SC Economic Development: Electrification Programme Ms Ayanda Noah Group Executive Distribution. Date 08 October 2013. Content. Orientation on the Electricity Value Chain. Planning Principles. Current Network Status. Electrification Backlog. Risks and Challenges. - PowerPoint PPT Presentation
Citation preview
Date 08 October 2013
SC Economic Development:Electrification Programme
Ms Ayanda NoahGroup Executive
Distribution
Content
2
Orientation on the Electricity Value Chain
Current Network Status
Electrification Backlog
Risks and Challenges
Planning Principles
Progressing Towards Universal Access
3
Electricity GenerationElectricity Generation
Transmission Transmission Lines Lines
(400/275 kV)
Distribution LinesDistribution Lines
ResidentialResidential
Reticulation HV LineReticulation HV Line(11 & 22kV)(11 & 22kV)
ReticulationReticulationLV LineLV Line
(380/220V)(380/220V)
Distribution SubstationDistribution Substation
Transmission SubstationTransmission Substation
The Electricity Supply Chain
POWER POWER STATIONSSTATIONS
Industry, Mining &
Large Metros
Commercial/Small industry/
Farming/Small Munics
High voltage
Medium voltage
Lowvoltage
Customer Services
• Total electricity sales of 216 561GWh and 5 million customers (including transmission customers) as at 31 March 2013
• Supplies approximately 95% of South Africa’s electricity supply• Two main types of customers:
• Redistributors: Mainly municipalities that sell electricity to end customers.• Direct customers: Industrial, commercial, mining, agricultural and residential consumers
• Key Sales and Customer Service unit deals with customers using ≥100GWh of energy per year• As at 31 March 2013, Eskom had 5.0 million customers accounting for electricity revenues of R126.7
billion• One customer has a supply contract indexed to commodity prices• A member of Southern African Power Pool (“SAPP”)
4
Key figures year end to 31 March 2013
Gross Electricity Revenue SplitTotal: 126.7 billion
Number of customersTotal: 5.0 million
Electricity sales by customer for year ended 31 March 2013
Distribution: Division Profile
To service the customer through provision of reliable electricity by building, operating and maintaining distribution assets, while also acting in the national interest by actively partnering with the wider industry in resolving distribution industry issues and enhancing stakeholder relations
Scope and mandate
67 488km of distribution lines269 535km of reticulation power lines6 960km of underground cables3 580MVA of new transformer capacity15 350 employees
Asset base Organisation structure
• Implemented several safety initiatives, which saw an improvement in most of the safety indicators• Sustained improvement of the system average interruption duration index (SAIDI) and the system average interruption frequency index (SAIFI)• Electrification connections exceeded target and also created 4 320 job opportunities• Since inception of the electrification programme in 1991, a total of more than 4.3 million (2012: 4.2 million) homes have been electrified
Highlights and output
• Employee and, in particular, contractor safetyperformance and lost-time injuries• High levels of theft of equipment andelectricity, including illegal connections, affectnetwork and service performance, increasingEskom’s costs• Ageing networks, making maintenance achallenge
Key challenges and priorities
• 5.0 million customers nationally• Nine provincial operating unit Structures are now in place,with fully functional management.
5
Distribution Network Planning Process
6
• Electrification Plan • Land use study • Demographic study • Econometric study • Zoning exercise • Load forecast - geo-based - trend-based • Demand & energy forecast • Scenario creation
Gather & Verify Network & Load
Information
• Geographical background data • Network asset information • Load (MD) profiles • Reports, Guides, Standards, etc • Customer data • Electrification data • Performance KPIs • Transmission plans • Refurbishment plans • Environmental issues
Identify &
Evaluate Alternatives
Capital Plan
& Financial Evaluation
Reporting, Approval
& Project Initiation
• Formulate alternatives • Map alternatives • Technical evaluation - load flow - fault studies • Reliability analysis • Life cycle costing • Economic evaluation • Integrated plans - transmission - sub-transmission - reticulation
• Select Preferred Alternatives • Capital Requirement Plan - Phasing • Financial Evaluation - cash flow - income - tariffs
• Reporting - conceptual plan - geographical presentation • Approval - NMP / NDP • Project initiation - DPA’s / CRA’s • Environmental assessments - SEA’s (EIA’s) • Long lead-time equipment • Servitude acquisition
Analyse Existing
Network Capability
& Define Problem
Statement
• Build network models • Analyse existing network capability - present loads - future loads • Analyse plans - refurbishment - electrification - environmental • Analyse reliability requirements • Define problem statement
Study Objective
& Review of Study Area
•Define study objective •Compile map showing existing NMP/NDP boundaries • Map showing existing networks • Prepare network SLD’s • Review/redefine Study Area boundaries
Compile Load
Forecast & Strategic
Study
Integration of Electrification, Refurbishment, Transmission and Environmental Plans
• Comprehensive Network Planning process - Supported by appropriate Network Planning criteria/standards
• Network Development Plans reviewed every three years (license condition)
• Distribution Master Plans reviewed every 5 years
• Ensure integrity of the design base – compliance assessed by Group Technology
Eskom Electrification Planning Principles
-
23-04-21 7
23-04-21 8
Universal Access Workstream
Distribution Network Constraints
91421 of a total of 8310 MV feeders fail Network Planning criteria (feeders in Red)
February 2013 (as is network)
Planning Criteria assessed:-Voltage limits-Thermal limits-Maximum customer numbers-Maximum line lengths
Estimated cost to addresscapacity constrainednetworks R42.7bn
Distribution Current CAPEX
R54 BN BUDGET Grand Total
Strengthening 24,506Refurbishment 12,857Reliability 2,930
Dx Wires m_report Dec 2012.pt 10
R43 Bn BUDGET 1st CUT Grand Total
Strengthening 19,317
Refurbishment 9,363
Reliability 2,766
R39 Bn BUDGET 2nd CUT Grand Total
Strengthening 16,088
Refurbishment 9,579
Reliability 1.513
11
Electrification Highlights Since Inception
• Added ~4.3 million households to the grid since 1990
• Electricity access has significantly increased from 1994 to-date:
– Nationally from 36% to 83%– Rural electrification from 12% to 57%
• Government’s target of 1.75 million connections between 1994 and 2000 exceeded through a self-funded and managed programme
• Massive delivery– A connection every 30 seconds– A pole every 10 seconds– 200 metres of cable every minute
• Eskom and Shell Joint Venture connected around 6,000 solar home systems between mid-1990s and mid-2000s
• Nearly 32,000 systems have been installed by Non Grid Service Providers granted concessions by the DoE in 2003
There have also been a limited number of off-grid connections
Eskom has made significant strides in connecting South Africans to the grid +
SOURCE: Eskom
Electrification Success : Cumulative Connections
23-04-21 12
Stats SA FiguresStats SA Figures
National Electrification Backlog (2012)
PROVINCE CONNECTION BACKLOG
Free State 200 435
Limpopo 270 877
Gauteng 878 725
Western Cape 212 552
Northern Cape 44
397
Mpumalanga 214 409
North West 157 419
Kwa-Zulu Natal 829 737
Eastern Cape 613 113
TOTAL3 421 664
The national backlog, including municipal backlog is 3,3-million households, of which Eskom’s backlog in proclaimed areas is 1,8-million households, including estimated growth in the Western Cape, Gauteng and Free State. Eskom’s backlog in proclaimed and un-proclaimed areas is 2,3- to 2,5-million households (DoE figures).
The national backlog, including municipal backlog is 3,3-million households, of which Eskom’s backlog in proclaimed areas is 1,8-million households, including estimated growth in the Western Cape, Gauteng and Free State. Eskom’s backlog in proclaimed and un-proclaimed areas is 2,3- to 2,5-million households (DoE figures).
5% 20%
1.5%
6%
24%
5.5%21% 6.5%
10.5%
The Household Back Log (Including Sub- letting residents)
Operating Unit
Households with electricity
Households without electricity
Sub-letting
Free State 726 696 81 397
Limpopo 1 243 642 182 011
Gauteng 3 416 361 492 644
Western Cape 1 525 979 108 017
Northern Cape 257 253 44 152
Mpumalanga 929 372 146 136
North West 892 424 169 560
KwaZuluNatal 1 977 260 562 059
Eastern Cape 1 265 759 421 625
TOTALS 12 234 746 2 207 601 1 214 064
TOTAL 3 421 665
Census 2011/12 FiguresCensus 2011/12 Figures
Sub-letting refers to units constructed on a property in addition to the main home or primary dwelling and are not on an individual plot or stand in the title scheme/cadastre, and can be located within, attached to, or separate from, the principal dwelling.
Sub-letting refers to units constructed on a property in addition to the main home or primary dwelling and are not on an individual plot or stand in the title scheme/cadastre, and can be located within, attached to, or separate from, the principal dwelling.
Estimated Cost To Eradicate Backlog Per Province
Census 2011/12 results 15
PROVINCE
2011/12 Cost per Connection
Provincial Connection
backlog
Cost to Connect Backlog
Free State 7 383.00R 200 435 1 479 814 108.32R
Limpopo 7 655.00R 270 877 2 073 566 687.86R
Gauteng 8 867.00R 878 725 7 791 654 322.99R
Western Cape 9 508.00R 212 552 2 020 939 946.44R
Northern Cape 9 954.00R 44 397 441 927 554.80R
Mpumalanga 10 366.00R 214 409 2 222 560 600.68R
North West 12 711.00R 157 419 2 000 954 817.76R
Kwazulu Natal 19 935.00R 829 737 16 540 813 145.79R
Eastern Cape 22 157.00R 613 113 13 584 750 625.03R
TOTAL/AVERAGE 3 421 665 48 156 981 809.66R
Challenges To Achieving Universal Access
23-04-21 16
Increase of the cost per connection due to long Medium Voltage line (11 and 22KV )
Project management & design skills shortage;
Sparsely populated rural areas;
Infrastructure projects in support of other implementing agents;
Municipal upgrades for After Diversity Maximum Demand (ADMD)
Constrain due to reduced Eskom Capex expenditure;
• Refurbishment (Eskom funded)
• Network Upgrade (Eskom funded)
• Strengthening projects (Eskom funded)
• New build (Funded by DoE 70/30 principle applies)
23-04-21 17
Grid & non-grid, Master Plan (DoE & Eskom working on a Master Plan);
Agreed service levels of the non grid to be similar to grid;
Harmonization of government initiatives e.g. electrification and housing programmes
Aligned policies to facilitate implementation process (e.g. un-proclaimed, land usages);
Installation of two meters in double stand dwellers;
Increase fund allocation to cater for infrastructure projects:
Refurbishment of constraint networks related to electrification.
Upgrading of the networks.
70/30 principle in new builds networks to be continued.
Some Opportunities To Facilitate UAP Achievement
Single homestead in a mountain(High cost per connection)
23-04-21 18
Cost per connection in Densely populated area is low
23-04-21 19
The burden falls disproportionately on women and girls
TThe girl child & her mom are still fetching wood
to cook & keep warmBrussels, April 21, 2023 page 20
The elect. challenge is Real & Material
Universal Access Programme
23-04-21 21