Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
November 2014
Deadline VI Appendix 7 Description of Export Cable Protection Parameters
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 © 2014 Forewind Page ii
Document Title Dogger Bank Teesside A & B
Deadline VI Appendix 7
Description of Export Cable Protection Parameters
Forewind Document Reference F-EXL-DVI-002 Appendix 7
Issue Number 1
Date November 2014
Drafted by Edward Ross
Approved by Mark Legerton
Date / initials approval ML 19-Nov-2014
DOGGER BANK TEESSIDE A & B
F-EXL-DV-003 Appendix 8 © 2014 Forewind Page iii
Contents
1. Introduction ................................................................................................................... 1
1.1. Introduction ......................................................................................................... 1
1.2. Remedial Cable Protection ................................................................................. 1
2. Export Cable Indicative Rock Berm Design .................................................................. 3
2.1. Rock Cable Protection Design Considerations ................................................... 3
2.2. Rock Berm Design Considerations ..................................................................... 3
2.3. Indicative Rock Berm Design .............................................................................. 4
3. Export Route Remedial Protection Quantities ............................................................... 6
3.1. Export Cable Corridor Burial Feasibility .............................................................. 6
3.2. Remedial Cable Protection Quantity ................................................................... 9
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 1 © 2014 Forewind
1. Introduction
1.1. Introduction
1.1.1. In the Issue Specific Hearing of 11-12 November 2014, the Examining Authority
requested more detail from Forewind on how the worst case parameters were
developed for the use of remedial cable protection for the High Voltage Direct
Current (HVDC) export cables from the offshore converter station to the cable
landfall on the Teesside coast. This request was further referenced in the
Hearing Action Points List 2 – point 2.10. Forewind’s considered response to
this specific Action Point is detailed in this document.
1.2. Remedial Cable Protection
1.2.1. Burial is the preferred protection technique for the Dogger Bank Teesside A & B
HVDC export cables, as it typically provides the best protection, at the lowest
cost, in the shortest time. The offshore cables will, therefore, be buried wherever
it is feasible and economic to do so, with additional or alternative remedial cable
protection measures applied only if necessary.
1.2.2. Typically, the most common drivers for the installation of remedial cable
protection are adverse geotechnical conditions and the proximity of other
structures or assets. The presence of hard rock or other challenging seabed
conditions, such as rapidly changing sediment strata types or buried boulders,
can prohibit the burial of cables. Additionally, due to safety considerations, it is
not always possible to operate cable burial equipment in close proximity to
offshore structures. As a result, some form of remedial cable protection will be
required in the vicinity of the structure. The remedial cable protection method
and detailed design chosen will reflect the level of risk to which the cable is
exposed, e.g. the expected levels of scouring, seabed mobility, fishing activity,
and anchoring.
1.2.3. The Dogger Bank Teesside A & B application describes a range of potential
remedial cable protection parameters and technology options. Typical remedial
cable protection measures include one or a combination of the following options:
Rock or gravel burial;
Concrete mattresses;
Flow energy dissipation devices;
Protective aprons or coverings and;
Bagged solutions.
1.2.4. Section 3.10 (Remedial Cable Protection) of Chapter 5 Project Description of the
ES (ref 6.5) provides a fuller description of the various forms of remedial cable
protection types.
1.2.5. Protection of the HVDC export cables by rock burial (also known as rock
placement or rock dumping) has been identified as the worst case remedial
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 2 © 2014 Forewind
cable protection for seabed footprint due to the width of rock berm that may be
required. The methodology used in developing this worst case based upon rock
burial is described within the following sections.
Figure 1 Illustrative example of rock berm protection for unburied export cables
1.2.6. Rock burial is one of most technically robust and commonly used remedial cable
protection techniques and involves installation of a rock ‘berm’ over the cable.
Shown in the figure above is the indicative rock berm profile used for calculating
the worst case parameters contained within the ES. Rock protection can be
deployed from specialist ships or barges using techniques such as side casting,
where rocks are pushed overboard with lateral hydraulic slides and discharged
onto the seabed. Alternatives include fall-pipe systems; where rocks are fed into
a funnel at the top of a fall-pipe and discharged at a controlled rate as guided by
sensors at the base of the pipe – which can also be remotely steerable.
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 3 © 2014 Forewind
2. Export Cable Indicative Rock Berm Design
2.1. Rock Cable Protection Design Considerations
2.1.1. As discussed in the response to ExA [1] 6.12, the HVDC export cables have
been identified as key risk areas for the Dogger Bank Teesside A & B projects;
the HVDC cables are a key long-lead component, suitable installation and repair
vessels are a global supply chain bottleneck and the installed cables are a
single point of failure for the whole project, with both cables required to be fully
operational for any power to be exported.
2.1.2. In developing the design of a rock berm consideration has to be given to the
hazards posed to the cables. These can include environmental hazards, such as
wave and current exerting hydraulic forces on the objects on the seabed, and
manmade hazards such as dropped objects, fishing, a vessel negligently
dragging an anchor whilst underway, or a drifting anchored vessel (due to bad
weather or power loss). An analysis undertaken by BT of the causes of
submarine telecommunication faults around UK waters between 2007 and 2010
identified 39% of faults resulted from fishing activities and 36% resulted from
anchors. A copy of this study has been provided in response to ExQ [2] 3.3.
2.1.3. Whilst the BT study identified that fishing activities resulted in slightly more of the
submarine telecommunication faults, Forewind developed its rock berm consent
envelope for the HVDC export cable based upon interaction with anchors. Any
form of interaction between cables an anchor is more likely to lead to a cable
failure, due to the high amount of forces caused by a dropped or dragged
anchor. There is also a possibility that in a single incident a vessel, whilst
underway, could drag an anchor across the HVDC export cables for both the
Dogger Bank Teesside A & B projects. The loss of both projects at the same
time could have an impact on the UK transmission network.
2.2. Rock Berm Design Considerations
2.2.1. Given the extremely low probability of an anchor being dropped directly on top of
a section of cable, the common industry practice is for rock berms to be
designed assuming the anchor will be dragged over it. In the event of a dragging
anchor, a rock berm should initiate an outbalancing force on the anchor and
anchor chain, resulting in breakout of the anchor, allowing it to travel over the
berm.
2.2.2. In addition to the interaction mechanism between the anchor and the rock berm
the following factors would also be considered:
Anchor Type (Standard, HHP, etc.);
Anchor Dimensions (fluke length, shank length, etc.);
Anchor penetration depth;
Seabed Characteristics; and
Materials used in the construction of the rock berm
2.2.3. It is not possible to design a rock berm that is optimal for every possible
combination of the factors listed above. Instead, a risk based approach,
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 4 © 2014 Forewind
considering the factors, would be undertaken during the detailed design phases
of the projects. This work would be informed by further geotechnical surveys
(cone penetration tests, boreholes, etc.), conducted along the cable corridors to
complement and ground-truth the geophysical survey data collected so far by
Forewind and by further work looking at the marine traffic in the vicinity of the
HVDC export cable corridor. It is likely that the profile of the rock berm will vary
along the HVDC export cable corridor to take account of local conditions. For
example, areas in which hard seabed conditions are present the rock berm may
be reduced due to the shallower anchor penetration depth. Conversely the rock
berm may be bigger in areas where larger vessels frequently operate due to the
larger dimensions of their associated anchors.
2.3. Indicative Rock Berm Design
2.3.1. For the ES, Forewind developed the indicative rock berm profile, shown
previously, for the HVDC export cables to allow a maximum footprint and
volume of remedial cable protection to be assessed. A typical 3 tonne stockless
anchor, shown in the figure below, was used as the basis for this rock berm
design. This anchor size is widely used and is commonly carried by ferries and
medium sized commercial vessels.
Figure 2 Dimensions of a typical 3 tonne anchor
2.3.2. At this stage it is not possible to perform detailed design calculations for the rock
berm, as there is insufficient information available. However, a number of broad
guidelines have been developed by marine contractors to provide preliminary
dimensions when designing a rock berm. The equations within guidelines,
shown below, allowed Forewind to develop an indicative rock berm profile for
the 3 tonne anchor.
𝐵𝑡𝑜𝑝 = 2 × 𝑆ℎ𝑎𝑛𝑘 𝐿𝑒𝑛𝑔𝑡ℎ
𝐵𝑏𝑜𝑡𝑡𝑜𝑚 = 𝑂𝐷𝑐𝑎𝑏𝑙𝑒 + 10 × 𝐹𝑙𝑢𝑘𝑒 𝐿𝑒𝑛𝑔𝑡ℎ
2.3.3. Where by:
Btop is the breadth at the top of the rock berm [m]
Bbottom is the breadth at the base of the rock berm [m]
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 5 © 2014 Forewind
ODcable is the outer diameter of the cable [m]
2.3.4. Using these guidelines the indicative breadth at the base of the rock berm was
estimated to be 15.2m.
2.3.5. During the detailed design phase of each project further engineering analysis,
including model tests, would be undertaken to identify the suitable rock berm
dimensions for the specific location and the associated risks identified.
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 6 © 2014 Forewind
3. Export Route Remedial Protection Quantities
3.1. Export Cable Corridor Burial Feasibility
3.1.1. In addition to developing an indicative profile for rock berms placed over the
HVDC export cables, Forewind performed a burial assessment along the export
cable corridor. Whilst the final selection of cable burial and remedial protection
methods will be made during the detailed design phases of the Dogger Bank
Teesside A & B projects, and require additional geotechnical surveys (cone
penetration tests, boreholes, etc.), to have been conducted along the cable
corridors, the geophysical surveys undertaken by Forewind were sufficient to
allow a feasibility study to be undertaken for the purposes of informing the ES.
This feasibility study allowed Forewind to identify those areas along the export
cable corridor potentially with problematic conditions, such as hard rock, where
burial may not be feasible and some form of remedial protection will be required.
3.1.2. The Dogger Bank Teesside A & B export cable corridor seabed is characterised
by a combination of bedrock outcrops, gravel, sand and clays. This is illustrated
within the map supplied in response to ExQ [2] 3.1 part 1 which shows the
surface geology for Dogger Bank Teesside A & B export cable corridor. The
rock outcrops primarily occur towards the landwards portion of the cable route,
whilst clays primarily occur within the Dogger Bank zone itself. The presence of
boulders is generally associated with the bedrock outcrops and clays.
3.1.3. The subsurface geology, strata occurring at depths of greater than 30cm, will
exert a significant influence on the installation of the HVDC export cables.
Throughout the export cable corridor it is anticipated there will be sections of
sub-cropping rock that will make cable burial more challenging and may require
the use of remedial cable protection. Shown in the figures below is a section of
export cable corridor from the map supplied with ExQ [2] 3.1 part 1 and the
same section overlain with the anticipated subsurface geology.
Figure 2 HVDC export cable corridor seabed surface geology, approximately 27 to 47km from landfall.
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 7 © 2014 Forewind
Figure 3 HVDC export cable corridor seabed subsurface geology, approximately 27 to 47km from landfall.
3.1.4. The anticipated depth of the sub-cropping bedrock varies along the export cable
corridor. Where the sub-cropping bedrock occurs at depths exceeding 3m, it is
considered to have no impact on cable installation as this is deeper than the
anticipated maximum cable burial depth. The target cable burial depth will be
specified during the detailed design phase of the projects and will likely vary
along the route based on consideration of a number of factors, including;
seabed geology, physical processes and risk posed by and to other marine
users.
3.1.5. The feasibility study identified that approximately 30% of the Dogger Bank
Teesside A and 31% of the Dogger Bank Teesside B cable corridor may
encounter challenging geotechnical conditions. These conditions are primarily
hard sediments encompassing areas of outcropping and sub-cropping rock and
to a lesser extent stiff clays. These hard sediments do not rule out cable burial
but some installation techniques, described within Section 3.9 (Offshore Cable
Installation and Removal) of Chapter 5 of the ES (ref 6.5), will not be suitable.
For example, jetting, injecting high pressurised water into the seabed to fluidise
a trench, is only suitable for sands and low density clays and would be incapable
of installing a cable in the presence of rock. However, mechanical trenching
installation methods are typically designed and utilised for installing cables
within harder sediment types.
3.1.6. To generate a worst case for the ES, Forewind has assumed that it would be
necessary to use remedial cable protection in all areas of the export cable route
identified as being potentially challenging for cable installation. Whilst this is a
conservative approach, given the potential to overcome these challenges with
the selection of installation tools, it was felt appropriate for the purposes of the
ES. A conservative approach was taken as at this stage only geophysical data
was available. Until additional geotechnical surveys are undertaken (cone
penetration tests, boreholes, etc.) the precise physical characteristics of the soils
cannot be known, which s is critical to understanding which burial or protection
techniques will be suitable
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 8 © 2014 Forewind
3.1.7. Forewind also considers that this level of conservatism is appropriate as it was
not possible for the feasibility study to access all the possible constraints on
cable installation. The requirement for remedial cable protection is most
commonly a result of adverse geotechnical conditions and the proximity of other
structures or assets, however, other factors such as seabed topography, current
strength, seabed mobility, etc. can all constrain cable burial.
3.1.8. For example, the seabed topography can have a significant effect on cable
burial, with steeper slopes being particularly challenging or impossible for some
installation tools. In general tools mounted on tracked ROV’s are incapable of
working on slopes steeper than 12° to 15°. The stability of the slope is also a
consideration, as tracked ROV’s require sufficient traction for their tools to
operate effectively. It may be possible to microsite cable burial around areas of
difficult topography or it may be necessary to use some form of remedial cable
protection.
3.1.9. The strategy for challenging areas of seabed topography and other cable
installation constraints will be defined during the detailed design phases of the
Dogger Bank Teesside A & B projects.
DOGGER BANK TEESSIDE A & B
F-EXL-DVI-002 Appendix 7 Page 9 © 2014 Forewind
3.2. Remedial Cable Protection Quantity
3.2.1. Using the parameters discussed in the previous sections it was possible to
develop a worst case usage of remedial cable protection for the HVDC export
cables to be assessed as part of the ES using the following assumptions:
Up to 30% of the Teesside A HVDC export cables may require remedial
cable protection;
Up to 31% of the Teesside A HVDC export cables may require remedial
cable protection;
Rock burial is the chosen method of remedial cable protection;
An indicative breadth of 15.2m for the rock berm; and
An indicative cross-sectional area of 14.8m2 for the rock berm.
3.2.2. Based upon these assumptions worst case footprints and volumes of remedial
cable protection were produced for each of the Dogger Bank Teesside A & B
projects. These values are surmised in the table below.
Table 1 HVDC export cables indicative remedial cable protection values.
Parameter Teesside Project A Teesside Project B
Maximum total offshore HVDC export cable length
(from offshore platform to landfall) per project (km) 573.2 484.4
Maximum export cable protection footprint area per
project (km2)
2.57 2.31
Maximum export cable protection volume per project
(m3)
2,496,785 2,242,473
3.2.3. In addition to the use of remedial cable protection for unburied sections of the
HVDC export cable, similar methods and materials may be used when it is
necessary to cross existing pipelines and submarine telecommunication cables.
At a crossing point it will be necessary to bring the HVDC export cable to the
surface of the seabed so it can be laid across the existing asset. Section 3.10
(Offshore Cable & Pipeline Crossings) of Chapter 5 of the ES (ref 6.5) provides
further details on the requirements for cable crossings.