14
Dec. 14, 2004 PEP-II MAC Tonee Smit h, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan Cruz Tonee Smith

Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

1

LER BBA Quad Shunt Project

Marc RossDoug McCormick

Justin MayJanice Nelson

Jerry YockyNicole Varela

Juan CruzTonee Smith

Page 2: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

2

LER BBA Retrospective• Last fall a BBA program was initiated in

both PEP-II rings as part of a larger effort to further understand the BPM performance.– HER results were successfully implemented,

and served to validate the BBA procedure.– LER results have also been implemented, but

not fully utilized.• Reanalysis of results with fully coupled algorithm

was needed.• IR2 results (the most important) have been limited

by lack of independent quadrupole control

Page 3: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

3

LER BBA: Program goals

• To find the magnetic center of quadrupoles at optically sensitive locations in the ring. Shunts are used to vary the field in one magnet which otherwise lacks individual control.

• In IR2, there are four strings powering a total of 14 quads: QFCY1 (4), QDCY2 (4), QFCX3 (2), QDCX2 (4)

• Throughout the ring there are 37 individual QD and QF (tune) quads which have been identified as prime candidates for BBA.– These are in the arcs, immediately adjacent to

sextupoles– There are 2-5 quads per half-arc

Page 4: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

4

LER BBA: Quad Shunt History

• In 1995, switchable shunt resistor circuits were installed on each quadrupole in the SPEAR ring to facilitate beam-based alignment. They were used with great success.

• These shunts were removed as part of the SPEAR3 upgrade, and the hardware was sent to Salvage.

• The shunts were moved to B15 and proposals were made to upgrade them for use in PEP-II (all ultimately deemed too costly) .

• The shunts were taken as is to NLCTA, cleaned up, and tested on a LER Quad in Magnetic Measurements. 42/45 were found to be fully functional.

Page 5: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

5

LER BBA: Quad shunt hardware

The shunts consist of two high-power (250W) resistors in parallel on a 1” copper heat sink, controlled by an IDOM-driven FET switch.

Page 6: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

6

LER BBA: Shunt Hardware details

• Water cooling unnecessary for our application (resistors operating at ~15% rated power on a large thermal mass).

– We have tested at 150% expected operating power for ~1 hour. Max temperature reached was 55ºC without water cooling.

• Design is simple yet robust, with a low mortality rate even after months outside in Salvage.

• Minor control board modifications (snubber circuit) were made to protect the FET switches at our operating values.

• No-frills controls (+24V, on/off, and minimally-calibrated analog read back of shunt current) allowed for a straightforward cable plant.

Page 7: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

7

String  Magnet

RMag

IMag

VShunt

VShunt

RShunt

IShunt

% Shunt

P

QD(18) 0.019 300 5.7 4.2 0.45 9.3 3.11 39.2

  0.019 300 5.7 4.2 0.55 7.6 2.55 32.1

QF(19) 0.019 300 5.7 4.2 0.45 9.3 3.11 39.2

  0.019 300 5.7 4.2 0.55 7.6 2.55 32.1

•We currently have 18 shunts installed on individual QD and QF magnets throughout the ring.

•High power resistor values 0.45 and 0.55 will shunt ~3% of an individual QD or QF magnet’s current

•These have been checked out on the bench (dummy load and test stand magnet) and in the field (SCP control) and are ready for BBA when PEP turns on next year.

LER BBA: Quad shunt installation

Page 8: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

8

LER BBA: Quad shunt inventory

• We have 8 of the IR2 shunts completed, three were installed before the safety stand-down.

• Resistors available off-the-shelf (18 giving shunts with two in parallel) will shunt 1.8-1.9 % magnet current.

• Resistors for the remaining 6 boards are on order, we expect delivery this week.

• These will also be 9 shunts.• Boards are ready, just awaiting resistor delivery.• Cable plant is in place. Final checkout SCP Shunt

required.

Page 9: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

9

String  Magnet

RMag

IMag

VShunt

VShunt

RShunt

IShunt

% Shunt

P

QFCY1.1 0.18 70 12.8 11.3 9 1.3 1.79 14.1

1.2 0.18 70 12.8 11.3 9 1.3 1.79 14.1

1.3 0.18 70 12.8 11.3 9 1.3 1.79 14.1

1.4 0.18 70 12.8 11.3 9 1.3 1.79 14.1

QDCY2.1 0.18 106 19.3 17.8 9 2.0 1.87 35.3

2.2 0.18 106 19.3 17.8 9 2.0 1.87 35.3

2.3 0.18 106 19.3 17.8 9 2.0 1.87 35.3

2.4 0.18 106 19.3 17.8 9 2.0 1.87 35.3

QFCX3.1 0.18 140 25.6 24.1 9 2.7 1.91 64.3

3.2 0.18 140 25.6 24.1 9 2.7 1.91 64.3

QDCX2.1 0.18 147 26.7 25.2 9 2.8 1.91 70.6

2.2 0.18 147 26.7 25.2 9 2.8 1.91 70.6

2.3 0.18 147 26.7 25.2 9 2.8 1.91 70.6

2.4 0.18 147 26.7 25.2 9 2.8 1.91 70.6

LER BBA: IR2 Quad Shunts

Page 10: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

10

Quad shunt installation, QD/QF

• We have installed 1-2 moveable shunts per half-arc (2-4 shunts per IR/micro), based on quad(/sext) population.– The shunts hook directly across the busses of a quad with

leads that bear an uncanny resemblance to automotive jumper cables.

– Shunt blocks/enclosures are grounded to the PEP magnet rafts.

• After a round of BBA, these shunts will be moved at the next opportunity to a neighboring candidate QD or QF.

• Lather, rinse, repeat. (Two RODs to complete the QD/QF magnets)

Page 11: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

11

Quad shunt installation, IR2• We are planning to complete installation of

one shunt on each of the 14 QF/DCX/Y quads in IR2.– The shunts also hook directly across the busses

of the quads, but will not be moved from magnet to magnet.

– Modifications to the shunt covers have been made to prevent contact with electrical hazards within.• IR2 magnets are not PPS-interlocked, and the shunts

are not contained within existing magnet covers.

• We are prepared to install the eight we have pending work approval, the remaining six as soon as they’re ready.

Page 12: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

12

Quad shunt controls• To the control system, the shunts look like generic

digital devices with a corresponding analog readback.– Moveable shunts have names like: PR04 SHUNT1, 2, 3…– One digital control (IDOM bit) per shunt (command

ON/OFF)– One status (ON/OFF) reflecting that IDOM bit– One ASTS value reflecting current through the shunt

resistors• Not presently calibrated well enough to tell more than whether

the shunt is shunting or not, really.

– We’ve requested that the shunt on/off status be on the SDS CUD under LGPS with ON being RED.

Page 13: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

13

SCP Panel & Analog display

Page 14: Dec. 14, 2004PEP-II MAC Tonee Smith, ILC 1 LER BBA Quad Shunt Project Marc Ross Doug McCormick Justin May Janice Nelson Jerry Yocky Nicole Varela Juan

Dec. 14, 2004 PEP-II MAC Tonee Smith, ILC

14

How it all works• We are creating a flat file to hold the

information of which shunt is on which quad, with a list at the bottom of which shunts can go to which quads. – This file will live on the VAX with an entry in e-log

(which e-log to be determined) with its location.– The person who physically moves the shunts to new

magnets is required to change this file.• For data acquisition, a button macro will prompt

which magnet or which shunt you wish to do BBA on, then load up a CRR and take data.

• Data to be analyzed offline by the Woodley/Wolski coupled analysis matlab code.