18
D. Lincoln Run II MTG D D What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K * that’s John’s title, not mine........

D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

Embed Size (px)

DESCRIPTION

D. Lincoln Run II MTG May 12, Y2K Central Fiber Tracker Status  8 layers u Outer 6 s 2.52 m u Inner 2 s 1.66 m  r -.2 to.51 m  Axial readout to south  VLPC Readout  Waveguide system u m u “Pipes” light from detector to VLPCs

Citation preview

Page 1: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DDWhat will it take to get data out of the

CFT?*

Don LincolnCFT Commissioning Czar

Fermilab

Run II MeetingMay 12, Y2K

* that’s John’s title, not mine........

Page 2: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD What will it take to get data out of the CFT?

Work

Lots and Lots of Work

Page 3: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD Central Fiber Tracker Status

8 layers Outer 6

2.52 m Inner 2

1.66 m r - .2 to .51 m Axial readout to

south VLPC Readout Waveguide system

8-11.5 m “Pipes” light from

detector to VLPCs

Page 4: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Done Stuff

Fiber Ribbons (roughly 400 ribbons)

VLPC Characterization 17,000 chips tested, 15,500 OK

VLPC Recovery 2,200 tested, 1,100 recovered So total useful chips 16,600

Page 5: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD

(r)measured - (r)predicted

Cylinder 4 axial, r (incl. correct.) and res. slopes

0100200300400500600

-0.01 -0.005 0 0.005 0.01 0.015 0.02

MeanRMS

0.4723E-04 0.1188E-02

Constant 501.8Mean 0.5674E-04Sigma 0.1149E-02

inch

d(r)/dz correction0

0.250.5

0.751

1.251.5

1.752

2.252.5

-10 -8 -6 -4 -2 0 2 4 6 8 10mil/100in

RM 1=RM 1.5=RM 2=

2.02367 mil2.23837 mil2.4196 mil

CFT Status - Ribbon Mounting

30 m rms

50 m e-e offset

Going Very Well - To Spec

Last cylinder (1) getting stereo ribbons attached now

Project Tomorrow completion

Page 6: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Nesting

Cylinders 8,7,6,5,4 & 3 nested

CFT Completion - 5/19/00Delivered to DAB by

6/15/00

Global precision 15 m (Measured vs Desired)

Page 7: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Waveguides

Waveguide Production CPS complete (IU) Fiber pulling/sheathing at ND

75% complete for CFT Fiber sorted

– Best (attn.L from Kuraray) - longest runs [8-11.5m]

FPS at IU CFT WG Connectorization

At ND + Fermilab + IU 50 with curved end connectors

Expect to complete production in August (100+ July 15)

CFT Hookup and commissioning complete by 9/1/00

Page 8: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Readout System

VLPC Characterization/test/sort now complete

Cassette Assignment

As shown (includes cassettes 1-10)

Page 9: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Readout System II

Cassette production Approximately 50%

of sub-component complete

All components in-house except Flex circuit

Flex Circuit Production deliveries

starting 600 of 2000 in hand 100/week

Page 10: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Readout III

Cassette Test - Going Well

Noise low (Stereo Board) Good uniformity

Page 11: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Cryo

Fabrication delayed by delivery of top plates

Now in house To spec

Making up some time

Welding going well

Final Cryo Operational in June

Page 12: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD CFT Status - Conclusions

CFT construction is going well Mechanical assembly is to specification Complete in mid-May

VLPC + Cryo VLPC characterization/selection complete 1024 channel cassettes working well Cassette production assembly underway

Subcomponents 50% complete First 10 (11?) production cassettes assembled All cassettes leaving factory have met specifications

CFT wave guide production Fiber pulling/sheathing going well (far along) Connectorization underway

Page 13: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD Major Installation Activities During Next 3 Months

April May June July

Install/align CFT

Platform moves: pick

up EF north/south

Install VLPC cryostats in

platform

Collision Wall down – Hi Bay full

Rework EF shielding pieces

End detectors installed (FPS, ICD, L0)

Install N/S A-layer MDTs

Install both

EF shields

Install gas/cooling lines in Collision Hall

Rework/reassemble

shielding mid-pieces

Collision Wall back up

Install CFT cable ductwork in platform

Collision Wall down

Stage/survey N/S shielding

Solenoid Test

Install N/S A-layer pixels

Install EMC-S MDTs and pixels • Crane needed

• Platform occupied• ICR occupied• CF closed; no cal preamp access

survey

survey

survey

survey

survey

survey

survey

Survey east PDTssurvey

Install South truss in Hi Bay, re-weld arms

Forward Muon Installation

Disassemble EMC-S for

move to sidewalk

to July 15

Page 14: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD DO TimelineVersion N

2000 2001 J F M A M J J A S O N D J F M

D

Install silicon front-end

CFT install/hookup

1/2 VLPCs installed

1st CFT crate operational

Waveguide production

All VLPCs installed

Cosmic Ray CommissioningPhase I: Central

muon, DAQ, RECO, trigger, silicon front-end

Phase II: Tracker

Commissioning (CFT, SMT, PS), VLPCs, Forward

Muon

Phase III: Full Cosmic

Ray Run (add CAL, full TRIG & SMT)

Run II begins:

Mar 1, 2001

Roll in detecto

r

Remove shield wall

Beam-ready

Install final CFT electronics

Platform moves

No Services

No Services

Install/hookup/checkout SMT

South half North half

ICDFPSLum (L0)

Page 15: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD Commissioning Plan

CFT arrives DAB mid-June, install and survey (Gaston) Cryostat install and hookup through mid June, testing

cooldown followed by cassette insertion, end of June (Russ)

As waveguides hooked up (CPS, 8, 7, etc.), testing is needed

Current plan: 2 people/crew, 2 crews/shift, 2 shifts/day, 2 LG/crew/shift 8 lightguides/day. (300 CFT light guides 8 weeks)

Initial test, LED pulsers on the ribbons, secondary electrical.

Verify light continuity. Verify photoelectron noise consistent with temperature and

voltage Electrical noise.

Page 16: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD Needed Components

CFT cylinders: In DAB mid-late June Cryostat: Operational late-June Cassettes: In DAB June/July (30-ish, 11 in hand now) LHe: Tested already, hiatus early July (end iron) Lightguides: In DAB June/July, all CPS, 100 CFT (7/8 S/A) Cables: In house (AFE sequencer VRB) DAQ: Running now Unpacking: SVX unpacking done, some mapping

remains. Examines: Available now, will need tweaking for commissioning Cosmics: Piggyback on muon trigger Tracking: Cosmic tracking mostly OK, minor technical fixes Event Display: Ready in some form

Page 17: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD Front End Electronics:

AFE not available, use stereo board, limited availability LED Electronics:

Two components, small card (300-ish), large driver/control card (10-ish) Small cards available early June Large controller cards maybe available mid-August...Gack!

Sequencer VRB cable pull late July Silicon uses same cables, need splitter, not available Can pull the small number of CFT fiber optic cables first

CFT Online guru: CFT Calibration guru: Not yet filled Control/Download guru:

Needed Components

}

Page 18: D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K

D. Lincoln Run II MTG May 12, Y2K

DD Summary

Much of the required components are in place for mid-July hookup/commissioning

Some aren’t

They will be