DASR: A Poseidon Adventure
SQNLDR Justin TaylorResponsible Manager
11SQN DASR.145
A New Platform Under a New Reg Set
• This is a discussion about my experience in standing up the P-8A part 145.
• It will cross over instuff about P-8A, the CAMO, DASR etc.
• But that is coincidental
Setting the scene• A cooperative program to produce, sustain and develop the
P-8A Poseidon with the USN
• The acquisition strategy drove the design acceptance strategy to RPA (TAREG 2.2.7)
• The acquisition strategy drove the sustainment concept to remain in lock step
• The sustainment strategy drove the maintenance and operational concept to be a 13th squadron
• But...
...we can't help ourselves
• That 13th squadron is a second FEG, a second FST, a second Model Manager, a second (and third and fourth) supply chain, a second airworthiness authority, a second capability developer, etc.
• And an infinite number of opinions...
• And that is all okay
A47-001 Timeline• First Pass - 16 Jul 2007
• IC - 05 Dec 2011
• Second pass - 17 Feb 2014
• Contract Award - 28 Aug 2015
• DASR M Approval - 23 Sep 2016
• Airworthiness Board - 28 Sep 2016
• DASR 145 Approval - 30 Sep 2016
• A47-001 delivers to NAS JAX - 19 Oct 2016
• Design Acceptance - 19 Oct 2016
• MTC - 26 Oct 2016
• CoA - 28 Oct 2016
• Functional Acceptance - 03 Nov 2016
• Home - 17 Nov 2016
The Other Factors• Pre-improved workforce
• FWR, MPIP & Fitters
• Sustained AP-3C Ops
• Air Movements
• Australian-unique Maintenance Data (publications)
• SEWP, IMI, usability
• Common Configuration
• S&TE
Challenges of building Maintenance Organisations on the fly
• The concept of Phase 1 was to migrate existing TAREG AMO to DASR 145
• KC-30 and E-7 maintenance OIP are closer than AP-3C
• No experienced P-8A maintainers
• No experience in the Cooperative Program
• The facilities designed for P-8A are not only late to need (albeit on schedule), but actively impinging on the available space to operate.
• The maintainers under training left TAREG and got experience in NAMP*... and come home to DASR
• The SEWP publications weren't delivered until 29 Sep 2016
• Lots of draft procedures for the Lot 6 (Block 4) configuration
• Based on a low feedback culture
• Support & Test Equipment sustainment & use
Vague enough to work, specific enough to be approved
The Rub• Adaptability - the life we have
chosen
• Scope of Work
• Line, component & base Vs O/(I)/D
• Facilities
• Workforce plan
• Relationships
• RM - AM - QM
• AMC
The Genius
• IAPC
• 0 days under TAREG
• Additional rigour to OIP review
• Ownership
• And an excuse for change
The Future• Cross-platform Line Maintenance
• More granular workforce planning
• Articulation of the shortfall
• More flexibility in the non-airworthiness tasking
• Better use of allied and CIS trades
Reflection
CRE
CAMO trust
But I wouldn't have had it any other way
QUESTIONS?