d31pz1 Exam 2008-9 Incl Dubai

Embed Size (px)

Citation preview

  • 7/30/2019 d31pz1 Exam 2008-9 Incl Dubai

    1/3

    THIS PAPER MUST BE ATTACHED TO YOURSCRIPT AT THE END OF THIS EXAM

    SCHOOL OF THE BUILT ENVIRONMENT

    D31PZ1 Contracts and ProcurementD31PX1 Contracts and Procurement (DUBAI)

    Semester 1 - 2008/09

    Date: Wednesday 17 December 2008 Time: 13:30 -15:30 (UK)16:30 -18:30 (Dubai)

    Course(s)

    Students are entitled to bring an unmarked copy of the JCT05 Standard BuildingContract With Quantities SBC/Q Revision 1 2007 into this examination.

    Answer any THREE questions.

    All questions carry equal marks.

    Attached:

    Supplied

  • 7/30/2019 d31pz1 Exam 2008-9 Incl Dubai

    2/3

    Heriot-Watt University D31PZ1 Contracts and Procurement Semester 1 2008-09

    D31PX1 Contracts and Procurement Semester 1 2008-09

    Page 2 of 3

    Q.1

    A client wants to adapt the design and build procurement route to improve the qualityof design and workmanship they will receive. They are undecided between:

    requiring prospective contractors to pass a pre-qualification process thatassesses the contractors' design competency; or

    appointing their own design team to develop a concept solution so that they cannovate this solution to the successful contractor.

    Which of these two options would you recommend to this client? Explain why youwould make this recommendation and why the alternative is not, in your view,appropriate.

    (33 marks)

    Q.2

    When a PFI scheme is developed by negotiation with a single interested bidder,value for money cannot be achieved. (Anon., 2008).

    Critically analyse the ability of the Competitive Dialogue process to address thiscriticism of current PFI procurement practices.

    (33 marks)

    Q.3

    A partnership structured by a partnering contract that defines a "core group" is notreally a partnership. Discuss.

    (33 marks)

  • 7/30/2019 d31pz1 Exam 2008-9 Incl Dubai

    3/3

    Heriot-Watt University D31PZ1 Contracts and Procurement Semester 1 2008-09

    D31PX1 Contracts and Procurement Semester 1 2008-09

    Page 3 of 3

    Q.4

    a) A prospective construction industry client is proposing to employ a contractorusing a contract that it has written specifically for the project. Advise the clientas to whether or not they should do this. Support your position with an analysisof the main risks the client would be exposed to by using its own contract ratherthan one of the many standard construction contract forms.

    (11 marks)

    b) Assume that the Client employed a Contractor using a non-standard contractwritten specifically for the project. Also assume that expenditure on the projecthas exceeded the agreed Contract Sum but the work is not yet complete and

    the Contractor is requesting additional payment. The Client has discovered thatthe contract does not provide a process for paying the Contractor extra money.Advise the Client regarding how it should respond to the Contractor's request.

    (22 marks)

    Q.5

    In a site meeting, the Contractor provides a fully-documented heads of claim

    requesting payment of Loss and Expense incurred as a consequence of ongoingdelays in the Employer's response to a series of queries over the last three months.How should the Employer react to the provision of this document in accordance withJCT05 SBC/Q?

    (33 marks)

    END OF PAPER