D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS Status & Requirements
Topics covered: CMS Grid Status CMSUK approach to Grid work First stab at high-level requirements Proposed UK work areas
Other sources of info: Our EB/TAG submission – this talk summarises it. CMS Note 2001/037 (Holtmann et al)
• Do NOT read as a fixed statement of CMS approach or priorities
• Our approach has already evolved since then… DataGrid WP8 validation proposal – public at end of this week.
DMN at CERN for CMS software week – apologies sent.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS Grid Status
Many active Grid groups within CMS US (Caltech, FNAL, UCSD, …); INFN; CERN
Some Grid technologies already used ‘in production’ Data replication via GDMP (for 12 months) Data movement across WAN using bbcp, and now GridFTP
…and some have been tried in large-scale tests CONDOR / DAGman
Formal CMS Grid Project just started Coordinator: C. Grandi (Bologna) Oriented toward coordination of existing work areas + manpower Many of the ‘obvious’ work areas already well covered
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
28 Pages
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS Overview and Requirements Document
“The document contains a snapshot, taken in 2001, of the vision of the intended software capabilities of the production system in 2003, and the expected scaling towards 2007”
But contains architectural choices and constraints.
Document admits that the “vision” will evolve….
There is a detailed “Division of labour” between tasks for grid-projects components and tasks for CMS components.
CMS is developing a detailed vision of the Grid.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
2003 CMS Grid-Job (Vision)
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS Software Today
Pythia PythiaPythiaHEPEVT
Ntuples
CMSIM(Geant3)
C)C)Zebra fileswith Hits
ORCAooHit
FormatterDataBase
ORCAAdd Pile-up
ORCAUser
AnalysisHistogramsNtuplesRoot files...
CMS has considerable experience already of distributed computing on large scales.
Production presently at about 10 regional centres - UK one of the largest - has produced 10TB of data (15TB by eoy)
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS Production Status
MC Production aims: Satisfy (increasing) requests for samples by physics/HLT groups;
will get worse as HLT + Physics TDRs approach Investigate scalability of hardware, software, people (!) Put in place the correct communication mechanisms + policies
Status: We are now/soon at the 10’s of TB scale Production runs quasi-continuously, worldwide. We are continually find (sometimes even solve!) the expected
scaling, communication problems… CMS physicists:
• Gripe a lot• Demand lots of support + a high level of reliability• Are highly clued-up, and provide very useful input + steerage
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS Milestones
Dec-01: 2x10*7 MC events (reduced processing chain).
Jun-02: 2x10*7 MC events (full chain and storage).
Late-02: Specification of final CMS software system for LHC era.
Dec-02: Higher-level-trigger TDR completed.
Dec-03: Computing TDR completed; includes 5% challenge.
Late-04: 20% data challenge.
Dec-04: Physics TDR completed.
Can these milestones contribute to the success of GridPP,and vice versa?
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS in the UK
Plan to contribute via GridPP in two ways:
Assist with the Grid-enabling of our current world-wideMC production system.
Deploy test and operate production software at prototype Tier-1, 2, 3 centres in the UK to test the scalability and performance of the developing software.
Main UK contribution to date has been the development of MC production software and its exploitation to meet ongoing simulation requirements. The UK has provide over 25% of the data to date.Plan is to maintain this high profile (much greater than our size).
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
Requirements: protoT1
What do we need? A rapidly-deployed protoT1 at RAL Scale attained should be ~0.5 of a Hoffmann T1 centre by end
2003 (all available to CMS for short periods) Good + responsive hardware and operations support / expertise Direct support for the tools we need to use there
• Large, fast database systems
• Commercial software installations (e.g. LHC++, Objy, Oracle)
Is this a ‘technical requirement’? Yes (IMHO). There is more to building / operating a T1 than stacking boxes (i.e.
we need a real programme of R&D) Industry does NOT yet know how to do this in a cost-effective way CMS has valuable experience + real plans for this area.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
Requirements: Middleware
Middleware / uppermiddleware req’d by CMS includes: Data management
• Covered (for flat files) by GDMP Workload management
• Lots of work being done in US, DataGrid projects, INFN Monitoring / control
• A UK contribution?
How to integrate middleware? No plans to ‘Gridify’ our core applications (OSCAR, ORCA, etc) We take a ‘toolkit’ approach for our production (-> analysis)
framework; will start to introduce Grid middleware under the toolkit, where it makes life easier.
Integration + testing will be a primary technical task in the UK.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
Requirements: ooStuff (I)
Object data management (from a non-expert): Traditionally, HEP experiments have used flat-file storage Flat files are ‘easy’ to deal with, but often inefficient, reliant upon
huge and complex metadata system, not amenable to ‘virtual data’ approach.
CMS plans to use a true object-based data model, and a corresponding persistent object store.
The problem: OS / Mass storage only knows about flat files Worse: data replication tools only know about flat files Vendor-supplied data management tools are inadequate /
insecure for use on the WAN Files will get very big soon (remember: 2GB limit will not exist for
much longer) – no longer a good unit of data transfer.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
Requirements: ooStuff (II)
A short-term solution: CMS will need to implement an object clustering/declustering layer Stuffs object collections into flat files when required for: Archiving;
Data Movement; Creation of compact ‘final stage’ datasets from tagged collections
Destuffs them for efficiency when required.
Long-term solution: Our data management / metadata tools need to understand object
granularity (or at least, object collections and their properties). This is not a well-understood problem (to say the least); lots of
interesting computer science here Presumably (?) very interesting to industry.
A role for GridPP / UK ?
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
Requirements: Interoperability
We have middleware coming from all over the place Probably a more visible problem within CMS than anywhere else
right now.
Please please please: Coordinate at a high level between projects Make sure the tools work together wherever possible Avoid architectural mismatches.
Otherwise: CMS will have to ‘make a choice’ GridPP / UK T1 will have to support it. We will all have to test / integrate twice as much stuff
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
CMS-UK: Areas of interest
DataGrid deliverables within the WP8 programme (installation,testing, organisation and support of data challenges).
MC Grid development: Introducing more grid-elements into the CMS data challenges.
Development and integration of object database into regional centres.
Monitoring tools for CMS applications and T1 hardware.
Object-level replication tool development.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
UK Proposed Work Areas (I)
NOT in any priority order protoT1 database management/support
Primary goal: to enable and support use of last, fast, modern object database systems at the protoT1
Some ‘operations’ tasks Some technical development tasks (which can be monitored /
managed): e.g. integration with Grid StorageElement. Also a very important liaison role with
• CERN / SLAC / whoever
• Vendors This is a necessary condition for use of the Tier-A/protoT1 by
CMS and BaBar• We intend to collaborate in this area.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
UK Proposed Work Areas (II)
Production / analysis Grid framework: The enhancement of our existing MC production toolkit (IMPALA)
using Grid technology This project is starting NOW Integrates with DataGrid WP8 work to some extent Will lead directly to Grid analysis framework development (no
acronym yet assigned!)
UK contribution: Use our experience to guide detailed requirements defn Deploy and test first tools at our protoT1/T2/T3 sites Investigate possible collaborations with other expts Also: provide input from working physicists who need the tools!
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
UK Proposed Work Areas (III)
Monitoring / T1 management + simulation Development of tools to allow effective:
• Monitoring of workflow• Monitoring of application performance• Analysis of bottlenecks + computing system performance• Comparison of T1 performance with simulation• Infra-T1 workflow scheduling and work pattern optimisation
Builds upon UK expertise in monitoring, info services, data publication
Builds upon MONARC work towards ‘real’ simulation of a local or worldwide computing system
Builds upon UK interest (incl. computer science) in network performance, application optimisation, workflow management.
First tools required (Real Soon) for optimisation of work at T1.
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
UK Proposed Work Areas (IV)
Object data management / replication: Provision of short-term solutions to this problem
• Provision of a ‘clustering layer’
• A good example of an indirect contribution by Grid projects to solve a real ‘core software’ problem
Investigation of possible long-term approaches Lots of potential collaboration with
• US projects
• Replication tool developers in DataGrid (etc)
• Computer scientists
• Industry This work should not be tied to one DB product or approach
D. Newbold / D. Britton GridPP Collaboration Meeting, 5/11/2001
Summary CMS and the Grid:
We have considerable experience already. We are already “pushing-the-envelope” with our MC productions.
We have uncovered many problems, issues, impedance mismatches already. CMS is developing a grid plan.
The UK contribution: Build upon our practical experience / expertise. Make use of the large protoT1 we will have Focus upon:
• integration / deployment / testing• interesting development projects needed by CMS
There are real, interesting, CMS-related things to do GridPP can make a big contribution to CMS CMS UK data challenges can make a big contribution to GridPP