Leighton Qatar – Al Jaber Engineering JV
Leighton Qatar – Al Jaber Engineering JV
NEW ORBITAL HIGHWAY CONTRACT 3
Leighton Qatar – Al Jaber Engineering JV
NEW ORBITAL HIGHWAY CONTRACT 3
Junction 7
2*5 (2+3) Main Bridges:
700m total length, 16 spans,
2 Ramp Bridges:1 450m total
length,35 spans,
Leighton Qatar – Al Jaber Engineering JV
NEW ORBITAL HIGHWAY CONTRACT 3
2 Ramp Bridges:780m total
length,18 spans,
Junction 8
Leighton Qatar – Al Jaber Engineering JV
NEW ORBITAL HIGHWAY CONTRACT 3
2*6 (3+3) Main Bridges:620m total
length, 16 spans,
2 Ramp Bridges:1 400m total
length,34 spans,
Junction 9
Leighton Qatar – Al Jaber Engineering JV
Junction 10
2 *1 Main Bridges:260m total
length,8 spans,
2 Ramp Bridges:1 280m total
length, 33 spans,
Leighton Qatar – Al Jaber Engineering JV
Junction 11
2 *2 (3+3) Main Bridges:520m total length,
16 spans,
Leighton Qatar – Al Jaber Engineering JV
Ramp Bridges Typical DetailsPlan, Elevation and Cross section of typical module (Junction 7)
Constant width (13.60m) and constant depth (2.60m) for
all ramp bridge boxesWeight between 55 & 87tons
Leighton Qatar – Al Jaber Engineering JV
Main Bridges Typical Details
Segments stitched together transversely to create varying widths required for each Main
Bridge
Constant width (7,00m) and constant depth (2.35m) for all
main bridge boxesWeight between 48 & 69 tons
Plan, Elevation and Cross section of typical module (Junction 9)
Leighton Qatar – Al Jaber Engineering JV
Precast Yard Location
Leighton Qatar – Al Jaber Engineering JV
Precast Yard Decomposition
PROD
UCTI
ON D
IREC
TION
REBAR AREA
CASTING AREA
FINISHING AREASTORAGE AREA
Leighton Qatar – Al Jaber Engineering JV
Stage of Precasting
oRebar – Cage Assembly
oSegment Casting & Curing
oSegment Finishing
oSegment Storage
Leighton Qatar – Al Jaber Engineering JV
WHAT IS NEEDED?
• Materials
• Manpower
Special Team for Civil & PT Works
• Rebar & Formwork Shop Drawing
• Equipment:
Gantry Crane 100t 3uTower Crane 8,2t @ 40m 2uRegar Jig 8u* 3 linesRebar-Cage Lifting Beam
Segment Steel Skeleton
Leighton Qatar – Al Jaber Engineering JV
Segment Casting & Curing
1. Rebar – Cage Positioning in Casting cell
2. Adjustment cover, insert, opening PT items,
3. Close Formwork,
4. Order & Delivery of Concrete,
5. Concrete placement,
6. Curing Compound:a) 12 hours water curing,b) After 12 hours Application of
Curing Compound application,
7. Stripping Formwork after12 hours – shift mash-cast segment with manipulator,
8. After 36hours lifting Segment,
Leighton Qatar – Al Jaber Engineering JV
Segment Finishing
1. Curing Compound application on Segment Bottom Slab,
2. Segment Finishing,
3. Segment lifting,
Leighton Qatar – Al Jaber Engineering JV
Segment Storage
1. Segment Storage, 2 layers,
2. Storage 28days,
3. Segment Lifting to trailer for erection site,
Leighton Qatar – Al Jaber Engineering JV
Precast Yard – Moulds & Production Rate
Moulds
•Ramp Bridges: 1 434 Segments No. of Moulds = 8
6 Field Segments + 1 Pier + 1 Expansion JointFor all Casting Cells the installation & commissioning are done
•Main Bridges: 846 Segments No of Moulds = 5
2 Field Segment + 1 Deviator + 1 Pier + 1 Expansion Joint 1 Field Segment casting cell Installation & commissioning done
The other casting cells the installation is ongoing
Production Rate:
•Field and Deviator segment = 1 segment per mould per day 9 Segments/Day •Pier and Expansion Joint = 1 segment per mould every 2 days 2 Segments/Day
Transportation of Segments:
•Ramp Bridges: 6 Trucks * 2 trips/ day by 2 shifts 24 Segments/Day
•Main Bridges: 6 Trucks * 2 trips / day 12 Segments/Day
Leighton Qatar – Al Jaber Engineering JV
Erection Segments – Ramps Bridges
Segments are transported one by one to site and lifted to their final position.
This erection process will involve:
1.Lifting the segment off the transport truck using special equipment or crane to place them to their
final position in the superstructure.
2.Temporarily hanging or supporting the segment from temporary works
3.Once all the segments are in the final position, they are joined and post-stressed to form the
permanent monolithic superstructure
For NOH Contract 3 - The most effective method to construct the ramps with precast segments is to use the:
Span by Span Method with an Underslung Launching Gantry
The first launching girder is under delivery at Ramp Bridges Junction 8The second are under fabrication delivery planned before the end of this year
.
Leighton Qatar – Al Jaber Engineering JV
Erection Sequence – Ramps Bridges
Launching Gantry
Underslung
Precast segments
Typical span by span erection with Underslung Launching Gantry
And crawler cranes 2 units of 220tnsSupplier of Crawler Crane AERTSSEN
Production Rate: 2,5 days by span
Leighton Qatar – Al Jaber Engineering JV
Erection Sequence – Ramps Bridges
Leighton Qatar – Al Jaber Engineering JV
Erection Sequence – Main Bridges
Segment placement by use of crawler cranes of 200 tons
Main Bridge Erection works on Falsework
Production Rate: 5 days by line
Leighton Qatar – Al Jaber Engineering JV
Erection Sequence – Main Bridges
Erection over Salwa Road with 2 x Portals
Leighton Qatar – Al Jaber Engineering JV
NEW ORBITAL HIGHWAY CONTRACT 3
Thank you for your Thank you for your attentionattention