View
214
Download
0
Embed Size (px)
Citation preview
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20081
Far Experimental Hall - Hutches
Scope
Budget
Schedule
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20082
SLAC Site PlanSLAC Main Gate
MMF
Research Yard
Pep Ring Road
LCLS General Work Boundary
Sector 25
Sector 20 Upstream
B028 B751
FEH
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20083
FEH Location
FEHX-RAY TUNNEL
ACCESS TUNNEL
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20085
Far Hall rebar latticeTunnel construction complete 25 April 2008
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20086
Far Experimental Hall south ribInstalling re-bar in the Far Experimental Hall
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20087
ScopeCavern space is well defined as part of current civil construction preformed by TCCo
Scheduled Beneficial Occupancy date is Aug 08Issue For Construction (IFC) set had sufficient spatial and utility capacities to support future hutches Draft requirements of Room Data Sheets (RDS) have been provided for hutchesHeld meeting 12/07 to discuss further hutch program requirements
Data received to date is at early stage of determining final scope to support scientific mission needs
Need to advance quickly
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20088
Scope Per IFC
RATED WALL/RADITION BARRIER
ACCESS TUNNEL
Denotes hutches (not a part of current construction)
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 20089
Recent FEH Changes
Monolithic single pour floor for entire FEH and to include 50 meter at the east end of X-Ray tunnel
Relocation of wall (fire rated, radiation barrier) to inside X-Ray tunnel
Relocation of pipes and ducting for exhaust of X-Ray tunnel
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200810
FEH Location
FEHX-RAY TUNNEL
ACCESS TUNNEL
RATED WALL RADIATION BARRIER
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200811
Hutch #4 & #5 Layout-Aug 07
Hutch #4Hutch #6?Hutch #5
Denotes ancillary space for hutches #4
and #5
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200812
WBS for FEH Hutches has a TPC of $2.82M EDI at $.24M
Independent cost estimate
Title I/II design
Construction at $2.58MTitle III
Budget
Construction cost estimate as provided by JE, based on Room Data Sheets, Rev 0 include the following:
Escalation (thru July 09), sales tax, below grade factor (difficulty factor), oh&p, bonding, general conditions, hutch doors, 1/8” lead lined walls and ceilings, 1 ton hoist, mechanical and electrical
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200813
FEH Hutches 4 and 5Title I Design (present – end of 6/08)Title II
Procurement (7/08) Design (8/08 – 11/08)
Title III Procurement (11/08 – 12/08)Construction (1/09 – 7/09)Construction Complete July 09
Beneficial Occupancy July 09Project Complete Aug 09
Schedule
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200814
Next 6 MonthsComplete Title I effort (in house resources) 6/08Procurement activities for Title II 7/08 Commence Title II design 8/08Independent cost estimate 10/08 Complete Title II 11/08Procurement activities for Construction 11/08Construction start 1/09
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200815
Summary
Cavern support space as currently being constructed is well defined
Scheduled date for Beneficial Occupancy Aug 08 is reasonable
Hutch requirements need to be solidified no later than June 30, 08
Rad Physics requirements play major role
Need liaison between CF and LUSI
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200817
Scope in TCCo Contract
PowerLighting and power FEH cavernCapacity for two independent panels in each hutchCable trays at perimeter of FEHWelding outlet, 480 volts, 3 ph.
MechanicalFEH cavern: conditioned spaceRestrooms including showers
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200818
MechanicalDrainage (3 sump pumps inc. access tunnel) and SW piping to sanitary waste system through FEH access tunnel
Outside air capacity for three future hutches
Compressed air (from CUP) south wall (stub outs w/valves)
Process cooling water (PCW) for Hutches and work area- 68°F, 10GPM/ea
Scope in TCCo Contract
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200819
Utility Yard at Entrance AT
FEH ACCESS TUNNELFEH ACCESS TUNNEL
TRANSFORMER
EXHAUST FANS
CROSS SECTION AT THE ENTRANCE OF ACCESS TUNNEL
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200820
Room Data Sheets (RDS)
Preliminary “draft” for hutches #4 and 5Requirements for:
Power (clean and dirty)
HVAC, 72 °F, ± 1°F, RH 45% ± 10%
Exhaust
1 ton crane
Fire protection/fire alarm system
Network and phone systems
Cable trays and penetrations thru walls
Lead lined walls
David Saenz
Far Experimental Hall - Hutches [email protected]
June 17, 200821
Hutch #4 Utilities Requirements