PROPOSALSUMMARY

PROBLEMDESCRIPTION FairbairnDamisapproximately17kilometressouthwestofEmeraldand270kilometreswestofRockhamptoninCentralQueensland.RoutinedaminspectionsofFairbairnDamhavedetectedthattheconditionoftheoriginalspillwaydrainagesystemandgroundanchorshavedeterioratedandarenolongerfunctioningefficiently.

PROPOSALDESCRIPTION SunWaterisproposingtoundertakeimprovementworkstothespillwaytoensurethedamcancontinuetofunctionsafelyandinlinewithcurrentbestpracticestandards.

NEXTSTEPS CompleteBusinessCase.

PROPOSALNAMEResponsibleAgency:BQRole:ProposalStageofDevelopment:CurrentStageEndDate:DateofPublication:

FAIRBAIRNDAMSPILLWAYSAFETYIMPROVEMENTPROJECTSunWaterAssistwithbusinesscase

BusinesscaseupdateunderwayQ3 2016July2016