

log

ical

Sci

ence

s

Sch

Ch

em a

nd

Ph

arm

a S

ci

Sch

Co

mp

uti

ng

Sch

Fo

od

Sci

/En

v H

ealt

h

Sch

Mat

h S

cien

ces

Sch

Ph

ysi

cs

DIT

IC

T S

erv

ices

Aca

dem

ic S

taff

mo

vin

g

Ad

min

/su

pp

ort

mo

vin

g

Stu

den

ts U

nio

n

Sta

ff U

nio

ns

Cam

pu

s P

lan

nin

g

DIT

Est

ates

DIT

Pu

bli

c A

ffai

rs o

ffic

e

HR

Fin

ance

Pu

rch

asin

g

LT

TC

ND

FA

GD

A

CJ

V

11. Obtain planning permission for

alteration works if necessary

I I I I I I I I I I I I I I I I I I I I I I A R I

12. Carry out alteration works

necessary for decant

I I I I I I I I I I I I I I I I I I I I I I I I I AR I

13. Carry out decant cost benefit

analysis on equipment

I A A C R R R R R R R R R R R R R R R R R R R I I C C

14. Carry out risk assessment of

moving equipment

I A A C R R R R R R R R R R R R R R R R R R R C C C C I

15. Refine list of actual equipment

to be moved

I A A C R R R R R R R R R R R R R R R R R R R I I C C I I I

16. Appoint External Project

Manager for the relocation

AR C C I I I I I I I I I I I I I I I I I I I I I I C I C C I I I

17. Carry out pre-move equipment

testing

I I I I A R R R R R R R R R R R R R R R R R I I I C I I I

18. Review draft list of equipment

to be moved

I I I I A R R R R R R R R R R R R R R R R R I I C C I

19. Issue final list of equipment to

be moved

I I I I A R R R R R R R R R R R R R R R R R I I I I C C I I I

20. Labelling of equipment I I I I A R R R R R R R R R R R R R R R R R R R I R I I I

21. Disconnection of equipment I I I I C C C C C C C C C C C C C C C C C C I I R AR

22. Packing, moving, unpacking

equipment

I I I I C C C C C C C C C C C C C C C C C C C C C C I I AR

23. Reconnecting equipment I I I I C C C C C C C C C C C C C C C C C C I I AR

24. Testing/recalibration/

commissioning of equipment

I I I I C C C C C C C C C C C C C C C C C C I I AR

Page 15: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

iv

Moving DIT Consumables DIT Decant

Leadership

Decant Subgroups Staff

/Students

Decant Support Non DIT

R: Responsible

A: Accountable

C: Consulted

I: Informed

Project Deliverable

DIT

Sen

ior

Lea

der

ship

Tea

m

Mig

rati

on

Pro

ject

Bo

ard

Cen

tral

Qu

ad M

PT

Eas

t Q

uad

MP

T

Dec

ant

Pro

ject

Tea

m

Dec

ant

Pro

ject

Man

ager

Co

lleg

e o

f E

ng &

BE

Co

lleg

e o

f A

rts

& T

ouri

sm

Co

lleg

e o

f S

cien

ces/

Hea

lth

Sch

Mu

sic

& D

ram

a

Sch

Cre

ativ

e A

rts

Sch

Med

ia

Sch

Lan

g,

Law

So

c S

cien

ces

Sch

Cu

lin

ary

Art

s

Sch

Ho

spit

alit

y M

gt

& T

our

Sch

Ele

ctri

cal/

Ele

ctro

nic

En

g

Sch

Bio

log

ical

Sci

ence

s

Sch

Ch

em a

nd

Ph

arm

a S

ci

Sch

Co

mp

uti

ng

Sch

Fo

od

Sci

/En

v H

ealt

h

Sch

Mat

h S

cien

ces

Sch

Ph

ysi

cs

DIT

IC

T S

erv

ices

Aca

dem

ic S

taff

mo

vin

g

Ad

min

/su

pp

ort

mo

vin

g

Stu

den

ts U

nio

n

Sta

ff U

nio

ns

Cam

pu

s P

lan

nin

g

DIT

Est

ates

DIT

Pu

bli

c A

ffai

rs o

ffic

e

HR

Fin

ance

Pu

rch

asin

g

LT

TC

ND

FA

GD

A

CJ

V

25. Establish the extent of

consumables to be decanted

I A A I R R R R R R R R R R R R R R R R R C R C R I I

26. Carry out decant cost benefit

analysis on consumables

I A A C R R R R R R R R R R R R R R R R R C R C R I C

27. Carry out risk assessment of

moving consumables

I A A C R R R R R R R R R R R R R R R R R C R C R I C I

28. Compile draft list of actual

consumables to be moved

I A A C A R R R R R R R R R R R R R R R R R C R C R I I I

29. Review consumable stock and

update list of consumables to

move

I A A C A R R R R R R R R R R R R R R R R R I I C R I

30. Issue final list of consumables

to move

I I I C A R R R R R R R R R R R R R R R R R I I C R I I I

31. Labelling of consumables I I I I A R R R R R R R R R R R R R R R R R R R I R I I I

32. Packing, moving, unpacking

consumables

I I I I C C C C C C C C C C C C C C C C C C C C C C I I AR

Page 16: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

v

New Specialist

Educational Equipment

(Group 3)

DIT Decant

Leadership

Decant Subgroups Staff

/Students

Decant Support Non DIT

R: Responsible

A: Accountable

C: Consulted

I: Informed

Project Deliverable

DIT

Sen

ior

Lea

der

ship

Tea

m

Mig

rati

on

Pro

ject

Bo

ard

Cen

tral

Qu

ad M

PT

Eas

t Q

uad

MP

T

Dec

ant

Pro

ject

Tea

m

Dec

ant

Pro

ject

Man

ager

Co

lleg

e o

f E

ng &

BE

Co

lleg

e o

f A

rts

& T

ouri

sm

Co

lleg

e o

f S

cien

ces/

Hea

lth

Sch

Mu

sic

& D

ram

a

Sch

Cre

ativ

e A

rts

Sch

Med

ia

Sch

Lan

g,

Law

So

c S

cien

ces

Sch

Cu

lin

ary

Art

s

Sch

Ho

spit

alit

y M

gt

& T

our

Sch

Ele

ctri

cal/

Ele

ctro

nic

En

g

Sch

Bio

log

ical

Sci

ence

s

Sch

Ch

em a

nd

Ph

arm

a S

ci

Sch

Co

mp

uti

ng

Sch

Fo

od

Sci

/En

v H

ealt

h

Sch

Mat

h S

cien

ces

Sch

Ph

ysi

cs

DIT

IC

T S

erv

ices

Aca

dem

ic S

taff

mo

vin

g

Ad

min

/su

pp

ort

mo

vin

g

Stu

den

ts U

nio

n

Sta

ff U

nio

ns

Cam

pu

s P

lan

nin

g

DIT

Est

ates

DIT

Pu

bli

c A

ffai

rs o

ffic

e

HR

Fin

ance

Pu

rch

asin

g

LT

TC

ND

FA

GD

A

CJ

V

Preceded by Deliverable No 16

33. Finalise list of new equipment

to be purchased A A A C I R R R R R R R R R R R R R R R R R R R C C

34. Set up procurement process I I I C A I I I I I I I I I I I I I I I I I I I C C R

35. Place orders for new

equipment I I I I A R R R R R R R R R R R R R R R R R R R C C R

36. Develop protocols with CJV

for receipt and security of new

equipment

I I I R A C C C C C C C C C C C C C C C C C C C C C C R

37. Develop protocols for access

to site for installation and

commissioning of new

equipment

I I I R A C C C C C C C C C C C C C C C C C C C C C C R

38. Manage delivery of new

equipment I I I I A C C C C C C C C C C C C C C C C C C C I C I

39. Testing/recalibration/

commissioning of new

equipment

I I I I A R R R R R R R R R R R R R R R R R R R I C I

Page 17: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

vi

Moving Staff, Students

and Their Belongings

DIT Decant

Leadership

Decant Subgroups Staff

/Students

Decant Support Non DIT

R: Responsible

A: Accountable

C: Consulted

I: Informed

Project Deliverable

DIT

Sen

ior

Lea

der

ship

Tea

m

Mig

rati

on

Pro

ject

Bo

ard

Cen

tral

Qu

ad M

PT

Eas

t Q

uad

MP

T

Dec

ant

Pro

ject

Tea

m

Dec

ant

Pro

ject

Man

ager

Co

lleg

e o

f E

ng &

BE

Co

lleg

e o

f A

rts

& T

ouri

sm

Co

lleg

e o

f S

cien

ces/

Hea

lth

Sch

Mu

sic

& D

ram

a

Sch

Cre

ativ

e A

rts

Sch

Med

ia

Sch

Lan

g,

Law

So

c S

cien

ces

Sch

Cu

lin

ary

Art

s

Sch

Ho

spit

alit

y M

gt

& T

our

Sch

Ele

ctri

cal/

Ele

ctro

nic

En

g

Sch

Bio

log

ical

Sci

ence

s

Sch

Ch

em a

nd

Ph

arm

a S

ci

Sch

Co

mp

uti

ng

Sch

Fo

od

Sci

/En

v H

ealt

h

Sch

Mat

h S

cien

ces

Sch

Ph

ysi

cs

DIT

IC

T S

erv

ices

Aca

dem

ic S

taff

mo

vin

g

Ad

min

/su

pp

ort

mo

vin

g

Stu

den

ts U

nio

n

Sta

ff U

nio

ns

Cam

pu

s P

lan

nin

g

DIT

Est

ates

DIT

Pu

bli

c A

ffai

rs o

ffic

e

HR

Fin

ance

Pu

rch

asin

g

LT

TC

ND

FA

GD

A

CJ

V

40. Develop Decant

Communications Strategy

I C C AR C C C C C C C C C C C C C C C C R C C C C C R R C I I

41. Develop declutter strategy I C C A C C C C C C C C C C C C C C C C R C C I I C R C C C I I

42. Provide support to staff to

digitise teaching materials

I A A R C C C C C C C C C C C C C C C C R C R I C R R I I

43. Prepare Staff to decant I A A R C C C C C C C C C C C C C C C C C C C I C C R R I I

44. Allocate staff desks at new

destination

I A A I R R R R R R R R R R R R R R R R R C C I I C I I I I

45. Establish procedures with CJV

for movement of equipment

I C C AR C C C C C C C C C C C C C C C C C C R I I C C R C C C

46. Brief DIT Staff & Students on

agreed procedures

A A A R C C C C C C C C C C C C C C C C C C C C I C C R

47. Labelled boxes delivered to

existing staff offices

I I I I I C C C C C C C C C C C C C C C C C I I I C C I I A R

48. Academic staff pack items to

be moved

I I I A A R R R R R R R R R R R R R R R R R R I I C I

49. Administrative & Technical

staff pack items to be moved

I C C A R R R R R R R R R R R R R R R R R I R I C I

50. CJV moving staff belongings I C C C C I I I I I I I I I I I I I I I I C I I C C C I I A R

51. Staff unpack at new

destination

I A A C A R R R R R R R R R R R R R R R R R R R I I I I

52. Monitor the moving process I I I C AR I I I I I I I I I I I I I I I I I C R I I C I I C C

53. Issue Decant Completion

Report to SLT

I A C C R R C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C

Page 18: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

vii

Appendix C

Categories of Equipment to be relocated

A. Equipment impacting on construction e.g. equipment requiring specialised ducting for exhaust

fumes, items that must be built in to the new building, etc.

B. Equipment whose movement will require alteration of existing building

C. Large scale equipment requiring disconnection, specialist movement, reconnection and certification

prior to use, e.g. woodworking equipment, large electrical equipment, etc

D. Small fixed equipment requiring disconnection, reconnection and certification prior to use

E. Sensitive equipment that is susceptible to damage, e.g. laboratory glassware, etc.

F. Equipment requiring specialist commissioning or calibration, e.g. measurement equipment in

science labs, specialist equipment for Optometry, etc.

G. Portable laboratory/workshop/kitchen equipment

H. Equipment of irregular shape that will not readily fit into a crate

I. Staff belongings/personal effects

(Other categories to be added)

Page 19: Decant Strategy - Dublin Institute of Technology · The strategy will also be useful to the (CJV) so that it can be used to inform the planning of their works relating to the relocation

DIT Decant Strategy – Moving to the Central and East Quads

viii

Appendix E