26
DAMAGES WITHOUT A CLAUSE: LIQUIDATED DAMAGES ARE A PENALTY WHEN OWNERS RECOVER DAMAGES FOR THEIR OWN DELAY September 9-11, 2019 Christopher J. Brasco [email protected] Presented by: 1765 Greensboro Station Place Suite 1000 McLean, Virginia 22102 703-749-1000 www.watttieder.com Presented at Kathleen O. Barnes [email protected] 1

DAMAGES WITHOUT A CLAUSE - Tunneling Short …...DAMAGES WITHOUT A CLAUSE: LIQUIDATED DAMAGES ARE A PENALTY WHEN OWNERS RECOVER DAMAGES FOR THEIR OWN DELAY September 9-11, 2019 Christopher

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

  • DAMAGES WITHOUT A CLAUSE: LIQUIDATED DAMAGES ARE A PENALTY WHEN OWNERS RECOVER DAMAGES FOR THEIR OWN DELAY

    September 9-11, 2019

    Christopher J. [email protected]

    Presented by:

    1765 Greensboro Station PlaceSuite 1000

    McLean, Virginia 22102703-749-1000

    www.watttieder.com

    Presented at

    Kathleen O. [email protected]

    1

  • HYPOTHETICAL

    2

  • O O C C

    OWN-R-US OWNER

    CORDIALCONTRACTOR

    Kathy Barnes Chris Brasco

    3

  • Case Background

    Tunnel project 12 months behind scheduleVarious delays associated with the

    Project Contractor does not submit Notice of the

    Delays or a Request for a Time ExtensionAt end of the Project, Owner assesses

    twelve months of LDs

    4

  • Hypothetical Contract Language

    Notice Provision● “Should the Contractor be delayed or disrupted in performing

    the Work, Contractor shall promptly, and in no event more than five (5) business days after the occurrence of the event, notify the Owner in writing of the condition. Failure to strictly comply with this notice requirement shall be sufficient cause to deny the Contractor an extension of time / any additional compensation.”

    5

  • Hypothetical Contract Language

    Claim Submission Provision● “Any request by the Contractor for an extension of time shall

    be made in writing to the Owner no more than thirty (30) days after the initial occurrence of any event which, in the Contractor's opinion, entitles the Contractor to an extension of time. The claim must include a Time Impact Analysis (TIA) including a written narrative and supporting schedule fragnetdetailing the anticipated schedule impact of the change(s), if any. Failure to timely submit a claim to the Owner shall constitute a waiver by the Contractor of any claim for an extension of time and/or additional compensation.”

    6

  • Hypothetical Facts- Round 1Scenario No. 1

    (Concurrent Delay)

    7

  • Hypothetical Facts- Round 1

    Scenario No. 2(Owner-Caused Delay)

    8

  • LIQUIDATED DAMAGESOverview and Evolution

    9

  • What Are Liquidated Damages?

    Liquidated Damages (“LDs”) provisions generally specify a per diem charge that will be assessed against the contractor for each calendar day project completion is delayed beyond an established contractual milestone (i.e., substantial completion)

    10

  • Public Policy Against Penalties / Forfeitures

    v.Freedom to Contract

    Conflicting Concerns

    11

  • “Damages for breach by either party may be liquidated in the agreement but only at an amount that is reasonable in the light of the anticipated or actual loss causedby the breach and the difficulties of proof of loss. A term fixing unreasonably large liquidated damages is unenforceable on grounds of public policy as a penalty.”-Restatement (Second) of Contracts § 356 (1981)(emphasis added)

    Centrality of Causation

    12

  • Elements of a Breach of Contract Claim1) Existence of a contract2) Contractual performance by plaintiff3) Breach of the contract by defendant 4) Resulting damages

    “Causation is an essential element of damages in a breach of contract action.” - Nat'l Mkt. Share, Inc. v. Sterling Nat. Bank, 392 F.3d 520, 525 (2d Cir. 2004)

    Basics of Contract Damages

    13

  • Liquidated Damages provisions are generally enforceable when:● Intended to be compensatory rather than punitive;●The injury from the contractual breach is difficult to precisely

    quantify; and●The amount of stipulated damages is a reasonable forecast

    of future loss[Source: 24 Williston on Contracts § 65:3 (4th ed.)]

    Enforceability

    14

  • Evolution of the Law on LDs

    15

    1907LDs Generally Recognized in the U.S.

    (United States v. Bethlehem Steel Co., 205

    U.S. 105, 119 (1907))

    1914Rule Against

    Apportionment (United States v. United

    Eng'g & Constr. Co.,234 U.S. 236, 242

    (1914))

    1931Gantt Chart used for the Hoover Dam

    Project

    1957DuPont successfully implements CPM with

    Remington Rand Univac on a chemical

    plant project

    1983Primavera’s

    (P3) first release on MS-DOS

    platform

    2000Federal Circuit

    adopts Rule of Clear Apportionment

    (Sauer Inc. v. Danzig, 224 F.3d 1340

    (Fed. Cir. 2000))

    2011“Rule” Abandoning

    Apportionment applied (Greg Opinski Constr., Inc. v.

    City of Oakdale, 199 Cal. App. 4th 1107, 1112 & 1121

    (Ct. App. 2011))

    1900's 1910's 1920's 1930's 1940's 1950's 1960's 1970's 1980's 1990's 2000's 2010's

    Sheet1

    1900's1910's1920's1930's1940's1950's1960's1970's1980's1990's2000's2010's

  • Modern Rule of Clear Apportionment

    Rule: When both the owner and the contractor proximately contribute to the project delay, the owner can recover liquidated damages if the delay attributable to each party is capable of being clearly apportioned.Rationale: CPM SchedulingSauer Inc. v. Danzig, 224 F.3d 1340 (Fed. Cir. 2000)

    16

  • CONCURRENT DELAY

    17

  • LDs and Concurrency – The Basics

    Concurrent Delay Defined● “[T]wo delays occurring at the same time that are the legal

    responsibility of different parties, each of which, independent of the other, delay the completion of the project.” John Livengood and Daniel S. Brennan, “Approaches to

    Concurrent Delay,” 38 Construction Lawyer 1, p. 27 (Winter 2019)

    Concurrent Delay and LDs●No clear apportionment = No Owner recovery of LDs during

    period of concurrent delay

    18

  • Redefining Concurrency

    Contract Provision Example:● “If an Unexcused Delay [Contractor Fault] occurs

    concurrently with either an Excusable Delay [Shared Fault] or a Compensable Delay [Owner Fault], the maximum extension of the Contract Time shall be the number of Days, if any, by which such Excusable Delay [Shared Fault] or Compensable Delay [Owner Fault] exceeds the number of Days of such Unexcused Delay [Contractor Fault].”

    19

  • Hypothetical Contract Language

    Unexcused Delay (Contractor Caused)

    Excusable or Compensable Delay (Owner Caused)

    Time Extension

    $

    Unexcused Delay (Contractor Caused)

    Excusable or Compensable Delay (Owner Caused)

    T.E.

    $

    Conventional Rule

    Hypothetical Contract Language

    20

  • EMERGING “RULE” ABANDONING APPORTIONMENTIllustrative Cases

    21

  • “Rule” Abandoning Apportionment

    Emerging “Rule”: When the contractor does not proximately cause the delay, the owner can still recover liquidated damage where the contractor fails to properly request a time extension / additional compensation under the contract

    22

  • Illustrative CasesEmerging Rule:

    Abandoning Apportionment

    Greg Opinski Constr., Inc. v. City of Oakdale, 199 Cal. App. 4th 1107 (Ct. App. 2011)

    “If the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer. It did neither. The court was correct to rely on its failure and enforce the terms of the contract. It makes no difference whether Opinski's timely performance was possible or impossible under these circumstances.”

    Rule of Clear Apportionment

    Stone v. City of Arcola, 536 N.E.2d 1329 (Ill. App. Ct. 4th Dist. 1989)

    “…the failure of the plaintiff to give written notice of the delay may be considered a waiver of a claim for delay, but ‘the waiver of a claim for delay does not correspondingly dictate that the party waiving the delay be held liable for the delay.’”

    23

  • Arguments Against Emerging “Rule”

    Departure from historic evolution of apportionment of liquidated damages rooted in causationAllowance of liquidated damages regardless of cause

    constitutes an unenforceable penaltySword v. Shield Distinction – Waiver of affirmative

    recovery doesn’t justify a windfallEstoppel / Waiver – Both parties complicit in

    contemporaneous failure to press claims

    24

  • What Can Contractors Do?

    Review the Contract●LD provision●Procedural requirement for asserting claim/time extension●Definition of concurrency?

    Follow all contractual requirements for obtaining a time extensionEducate the project team on principles of timely claim

    resolution●Concurrency is not a cure-all

    25

  • 26

    Christopher J. [email protected]

    1765 Greensboro Station PlaceSuite 1000

    McLean, Virginia 22102703-749-1000

    www.watttieder.com

    Kathleen O. [email protected]

    Damages without a clause: Liquidated Damages are a Penalty When Owners Recover Damages for Their Own delayHypotheticalSlide Number 3Case BackgroundHypothetical Contract LanguageHypothetical Contract LanguageHypothetical Facts- Round 1Hypothetical Facts- Round 1Liquidated DamagesWhat Are Liquidated Damages?Conflicting ConcernsCentrality of CausationBasics of Contract DamagesEnforceabilityEvolution of the Law on LDsModern Rule of Clear ApportionmentConcurrent DelayLDs and Concurrency – The BasicsRedefining ConcurrencyHypothetical Contract LanguageEmerging “Rule” Abandoning Apportionment“Rule” Abandoning ApportionmentIllustrative CasesArguments Against Emerging “Rule”What Can Contractors Do?Slide Number 26