Leighton Qatar – Al Jaber Engineering JV

DATA2015-12-06 Ashghal Presentation 2

Embed Size (px)

Citation preview

Page 1: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Page 2: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

NEW ORBITAL HIGHWAY CONTRACT 3

Page 3: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

NEW ORBITAL HIGHWAY CONTRACT 3

Junction 7

2*5 (2+3) Main Bridges:

700m total length, 16 spans,

2 Ramp Bridges:1 450m total

length,35 spans,

Page 4: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

NEW ORBITAL HIGHWAY CONTRACT 3

2 Ramp Bridges:780m total

length,18 spans,

Junction 8

Page 5: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

NEW ORBITAL HIGHWAY CONTRACT 3

2*6 (3+3) Main Bridges:620m total

length, 16 spans,

2 Ramp Bridges:1 400m total

length,34 spans,

Junction 9

Page 6: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Junction 10

2 *1 Main Bridges:260m total

length,8 spans,

2 Ramp Bridges:1 280m total

length, 33 spans,

Page 7: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Junction 11

2 *2 (3+3) Main Bridges:520m total length,

16 spans,

Page 8: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Ramp Bridges Typical DetailsPlan, Elevation and Cross section of typical module (Junction 7)

Constant width (13.60m) and constant depth (2.60m) for

all ramp bridge boxesWeight between 55 & 87tons

Page 9: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Main Bridges Typical Details

Segments stitched together transversely to create varying widths required for each Main

Bridge

Constant width (7,00m) and constant depth (2.35m) for all

main bridge boxesWeight between 48 & 69 tons

Plan, Elevation and Cross section of typical module (Junction 9)

Page 10: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Precast Yard Location

Page 11: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Precast Yard Decomposition

PROD

UCTI

ON D

IREC

TION

REBAR AREA

CASTING AREA

FINISHING AREASTORAGE AREA

Page 12: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Stage of Precasting

oRebar – Cage Assembly

oSegment Casting & Curing

oSegment Finishing

oSegment Storage

Page 13: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

WHAT IS NEEDED?

• Materials

• Manpower

Special Team for Civil & PT Works

• Rebar & Formwork Shop Drawing

• Equipment:

Gantry Crane 100t 3uTower Crane 8,2t @ 40m 2uRegar Jig 8u* 3 linesRebar-Cage Lifting Beam

Segment Steel Skeleton

Page 14: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Segment Casting & Curing

1. Rebar – Cage Positioning in Casting cell

2. Adjustment cover, insert, opening PT items,

3. Close Formwork,

4. Order & Delivery of Concrete,

5. Concrete placement,

6. Curing Compound:a) 12 hours water curing,b) After 12 hours Application of

Curing Compound application,

7. Stripping Formwork after12 hours – shift mash-cast segment with manipulator,

8. After 36hours lifting Segment,

Page 15: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Segment Finishing

1. Curing Compound application on Segment Bottom Slab,

2. Segment Finishing,

3. Segment lifting,

Page 16: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Segment Storage

1. Segment Storage, 2 layers,

2. Storage 28days,

3. Segment Lifting to trailer for erection site,

Page 17: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Precast Yard – Moulds & Production Rate

Moulds

•Ramp Bridges: 1 434 Segments No. of Moulds = 8

6 Field Segments + 1 Pier + 1 Expansion JointFor all Casting Cells the installation & commissioning are done

•Main Bridges: 846 Segments No of Moulds = 5

2 Field Segment + 1 Deviator + 1 Pier + 1 Expansion Joint 1 Field Segment casting cell Installation & commissioning done

The other casting cells the installation is ongoing

Production Rate:

•Field and Deviator segment = 1 segment per mould per day 9 Segments/Day •Pier and Expansion Joint = 1 segment per mould every 2 days 2 Segments/Day

Transportation of Segments:

•Ramp Bridges: 6 Trucks * 2 trips/ day by 2 shifts 24 Segments/Day

•Main Bridges: 6 Trucks * 2 trips / day 12 Segments/Day

Page 18: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Erection Segments – Ramps Bridges

Segments are transported one by one to site and lifted to their final position.

This erection process will involve:

1.Lifting the segment off the transport truck using special equipment or crane to place them to their

final position in the superstructure.

2.Temporarily hanging or supporting the segment from temporary works

3.Once all the segments are in the final position, they are joined and post-stressed to form the

permanent monolithic superstructure

For NOH Contract 3 - The most effective method to construct the ramps with precast segments is to use the:

Span by Span Method with an Underslung Launching Gantry

The first launching girder is under delivery at Ramp Bridges Junction 8The second are under fabrication delivery planned before the end of this year

.

Page 19: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Erection Sequence – Ramps Bridges

Launching Gantry

Underslung

Precast segments

Typical span by span erection with Underslung Launching Gantry

And crawler cranes 2 units of 220tnsSupplier of Crawler Crane AERTSSEN

Production Rate: 2,5 days by span

Page 20: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Erection Sequence – Ramps Bridges

Page 21: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Erection Sequence – Main Bridges

Segment placement by use of crawler cranes of 200 tons

Main Bridge Erection works on Falsework

Production Rate: 5 days by line

Page 22: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

Erection Sequence – Main Bridges

Erection over Salwa Road with 2 x Portals

Page 23: DATA2015-12-06 Ashghal Presentation 2

Leighton Qatar – Al Jaber Engineering JV

NEW ORBITAL HIGHWAY CONTRACT 3