Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
1
Date of Board: 24th April 2019 Title of Report:
Innovation & Improvement Quarterly Report
Purpose of Report
Quarterly update on projects and innovation within the Trust
Recommendation:
The report is presented for information.
Written by: Mike Yarde Presented by:
Paul Cracknell
Relevant Trust Objective or Quality Goal:
Improving quality/Securing our future/enabling our staff/Quality
Previous consideration by Committee or Executive:
Content informed by Trust Portfolio Programme Board and a more detailed paper discussed at Finance and Performance Committee
Appendices:
Implications considered for: Compliance with NHS Constitution, CQC registration, legal issues, equality & diversity, environment, stakeholders, staff, patients & public, risks & benefits, value for money, and governance. Executive summary This is the quarterly report that considers innovations within the Trust and reviews the three categories of projects managed by the Projects & Investment team:
• CIP
• Capital Programme
• Service Development projects The report also updates on the Projects and Investment team development and achievements.
ENCLOSURE: N
Innovation & Improvement Quarterly
Report
Wednesday 24 April 2019
Presented by Paul Cracknell
Deputy Chief Executive Officer
Looking after you locally
Contents
1.0 Summary
2.0 Project & Investment Update 2.1 Team Update
2.2 Ideas Generation
3.0 Programme Updates 3.1 CIP Update
3.2 Capital Programme Update
3.3 Service Development Update
4.0 Gateway 4.1 Gateway Update
CIP Programme
Weekly progress meetings are in place to maintain the momentum of CIP challenge and delivery. Initiatives currently underway are:
• Business unit CIP targets & detailed budget review (led by Finance)
There are 118 cost centres with a total underspend (i.e. possible recurrent CIP) of £4.98m. These are all to be investigated and
a comment completed for every budget line to explain the variance and identify the amount able to be realised as recurrent
CIP. This is to be completed within three weeks (03/05/19)
• Benchmarking Data
Projects, with support from Performance & Information, are finalising some key benchmarking data to enable localities to
identify where efficiencies could provide CIP opportunities. The Projects team will support localities in identifying changes and
CIP potential
Workforce
The Workforce Recovery Programme Board, led by our CEO, has achieved the desired outcome and has now move to a BAU
Programme Board. The project currently has an amber RAG status due to some missed milestones. A recovery plan for milestones is
planned. Currently the apprenticeship recruitment is on schedule.
Capital Programme
• The 2018-19 capital programme was completed £18K under budget, realising a spend against budget of 99.7%. There was less
spend in the final two months than previous years. Difficulties in completing some Estates projects at year end contributed to the
underspend
• The 2019-20 programme has been set at £2.4M plus an additional £200K of charitable projects.
1.0 Summary Overview
Projects Team Vision: The Vision for the Project and Investment team has now been agreed by all team members and the Trust
Portfolio Board.
REACH Awards: Projects and Investment team members were nominated for multiple awards and the following teams were finalists
and Runners up during the award event on Thursday 7 March 2019.
Winners in the Innovation Awards for Business Services Runners Up – Team of the Year Business services
Mobile App Team
2.0 Enabling Our People
2.1 Projects Team Update
Health Education England (HEE) – Project Management Competency Framework:
The Trust were approached to be involved in a new project by HEE, who are working on
developing a Project Management Competency Levels Framework. This project was
requested by central government, who observed that the standards of project management
and change expertise, generally within the NHS, were not at a level to manage the scale of
change required.
NCHC were approached to take part in developing the project, based on our implementation
of the Association of Project Management (APM) Competency Framework. HEE are looking
to set up a three level grade system similar to the one we have already implemented, so are using our experience to help
to develop the national standard.
HEE are also developing an online training course for clinicians who
switch into project management roles. The team asked if we could help them with
some video content for the training videos. Suzie Mallett, our Project Manager
who switched from a who changed her nursing career into projects, talked about her experience of
making the change from clinician to Project Manager, and the value that experiencing both of the
roles bring to her work.
Tarandeep Kaur, Capital Programme Manager, talked about her experience of
project management in other sectors, as well as her personal experience of
coming from India and joining the NHS.
2.0 Enabling Our People
2.1 ProjectsTeam Update
The following action plan has been implemented by the Projects Team:
• Bullying & HarassmentEveryone encouraged to share details of bullying and harassment - completeSuzie Mallet is a buddie and talked to the team about the role - completeSimon Bailey has been trained to be a Freedom to Speak Up rep - complete
• Clarity Team Roles & StructurePublish agreed parts of methodology - completeComplete methodology – due end MayReview methodology – due three months after finalisation
• FeedbackSenior Management Team to do 360 degree appraisals – two booked, one person on longterm sick and one on maternity leaveUse standard 1:1 form for everyone with headers for feedback & ideas - form agreedEncourage feedback to managers/team meetings on what is good/bad – happening
The QCP team are aiming to hold 3 cohorts of QCP in 2019/20, the first one to be held in May. We are exploring the possibility of holding future programmes with our STP colleagues, and are currently working with IC24 to explore this for the September 2019 cohort.
Business Analysts are now being involved in the projects to ensure that good ideas can be transferred to other areas of the Trust.
2.0 Enabling Our People
2.3 QCP
2.2 Projects Short Staff Survey
PROGRAMME STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
A GGAR AA
3.0 Programme Update - Secure the Future
This section details the current programme of CIP projects in the portfolio
3.1 CIP Programme Update
Overall Portfolio
CIP delivery
The Projects & Investment team will continue to attend Locality meetings to help use benchmarking data develop local CIP
plans.
Time:
The revised Workforce Plan is now on red status due mainly to slippage on key milestones. New resource has been added to this
project during the Programme Manager sickness absence. Completing outstanding milestones is being as the priority to bring the
project back to green.
Capital:
The Capital Programme was delivered £18K under budget, which represents 0.5% of the total budget. The variance was largely
due to variances within the Estates programme which had to be tightly controlled during month 12 due to a potential overspend of
budget of upto £100K. This was a good result for the Capital Projects team. The programme was closely managed and resulted
in less end of year spend than previous years.
Cost:
Resource and operating costs remain within budget. Recruitment, within budget, ongoing.
Quality:
No adverse impact has been reported for patient safety, patient experience and effectiveness.
Benefits:
A plan to reduce this years CIP planning gap of £800K is being actively pursued.
Risks:
Workforce Transition Plans should have been in delivery from 1st April 2018. The lack of completion of some of these is resulting
in delays to CIP identification and achievement and also preventing the closure of the Empowering Our people programme. This
causes a risk to achieving the required outcomes of the Workforce Plan as well as CIP targets. Target dates for completion of
outstanding Workforce Schemes have been agreed by EDT
PROGRAMME STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
A AAn/a GG
A GGAG AG
3.0 Programme Update - Secure the Future
This section details the current programme of CIP projects in the portfolio
3.1 CIP Programme Update
Workforce Development
Health & Care Strategy
CIP
Self-Care: (p/l)
19/20 - £2580K
Clinic Des/Mgt(p/l)
19/20 - £25K
• Overall project status is amber due to milestone slippage.
• New meeting structure commenced 5th April 2019. New sponsor Laura Clear. Accountable owner review meetings established.
• Locality feedback for clinical education support is positive overall. No feedback received from clinical education leads.
• KPI review for 2018/19 ongoing including manual audit of current compliance for spans of control. Current structure charts
being sourced and manual comparison undertaken mid-April. KPIs for 2019/20 agreed. final template presented at May Board.
• Milestones being managed to bring project back to green
• Health & Care Strategy update included in March Exchange
• Health Coaching: Awaiting confirmation of funding and commencement of recruitment process for HC lead role to define
handover to BAU/project closure date
• Self-Care - Submit NHS England application for LEAD site status, now decision has been made – All three pilot phases now
delayed/missed
• Wound Care (3D) – Wound Cameras delivered - Staff identified for training - Supporting eLearning material drafted
• Clinic Design & Mgt: Kick off meeting with project group held - Updated analysis of clinic data completed - Outline business
case finalised for April TPB
A
PROGRAMME STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
A GGGG AG
This section details the current programme of CIP projects in the portfolio
3.1 CIP Programme Update
Palliative Care
CIP
EOL Pathway Redesign:
18/19 - £39K
19/20 - £9K
Overall – the Palliative/End of Life Care Programme is amber.
For Portfolio Report – Palliative/EoL Care Change Programme Highlights
Leadership – Resources – RED . Unable to recruit to consultant post West impacting their CQC result. Exec level discussions and
action plan implemented
NCHC Workstreams - Key Points
Evidence & information – GREEN– West CCG and NCHC local incentive scheme commenced re Care Home education
Individualised Plans of Care – AMBER – Following CQC feedback at NNUH IPoC reviewed and changed. To implement the revised
document across NCHC
Co-design –GREEN– Hospice at Home live in all areas as of 1st November. Discussions with CCG about demand and capacity/skill mix
of team.
Marie Curie –GREEN – Norwich and North Marie Curie staff have been TUPE’d across and consultation underway. West Marie Curie
budget is being reviewed as significant overspend. To bring this budget back on track.
PBH (GREEN) – Terms of Reference for stakeholder development meeting to be shared with EDT.
3.0 Programme Update - Secure the Future
PROGRAMME STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
A GGAR GA
A AGAR AG
3.0 Programme Update - Secure the Future
This section details the current programme of CIP projects in the portfolio
3.1 CIP Programme Update
Community Gateway
CIP
Patient Check-In:
19/20 - £101K
eScheduling: (p/l)
19/20 - £605K
• CAST/Locality Admin Project: CAST & Locality Admin project scope reviewed and amended with project lead. Amendments
to be made and approved by project sponsor by 12/04/19.
• Patient Check-In: Project to close-down asap once final 2 devices deployed, supported into BAU by IM&T - CIP meeting
scheduled for 03/04/19 with programme manager and project sponsor for financial benefits and potential change control
discussion. CIP unlikely to be achieved by this project – currently being reviewed
• E-Scheduling: Risk has reduced to AMBER following improvements to system performance - Benefit remains at AMBER due
to the lack of real-time interface between SystmOne and eCommunity . Meeting arranged for 3rd April with TPP/Allocate/NCHC
to clarify API interface requirements and agree next steps/timeline.
• SafeCare – Clinical Lead for each unit would be required in order to develop, test and implement acuity model
Empowering ourPeople Programme
• Amber due to milestones being complete or transferred to DTWP Project Plan
• Risks have either closed or transferred.
• Closure report being prepared and closure meeting as soon as the last workforce transition plan approved EDT
PROGRAMME STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
A GGAA GG
A AGAA R A
3.0 Programme Update - Secure the Future
This section details the current programme of CIP projects in the portfolio
3.1 CIP Programme Update
Estates & Facilities
CIP
Car Parking:
18/19 - £42K
19/20 - £24K
Staff Travel Review:
19/20 - £87K
Hybrid Mail: (p/l)
19/20 - £58K
Space Utilisation: Dereham: (p/l)
19/20 - £392K
Adelaide St: (p/l)
19/20 - £98K
King St – Dental: (p/l)
19/20 - £TBC
CYPASS
CIP
Dental consumables: (p/l)
19/20 - £25K
• Car Parking – Consultation Outcome Document has been circulated. EDT decision to now implement charges at Kelling
Hospital, this will effect CIP and a change control will be required
• Estates Workforce – Options analysis is currently being reviewed between Estates and Facilities and Procurement Dept for
Hard/Soft FM tender.
• Travel Review – Pool vehicles currently being reviewed, prior to re-procurement. Policy is being reviewed, as current scheme
not achieving value for money. Draft spec. written. It is being reviewed by procurement, however due to availability this has not
been reviewed by the end of March as planned. Once we have a timeline in place, a change control document will be required
as BUO fleet is not currently in scope of this project.
• Hybrid Mail– Delay in workbook due to finance availability. However as we have not yet gone to tender due to procurement
availability the costs in the workbook would only be indicative until a supplier has been selected.
• Overarching programme of work created for CYPASS showing all ongoing change requirements, both internally &
externally managed – reviewed and signed off by AD and Service Leads.
• Stroke Pathway Change Control being submitted to April TPB
• Seconded staff member returned to substantive role, resulting in a reduction of PM capacity
• Overall RAG status has improved to Amber, based on the collective position of the individual projects
PROGRAMME STATUS
RAG Status
Overall CIP Time Cost Quality Benefit Risks
A GGA AG
3.0 Programme Update - Secure the Future
The section monitors the capital programme for 2018-19.
Overall Programme
Capital - £3.7M
Unallocated -
£7K
Pending ATIRs
- £0K
Programme
Administration
- £200K
Overall the Trust Capital programme for FY2018/19 is mostly delivered and complete expect a couple of projects which have
been moved into Q1 FY2019/20. These projects are being monitored by relevant programmes closely to ensure full delivery prior
to closure. The Capital spend for FY2018/19 is within acceptable tolerance.
IT
• All sites now have new equipment installed, and been migrated to HSCN. Digital Inpatients has implemented as supported both
Alder and Foxley ward, with North Walsham going live in April 19. All equipment for Mobile working rollout, Digital Inpatients and
cyber security were received within the 18/19 FY. A TMT presentation on the overall rollout of Purchasing and Inventory
management and benefits realised is planned for April-2019. Windows 10 build delayed to pick up NHS Digital technical
approach, IM&T are investigating and testing a robust and secure build. Resourcing for FY 19/20 projects is now complete for
most projects. Teams assurances provided to and approved by IG, IAO’s and SIRO. Drop-in and training sessions held across
all localities. Rollout now in progress, all sites to be enabled by April 19
Estates
• Staff Wellbeing and PLACE works projects are ongoing. The works completed by suppliers are being challenged as of poor
quality and conversations ongoing to bring them to the standard expected by the Trust. Procurement team providing support
with this. Simpson centre and the Squirrels projects have moved into FY19/20 partly due to delay on NCHC’s part and partly as
additional works have been identified at Simpson centre. Procurement plan to tender and procure services for the works in
Dereham office admin block are deferred until early Financial year 2019-20. The Capital programme changes for FY 2019/20
are ongoing post review of the latest Estates strategy.
Clinical Equipment
• Commodes were delivered and receipted within 2018/19. All other purchases have been reconciled or are anticipated by
Finance. The plan is now fully delivered and has justified the full spend within year.
N/A
3.2 Capital Programme Update
Programme Status
Issues/
Points for
Escalation/
Decision
Current
RAG
Estates Backlog
maintenance
(£826.9K)
• ZT 110 The contractors performance on the staff wellbeing project has given significant concerns.
The situation has been escalated and is being mitigated alongside Procurement team
• ZT 111 Place works at Swaffham has been poorly delivered by the contractor and a remedial
action plan is in development with all parties concerned
• ZT119 - Simpson Centre refurbishment project started, the project will have a two week overrun
and cost overrun due to extra steel works and demands from building control. with potential for
small time overrun
• ZT125 - Squirrels additional works are due to complete by 10th April 2019. This is due to delay in
sending the PO to the supplier post tender approval
• The Capital plan for 2019-20 has been developed and items of backlog capital investment are
monitored
None
Estates
Development
(£1.105M)
• Procurement plan to tender and procure services for the works in Dereham office admin block are
deferred until early Financial year 2019-20
• Negotiations with BBC to move most of Dereham Hospital into The Enterprise Centre Dereham are
picking up again and we now have a new Programme Manager appointed to support with this. Due
diligence survey works at Dereham Hospital and Kelling Hospital, are underway. The survey
reports will feed into the requirements of Homes England to enable the master plan for the
Dereham Hospital and Kelling Hospital
None
Estates Charity
Works
(£15K)
• Initial discussions to determine the FY19/20 Charity works projects are now complete
• The funding request for the Dereham Hospital – day rooms development has been approved under
ATIR 1920-003
None
A
A
G
3.0 Programme Update - Secure the Future
3.2 Capital Programme Update
Programme Status
Issues/
Points for
Escalation/
Decision
Current
RAG
Clinical
Equipment
Group
(247K)
• Commodes were delivered and receipted within 2018/19.
• All other purchases have been reconciled or are anticipated by Finance.
• The plan is now fully delivered and has justified the full spend within year.
None
ZT001 - Mobile
Community
Working Phase
2
(£229.2K)
• 704 Staff trained on the Mobile App (MILESTONE completed)
• 264 mobile working devices have been issued to clinicians
• Video conferencing within meeting rooms has been installed in 13 rooms across the trust
• Mobile working assets received in March 19
• Closure report for Project completed
None
ZT002 -
Enhancing
Cyber Security
&
Infrastructure
(£634K)
• HSCN - All 3 sites now have new equipment installed, and been migrated to HSCN.
• Windows 10 build delayed to pick up NHS Digital technical approach, IM&T are investigating
and testing a robust and secure build.
• SAN storage, firewalls and servers delivered
• Disaster Recovery, Equipment to value £128k ordered and received within the 18/19 FY
None
ZT004 – Joint
Directory
(£20K)
• Project handed over to other Project Manager – outstanding actions being determined with
project team and supplier
• Data matching issues now resolved – mostly differences in names e.g. Mike vs. Michael. HR
have agreed this to be consistent with ESR name going forward
• To-be processes to be determined – supplier to share notification options. Configuration in
Support-works expected by IM&T to cater for new processes (starters, leavers, change of
circumstances)
• Test plan being drafted and communications plan needed to inform staff of updates to details
that will be made in AD – this will not cover phone numbers
• Expected go live was reported as March, actual date anticipated as early-mid May.
None
G
G
G
A
3.0 Programme Update - Secure the Future
3.2 Capital Programme Update
Programme Status
Issues/
Points for
Escalation/
Decision
Current
RAG
ZT005 -
Introducing Digital
Inpatients
(£149K)
• Alder and Foxley ward have been supported for Digital inpatients.
• Project has gone live with North Walsham on the 2nd Apr 19
• IT Equipment has been procured, all assets received in the 18/19 FY
• Digital Inpatients Governance Group (DIGG) is ongoing with good representation from operational
teams to ensure engagement and communication is consistent
• High risk raised relating to TWS and scanning of documents – discussion held with senior
stakeholders 29th March.
None
ZT006 - Enhancing
Public, Patient and
Trust Wi-Fi
(£179K)
• Public and staff Wi-Fi rolled out across the Trust Estate on 26/02. Full details on locations and user
guides available on Intranet
• Project Ready for closure and closure report submitted to TPB for approval
None
NC002
Purchasing and
Inventory
Management
• Phase 2 rollout in progress.
• Wheelchair services is likely to go live in Q1 2019/20 due to complexity around product
identification and lack of historic order data in Eros/Powergate resulting in additional resource
needed during setup phase
• A TMT presentation on the overall rollout of Purchasing and Inventory management and benefits
realised is planned for April-2019
None
3.0 Programme Update - Secure the Future
G
A
3.2 Capital Programme Update
G
3.2 Capital Programme Update
3.0 Programme Update - Secure the Future
Programme StatusRAG Status
Overall
Overall
ProgrammeProgramme flagging amber as most projects within the programme are Amber.
SystmOne
Optimisation
• Authority to Invest Paper presented at Investment Group to optimise 13 services which include 400 mobile working
staff. Decision made not to fund this project and focus on benefiting from existing services where Mobile working is
rolled out
Wound
Cameras
• Capital funding approved
• Cameras ordered and delivered
• Staff identified for training - Supporting eLearning material drafted
Health
Coaching
• Awaiting confirmation of funding and commencement of recruitment process for HC lead role to define handover to
BAU/project closure date
eScheduling
• Risk has reduced to AMBER following improvements to system performance –
• Benefit remains at AMBER due to the lack of real-time interface between SystmOne and eCommunity .
• Meeting arranged for 3rd April with TPP/Allocate/NCHC to clarify API interface requirements and agree next
steps/timeline.
NC001 Enabling
Collaboration
Services
• Teams assurances provided to and approved by IG, IAO’s and SIRO. Drop-in and training sessions held across
all localities. Rollout now in progress, all sites to be enabled by April 19.
• OneDrive – technical actions continue to be worked through. ‘
• SharePoint – high level plan to be created
Operational
Management
System
Optimisation
Programme
(OMSOP)
• PROGRAMME GOAL: To have removed unwarranted variation, increased productivity and reduced risk, through
optimisation of operational and staff management systems across NCH&C
• A review of the programme to take place over the coming days (this will be tied-in in with the Community
Gateway review)
• Workstreams:
1. HealthRoster/ESR 2. Competencies 3. Mobile Working 4. Care Plans
5. eScheduling 6. Reporting/IMAS 7. Self Care 8. Case Management
3.3 Service Development Programme UpdateThis section outlines projects that either update or enhance a service or are enablers for CIP projects.
A
A
G
A
3.0 Programme Update – Improve our Quality
A
G
A
3.3 Service Development Programme Update
3.0 Programme Update – Improve our Quality
Programme Status
RAG Status
Overall CIP Time Cost Quality Benefit Risks
Indicator 9:
Preventing Ill
Health by Risky
Behaviours-
smoking and
alcohol
• Data collection ongoing for inpatient units and HomeWard
• Percentage compliance for screening for smoking has remained
static across all units since Q3 and has meant that once again is
short of the targets set. There has been an improvement in the
number of patients given brief advice and referred on to specialist
stop smoking services.
• Screening for alcohol has remained static and has again met the
targets for the Quarter
• The roll out of the Digital Inpatients project will see all units using
the same data collection process via SystmOne. Training will
include data collection against the template and it is hoped that
compliance levels will improve during 2019 – 20
• Full report due end April 2019
N/A N/A N/A
Indicator 10:
Improving the
Assessment of
wounds
• Wound Care Training for community nursing staff is ongoing
• Q4 audit is underway and closing on 12.4.19 . Looking at the
number of responses so far, the sample size has once again
exceeded the requirement of the CQUIN.
• Analysis scheduled w/c 15.4.19 and the full report is due for
submission end April 19
N/A N/A N/A
Indicator 11:
Personalised
Care
and Support
Planning
• Patients identified in the cohort for this CQUIN have been re-asked thepatient activation question. Analysis is underway to ascertain if anyimprovement in scores can be seen following the Care and SupportPlanning interventions. Reports due for submission end of April 19
• Anecdotal evidence has shown that for some patients the Care and SupportPlanning approach has resulted in significant benefits for patients and theircarer/families. See quote below:
‘……The feed -back of my work has been really positive, patients felt involved, more in
control with a little prompting and assistance to enable a pathway of care to refer to.
They liked having phone numbers all in one place also. I had lots of compliments and as
a nurse felt I was making a huge difference to the patients that I care about…..’
Specialist Neuro Nurse
N/A N/A N/A
3.3 Service Development Programme Update
National CQUIN Programme 2017-19.
3.0 Programme Update – Improve our Quality
A A A A
GG
G
G A
GG G
Pipeline/Scheme
#Project Gateway
Change
ControlClosure Date
Financial
BenefitOutcome
To be
allocated Clinic Optimisation 11.01.19 £777.4K
The previous project had been closed. The replacement
project ‘Clinic Design & Management’ is being scoped.
New leads have been agreed:
• Sponsor, Andrew Hopkins
• Project Lead, Lisa Edwards
PL213 Staff Travel Review GW3 11.01.19 £87.5kStaff Travel Review Phase 1 GW2&3 was signed off and
agreed at meeting.
IT17-01
(PL200)SystemOne Efficiencies X 11.01.19 £0
CIP delivered successfully in FY 17/18, agreed for
closure.
WTP14Palliative Care
workforce planX 08.02.19 £143k Change control approved
WTP22 Procurement X 08.02.19 £468k Change control approved
NC&HC Projects and
Investment – Vision and
Proposed Programme
Structure
08.02.19 £0Vision logo and statement was approved by board
members. Board members happy to implement strucutre.
ZT124Thorpe Health Centre
Refurbishment 08.02.19 £0 Capital PID approved by board members
ZT119Simpson Centre
Refurbishment 08.02.19 £0 Capital PID approved by board members
ZT131Caroline House Door
Refurbishment 08.02.19 £0 Capital PID approved by board members
ZT123 Mulberry Refurbishment 08.02.19 £0 Capital PID approved by board members
WTP02Neurology Rehab
Service X 08.03.19 £121k Change control approved
Final Capital
Programme 08.03.19 £0 Final Capital Programme approved by board members
TPB Terms of
Reference & Approval
Process Map
08.03.19 £0
Changes to Workforce
Programme Board08.03.19 £0
Paper presented in meeting and approved by board
members in attendance
4.0 Project Decision Update – Secure the Future
This section highlights the decisions made at Transformation Programme Board (TPB) during the last three months.