David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20081

Far Experimental Hall - Hutches

Scope

Budget

Schedule

Page 2: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20082

SLAC Site PlanSLAC Main Gate

MMF

Research Yard

Pep Ring Road

LCLS General Work Boundary

Sector 25

Sector 20 Upstream

B028 B751

FEH

Page 3: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20083

FEH Location

FEHX-RAY TUNNEL

ACCESS TUNNEL

Page 4: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20084

Page 5: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20085

Far Hall rebar latticeTunnel construction complete 25 April 2008

Page 6: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20086

Far Experimental Hall south ribInstalling re-bar in the Far Experimental Hall

Page 7: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20087

ScopeCavern space is well defined as part of current civil construction preformed by TCCo

Scheduled Beneficial Occupancy date is Aug 08Issue For Construction (IFC) set had sufficient spatial and utility capacities to support future hutches Draft requirements of Room Data Sheets (RDS) have been provided for hutchesHeld meeting 12/07 to discuss further hutch program requirements

Data received to date is at early stage of determining final scope to support scientific mission needs

Need to advance quickly

Page 8: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20088

Scope Per IFC

RATED WALL/RADITION BARRIER

ACCESS TUNNEL

Denotes hutches (not a part of current construction)

Page 9: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 20089

Recent FEH Changes

Monolithic single pour floor for entire FEH and to include 50 meter at the east end of X-Ray tunnel

Relocation of wall (fire rated, radiation barrier) to inside X-Ray tunnel

Relocation of pipes and ducting for exhaust of X-Ray tunnel

Page 10: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200810

FEH Location

FEHX-RAY TUNNEL

ACCESS TUNNEL

RATED WALL RADIATION BARRIER

Page 11: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200811

Hutch #4 & #5 Layout-Aug 07

Hutch #4Hutch #6?Hutch #5

Denotes ancillary space for hutches #4

and #5

Page 12: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200812

WBS for FEH Hutches has a TPC of $2.82M EDI at $.24M

Independent cost estimate

Title I/II design

Construction at $2.58MTitle III

Budget

Construction cost estimate as provided by JE, based on Room Data Sheets, Rev 0 include the following:

Escalation (thru July 09), sales tax, below grade factor (difficulty factor), oh&p, bonding, general conditions, hutch doors, 1/8” lead lined walls and ceilings, 1 ton hoist, mechanical and electrical

Page 13: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200813

FEH Hutches 4 and 5Title I Design (present – end of 6/08)Title II

Procurement (7/08) Design (8/08 – 11/08)

Title III Procurement (11/08 – 12/08)Construction (1/09 – 7/09)Construction Complete July 09

Beneficial Occupancy July 09Project Complete Aug 09

Schedule

Page 14: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200814

Next 6 MonthsComplete Title I effort (in house resources) 6/08Procurement activities for Title II 7/08 Commence Title II design 8/08Independent cost estimate 10/08 Complete Title II 11/08Procurement activities for Construction 11/08Construction start 1/09

Page 15: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200815

Summary

Cavern support space as currently being constructed is well defined

Scheduled date for Beneficial Occupancy Aug 08 is reasonable

Hutch requirements need to be solidified no later than June 30, 08

Rad Physics requirements play major role

Need liaison between CF and LUSI

Page 16: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200816

End of presentation

Page 17: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200817

Scope in TCCo Contract

PowerLighting and power FEH cavernCapacity for two independent panels in each hutchCable trays at perimeter of FEHWelding outlet, 480 volts, 3 ph.

MechanicalFEH cavern: conditioned spaceRestrooms including showers

Page 18: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200818

MechanicalDrainage (3 sump pumps inc. access tunnel) and SW piping to sanitary waste system through FEH access tunnel

Outside air capacity for three future hutches

Compressed air (from CUP) south wall (stub outs w/valves)

Process cooling water (PCW) for Hutches and work area- 68°F, 10GPM/ea

Scope in TCCo Contract

Page 19: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200819

Utility Yard at Entrance AT

FEH ACCESS TUNNELFEH ACCESS TUNNEL

TRANSFORMER

EXHAUST FANS

CROSS SECTION AT THE ENTRANCE OF ACCESS TUNNEL

Page 20: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200820

Room Data Sheets (RDS)

Preliminary “draft” for hutches #4 and 5Requirements for:

Power (clean and dirty)

HVAC, 72 °F, ± 1°F, RH 45% ± 10%

Exhaust

1 ton crane

Fire protection/fire alarm system

Network and phone systems

Cable trays and penetrations thru walls

Lead lined walls

Page 21: David Saenz Far Experimental Hall - Hutchessaenzd@slac.stanford.edu June 17, 2008 1 Far Experimental Hall - Hutches Scope Budget Schedule

David Saenz

Far Experimental Hall - Hutches [email protected]

June 17, 200821

Hutch #4 Utilities Requirements