LHB POPULATION (RAILWAY WISE)
SR CR NCR SCR SWR ECR SER ECoR ER WR NR TOTAL
14 16 18 22 26 41 44 49 182 171 505 1088
WARRANTY PERIOD OF MAJOR COMPONENTS
WARRANTY PERIOD ITEMS
Service Life >= 30,00,000 KM
•CTRB (Roller Bearing)
06 Years •Lateral Bump stop•Ball Joint Control Arm•Ball Joint Roll Link•Traction Center Elastic Joint•Rubber Spring
4 Years •Dampers (all types)•Secondary Rubber Pad
WARRANTY PERIOD OF MAJOR COMPONENTS WARRANTY PERIOD ITEMS
2 Years (IRS
Conditions)
•Springs (all types)•Ball Joint Traction Lever•Axle mounted Disc brake system•Doors (all types)•Water Tanks (all types)•Fuel Tank•UIC Vestibule•CDTS (all types)•Seats & berths (all Types)•Secondary Rubber Pad•High Tensile AAR “H”
Type Tight lock CBC•Lavatory Module.•FRP Ceiling Panels (All Types)•FRP Side Panels (All Types) •Sealed Windows (all Types)•Honey Comb Partition Frame (all types)•PU Paint•Flooring
1 Years •Wheel Set
WARRANTY PERIOD OF MAJOR ELECTRICAL COMPONENTS Item (Electrical) Warranty period
500KVA, 3 PHASE Diesel Driven Alternator set 5 YearBattery chargers 12 monthsRMPU 12 months50KVA, 3 PHASE Diesel Driven Alternator set
IRS Conditions
TransformersPre‐cooling transformers60 KVA transformersPA system for 1ACPA system for BuffetPA system for Power CarPA system for EOG CoachesPA system PA system for Chair CarBatteries
WARRANTY PERIOD OF MAJOR ELECTRICAL COMPONENTS
Item (Electrical) Warranty period
Regulated Battery chargerIRS Conditions
Emergency Battery Charger
Switch Board Cabinet for BUFFET
Switch Board Cabinet for AC/SG
Switch Board Cabinet for EOG
Switch Board Cabinet for Power car
Pantry equipments
FIRM WISE COMPLAINTS OF CDTS IN ALL TYPES OF COACHES
FIRM AIKON VIBHU AMIT DARSHAN Total2009‐10 53 62 4 8 1272010‐11 78 127 26 34 2652011‐12 43 7 33 ‐ 83Total 174 196 63 42 475
Pending 35 (TKPR, SRC) ‐ 33 (SRC) ‐ 68
YEAR WISE COMPLAINTS OF CDTS IN ALL TYPES OF COACHES
FIRM AIKON VIBHU AMIT DARSHAN Total
2009‐10 53 62 4 8 1272010‐11 78 127 26 34 2652011‐12 43 7 33 ‐ 83Total 174 196 63 42 475
FAILURES OF CDTS IN ALL TYPES OF COACHESDefects AIKON VIBHU DARSHAN AMIT Total
Speed sensor 35 26 12 12 85
Dislodging of lav. Pan 10 47 8 - 65
Power supply /DC-DC converter 28 17 2 1 48
Slide / cylinder 37 6 - 43
Switches defective 16 11 14 - 41
Slide valve problem 5 24 1 1 31
Flapper/ valve 1 9 - 19 29
Solenoid valve 13 3 1 5 22
Retention Tank - 5 - 16 21
PLC defective 5 13 1 - 19
Lower slide paddle/ gasket - 15 - - 15
Pressurizer control NRV/ rubber 1 11 1 6 15
Air filter problem 4 - 2 3 9
Air pipe/ isolating cock 5 2 - 5
Flush cover - 4 - - 4
Water supply 4 - - - 4
Flush valve 4 - - - 4
Water filter 3 - - - 3
Flapper cylinder bkt. - 3 - - 3
Leakage 3 - - - 3
Total 174 196 42 63 469
DAMPER POPULATION UPTO JUNE’11Firm name KONI SACH GEREP MEDITTER ESCORT ABROL TOTAL
PRIMARY 8 0 0 0 0 0 8
SECONDARY 4 0 0 0 0 0 4
YAW 2165 2031 900 75 15 0 5186
secondary V/GS 73 123 12 0 0 0 208
LATERAL 756 1582 400 44 5 0 2787
PRIMARY 1948 5870 2366 139 19 0 10342
SECONDARY 997 2806 1201 80 10 48 4805
TOTAL Population
5951 12412 4879 338 49 48 22340
Major defects: leaky, fixing arrangement failure, silent bush perishing, breakage & corrosion on protecting tube casing.
DAMPER FAILURE UPTO JUNE’11
Firm name KONI SACH GEREP MEDITTER ESCORT ABROL TOTALTOTAL
Population5951 12412 4879 338 49 48 22340
FAILURES 82 587 84 0 0 0 753
% age Failure 1.37 4.8 1.7 0 0 0 3.37
2008-09 - 306 - 306
2009-10 0 142 0 0 0 0 1422010-11 81 139 84 0 0 0 304
2011-12 1 0 0 0 0 7
TOTAL 82 587 84 0 0 0 753PENDING
COMPLAINTS 01 103 05 0 0 0 109
ER –
32, SR ‐22, NR ‐21, SER ‐13, WR‐7, NCR‐7, SCR‐7Major defects: leaky, fixing arrangement failure, silent bush perishing,
breakage & corrosion on protecting tube casing.
FIRMS WISE FAILURE DATA OF DAMPERSYear Name of firm Primary Secondary Yaw Railways
2008‐09 Sach (M.G.World wide) 15 ‐ ‐ ECR
Sach (M.G.World wide) 88 44 9 ER
Sach (M.G.World wide) 150 ‐ ‐ WR
TOTAL 253 44 9
2009‐10 Sach (M.G.World wide) 53 29 9 ERSach (M.G.World wide) 12 7 32 NR
TOTAL 65 36 412010‐11 Sach (M.G.World wide) 62 15 6 ER
Sach (M.G.World wide) 22 ‐ ‐ SRSach (M.G.World wide) 15 4 2 SERSach (M.G.World wide) 6 1 ‐ WR
Sach (M.G.World wide) 3 ‐ ‐ NCR
Sach (M.G.World wide) 2 ‐ ‐ SCR
TOTAL 110 20 8
FIRMS WISE FAILURE DATA OF DAMPERSYear Name of firm Primary Secondary Yaw Railways
2010‐11 Koni (Pan India) 22 28 4 ER
Koni (Pan India) 3 ‐ 5 NCR
Koni (Pan India) 3 ‐ ‐ SR
Koni (Pan India) 2 ‐ ‐ SCR
Koni (Pan India) 1 ‐ ‐ SER
TOTAL 31 28 9GEREP (SFT Engg.) 21 47 2 ER
GEREP (SFT Engg.) 9 ‐ ‐ SER
GEREP (SFT Engg.) 5 ‐ ‐ SCR
TOTAL 35 47 2
2011‐12 Koni (Pan India) ‐ 1 ‐ SER
TOTAL ‐ 1 ‐
RAILWAY WISE FAILURE DATA OF DAMPERSYear Type of
damperSER ER WR NCR NR SR ECR SCR TOTA
L
2008‐
09PRIMARY ‐ 88 150 ‐ ‐ ‐ 15 ‐ 253
SECONDARY ‐ 44 ‐ ‐ ‐ ‐ ‐ ‐ 44
YAW ‐ 9 ‐ ‐ ‐ ‐ ‐ 9
2009‐
10PRIMARY ‐ 53 ‐ ‐ 12 ‐ ‐ ‐ 65
SECONDARY ‐ 29 ‐ ‐‐ 7 ‐ ‐ ‐ 36
YAW ‐ 9 ‐ ‐ 32 ‐ ‐ ‐ 41
2010‐
11PRIMARY 25 105 6 6 ‐ 25 ‐ 9 176
SECONDARY 4 90 1 ‐ ‐ ‐ ‐ ‐ 95
YAW 2 12 ‐ 5 ‐ ‐ ‐ ‐ 19
2011‐
12PRIMARY ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
SECONDARY 1 ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1
YAW ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
TOTAL 32 439 157 11 51 25 15 9 739
Firm Type of coach LWRRM LWACCN LWACC W
LFA C
TOTA L
LPDN
PRIMARY INNER - 2 - - 2
SECONDARYINNER 1 3 - - 4
OUTER 5 - - - 5
GRUEBER PRIMARY OUTER 1 5 3 3 12
TOTAL 07 10 3 3 23
BREAKAGE PRIMARYINNER 1 5 3 3 12
OUTER 1 5 - 06LIP
DEFORMATIONSECONDARY OUTER 1 - - - 01
BUFFER HEIGHT
SECONDARY OUTER 4 - - - 04
TOTAL 07 10 3 3 23
Data of Spring Failure 2008‐09 TO 2011‐12
LHB SPRING DETAILSTYPE OF COACH OUTER SPRING INNER SPRING
DRG. NO. PL NO. DRG. NO. PL NO.
PRIMARY PRIMARYChair Car, Ex. CC, 2 Tier, Hot
Buffet, First Class
1267411 33503035 1267412 33503047
3 Tier 1267411 33503035 1277143 33500356
Power Car (Guard & Gen) 1277142 33500368 1277143 33500356
SECONDARY SECONDARYChair Car, Ex. CC, 2 Tier, Hot
Buffet, First Class
1269514 33503060 1269513 33503059
3 Tier 1268836 33500400 1269513 33503059
Power Car (Guard) 1277146 33500381 1277145 33500370
Power Car (gen) 1268836 33500400 1268837 33500393
DEFECTS IN CBCFirm name Faiveley Escort ASF Key
StoneTOTAL
Knuckle pin replaced ‐ 52 ‐ 52Supporting Compression spring
replaced08 ‐ ‐ 08
Supporting bolt shear ‐ ‐ 08 08CBC knuckle changed ‐ 06 ‐ 06CBC tell tale recess unclear 06 ‐ ‐ 06
Defective spring cartridge
assembly of back lash
compensating device
01 ‐ ‐ 01
Unclamping device not working 1 ‐ ‐ 01Total 16 58 08 82
YEAR WISE FAILURES OF CBCFirm name Faiveley Escorts ASF Key Stone TOTAL
2008‐09 02 ‐ 08 102009‐10 06 ‐ ‐ 062010‐11 08 58 ‐ 66
Total 16 58 08 82
FIRM WISE FAILURES OF CBCFirm name Faiveley Escorts ASF Key Stone TOTAL 2008‐09 02 ‐ 08 102009‐10 06 ‐ ‐ 062010‐11 08 58 ‐ 66Total 16 58 08 82
FIRM WISE FAILURE OF CBC IN 08‐09, 09‐10, 10‐11
Firm name Faiveley Escorts ASF Key Stone TOTAL
2008‐09 02 ‐ 08 102009‐10 06 ‐ ‐ 062010‐11 08 58 ‐ 66
Total 16 58 08 82
ENROUTE COACH DETACHMENT (BEARING FAILURES) 2008‐09DATE 20/09/2008 22/10/2008
TRAIN NO. (SDAH‐
Rajdhani) 2423 (Rajdhani Exp.)
PRIMARY SDAH NDLS
STATION Bela Koba (KIR Division)
COACH DETAILS ER 06116 LWACCNB/ DATE: R/DATE : IOH : 08/11/2007
NR06854 LWLRRMB/DATE: 02/2007(RCF)R/DATE : 02/2010IOH :
BEARING DETAILS TIMKEN TIMKEN
PERIOD BEFORE FAILURE 20 Months
VISUAL INSPECTION
Cage broken.
Sealing Ring damaged.
Cage broken
Rollers damaged.
ENROUTE COACH DETACHMENT (BEARING FAILURES) 2008‐09
DATE 23/01/2009TRAIN NO. 2310 (NDLS‐RNCC)PRIMARY RNCC
STATION Somna (GHZ‐TDL section)COACH DETAILS EC 07851 LWLRRM
B/ DATE: 04/2007 (RCF)R/DATE : 04/2010IOH :
BEARING DETAILS TIMKEN
PERIOD BEFORE FAILURE 20 Months VISUAL INSPECTION
Cage broken.
Grease burnt.
Outer race broken.
Rollers seized.CAUSES
Cage broken
ENROUTE COACH DETACHMENT (BEARING FAILURES) 2010‐11
DATE 02/05/2010TRAIN NO. 2444 (BBS‐NDLS RAJDHANI)PRIMARY NEW DELHISTATION DHANMANDALCOACH DETAILS NR‐LACCN 10106
B/DATE : 02/2010 (RCF)R/DATE : 04/2012IOH : ‐‐‐
BEARING DETAILS TIMKENPERIOD BEFORE FAILURE 2 MonthsVISUAL INSPECTION
LTTR
Outer race melted.
Cage melted
Inner race partially melted.
Locking plate meltedCAUSES
Over heating , melting and breakage of outer race.
CORRECTIVE MEASURES
RWF to ensure thread length as 35 mm.
Axle end cap screw is standardized to 60 mm.
Locking plate to be modified to ensure proper locking of
screw head.
IMPROPER LOCKING PLATE
Though locking plates are received as per the drawing but it
is
observed
that locking tabs are not
in
a
position
to
lock the hex head screw from three faces.
Suggestion:Position of locking tabs should be at 120º .
ENROUTE COACH DETACHMENT (BEARING FAILURES) 2010‐11DATE 5/9/10 25/10/2010TRAIN NO. 2421 (BBS‐NDLS) Rajdhani Patna‐NDLS RajdhaniPRIMARY New DelhiSTATION Hijli near KGP Mugal SaraiCOACH DETAILS NR 07122 LWACCN
B/Date : 09/2007R/Date : 11/2010IOH: 02/05/2009 (JUDW)
NR 9057 LACCWB/Date : 03/2010R/Date: 03 /2013
BEARING DETAILS TIMKEN TIMKENPERIOD BEFORE
FAILURE
23 Months 7 Months
VISUAL INSPECTION
Journal badly scoured
Partially melted and elongated
Axle box front cover &rollers
were missing
Inner & outer recess had also
melted.
Earthing equipment missing
Earthing housing found broken.
Rubbing mark on bearing seal.
01 no. Axle end screw worked out.
CAUSES
Could not be ascertained due to
complete rollers falling down.
Due to breakage of wheel set earthing
equipment.
CORRECTIVE MEASURES
Look out glass has been incorporated on the
housing.
Inspection of wheel set earthing equipment is to
be incorporated in the maintenance schedule.
Improper grinding of sole bar & sidewall joints of LHB & Hybrid type coaches.
Grinding of welding joints between sole bar and sidewall ensured.
SOLE BAR WELDING
Undulations on Lavatory floor (Front Part)
Heavy undulations Undulations eliminated
Ribs provided
Complaints
from
various
railways
were received regarding stagnation
of
water
on
lavatory
floors.
Undulations
in
front
part
have
been
eliminated
by
providing
supporting
ribs. This
is
to
be incorporated in the drawing.
Complaints
regarding
water
logging
near
doorways
and working
out
of
water
discharge
pipe
has
been
reported
by many railways.
3 Joints
Water Discharge Pipe
EARLIER NOW
Lavatory Pan dislodging problem
ProblemComplaints of Lavatory Pans getting loosened and dislodged from the
FRP base were reported from various railways.Solution
• Studs are welded on the backside of lavatory pan so as to hold the pan firmly with the FRP floor. This has completely eliminated the problem. Sikaflex 221 has been standardized for adhesion & sealing.
Studs
Breakage of Snack table were reported due to failure of adhesive at the joints .Corrective Actions :
•Single piece injection moulded polycarbonate snack table has been developed which can accommodate six water bottles.
Breakage of Polycarbonate Snack Table
Earlier Now
Brakage/theft of earthing unit
• Cases of breakage of Earthing Cable
• Breakage of Al. earthing box cover
Water tank level gauge
•Complaints of defective gauge has received from Zonal Rlys.
•Tank manufactures refuse to replace these defective gauges as RCF
has recommended BAYHAM make only.
QUALITY CONTROL ON APPLICATION OF VINYL WRAPPING
1.
Surface
preparation
is
ensured
by
way
of
roughening
and
removal of uneven paint marks for better adhesion.2.
Overlapping of vinyl sheets between two joints on sidewall. 2.
Edge sealing started immedietly & simultaneously after fixing of
vinyl sheets.3.
Shower test ing is done prior to Vinyl wrapping.4.
No Vinyl wrapping on door‐way corners.5.
Overlapping of vinyl wrapping to endwalls .6.
No vinyl wrapping on turn‐under.7.
No vinyl wrapping on power car grills.8.
20 mm gap below rain water gutter. 9.
10 mm gap around non ac windows.10.
No vinyl wrapping on window rubber sealings.11.
Vinyl wrapping application done in covered shed
CBC Knuckle pin jamming reported by SER: Garnets were found adjoining knuckle pin housing. Thorough masking of CBC during garnet blasting is ensured.
High incidence of corrosion and pitting in FIAT Bogies within 3years of service.
Breakage of Allen bolts of upper berth guide - SER
Bump stop clearance problems – SER
Corrosion of dampers and its cover. – ER
Berth reading lights defective. – NCR
Soap dispenser rusty. – NCR
Air entrapment in water tank circulation.
Upper berth nylon sleeve breakages.
Working out of loading door.
Breakage of disc brake and its cooling fins.