Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Date: 20.01.2017 To, The Director, Infrastructure and Miscellaneous Projects & CRZ Indira Paryavaran Bhavan Jor Bagh Road, New Delhi - 110 003
Sub: Environmental Clearance of Proposed project of Residential cum
Commercial Project with Affordable housing on Plot bearing S No. 29/1, 30/1, 2, 3A of Village Ghodbunder, Bhayandar (E), District-Thane [F. No. 21-13/2016-IA-III]
Ref: Minutes of 11th EAC (Infra-II) meeting held on 24.11.2016 (Item no.
11.2.18) (File No. 21-13/2016-IA-III) Respected Sir, We are very much thankful to Expert Appraisal Committee (Infra-2) for appraising our above referred project in its 11th Meeting held on 24.11.2016 (Item no. 11.2.18) As per the minutes of the meeting, we were asked to comply with certain points raised by committee. The point wise reply to the queries raised is enclosed herewith. We hope that reply is in line with your requirement. Thanking you, Yours faithfully,
Enclosures:
1. As above
Umiya Developers
11th EAC MoM reply Page 2
POINTWISE COMPLIANCE TO QUIRIES RAISED DURING
11th EAC (Infra-II) MEETING
Point No.1: Status of application of the project proposal in SEIAA, Maharashtra.
Compliance: The application is not considered at SEIAA, Maharashtra as the
SEAC MMR’s tenure is over and there is no committee for appraisal of projects.
Hence, we have applied to MoEF&CC, Delhi on 28.10.2016.
Point No.2: Copy of application submitted for clearance from NBWL.
Compliance: As per the ESZ notification of Sanjay Gandhi National Park (SGNP),
vide no. S. O. 3645 (E) dated 05.12.2016, our project site is outside of ESZ i.e.
(100 m); hence clearance from the Standing Committee of the National Board for
Wildlife is not applicable for our project.
Point No.3: Present landuse of the proposed project site.
Compliance: The project site is under residential use as per the DP of MBMC
(Mira Bhayander Municipal Corporation). The project location on the DP is
shown in the figure 1.
Umiya Developers
11th EAC MoM reply Page 3
Figure 1: DP of MBMC with location of project site.
Project Site
Umiya Developers
11th EAC MoM reply Page 4
Point No.4: Building sanction plan.
Compliance: We have obtained location clearance for the site which is given in
figure 2.
Figure 2: Location Clearance from MBMC
Umiya Developers
11th EAC MoM reply Page 5
Point No.5: Commitment that shops and other establishments in residential
blocks with have to conform to residential area norms in terms of noise pollution
and vehicular movements and shall not create a nuisance for residents of the
Blocks.
Compliance: We hereby confirm that shops in the residential blocks will not
create any nuisance due to noise pollution and vehicular movements.
Point No.6:Layout plan indicating road, greenbelt, drainage, sewer line, STP,
solid waste handling area, rain water harvesting structure, etc. in different colour
to be furnished.
Compliance: Co-ordinated drawing showing Layout plan indicating road,
greenbelt, drainage, sewer line, STP, solid waste handling area, rain water
harvesting structure etc. with different colour codes is shown in the following
figure 3.
Umiya Developers
11th EAC MoM reply Page 6
SWD
Outfall
Figure 3: Coordinated layout with landscape, location of STP, SWM, RWH, SWD UG tanks and sewer line
D
W
DD
ELE.
DUCT
D
W
D D
LIFT
D
W
D
D
LIF
T
D
A B C-1 (R)O
PE
N S
TA
IR
OPEN STAIR
OPEN STAIR
OP
EN
ST
AIR
OP
EN
ST
AIR
OP
EN
ST
AIR
OP
EN
ST
AIR
OPEN S
TAIR
OPEN
STAIR
OPEN
STAIR
OPEN S
TAIR
OPEN
STAIR
OPEN S
TAIR
OPEN STAIR
OPEN
STA
IR
OPEN
STA
IR
OPEN STAIR
ELE
CTR
IC S
UBSTA
TIO
N
1.5
0 M
T.
WID
E H
EIG
HT
CO
MP
OU
ND
WA
LL
1.50
MT. W
IDE H
EIGHT
COM
POUND W
ALL
1.50
MT. WID
E HEIG
HT C
OMPO
UND WALL
23.06
15.38
46.6
5
6.00
ST+21
ST+21ST+21
ST+21
ST+21
ST+21
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22ST+22
ST+22 ST+22
ST+22ST+22
ST+22 ST+22
GR+12
30.7
5
GR+12
ST+12
ST+12
GR+13
GR+13
GR+13
GR+13
GR+13
W
VOID
W
VOID
W
D2
LIFT
D2
LIFT
D2
LIFT
D2
LIFT
D2
LIFT
D2
LIFT
VOID W
D5
D5
VOID
VOID
W
LIFT
D2
LIFT
D2
VOID
W
D5
LIFT
LIFT
D2
D2
A B-1 (BLDG NO 1)
A B C -1 (BLDG NO 2)
A B -1 (BLDG NO 3)
ELE.DUCT
ELE.
DUCT
VOID
VOID
VOID
LIF
T
LIF
T
18.00 MT. INTDPROAD
VO
ID
WD
5V
OID
WV
OID
W
VO
ID
WD
5
D2LIFT
D2LIFT
D2 LIFT
D2 LIFT
VOID
W
D5
VOID
W
D5
VOID
W
D5
VOID
ELECTRIC SUBSTATION
DG
SET
Sewer line
Umiya Developers
11th EAC MoM reply Page 7
Point No.7: Layout of parking plan indicating entry and exit points of vehicular
movement as well as traffic management plan. Highlight the fire tender pathway.
Compliance: The layout showing entry and exit points, driveways, parking slots,
vehicular movement and fire tender movement is shown in figure 4.
The proposed driveways will provide a safe and efficient connection to the
external road network
The traffic from the project will exit and enter from 18 m wide internal DP
road.
The entry and exit points will be manned by trained security staff. They
will manage the traffic at these points and prevent bottlenecks.
Entry and exit lanes do not cross and exit is after entry. Exit and entry are
segregated.
All the driveways are marked with guiding signs for better circulation.
All the driveways/aisles are straight with no dead ends
The minimum width of the driveway is 6m for efficient traffic circulation
and proper fire tender movement
Driveway will have speed humps at every 100 m, before a turn and before
entry/exit. This will control the speeding of vehicles within the project
premises.
Proper directional arrows will be used inside the parking bays
The parking plans and fire tender movement plan are given in the following
figure.
Umiya Developers
11th EAC MoM reply Page 8
Figure 4: Parking plan showing vehicular and Fire tender movement
R.G
R.G
R.G
6.00
R.G
R.G
2.4
02
.40
2.9
02
.90
0.1
5
LEGENDS SERVICES
STP
SWM
UG TANKS
RWH
SUBSTATION
DG SET
FIRE TENDER MMT
1
2
3
4
5
6
7
8
A B
ELECTRIC SUBSTATION
Entry
Exit Entry/Exit
Umiya Developers
11th EAC MoM reply Page 9
Point No.8: Details of source of water supply alongwith permission to be
submitted.
Compliance: Water supply for the project will be received from MBMC. The
commitment letter from MBMC is given in the following figure 5:
Figure 5: Water Commitment letter from MBMC:
Point No.9: Excess treated sewage disposal plan/scheme to be submitted.
Compliance: Excess treated water from our project will be disposed in the
proposed Municipal sewer lines. The letter regarding the proposed sewerage
Umiya Developers
11th EAC MoM reply Page 10
network of MBMC and its connection to the project site is given in the letter
given in figure 6.
Figure 6: MBMC letter regarding Sewer lines
Point No.10: Assessment of ground level concentration of pollutants due to DG
set (800 KVA).
Compliance: Assessment of ground level concentration of pollutants due to DG
set of total 800 kVA is done using dispersion modelling for estimated
concentrations of SO2. The DG set operation will contribute towards the air
pollution. These DG sets have been provided to take care of power availability
during power failure from MSEDCL. However in the project area 24 hrs
electricity is supplied, but on a precautionary basis the above DG sets have been
proposed in case of any emergencies arising out of routine power failure. The
Umiya Developers
11th EAC MoM reply Page 11
impact of the DG sets on the environment has also been studied using
mathematical model for ascertaining the gaseous pollutant impact.
The results of the mathematical model indicate that the maximum incremental
increase in the SO2 concentration is 2.5 ug/m3. The isopleths of predicted SO2
concentrations is given in the following figure. This is confined to a small area of
1000 m in and around the project site. The predicted concentrations from the
model will not lead to alter the baseline concentrations as it is well within the
norms stipulated and also as the DGs will be used only during emergency.
Figure 7: Isoplethes of predicted SO2 concentration
Point No.11:Effort shall be made to reduce capacity of DG set upto 500 KVA and
remaining standby power shall be met from solar energy.
Compliance: We will reduce capacity of DG set upto 760 KVA and remaining
standby power of 140kVA will be met from solar energy i.e. Solar PV panels &
Solar trees. Kindly refer point no. 15 for solar power generation calculations.
Point No.12: Treatment scheme for sewage and its recycling mode.
Compliance: Details of water treatment are as following:
-500 -400 -300 -200 -100 0 100 200 300 400 500
-500
-400
-300
-200
-100
0
100
200
300
400
500
0ug/m30.1ug/m30.2ug/m30.3ug/m30.4ug/m30.5ug/m30.6ug/m30.7ug/m30.8ug/m30.9ug/m31ug/m31.1ug/m31.2ug/m31.3ug/m31.4ug/m31.5ug/m31.6ug/m31.7ug/m31.8ug/m31.9ug/m32ug/m32.1ug/m32.2ug/m32.3ug/m32.4ug/m32.5ug/m3
Umiya Developers
11th EAC MoM reply Page 12
Total water required for the proposed development is 525 KLD which will be
met from Mira Bhayander Municipal Corporation (MBMC). Water requirement
calculations are given in following water balance chart:
Water Balance Chart
Note: Basis for Water supply is taken from BIS: National Building Code of India
2005: Part 9 pg 19
Figure 8: Water Balance during Dry Season
Sewage generation is about 490 KLD which will be treated in 500 KLD STP of
Oxic – Anoxic attached media growth Treatment. We are reusing treated water
for gardening (12 KLD) & flushing (178 KLD). Excess Treated Water will be
disposed to Municipal Sewer lines.
Umiya Developers
11th EAC MoM reply Page 13
Sewage Generation: 490 KLD
Calculation for STP Capacity:
Total Water demand = 525 KLD
The STP is Designed for 500 m3.
STP Technology: Oxic – Anoxic attached media growth Treatment
Figure 9: Flow-sheet of Oxic–Anoxic attached media growth Treatment:
Table: Expected Characteristics of Raw and treated Water
Sr. No.
Parameters Raw
Sewage Treated Sewage
Standards for New STP as per MoEF
Notification
1 pH 7-8 7-8 6.5 to 9
2 Total Suspended Solids mg/l
100-200 Upto 10 20
3 BOD (3 days 27˚C) (mg/l)
250-300 <10 10
4 COD (mg/l ) 450-600 Upto 40 50
5 Total Nitrogen (mg/l) 40-50 <10 10
6 Ammonical Nitrogen (mg/l)
<1 5
7 Fecal Coliforms (MPN/100 ml)
~ 107
/100ml
200/100 ml
<100
Point No.13: Details of rain water harvesting system to be furnished. Clarity on
recharge pits, storage systems for rain water and use of appropriate filtration
system for collected rain water to be detailed.
Compliance: The rooftop rainwater will be stored in Rain Water Harvesting
tanks after filtration. The roof top Rain water harvesting potential project is
57m3/day & the provision of 9 Rainwater Harvesting tank having capacity 120
m3 will be provided. The cross section of Rainwater harvesting unit is given in
figure 10. As the groundwater table is 2-3m in the project area recharge pits are
not feasible.
Umiya Developers
11th EAC MoM reply Page 14
Figure 10: Cross section of Rainwater harvesting unit
100 MM THK. PCC
230 MM THK.
RUBBLE PACKING
GR.LVL.MANHOLE600MM x 900 MM
150 MM Ø PVC PIPE
WITH CAP DRAIN OFF
FIRST RAINWATER
PIPE CARRYING
TERRACE
RAIN WATER
MANHOLE450MM x 900 MM
MANHOLE600MM x 900 MM
150 MM THK. RCC WALL
150 MM Ø PIPES (2NOS)
WITH CAP CONNECTING
VALVE CHAMBER TO
FILTERATION CHAMBER
RCC SLAB
STEEL BARS EMBEDDED
IN RCC WORK FOR
LADDER PURPOSE
150 MM THK.
MANHOLE600MM x 900 MM
MANHOLE600MM x 900 MM
150 MM Ø PIPE CONNECTING
FILTERATION CHAMBER TO
COLLECTION TANK
SECTION X-X
OVERFLOW
PIPE TO S.W.D.
STAINLESS
STEEL (SS) SCREEN PIPE
ROOFTOP R.W.H. UNIT CONCEPTUAL DWG
RCC SLAB
300
GR.LVL.
1ST BASEMENT LVL.
150 MM Ø PVC PIPE
WITH CAP DRAIN OFF
FIRST RAINWATER
PIPE CARRYING
TERRACE
RAIN WATER
MANHOLE600MM x 900 MM
230MM THK. BRICK
WALL WITH PLASTER
ON BOTH SIDES
350MM THK. BRICK
WALL WITH WATER
PROOFING & PLASTER
ON BOTH SIDES
STAINLESS
STEEL (SS) SCREEN PIPE
MANHOLE450MM x 900 MM
MANHOLE600MM x 900 MM
150 MM Ø PIPES (2NOS)
WITH CAP CONNECTING
VALVE CHAMBER TO
FILTERATION CHAMBER
OVERFLOW
PIPE TO S.W.D.
MANHOLE600MM x 900 MM
MANHOLE600MM x 900 MM
150 MM Ø PIPE CONNECTING
FILTERATION CHAMBER TO
COLLECTION TANK
VALVE CHAMBER
STEEL BARS EMBEDDED
IN BRICK WORK FOR
LADDER PURPOSE
FILTERATION CHAMBER COLLECTION TANK
X X
Umiya Developers
11th EAC MoM reply Page 15
Point No.14: Calculation on sizing of solar water heating systems to be
furnished.
Compliance: We are not providing solar hot water panels as the terrace area
will be utilized for provision of PV panels to provide energy for for 2 solar
powered lights and one fan in each flat and emergency backup.
Point No.15: Details on solar lighting for common areas as well as for two light
and one fan in each flat to be provided.
Compliance: We have proposed solar panels to provide 2 solar powered lights
and one fan for each of 765 tenements. The calculations for PV panels are as
following:
SOLAR PV PANEL CALCULATION
On average photovoltaic (PV) solar panels will produce 10-13 watts per square
foot of solar panel area. 10 kW/m2 of solar power generation is considered for
following calculations:
Total Terrace Area = 2863.91 m2
Actual usable terrace area for Solar Panels = 1718.34 m2 (60% of total
terrace area)
Power requirement of 2 lights and 1 fan
Connection for 765 tenements =80 W x 869= 61.2 kW approx.
Area required for generation of 1kW is 10m2
Hence area required for generation of 61.2 kW =612 m2
Area available for PV panels = 1106 m2
Solar Power generation = 111 kW = 140 kVA
Thus 140 kVA of Solar power will be supplied to grid and used as stand by
power during emergency.
Point No.16:Solid waste management plan alongwith area earmarked for solid
waste management scheme.
Compliance: Solid waste management plan along with area earmarked for solid
waste management scheme and the location of the SWM in layout is shown in
following figure 11 .
Details Information
Total Waste generation 1,949 kg/day
Biodegradable waste (60%) 1,170 kg/day
(Converted into manure)
Non-Biodegradable waste (40%) 779 kg/day
Umiya Developers
11th EAC MoM reply Page 16
Details Information
(to recyclers)
Sewage treatment Plant sludge 5 m3/d
Solid waste treatment technology Mechanical Composting Unit
No. of unit SWM 2 no.
Capacity 600kg/day
Machine floor area 48 m2
Space provided 60 m2
Figure 11: Areas Earmarked For Solid Waste Management
Point No.17: Management of excavated soil. Pollution control measures to be
taken to control fugitive emission during construction phase including marble
/stone cutting.
Compliance: Excavated soil will be used for the Road pavement & site leveling.
Fugitive emission during construction phase will be control by barricading &
plantation along the plot boundary, water sprinkling at regular interval to arrest
Air Bourne-dust, Use of Ready Mix concrete to avoid excessive movement of
vehicles on the site. Use of PPE such as ear plugs and masks for labours will be
made mandatory wherever there are excess emissions. Precut vitrified tiles will
be used for flooring. Tile cutting will be done within the building and will be
done using water so there will not be any considerable fugitive emission.
Point No.18: Details energy conservation measures to be taken. all points
mentioned in the proposal such as orientation to support reduced heat gain, use
of ASHRAE 90.1, use of ECBC compliant envelope measures to be supported
through drawings and details in the proposal.
Compliance: Internal and external lighting design will be provided as required
by ECBC which will have Lighting Power Density as per space requirements.
Umiya Developers
11th EAC MoM reply Page 17
The project would provide 20% lower LPD than as specified in ECBC, to achieve
energy saving, while providing the required illumination levels, by using high
efficacy lighting.
Tree plantation is proposed along the periphery of the site ensuring adequate
buffer and reducing heat gain by the building so that the buildings will remain
naturally ventilated.
The project design will use high energy performing building materials which
would have low U value (Thermal Conductance) as compared to the conventional
materials. The external wall of building would use fly ash blocks, which will have
mandatory SHGC as required by ECBC.
Point No.19: Layout plan indicating Greenbelt alongwith area earmarked to be
provided.
Compliance: Layout plan indicating Greenbelt is given in the figure 12:
Umiya Developers
11th EAC MoM reply Page 18
Figure 12: Landscape drawing:
18.00 MT. INTDPROAD
D
W
D D
LIFT
D
W
D
D
LIF
T
D
A B C-1 (R)
OP
EN
ST
AIR
OPEN STAIR
OPEN STAIR
OP
EN
ST
AIR
OP
EN
ST
AIR
OP
EN
ST
AIR
OP
EN
ST
AIR
OPE
N S
TAIR
OPE
N STAIR
OPE
N STAIR
OPE
N S
TAIR
OPE
N STAIR
OPE
N S
TAIR
OPE
N STAIR
OPE
N S
TAIR
OPE
N S
TAIR
OPE
N STAIR
ELE
CTR
IC S
UBSTA
TIO
N
1.5
0 M
T. W
IDE
HE
IGH
T C
OM
PO
UN
D W
ALL
1.50
MT. W
IDE H
EIGHT C
OM
POUN
D WALL
1.50 M
T. WID
E HEIG
HT COM
POUND WALL
4.61
3.08
9.33
ST+21
ST+21
ST+21
ST+21
ST+21
ST+21
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22
ST+22ST+22
ST+22 ST+22
ST+22ST+22
ST+22 ST+22
GR+12
GR+12
ST+12
ST+12
GR+13
GR+13
GR+13
GR+13
GR+13
ELECTRIC SUBSTATION
6.00
6.15
8.63
6.19
6.20 6.30
VO
ID
WD
5V
OID
WV
OID
W
VO
ID
WD
5
D2LIFT
D2LIFT
D2 LIFT
D2 LIFT
VOID
W
D5
VOID
W
D5
VOID
W
D5
VOID
W
VOID
W
VOID
W
D2
LIFT
D2
LIFT
D2
LIFT
D2
LIFT
D2
LIFT
D2
LIFT
VOID W
D5
D5
VOID
VOID
W
LIFT
D2
LIFT
D2
VOID
W
D5
LIFT
LIFT
D2
D2
A B-1 (BLDG NO 1)
A B C -1 (BLDG NO 2)
A B -1 (BLDG NO 3)
ELE.
DUCTELE.
DUCT
VOID
VOID
VOID
LIF
T
LIF
T
D
W
DD
ELE.
DUCT
Sr.
No.
Name Nos.
1. Nandruk 15
2. Satwin 10
3. Sita Ashoka 13
4. Royal Palm 7
5. Karanj 14
6. Neem 15
7. Apta 10
8. Coconut 12
9. Son Chapha 14
Total 110
RG on ground: 2,307.36 m2
No. of Trees to be Planted : 110
Nos.
Existing trees: nil