18
Date: 20.01.2017 To, The Director, Infrastructure and Miscellaneous Projects & CRZ Indira Paryavaran Bhavan Jor Bagh Road, New Delhi - 110 003 Sub: Environmental Clearance of Proposed project of Residential cum Commercial Project with Affordable housing on Plot bearing S No. 29/1, 30/1, 2, 3A of Village Ghodbunder, Bhayandar (E), District-Thane [F. No. 21-13/2016-IA-III] Ref: Minutes of 11 th EAC (Infra-II) meeting held on 24.11.2016 (Item no. 11.2.18) (File No. 21-13/2016-IA-III) Respected Sir, We are very much thankful to Expert Appraisal Committee (Infra-2) for appraising our above referred project in its 11 th Meeting held on 24.11.2016 (Item no. 11.2.18) As per the minutes of the meeting, we were asked to comply with certain points raised by committee. The point wise reply to the queries raised is enclosed herewith. We hope that reply is in line with your requirement. Thanking you, Yours faithfully, Enclosures: 1. As above

Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Date: 20.01.2017 To, The Director, Infrastructure and Miscellaneous Projects & CRZ Indira Paryavaran Bhavan Jor Bagh Road, New Delhi - 110 003

Sub: Environmental Clearance of Proposed project of Residential cum

Commercial Project with Affordable housing on Plot bearing S No. 29/1, 30/1, 2, 3A of Village Ghodbunder, Bhayandar (E), District-Thane [F. No. 21-13/2016-IA-III]

Ref: Minutes of 11th EAC (Infra-II) meeting held on 24.11.2016 (Item no.

11.2.18) (File No. 21-13/2016-IA-III) Respected Sir, We are very much thankful to Expert Appraisal Committee (Infra-2) for appraising our above referred project in its 11th Meeting held on 24.11.2016 (Item no. 11.2.18) As per the minutes of the meeting, we were asked to comply with certain points raised by committee. The point wise reply to the queries raised is enclosed herewith. We hope that reply is in line with your requirement. Thanking you, Yours faithfully,

Enclosures:

1. As above

Page 2: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 2

POINTWISE COMPLIANCE TO QUIRIES RAISED DURING

11th EAC (Infra-II) MEETING

Point No.1: Status of application of the project proposal in SEIAA, Maharashtra.

Compliance: The application is not considered at SEIAA, Maharashtra as the

SEAC MMR’s tenure is over and there is no committee for appraisal of projects.

Hence, we have applied to MoEF&CC, Delhi on 28.10.2016.

Point No.2: Copy of application submitted for clearance from NBWL.

Compliance: As per the ESZ notification of Sanjay Gandhi National Park (SGNP),

vide no. S. O. 3645 (E) dated 05.12.2016, our project site is outside of ESZ i.e.

(100 m); hence clearance from the Standing Committee of the National Board for

Wildlife is not applicable for our project.

Point No.3: Present landuse of the proposed project site.

Compliance: The project site is under residential use as per the DP of MBMC

(Mira Bhayander Municipal Corporation). The project location on the DP is

shown in the figure 1.

Page 3: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 3

Figure 1: DP of MBMC with location of project site.

Project Site

Page 4: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 4

Point No.4: Building sanction plan.

Compliance: We have obtained location clearance for the site which is given in

figure 2.

Figure 2: Location Clearance from MBMC

Page 5: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 5

Point No.5: Commitment that shops and other establishments in residential

blocks with have to conform to residential area norms in terms of noise pollution

and vehicular movements and shall not create a nuisance for residents of the

Blocks.

Compliance: We hereby confirm that shops in the residential blocks will not

create any nuisance due to noise pollution and vehicular movements.

Point No.6:Layout plan indicating road, greenbelt, drainage, sewer line, STP,

solid waste handling area, rain water harvesting structure, etc. in different colour

to be furnished.

Compliance: Co-ordinated drawing showing Layout plan indicating road,

greenbelt, drainage, sewer line, STP, solid waste handling area, rain water

harvesting structure etc. with different colour codes is shown in the following

figure 3.

Page 6: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 6

SWD

Outfall

Figure 3: Coordinated layout with landscape, location of STP, SWM, RWH, SWD UG tanks and sewer line

D

W

DD

ELE.

DUCT

D

W

D D

LIFT

D

W

D

D

LIF

T

D

A B C-1 (R)O

PE

N S

TA

IR

OPEN STAIR

OPEN STAIR

OP

EN

ST

AIR

OP

EN

ST

AIR

OP

EN

ST

AIR

OP

EN

ST

AIR

OPEN S

TAIR

OPEN

STAIR

OPEN

STAIR

OPEN S

TAIR

OPEN

STAIR

OPEN S

TAIR

OPEN STAIR

OPEN

STA

IR

OPEN

STA

IR

OPEN STAIR

ELE

CTR

IC S

UBSTA

TIO

N

1.5

0 M

T.

WID

E H

EIG

HT

CO

MP

OU

ND

WA

LL

1.50

MT. W

IDE H

EIGHT

COM

POUND W

ALL

1.50

MT. WID

E HEIG

HT C

OMPO

UND WALL

23.06

15.38

46.6

5

6.00

ST+21

ST+21ST+21

ST+21

ST+21

ST+21

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22ST+22

ST+22 ST+22

ST+22ST+22

ST+22 ST+22

GR+12

30.7

5

GR+12

ST+12

ST+12

GR+13

GR+13

GR+13

GR+13

GR+13

W

VOID

W

VOID

W

D2

LIFT

D2

LIFT

D2

LIFT

D2

LIFT

D2

LIFT

D2

LIFT

VOID W

D5

D5

VOID

VOID

W

LIFT

D2

LIFT

D2

VOID

W

D5

LIFT

LIFT

D2

D2

A B-1 (BLDG NO 1)

A B C -1 (BLDG NO 2)

A B -1 (BLDG NO 3)

ELE.DUCT

ELE.

DUCT

VOID

VOID

VOID

LIF

T

LIF

T

18.00 MT. INTDPROAD

VO

ID

WD

5V

OID

WV

OID

W

VO

ID

WD

5

D2LIFT

D2LIFT

D2 LIFT

D2 LIFT

VOID

W

D5

VOID

W

D5

VOID

W

D5

VOID

ELECTRIC SUBSTATION

DG

SET

Sewer line

Page 7: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 7

Point No.7: Layout of parking plan indicating entry and exit points of vehicular

movement as well as traffic management plan. Highlight the fire tender pathway.

Compliance: The layout showing entry and exit points, driveways, parking slots,

vehicular movement and fire tender movement is shown in figure 4.

The proposed driveways will provide a safe and efficient connection to the

external road network

The traffic from the project will exit and enter from 18 m wide internal DP

road.

The entry and exit points will be manned by trained security staff. They

will manage the traffic at these points and prevent bottlenecks.

Entry and exit lanes do not cross and exit is after entry. Exit and entry are

segregated.

All the driveways are marked with guiding signs for better circulation.

All the driveways/aisles are straight with no dead ends

The minimum width of the driveway is 6m for efficient traffic circulation

and proper fire tender movement

Driveway will have speed humps at every 100 m, before a turn and before

entry/exit. This will control the speeding of vehicles within the project

premises.

Proper directional arrows will be used inside the parking bays

The parking plans and fire tender movement plan are given in the following

figure.

Page 8: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 8

Figure 4: Parking plan showing vehicular and Fire tender movement

R.G

R.G

R.G

6.00

R.G

R.G

2.4

02

.40

2.9

02

.90

0.1

5

LEGENDS SERVICES

STP

SWM

UG TANKS

RWH

SUBSTATION

DG SET

FIRE TENDER MMT

1

2

3

4

5

6

7

8

A B

ELECTRIC SUBSTATION

Entry

Exit Entry/Exit

Page 9: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 9

Point No.8: Details of source of water supply alongwith permission to be

submitted.

Compliance: Water supply for the project will be received from MBMC. The

commitment letter from MBMC is given in the following figure 5:

Figure 5: Water Commitment letter from MBMC:

Point No.9: Excess treated sewage disposal plan/scheme to be submitted.

Compliance: Excess treated water from our project will be disposed in the

proposed Municipal sewer lines. The letter regarding the proposed sewerage

Page 10: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 10

network of MBMC and its connection to the project site is given in the letter

given in figure 6.

Figure 6: MBMC letter regarding Sewer lines

Point No.10: Assessment of ground level concentration of pollutants due to DG

set (800 KVA).

Compliance: Assessment of ground level concentration of pollutants due to DG

set of total 800 kVA is done using dispersion modelling for estimated

concentrations of SO2. The DG set operation will contribute towards the air

pollution. These DG sets have been provided to take care of power availability

during power failure from MSEDCL. However in the project area 24 hrs

electricity is supplied, but on a precautionary basis the above DG sets have been

proposed in case of any emergencies arising out of routine power failure. The

Page 11: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 11

impact of the DG sets on the environment has also been studied using

mathematical model for ascertaining the gaseous pollutant impact.

The results of the mathematical model indicate that the maximum incremental

increase in the SO2 concentration is 2.5 ug/m3. The isopleths of predicted SO2

concentrations is given in the following figure. This is confined to a small area of

1000 m in and around the project site. The predicted concentrations from the

model will not lead to alter the baseline concentrations as it is well within the

norms stipulated and also as the DGs will be used only during emergency.

Figure 7: Isoplethes of predicted SO2 concentration

Point No.11:Effort shall be made to reduce capacity of DG set upto 500 KVA and

remaining standby power shall be met from solar energy.

Compliance: We will reduce capacity of DG set upto 760 KVA and remaining

standby power of 140kVA will be met from solar energy i.e. Solar PV panels &

Solar trees. Kindly refer point no. 15 for solar power generation calculations.

Point No.12: Treatment scheme for sewage and its recycling mode.

Compliance: Details of water treatment are as following:

-500 -400 -300 -200 -100 0 100 200 300 400 500

-500

-400

-300

-200

-100

0

100

200

300

400

500

0ug/m30.1ug/m30.2ug/m30.3ug/m30.4ug/m30.5ug/m30.6ug/m30.7ug/m30.8ug/m30.9ug/m31ug/m31.1ug/m31.2ug/m31.3ug/m31.4ug/m31.5ug/m31.6ug/m31.7ug/m31.8ug/m31.9ug/m32ug/m32.1ug/m32.2ug/m32.3ug/m32.4ug/m32.5ug/m3

Page 12: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 12

Total water required for the proposed development is 525 KLD which will be

met from Mira Bhayander Municipal Corporation (MBMC). Water requirement

calculations are given in following water balance chart:

Water Balance Chart

Note: Basis for Water supply is taken from BIS: National Building Code of India

2005: Part 9 pg 19

Figure 8: Water Balance during Dry Season

Sewage generation is about 490 KLD which will be treated in 500 KLD STP of

Oxic – Anoxic attached media growth Treatment. We are reusing treated water

for gardening (12 KLD) & flushing (178 KLD). Excess Treated Water will be

disposed to Municipal Sewer lines.

Page 13: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 13

Sewage Generation: 490 KLD

Calculation for STP Capacity:

Total Water demand = 525 KLD

The STP is Designed for 500 m3.

STP Technology: Oxic – Anoxic attached media growth Treatment

Figure 9: Flow-sheet of Oxic–Anoxic attached media growth Treatment:

Table: Expected Characteristics of Raw and treated Water

Sr. No.

Parameters Raw

Sewage Treated Sewage

Standards for New STP as per MoEF

Notification

1 pH 7-8 7-8 6.5 to 9

2 Total Suspended Solids mg/l

100-200 Upto 10 20

3 BOD (3 days 27˚C) (mg/l)

250-300 <10 10

4 COD (mg/l ) 450-600 Upto 40 50

5 Total Nitrogen (mg/l) 40-50 <10 10

6 Ammonical Nitrogen (mg/l)

<1 5

7 Fecal Coliforms (MPN/100 ml)

~ 107

/100ml

200/100 ml

<100

Point No.13: Details of rain water harvesting system to be furnished. Clarity on

recharge pits, storage systems for rain water and use of appropriate filtration

system for collected rain water to be detailed.

Compliance: The rooftop rainwater will be stored in Rain Water Harvesting

tanks after filtration. The roof top Rain water harvesting potential project is

57m3/day & the provision of 9 Rainwater Harvesting tank having capacity 120

m3 will be provided. The cross section of Rainwater harvesting unit is given in

figure 10. As the groundwater table is 2-3m in the project area recharge pits are

not feasible.

Page 14: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 14

Figure 10: Cross section of Rainwater harvesting unit

100 MM THK. PCC

230 MM THK.

RUBBLE PACKING

GR.LVL.MANHOLE600MM x 900 MM

150 MM Ø PVC PIPE

WITH CAP DRAIN OFF

FIRST RAINWATER

PIPE CARRYING

TERRACE

RAIN WATER

MANHOLE450MM x 900 MM

MANHOLE600MM x 900 MM

150 MM THK. RCC WALL

150 MM Ø PIPES (2NOS)

WITH CAP CONNECTING

VALVE CHAMBER TO

FILTERATION CHAMBER

RCC SLAB

STEEL BARS EMBEDDED

IN RCC WORK FOR

LADDER PURPOSE

150 MM THK.

MANHOLE600MM x 900 MM

MANHOLE600MM x 900 MM

150 MM Ø PIPE CONNECTING

FILTERATION CHAMBER TO

COLLECTION TANK

SECTION X-X

OVERFLOW

PIPE TO S.W.D.

STAINLESS

STEEL (SS) SCREEN PIPE

ROOFTOP R.W.H. UNIT CONCEPTUAL DWG

RCC SLAB

300

GR.LVL.

1ST BASEMENT LVL.

150 MM Ø PVC PIPE

WITH CAP DRAIN OFF

FIRST RAINWATER

PIPE CARRYING

TERRACE

RAIN WATER

MANHOLE600MM x 900 MM

230MM THK. BRICK

WALL WITH PLASTER

ON BOTH SIDES

350MM THK. BRICK

WALL WITH WATER

PROOFING & PLASTER

ON BOTH SIDES

STAINLESS

STEEL (SS) SCREEN PIPE

MANHOLE450MM x 900 MM

MANHOLE600MM x 900 MM

150 MM Ø PIPES (2NOS)

WITH CAP CONNECTING

VALVE CHAMBER TO

FILTERATION CHAMBER

OVERFLOW

PIPE TO S.W.D.

MANHOLE600MM x 900 MM

MANHOLE600MM x 900 MM

150 MM Ø PIPE CONNECTING

FILTERATION CHAMBER TO

COLLECTION TANK

VALVE CHAMBER

STEEL BARS EMBEDDED

IN BRICK WORK FOR

LADDER PURPOSE

FILTERATION CHAMBER COLLECTION TANK

X X

Page 15: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 15

Point No.14: Calculation on sizing of solar water heating systems to be

furnished.

Compliance: We are not providing solar hot water panels as the terrace area

will be utilized for provision of PV panels to provide energy for for 2 solar

powered lights and one fan in each flat and emergency backup.

Point No.15: Details on solar lighting for common areas as well as for two light

and one fan in each flat to be provided.

Compliance: We have proposed solar panels to provide 2 solar powered lights

and one fan for each of 765 tenements. The calculations for PV panels are as

following:

SOLAR PV PANEL CALCULATION

On average photovoltaic (PV) solar panels will produce 10-13 watts per square

foot of solar panel area. 10 kW/m2 of solar power generation is considered for

following calculations:

Total Terrace Area = 2863.91 m2

Actual usable terrace area for Solar Panels = 1718.34 m2 (60% of total

terrace area)

Power requirement of 2 lights and 1 fan

Connection for 765 tenements =80 W x 869= 61.2 kW approx.

Area required for generation of 1kW is 10m2

Hence area required for generation of 61.2 kW =612 m2

Area available for PV panels = 1106 m2

Solar Power generation = 111 kW = 140 kVA

Thus 140 kVA of Solar power will be supplied to grid and used as stand by

power during emergency.

Point No.16:Solid waste management plan alongwith area earmarked for solid

waste management scheme.

Compliance: Solid waste management plan along with area earmarked for solid

waste management scheme and the location of the SWM in layout is shown in

following figure 11 .

Details Information

Total Waste generation 1,949 kg/day

Biodegradable waste (60%) 1,170 kg/day

(Converted into manure)

Non-Biodegradable waste (40%) 779 kg/day

Page 16: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 16

Details Information

(to recyclers)

Sewage treatment Plant sludge 5 m3/d

Solid waste treatment technology Mechanical Composting Unit

No. of unit SWM 2 no.

Capacity 600kg/day

Machine floor area 48 m2

Space provided 60 m2

Figure 11: Areas Earmarked For Solid Waste Management

Point No.17: Management of excavated soil. Pollution control measures to be

taken to control fugitive emission during construction phase including marble

/stone cutting.

Compliance: Excavated soil will be used for the Road pavement & site leveling.

Fugitive emission during construction phase will be control by barricading &

plantation along the plot boundary, water sprinkling at regular interval to arrest

Air Bourne-dust, Use of Ready Mix concrete to avoid excessive movement of

vehicles on the site. Use of PPE such as ear plugs and masks for labours will be

made mandatory wherever there are excess emissions. Precut vitrified tiles will

be used for flooring. Tile cutting will be done within the building and will be

done using water so there will not be any considerable fugitive emission.

Point No.18: Details energy conservation measures to be taken. all points

mentioned in the proposal such as orientation to support reduced heat gain, use

of ASHRAE 90.1, use of ECBC compliant envelope measures to be supported

through drawings and details in the proposal.

Compliance: Internal and external lighting design will be provided as required

by ECBC which will have Lighting Power Density as per space requirements.

Page 17: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 17

The project would provide 20% lower LPD than as specified in ECBC, to achieve

energy saving, while providing the required illumination levels, by using high

efficacy lighting.

Tree plantation is proposed along the periphery of the site ensuring adequate

buffer and reducing heat gain by the building so that the buildings will remain

naturally ventilated.

The project design will use high energy performing building materials which

would have low U value (Thermal Conductance) as compared to the conventional

materials. The external wall of building would use fly ash blocks, which will have

mandatory SHGC as required by ECBC.

Point No.19: Layout plan indicating Greenbelt alongwith area earmarked to be

provided.

Compliance: Layout plan indicating Greenbelt is given in the figure 12:

Page 18: Date: 20.01.2017 The Director, Infrastructure and ...environmentclearance.nic.in/writereaddata/Online/... · system for collected rain water to be detailed. Compliance: The rooftop

Umiya Developers

11th EAC MoM reply Page 18

Figure 12: Landscape drawing:

18.00 MT. INTDPROAD

D

W

D D

LIFT

D

W

D

D

LIF

T

D

A B C-1 (R)

OP

EN

ST

AIR

OPEN STAIR

OPEN STAIR

OP

EN

ST

AIR

OP

EN

ST

AIR

OP

EN

ST

AIR

OP

EN

ST

AIR

OPE

N S

TAIR

OPE

N STAIR

OPE

N STAIR

OPE

N S

TAIR

OPE

N STAIR

OPE

N S

TAIR

OPE

N STAIR

OPE

N S

TAIR

OPE

N S

TAIR

OPE

N STAIR

ELE

CTR

IC S

UBSTA

TIO

N

1.5

0 M

T. W

IDE

HE

IGH

T C

OM

PO

UN

D W

ALL

1.50

MT. W

IDE H

EIGHT C

OM

POUN

D WALL

1.50 M

T. WID

E HEIG

HT COM

POUND WALL

4.61

3.08

9.33

ST+21

ST+21

ST+21

ST+21

ST+21

ST+21

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22

ST+22ST+22

ST+22 ST+22

ST+22ST+22

ST+22 ST+22

GR+12

GR+12

ST+12

ST+12

GR+13

GR+13

GR+13

GR+13

GR+13

ELECTRIC SUBSTATION

6.00

6.15

8.63

6.19

6.20 6.30

VO

ID

WD

5V

OID

WV

OID

W

VO

ID

WD

5

D2LIFT

D2LIFT

D2 LIFT

D2 LIFT

VOID

W

D5

VOID

W

D5

VOID

W

D5

VOID

W

VOID

W

VOID

W

D2

LIFT

D2

LIFT

D2

LIFT

D2

LIFT

D2

LIFT

D2

LIFT

VOID W

D5

D5

VOID

VOID

W

LIFT

D2

LIFT

D2

VOID

W

D5

LIFT

LIFT

D2

D2

A B-1 (BLDG NO 1)

A B C -1 (BLDG NO 2)

A B -1 (BLDG NO 3)

ELE.

DUCTELE.

DUCT

VOID

VOID

VOID

LIF

T

LIF

T

D

W

DD

ELE.

DUCT

Sr.

No.

Name Nos.

1. Nandruk 15

2. Satwin 10

3. Sita Ashoka 13

4. Royal Palm 7

5. Karanj 14

6. Neem 15

7. Apta 10

8. Coconut 12

9. Son Chapha 14

Total 110

RG on ground: 2,307.36 m2

No. of Trees to be Planted : 110

Nos.

Existing trees: nil