Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Cygnus Coal Mine – Surface Water Specialist Study
Report Prepared for
Universal Coal Development V (Pty) Ltd
Report Number 535300/Surface Water/RevA
Report Prepared by
April 2019
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page i
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Cygnus Coal Mine – Surface Water Specialist Study
Universal Coal Development V (Pty) Ltd
SRK Consulting (South Africa) (Pty) Ltd 265 Oxford Rd Illovo 2196 Johannesburg South Africa
e-mail: [email protected] website: www.srk.co.za
Tel: +27 (0) 11 441 1111 Fax: +27 (0) 11 880 8086
SRK Project Number 535300
April 2019
Compiled by: Peer Reviewed by:
Oliver Malete, Pr. Sci. Nat. Senior Hydrologist
Peter Shepherd, Pr. Sci. Nat. Partner
Email: [email protected] [email protected]
Authors:
O. Malete; P. Shepherd
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page ii
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Executive Summary
SRK Consulting Limited, (SRK) has been appointed by Universal Coal Development V (Pty) Ltd
(Universal Coal) to undertake the surface water specialist study to support the authorisation
application. The CCM is located in the Limpopo Province, some 120 km to the north of Polokwane and
to the north east of Vetfontein Farm.
Principal objectives
The objectives of the surface water study are to conduct a:
• Baseline study;
• Stormwater management plan;
• Water balance; and
• Impacts assessment.
Work programme
The work programme included:
• Site visit in June 2018;
• Updating the surface water hydrology for the site;
• Sizing of clean and dirty water stormwater channels; and
• Preparation of water balance scenarios
Conclusions and Recommendations
The surface water specialist study provides an indication of the steps and processes required in order
to meet the Regulation 704 criteria in terms of the National Water Act (Act No. 36 of 1998). These
include the following have been addressed:
• Separation of clean and dirty water streams and the release and containment of each stream respectively by constructing diversion berms and canals;
• Assessment of the impact of MAR changes on the local and quaternary catchment level
• Operating water balance for the mine, especially the Opencast Pit
• Groundwater collected in the sump of the opencast pit, which requires containment, treatment and or use, where possible;
• Constructing five culverts at various locations around the mine along the haul and access roads to route water efficiently back into the environment
The opencast pit requires a clean water cut off canal which will discharge the water to the west and
east as it straddles a high point in the middle of the canal.
The nature of a pit excavation may generate dirty water and cause it to flow into the natural
environment. A sump has been proposed for the pit as a means of creating a point from which to pump
the water out to a suitable containment and treatment location.
The rainfall and storm water within the buildings and workshop areas will result in increased peak flows
of the local catchment but any effluent generated within workshop areas should be controlled and
managed using localised sumps at various isolated areas.
The effects of mining activity on the catchment MAR in which all infrastructure are located, will be a
reduction a reduction of MAR of 43 641 m3 per annum (0.5%) on a local scale and 0.04% on a
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page iii
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
quaternary catchment scale. With the mining activity located about 3 km away, this further lowers the
likelihood of negative impacts on the nearest surface water resource, the Brakrivier.
The project area is located in a very dry region of the Water Management Area resulting in a reduced
to absence of surface runoff for the majority of the year. As a result, the mine is likely to experience a
deficit in surface water supply resulting in an exclusive use of groundwater for the operations. The
foregoing ultimately results in surface water quality changes in the environment being very low.
The key impact assessment results are provided below.
Access Roads
Type of Impact
POTENTIAL IMPACT DESCRIPTION IN TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE
MITIGATION IMPACT
MANAGEMENT ACTIONS
(PROPOSED MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME
(ENVIRONMENTAL SIGNIFICANCE AFTER
MITIGATION) degree of mitigation
(%)
Significance (Degree to
which impact may cause
irreplaceable loss of
resources)
Significance Rating
Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Pre-Construction Phase
Direct Increased solids transport due to clearing/grubbing
30 Medium
Low
Construct in dry season and install silt bunds
20 Low 33
Indirect Increased runoff requiring retention on site
24 Low
Limit footprint and install retardation structures
16 Low 33
Direct Accidental hazardous substance spillages during construction phase
42 Medium
High Operate using best practices
24 Low 43
Construction Phase
Direct Impeding flow while under construction
30 Medium
Low
Construct in dry season.
20 Low 33
Protect with gabions & mattresses.
Remove litter & debris to stop blocking.
Direct
Accidental spillages of hazardous substances from construction vehicles used during construction of the crossings.
64 Medium
High
Control site access;
30 Medium
Low 53
Control refueling areas;
Restrict vehicular access to stream;
Clean spillages immediately they occur and remediate as necessary using spill kits.
Direct Contamination of runoff by poor materials/waste handling practices
35 Medium
Low
Park vehicles on hard standing with sump; 25 Low 29 Store hydrocarbons and other
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page iv
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Type of Impact
POTENTIAL IMPACT DESCRIPTION IN TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE
MITIGATION IMPACT
MANAGEMENT ACTIONS
(PROPOSED MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME
(ENVIRONMENTAL SIGNIFICANCE AFTER
MITIGATION) degree of mitigation
(%)
Significance (Degree to
which impact may cause
irreplaceable loss of
resources)
Significance Rating
Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
contaminants responsibly;
Bund fuel storage areas;
Store and dispose of waste responsibly.
Direct Debris from poor handling of materials and/or waste blocking watercourse
30 Medium
Low Operate using best practices
25 Low 17
Operational Phase
Direct Debris from upstream blocking watercourse at pipes/canals/culverts
49 Medium
High Operate using best practices
30 Medium
Low 39
Closure/Rehabilitation Phase
Direct Debris blocking watercourses if road continues to be used by the community.
49 Medium
High
Community needs to remove litter & debris to prevent blocking.
25 Low 49
Direct Impeding flow while under demolition
28 Medium
Low
Demolish infrastructure as far as possible in the dry season
20 Low 29
Direct Increased turbidity due to demolition.
36 Medium
Low
Demolish during dry season, limit the disturbed footprint.
20 Low 44
Direct
Accidental spillages of hazardous substances from construction vehicles used during demolition.
36 Medium
Low
Operate using best practices and clean spillages immediately they occur and remediate as necessary using spill kits.
24 Low 33
Post-Closure Phase
Direct Flooding caused by extreme rainfall event
35 Medium
Low
Warning signs to discourage crossing if pipes/culverts are submerged.
25 Low 29
Direct Damage to the crossings themselves
35 Medium
Low
Regular periodic inspections by successor in title and remediation as necessary.
20 Low 43
Opencast Pit and Plant Area
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page v
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Type of Impact
POTENTIAL IMPACT DESCRIPTION IN TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE
MITIGATION
IMPACT MANAGEMENT ACTIONS (PROPOSED
MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME
(ENVIRONMENTAL SIGNIFICANCE AFTER
MITIGATION)
degree of mitigation
(%)
Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Pre-Construction Phase
Direct Water runoff requiring retention on site
15 Low Construct in dry season;
9 Low 40 Limit footprint.
Direct Accidental hazardous substance spillages during construction phase
36 Medium
Low Operate using best practices 24 Low 33
Construction Phase
Direct Impeding flow while under construction
28 Medium
Low
Construct in dry season and
20 Low 29
protect with gabions & mattresses and
remove litter & debris to stop blocking.
Direct
Accidental spillages of hazardous substances from construction vehicles used during construction of the crossings.
35 Medium
Low
Control site access;
25 Low 29
Control refueling areas;
Restrict vehicular access to stream;
Clean spillages immediately they occur and remediate as necessary.
Direct Contamination of runoff by poor materials/waste handling practices
35 Medium
Low
Park vehicles on hard standing with sump;
24 Low 31
Store hydrocarbons and other contaminants responsibly;
Bund fuel storage areas;
Store and dispose of waste responsibly.
Indirect Separate clean and dirty water streams
27 Medium
Low Construct diversion drains timeously
21 Low 22
Operational Phase
Indirect Pump failure will result in dirty water accumulation in the pit
30 Medium
Low
Undertake regular structural inspections of pumps and pipes exiting pit. Ensure groundwater investigation is done to understand groundwater levels.
20 Low 33
Direct Reduction in catchment Mean Annual Runoff
54 Medium
High
Minimise dirty water areas requiring containment as far as practically possible
25 Low 54
Direct Spilling of the pollution control dam
54 Medium
High
Maintain stormwater levels as close to empty as possible by using it for dust suppression
21 Low 61
Indirect High rate of ground water ingress
33 Medium
Low
Implement recommendations from groundwater study with regards to pumping and dewatering
24 Low 27
Closure/Rehabilitation Phase
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page vi
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Type of Impact
POTENTIAL IMPACT DESCRIPTION IN TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE
MITIGATION
IMPACT MANAGEMENT ACTIONS (PROPOSED
MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME
(ENVIRONMENTAL SIGNIFICANCE AFTER
MITIGATION)
degree of mitigation
(%)
Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Direct Pit reaching capacity and overflowing to the environment.
40 Medium
High
Understand groundwater in the area and optimise mine planning activities
24 Low 40
Post-Closure Phase
Indirect Water quality changes downstream
40 Medium
High
Maintain stormwater collection system and monitoring. Consider an treatment effluent treatment plant if decanting is envisaged from the groundwater study
15 Low 63
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page vii
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Table of Contents
Executive Summary ..................................................................................................................................... ii
List of Abbreviations .................................................................................................................................... ix
1 Introduction .................................................................................................................. 1
2 Scope of Work .............................................................................................................. 1
3 Study Area .................................................................................................................... 2
3.1 Location ............................................................................................................................................... 2
3.2 Topography ......................................................................................................................................... 2
3.3 General description of the Limpopo Water Management Area .......................................................... 2
4 Climate and water quality ............................................................................................ 8
4.1.1 Evaporation ............................................................................................................................. 8
4.1.2 Rainfall..................................................................................................................................... 9
4.1.3 Water quality ......................................................................................................................... 10
5 Design rainfall depths ................................................................................................ 10
6 Stormwater Management Plan .................................................................................. 10
6.1 Proposed Mine Infrastructure ............................................................................................................ 11
6.2 Regional catchment delineation ........................................................................................................ 11
6.3 Mean annual runoff ........................................................................................................................... 14
6.4 Modelling ........................................................................................................................................... 15
6.4.1 Stormwater catchment delineation ........................................................................................ 15
6.4.2 Peak flows ............................................................................................................................. 16
6.4.3 Clean water management ..................................................................................................... 17
6.4.4 Dirty water management ....................................................................................................... 17
7 Water Balance ............................................................................................................. 21
7.1 Methodology ...................................................................................................................................... 21
8 Surface Water Impact Assessment ........................................................................... 23
8.1 Impact Assessment Methodology ..................................................................................................... 23
8.2 Activities to be rated .......................................................................................................................... 24
8.3 Project activities with potential to impact surface water resources ................................................... 24
8.4 Impacts associated with all activities ................................................................................................ 25
8.4.1 Pre-construction - site clearing and grubbing of the footprint areas ..................................... 25
8.4.2 Impacts during closure/rehabilitation ..................................................................................... 26
8.4.3 Post-closure .......................................................................................................................... 26
8.5 Impacts associated with the pit, plant area and associated infrastructure (e.g. pipelines, stormwater management) .................................................................................................................................... 26
8.5.1 Construction of the pit and associated infrastructure (access roads, pipelines) ................... 26
8.5.2 Operation of the Opencast Pit and Plant Area ...................................................................... 27
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page viii
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
8.5.3 Operation of the buildings and workshop areas .................................................................... 27
9 Conclusions and Recommendations ........................................................................ 32
10 References .................................................................................................................. 34
Appendices ...................................................................................................................... 35
Appendix A: Wet and Dry Seasons Water Balance .................................................... 36
List of Tables Table 4-1: Average monthly evaporation (mm) .................................................................................................. 8
Table 5-1: Design rainfall depth for 24 hour period (SRK, 2018) ..................................................................... 10
Table 6-1: Catchment parameters for the local catchments ............................................................................. 11
Table 6-2: Natural MAR (from WR2012) and loss of MAR due to dirty water containment ............................. 14
Table 6-3: Natural MAR (from WR2012) and increase of MAR due to building constructions ........................ 14
Table 6-4: Quaternary natural MAR (from WR2012) and net loss of MAR due to dirty water containment .... 15
Table 6-5: Clean and dirty water sub-catchments within the proposed mine ................................................... 15
Table 6-6: PCSWMM method peak flows for each sub-catchment .................................................................. 16
Table 6-7: Peak flows comparison between the pre- and post-development scenarios .................................. 16
Table 6-8: Dirty water stormflow volume ..................................................................................................... 18
Table 6-9: Clean and dirty water channel arrangement and hydraulic properties for the 1 in 50 year design storm .......................................................................................................................................... 19
Table 6-10: Culvert arrangement and hydraulic properties .............................................................................. 19
Table 7-1: Key parameters used for the water balance ................................................................................... 21
Table 8-1: Cygnus Project Activities ................................................................................................................. 24
Table 8-2: Impact assessment for the access roads ........................................................................................ 28
Table 8-3: Impact assessment for the opencast pit and plant area ................................................................. 30
List of Figures Figure 3-1: Locality map of the proposed Cygnus Coal Mine ............................................................................ 6
Figure 3-2: Location of Cygnus within Limpopo River Catchment WMA 1 ........................................................ 7
Figure 4-1: Total and mean annual rainfall for the years 1923 to 1999 ............................................................. 9
Figure 4-2: Mean monthly rainfall for the period 1923 to 1999........................................................................... 9
Figure 6-1: Proposed site infrastructure ........................................................................................................... 12
Figure 6-2: Cygnus local catchments in relation to quaternary catchments ..................................................... 13
Figure 6-3: Proposed stormwater management plan for Cygnus Coal Mine ................................................... 20
Figure 7-1: Annual average water balance for the proposed Cygnus Coal Mine............................................. 22
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page ix
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
List of Abbreviations
DWA Department of Water Affairs
DWAF Department of Water Affairs and Forestry
DWS Department of Water and Sanitation
EMP Environmental Management Plan
MRPDA Mineral and Petroleum Resources Development Act
NEMA National Environmental Management Act
NWA National Water Act
PCD Pollution Control Dam
SWD Storm Water Dam
SWMP Storm Water Management Plan
WMA Water Management Area
WULA Water Use Licence Application
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 1
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
1 Introduction
SRK Consulting was appointment by Universal Coal Development V (Pty) Ltd (UCDV) to undertake
environmental studies and associated authorisation application processes at the proposed Cygnus
Coal Mine (CCM). The CCM is located in the Limpopo Province, some 120 km to the north of
Polokwane and to the north east of Vetfontein Farm.
SRK Consulting (South Africa) (Pty) Ltd (SRK Consulting) was appointed by UCDV as the independent
environmental consultants to undertake the integrated EA/WML process. As part of this process, a
surface water specialist study is required to support the application.
This report outlines the hydrological baseline assessment, including the stormwater and water balance
for the proposed CCM.
2 Scope of Work
The scope of work for the investigation at CCM included the following:
• Baseline study
o Define and limit the boundaries and scale of the project, with respect to surface water (i.e. prepare surface water baseline);
o undertake an assessment of existing baseline data and supporting information;
o The baseline will be established during this task to develop a hydrological baseline with respect to water chemistry (quality) and quantity (flow), including the generation of flow statistics.
o Identify the major water courses within the area and estimate the catchment areas and hydrological parameters based on the site visit and contours/topography as supplied by the client;
o Estimate the Mean Annual Rainfall based on the rainfall available for the site. This will be estimated using a monthly Rainfall /Runoff model;
o The evaporation data will be estimated from the A-Pan data for stations near the area as supplied by the client or local metrological stations; and
o The Flood volumes for the identified catchments will be estimated using the SCS method.
o Calculate the impact of the mine on flood peaks and naturalised runoff
• Stormwater management plan
o Determination of catchment characteristics (catchment boundaries, water bodies, slope and drainage directions).
o Determination of impact on Mean Annual Runoff (MAR).
o Determination of storm water flows (m3/s) and volumes (m3) for the 1:50 and the 1:100 year return period event for the clean and dirty water areas.
o Determination of longer duration storm events for the purposes of storm water containment.
o Delineation of clean and dirty water areas on a drawing.
o Confirmation of the indicated placement of berms, channels and pollution control dams (PCD) to divert clean water around the dirty water areas as well as infrastructure required for the dirty water system, in line with Regulation 704 of the National Water Act (Act No. 36 of 1998) (NWA).
o Development of a plan/map for water diversion berms and conveyances for infrastructure; and
o Layout of the stormwater management plan.
• Water balance
o Annual average, wet and dry scenarios.
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 2
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
o Determination of water requirements for any excess water that will need to be absorbed into the mine.
• Reporting and Impact assessment
o All surface water impacts will be described and mitigation measures will then be proposed as normally required for the Environmental Impact Assessment/Environmental Management Plan (EIA/EMP), for the construction, operation, decommissioning and post closure phases.
o During this phase, refinements will be made to the stormwater management plan to improve the mitigation measures.
o The water balance will assist this phase by quantifying impacts and effects of the mitigation measures (where data are available).
3 Study Area
3.1 Location
The Project is located in the Limpopo Province, some 120 km to the north of Polokwane and to the
north east of Vetfontein Farm. The Project may be reached via an all-weather gravel road that
branches off from the tar road (road R584) between all days and Waterpoort. The Project Area is ~ 50
km by road from all days and 30 km by road from Waterpoort. The nearest sizeable town is Makhado
some 80 km by road to the southeast. The nearest accessible railway siding is at Waterpoort, ~ 30 km
southeast.
The location of the mine relative to the town of Waterpoort and its positioning in South Africa is shown
in Figure 3-1. A layout of the proposed site infrastructure is also indicated.
3.2 Topography
Although the catchment lies at a quaternary catchment divide, it consists of moderately hilly to
predominantly flat areas. The proposed Cygnus Coal Mine (CCM) is bordered by a small tributary of
the Sand River, Brakrivier, in the northern, flowing in a westerly direction, away from the DWM. No
other significant and defined water courses are to be found in close proximity to DWM and CCM.
3.3 General description of the Limpopo Water Management Area
Cygnus Coal Mine and its mining boundary is situated in Quaternary catchments A72B and A71J in
the Limpopo Water Management Area (WMA), WMA1, which is situated in the northern part of South
Africa, in the Limpopo Province. It is hydrologically associated with Sand River and all flows from the
site drain towards to Brakrivier, a non-perennial tributary of the Sand River. The Sand River, a tributary
of the Limpopo river, confluence with the Limpopo River, approximately 9 km east of Musina and 17
km downstream of Beitbridge.
The Limpopo River, formed by the confluence of both the Marico and Crocodile Rivers, originates in
the south west along the Botswana and South Africa borders approximately 70 km north west of
Thabazimbi.
The region is semi-arid, with economic activity mainly centred around livestock farming and irrigation,
together with increasing mining operations. Approximately 760 rural communities are scattered
throughout the water management area, with little local economic activity to support these population
concentrations. The WMA consists of a number of catchments which are mostly independent of each
other. The main catchments are the Matlabas, Mokolo, Lephalale, Mogalakwena, Nzhelele, and Sand,
where the project area is located.
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 6
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure 3-1: Locality map of the proposed Cygnus Coal Mine
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 7
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure 3-2: Location of Cygnus within Limpopo River Catchment WMA 1
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 8
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
4 Climate and water quality
Climate over the Limpopo WMA is temperate with frost occurring in winter, and is generally semi-arid.
The Mean Annual Precipitation (MAP) in the WMA ranges widely, with rainfall ranging from as little as
200 mm/annum in the north to over 1 200 mm/annum in the Soutpansberg mountains. In general
rainfall decreases from the south to the north, with the lowest rainfall occurring in the Limpopo valley
in the north-east of the WMA. The potential evaporation, which can be as high as 1 950 mm per year,
is well in excess of the rainfall.
The mean annual temperature of the Limpopo WMA ranges from 16° in the south to 22° in the north,
where the project area is located, with an average of 20° for the WMA as a whole. The average
maximum monthly temperature is 30° in the month of January, while the average minimum monthly
temperature is 4° in the month of July (DWAF, 2004).
Frost seldom occurs with the average number of frost days per year amounting to about 3 days that
is experienced mainly in the southern and western areas (DWAF, 2003).
Surface water quality within the project area is predominantly affected negatively during the rainy
seasons due to the very dry and arid nature of the region. This impact emanates predominantly from
the irrigation return flows from neighbouring agricultural lands.
4.1.1 Evaporation
The mean annual gross evaporation (as measured by Symons pan) ranges between 1 600 mm in the
southern region to 2 200 mm in the northern regions. The site evaporation character lies in the upper
levels of this range.
The monthly evaporation is presented in Table 4-1 (WR2012)
Table 4-1: Average monthly evaporation (mm)
Months Average Monthly Evaporation
Jan 203
Feb 166
Mar 166
Apr 135
May 128
Jun 105
Jul 119
Aug 145
Sep 176
Oct 204
Nov 196
Dec 208
Total 1950
High levels of evaporation mean that the soil dries up quickly reducing the amount of water available
for plant uptake meaning that crops become more prone to drought. Dryland subsistence farming is
generally not viable given the variable rainfall, high evaporation and high evapotranspiration (LEDET,
2015). Evaporation is highest during the rainfall season, and it significantly reduces effective rainfall,
runoff, soil infiltration and groundwater recharge. The Evaporative Demand in Limpopo ranges from
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 9
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
about 2 mm to 5 mm per day (ARC, 2015) and the project site demand more than likely lies in the
upper range of above 5mm/day.
4.1.2 Rainfall
Rainfall data was obtained from the Bandur weather station 0765007W. The Bandur data comprised
of 98 years of daily rainfall data (1903-2000) which was truncated to 77 years to obtain a period from
January 1923 to December 1999 due to data paucity. A long record of rainfall (>30 years) is required
to reliably assess statistical characteristics of the local rainfall therefore the combined rainfall record
is of sufficient length. Annual rainfall monitored between 1923 and 1999 was found to vary average
228 mm per annum with a range of between 51 mm and 525 mm (see Figure 4-1). The average
monthly rainfall variation is shown in Figure 4-2. The greatest proportion of rainfall occurs between
November and March and the least between May and September. Review of rainfall data presented
as Figure 4-1 suggests that between 1964 and 1981 rainfall followed a nine year cycle between periods
of high and low rainfall.
CYGNUS UNVERSAL COAL TOTAL AND MEAN ANNUAL RAINFALL FOR THE YEARS 1923 TO 1999
Project No. 535300
Figure 4-1: Total and mean annual rainfall for the years 1923 to 1999
CYGNUS UNVERSAL COAL MEAN MONTHLY RAINFALL FOR THE PERIOD 1923 TO 1999
Project No. 535300
Figure 4-2: Mean monthly rainfall for the period 1923 to 1999
0
100
200
300
400
500
600
Rai
nfa
ll (m
m)
Annual Rain Average 5-Year Annual Moving Average
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
0765007W 11.73 35.58 36.78 42.46 44.43 23.75 18.42 5.18 1.50 2.69 1.10 4.88
0.00
10.00
20.00
30.00
40.00
50.00
Mo
nth
ly R
ain
fall
(mm
)
MAP 228 mm
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 10
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
4.1.3 Water quality
The closest river or dam water quality sites recorded on the Department of Water Sanitation (DWS)
Resource Quality Information Services (RQIS) are situated approximately 20km upstream of the site
(A7H10 - Waterpoort 695 MS on Sand River) and 40 km downstream of the site (A7R1 - Dr Neethling
Dam on Sand River/Voorburg). No regional water quality site occurs within the Brakrivier catchment
and the Brakrivier was dry during the site visit. With this data, only the regional water quality status
could be inferred.
The Sand Key Area is by far the driest of all the Key Areas in the WMA, with a unit runoff of only 1
mm/a (DWAF, 2004), implying that surface water quality loads are very low throughout much of the
hydrological year.
Mining is an important economic driver in the Sand River catchment, comprising , silicon and diamond
mines and a platinum smelter. The introduction of a coal mine within the catchment will contribute to
a higher waste loading profile into the Sand River relative to the other commodities. This pollutant
loading is likely to occur via non-point source pollutant transport processes through a dry tributary such
as the Brakrivier during storm events. As a result, the cumulative water quality impacts to the surface
water resource within the region is minimal to negligible for most of the hydrological year.
5 Design rainfall depths
Based on the long daily record, various return periods were generated using the following statistical
methods and the best distribution fit, Log Pearson Type 3, was selected to determine the design rainfall
depths. The following table (Table 5-1) represents the calculated 24-hour rainfall depths from the
historical record between 1977 and 1999.
Table 5-1: Design rainfall depth for 24 hour period (SRK, 2018)
Design Storm (years) 1 in 2 1 in 5 1 in 10 1 in 20 1 in 50 1 in 100 1 in 200
Rainfall Depth (mm) 25 52 77 116 151 192 239
6 Stormwater Management Plan
The Department of Water and Sanitation (DWS) (previously known as the Department of Water Affairs
and Forestry (DWAF) and then the Department of Water Affairs (DWA)), has produced a range of Best
Practice Guidelines (BPGs) for the mining sector with each BPG having particular application to
different aspects of the mining process and to different components of the water management system
at a mine. BPG G1 (DWAF, 2006) provides four primary principles that need to be applied in the
development and implementation of a Storm Water Management Plan (SWMP). The first two
principles capture the clean and dirty water separation requirements of Regulation 704. The four
principles are as follows:
• Clean water must be kept clean and be routed to a natural watercourse by a system separate
from the dirty water system while preventing or minimising the risk of spillage of clean water
into dirty water systems. This will limit the reduction in water flow to the receiving water
environment/catchment (loss of water to the catchment) and thus increase the water available
in the water resource to other users.
• Dirty water must be collected and contained in a system separate from the clean water system
and the risk of spillage or seepage into clean water systems must be minimised. The
containment of dirty or polluted water will minimize the impact on the surrounding water
environment.
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 11
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
• The SWMP must be sustainable over the life cycle of the site and over different hydrological
cycles and must incorporate principles of risk management. Portions of the SWMP, such as
those associated with waste management facilities, may have to remain after site closure since
management is required until such time that the impact is considered negligible and the risk
no longer exists.
• The statutory requirements of various regulatory agencies and the interests of stakeholders
must be considered and incorporated.
Based on these principles and the guidelines in BPG G1, a framework for LDM’s SWMP was
developed.
6.1 Proposed Mine Infrastructure
A layout of the proposed mine infrastructure is shown in Figure 6-1 below. Based on the site catchment
delineation, the majority of the infrastructure will be located within catchments Cat_A and Cat_B
(Figure 6-2), following which these catchments will then be sub-divided to smaller Onsite
subcatchments around the major infrastructure areas such as the Opencast area, Pollution Control
Dam, Dumps, Offices and Workshops.
6.2 Regional catchment delineation
According to the published quaternary catchments of South Africa, the site infrastructure lies across
two quaternary catchments A72B and A72J. Based on this assumption, approximately 43% of the
Cygnus property lies in catchment A72B and the remainder (57%) lies in catchment A72J.
Based on the SRTM contour data catchment delineation, the catchment divide between A72B and
A72J bisects the property in the south eastern corner of the property. This means that, hydraulically,
approximately 91% (11.9 km2) of the Cygnus site drains towards the Brakrivier and therefore all
infrastructure for the proposed mine may impact only one quaternary catchment, catchment A72B.
Therefore only 9% of the site area, an area containing no proposed infrastructure, drain towards the
Sand River.
During the local catchment delineation, the site was found to lie within four (4) major catchments
namely Catchment A to D (denoted Cat A to Cat D). Two of the sub-catchments, Cat A and B, drain
northwards into the Brakrivier catchment (quaternary catchment A72B), while the remaining two drain
eastwards into the larger Sand River (Figure 6-2). The stream lines generated from Global Mapper
indicate the preferential pathway of runoff and in no way indicate the presence of actual streams on
the ground throughout the year. The following catchment characteristics in Table 6-1 were determined
for the local sub-catchments. These parameters represent the predevelopment scenario of the project
against which to compare the post-development scenario (the proposed coal mine and its
infrastructure).
Table 6-1: Catchment parameters for the local catchments
Catchment ID
Description Area (km2) Width (m) Flow Length (m) Slope (%)
Cat_A Regional 32.72 5,949 5,500 0.80
Cat_B Regional 5.20 1,528 3,400 1.00
Cat_C Regional 28.13 4,136 6,800 0.90
Cat_D Regional 22.55 3,580 6,300 1.10
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 12
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure 6-1: Proposed site infrastructure
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 13
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure 6-2: Cygnus local catchments in relation to quaternary catchments
Actual catchment divide
based on SRTM elevation
data
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 14
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Generally, quaternary catchments are used for regional purposes and not site-specific purpose such
as stormwater management plans. Due to the location of both the Pollution Control Dam and Opencast
area falling hydraulically within A72B, the catchment delineation mentioned above and shown Figure
6-2 above was used to assess the impact of the proposed mine on the Mean Annual Runoff (MAR)
using WR2012 data for quaternary catchments.
6.3 Mean annual runoff
The 0.80 km2 opencast pit and the proposed 0.18 km2 Pollution Control Dam sub-catchment will both
reduce runoff generated within the immediate catchment. The catchment in which the pit is located is
32.7 km2. In addition, the CCM is situated in quaternary catchment A72B, which is 1554 km2 (see
Figure 3-2 above).
All site infrastructure where runoff will be contained on site will invariably cause a reduction in MAR.
based on this, only the Opencast Area and the PCD sub-catchment area (the Plant Area and Discard
Dump area) will lead to a reduction in MAR. The access roads will not have any significant increasing
effect on the MAR for both catchments A72B and A72J.
The effects of mining activity on the catchment MAR in which the pit and PCD are located, will be a
reduction in MAR. The results for the localised investigation are shown in Table 6-2. The captured
dirty water will result in a reduction of MAR of 45,900 m3.
Table 6-2: Natural MAR (from WR2012) and loss of MAR due to dirty water containment
Catchment Area
(km2)
A72B MAR contributing
rainfall (mm)
MAR from Catchment
(mill m3)
Dirty water area
(km2)
MAR from dirty water
(m3)
Loss of MAR
(%)
Opencast Pit 33 7 0.228 0.80 5 566 2.4
Pollution Control Dam
33 7 0.228 0.18 1 242 0.5
The effects of erecting buildings on the catchment MAR in which the all the buildings (workshop area,
contractor laydown area, parking area, etc.) are located, will be an increase in the MAR due to an
increase in impervious areas. The results for the localised investigation are shown in Table 6-2. The
diverted clean water will result in an increase of MAR of 2 259 m3.
Table 6-3: Natural MAR (from WR2012) and increase of MAR due to building constructions
Catchment Area (km2)
A72B MAR contributing rainfall (mm)
MAR from Catchment
(mill m3)
Dirty water area (km2)
MAR from dirty water (m3)
Loss of MAR (%)
Buildings 5.2 7 0.228 0.80 5 566 2.4
In the greater context, all the proposed infrastructure is located within quaternary catchment, A72B.
The net effect on the prevailing catchment MAR will be 0.04% reduction or 4 549 m3. The catchment
area and the associated MAR is presented in Table 6-4
The reduction in MAR included in Table 6-4 was estimated using the runoff depth given in WR2012
(Midgley, Pitman and Middleton, 1994).
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 15
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Table 6-4: Quaternary natural MAR (from WR2012) and net loss of MAR due to dirty water containment
Catchment A72B Area (km2)
A72B MAR contributing rainfall (mm)
MAR from A72B
(mill m3)
Dirty water area (km2)
MAR from dirty water
(m3)
Loss of MAR A72B (%)
A72B 1554 7 10.83 0.98 6,808 0.04
6.4 Modelling
PCSWMM was used as a flood analysis model to determine peak discharges at each sub-catchment.
PCSWMM is a dynamic rainfall-runoff simulation model, based on the SCS-SA method, used for single
event or long-term simulation of runoff quantity. This model was set up for the site and used to calculate
the six-year recurrence interval flood peaks based on the design rainfall depths calculated in Section
5 above.
Manning’s ‘n’ coefficient used in the model for the impervious and pervious areas were 0.012 and
0.035 respectively. The Manning’s n for the pervious areas is based on medium to dense bush land
cover.
As inferred from the soils report by Scientific Aquatic Services (SAS, 2018), the soils were identified
as being predominantly of the sandy the loam group. The model uses this criterion to incorporate
infiltration into the analysis using the Green-Ampt infiltration method. This resulted in a Suction Head
of 110.1 mm, a Hydraulic Conductivity of 21.8 mm/hr and an Initial Deficit of 0.358 being used in the
modelling (Green and Ampt, 1911).
6.4.1 Stormwater catchment delineation
The based on the site infrastructure, the site was divided into both clean and dirty water sections
depending on the potential pollution sources and hence the likelihood of contact (dirty) and non-contact
water generation. These included:
• Dirty water areas: These are sub-catchment areas associated with the opencast pit area, the washing plant and the coal discard dump area. The area east of the opencast area consisting of the topsoil, hard and soft dumps has been deemed clean; and
• Clean water areas: The are sub-catchment areas associated with administration offices, parking lot, stores, contractor laydown areas and workshop areas. If any effluent is generated at these areas, such as the workshop area, it is isolated at source by means of localised sumps.
The sub-catchments for the various areas are shown in the table below.
Table 6-5: Clean and dirty water sub-catchments within the proposed mine
Sub-Catchment ID
Description Area (km2) Width (m) Flow Length (m) Slope (%)
S01 Clean 1.76 1171 1500 0.40
S02 Clean 0.13 427 300 0.50
S03 Clean 0.89 590 1500 0.40
S04 Clean 0.43 429 1000 0.10
S05 Clean 0.38 536 700 0.70
S06 Clean 0.19 338 550 0.01
S07 Clean 0.36 1184 300 0.50
S08 Clean 0.18 488 360 0.01
S09 Clean 0.11 190 600 0.70
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 16
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Sub-Catchment ID
Description Area (km2) Width (m) Flow Length (m) Slope (%)
S10 Dirty 0.09 339 260 0.40
S11 Dirty 0.07 325 220 0.40
S12 Dirty 0.02 231 80 0.10
S13 Dirty 0.80 1354 590 0.10
6.4.2 Peak flows
The calculated results from the PCSWMM analysis presented in Table 6-6 shows the seven various
recurrence interval flood peaks for the upstream catchments draining the immediate study area. These
peak flows represent the pre-development scenario, the current state of the study area prior to mining
and addition of site infrastructure.
Table 6-6: PCSWMM method peak flows for each sub-catchment
Catchment Name
Catchment Area (km2)
Peak Flow (m3/s)
2 year RI
5 year RI
10 year RI
20 year RI
50 year RI
100 year RI
200 year RI
S01 1.76 0.00 0.00 0.77 8.11 15.39 25.86 28.19
S02 0.13 0.00 0.00 0.23 1.78 3.16 5.03 5.42
S03 0.89 0.00 0.00 0.37 4.02 7.72 13.14 14.31
S04 0.43 0.00 0.00 0.26 2.54 4.69 7.76 8.42
S05 0.38 0.00 0.00 0.31 2.93 5.28 8.51 9.19
S06 0.19 0.00 0.00 0.20 1.78 3.13 4.93 5.30
S07 0.36 0.00 0.00 0.62 4.82 8.44 13.51 14.56
S08 0.18 0.00 0.00 0.27 2.22 3.78 6.13 6.62
S09 0.11 0.00 0.00 0.12 1.10 1.94 3.05 3.27
S10 0.09 0.00 0.00 0.27 5.13 9.92 16.79 18.33
S11 0.07 0.00 0.00 0.17 1.28 2.21 3.41 3.65
S12 0.02 0.00 0.00 0.33 5.58 10.86 18.52 20.16
S13 0.80 0.00 0.00 0.82 9.36 18.53 32.11 35.04
*RI: Recurrence Interval
For the post-development scenario, the sub-catchment areas were changed with altering the
catchment characteristics to reflect the proposed infrastructure. Peak flows were calculated for all
clean and dirty water sub-catchments. A comparison of the 1 in 50 and 1 in 100 year recurrence
interval peak flows for the pre-and post-development scenarios are shown below.
Table 6-7: Peak flows comparison between the pre- and post-development scenarios
Catchment Name
Catchment Area (km2)
Peak Flow (m3/s)
50 Year RI 100 Year RI
Pre-development
Post-development
Pre-development
Post development
S01 1.76 15.43 30.27 25.93 44.78
S02 0.13 3.16 3.16 5.03 5.03
S03 0.89 7.72 10.73 13.14 16.37
S04 0.43 4.69 10.52 7.76 15.35
S05 0.38 5.28 13.57 8.51 19.31
S06 0.19 3.13 3.13 4.93 4.93
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 17
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Catchment Name
Catchment Area (km2)
Peak Flow (m3/s)
50 Year RI 100 Year RI
Pre-development
Post-development
Pre-development
Post development
S07 0.36 8.44 8.44 13.51 13.51
S08 0.18 3.78 3.78 6.13 6.13
S09 0.11 1.94 1.94 3.05 3.05
S10 0.09 9.92 3.19 16.79 4.66
S11 0.07 9.91 3.76 17.06 5.14
S12 0.02 9.88 1.18 17.08 1.53
S13 0.80 29.21 48.53 45.37 63.47
The proposed development and the subsequent management of clean and dirty water separation will
result in a peak flow increase in five (5) sub-catchment areas as a result of an increase in impervious
areas such as erection of buildings and a reduction (peak attenuation) in three (3) sub-catchment
areas due to storage and or flow diversion.
The highest peak flow increases occur in sub-catchments S05 (157%), S04 (124%) and S01 (96%).
These catchments may contain supercritical flows and any stormwater infrastructure will likely require
energy dissipation structures at their outlets such as gabions or rip rap. ,
6.4.3 Clean water management
The clean water management around site will consist of
The proposed Opencast Pit area and Plant Area are positioned mid-slope. The result is that it is a
requirement to manage potential ingress of clean water into the Opencast Pit and divert any clean
runoff away from the Plant and Discard Dump areas. Two main clean water diversion canals have
been proposed:
• Diversion Canal 1 will be positioned uphill of the Opencast Pit just downstream of the Topsoil,
Hards and Soft Dumps, which will allow water to be collected and routed away from the dirty area,
for release to the environment at two points around the Opencast Pit area; and
• Diversion Canal 2 will be positioned upstream of the Plant and Discard Dump Area, also allowing
for the water to be collected and routed away from the dirty area, for release to the environment
at two points around the area.
Five (5) culverts have been proposed to be constructed at various locations around the mine along
the haul and access roads to route water efficiently back into the environment.
The clean water area and associated channels and culverts are shown in Figure 6-3 and the sizes are
presented in Table 6-9 and Table 6-10 below.
6.4.4 Dirty water management
The dirty water at CCM is confined to the open cast pit and the plant and discard dump area. As per
common practice, the edges of the open cast will have a berm built up to prevent ingress of surface
water, in addition to the sized and designed clean water canal. The source of water to the open cast
section is therefore limited to direct rainfall and ground water seep.
Rehabilitation of the opencast pit will take place on the as the new pit blocks are opened following the
box-cut. This will gradually reduce the area available for direct rainfall to accumulate on the floor of
the pit. The rate of backfilling and rehabilitation is not known at this stage. Taking this into
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 18
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
consideration, for the purposes of the report, the total area of the pit was used in the calculation of
direct rainfall accumulation in the pit.
Removal of water from the open cast area requires a localised sump and installed pumping capacity
to deal with collected water. The nature of opencast mining requires a temporary sump to collect the
water and allow pumping. The position of the sump will move in relation to the mining operations until
the end of 2025. For the management of dirty water in the pit at Cygnus, it is proposed that the sump
be approximately 30 m by 30 m with a depth of approximately 3 m. The sump will provide a holding
capacity of 2,700 m3 which will be sufficient for the more common rainfall events.
The 1:50 and the 1:100-year rainfall events are more severe rainfall events and will require the bottom
bench to accumulate in water addition to the sump. The results for the volume of water captured and
temporarily stored prior to pumping are shown in Table 6 8. It is proposed that the dirty water from the
plant and discard dump areas be collected in a Pollution Control Dam situated just north of the Discard
Dump area (S12)
Table 6-8: Dirty water stormflow volume
Assumptions made in calculating the water contained in the pit, requiring pumping:
• Opencast will be completely open (0.80 km2).
The dirty water area and associated channels are shown in Figure 6-3 and the sizes are presented in
Table 6-9 and Table 6-10 below.
Catchment Name Area (km2) 1:50 (m3) 1:100 (m3)
Opencast Pit 0.80 53 268 73 519
Pollution Control Dam 0.18 16 082 18 789
Sump capacity (m3) 2 700 2 700
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 19
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Table 6-9: Clean and dirty water channel arrangement and hydraulic properties for the 1 in 50 year design storm
Main Channel Name
Channel Section
Description Length
(m) Manning’s
n Cross Section
Depth (m)
Width (m)
Left slope (1:X)
Right slope (1:X)
Slope (m/m)
Max. Flow
(m³/s)
Max. Velocity
(m/s)
Max/Full Flow
(Fraction)
Max/Full Depth
(fraction)
Opencast Pit Diversion Canal
(Channel 1)
C1-01 Clean water channel 148 0.013 Trapezoidal 0.7 2.0 2.0 1.0 0.0020 1.58 1.38 0.35 0.74
C1-02 Clean water channel 197 0.013 Trapezoidal 0.7 2.0 2.0 1.0 0.0005 1.60 1.65 0.72 0.66
C1-03 Clean water channel 303 0.013 Trapezoidal 0.7 2.0 2.0 1.0 0.0013 0.24 0.31 0.07 0.48
C1-04 Clean water channel 389 0.013 Trapezoidal 0.7 0.5 1.0 2.0 0.0034 0.09 1.30 0.04 0.16
C1-05 Clean water channel 706 0.013 Trapezoidal 0.7 0.5 1.0 2.0 0.0017 0.03 0.88 0.02 0.09
C1-06 Clean water channel 550 0.013 Trapezoidal 1.6 2.0 1.0 2.0 0.0080 0.02 0.01 0.00 0.49
C1-07 Clean water channel 97 0.013 Trapezoidal 1.6 2.0 1.0 2.0 0.0040 30.26 4.45 0.95 0.98
Plant Diversion Canal (Channel 2)
C2-01 Clean water channel 240 0.013 Trapezoidal 1.4 1.5 2.0 1.0 0.0083 3.17 3.23 0.11 0.32
C2-02 Clean water channel 91 0.013 Trapezoidal 1.4 1.5 2.0 1.0 0.0121 0.00 0.00 0.00 0.16
C2-03 Clean water channel 429 0.013 Trapezoidal 0.8 1.5 2.0 1.0 0.0031 0.00 0.00 0.00 0.00
C2-04 Clean water channel 194 0.013 Trapezoidal 0.8 1.5 1.0 2.0 0.0078 0.00 0.00 0.00 0.50
C2-05 Clean water channel 272 0.013 Trapezoidal 1.2 1.5 1.0 2.0 0.0074 10.88 4.33 0.54 0.74
C2-06 Clean water channel 323 0.013 Trapezoidal 1.2 1.5 1.0 2.0 0.0074 10.91 3.99 0.54 0.78
C2-07 Clean water channel 44 0.013 Trapezoidal 1.2 1.5 1.0 2.0 0.0023 7.64 2.56 0.69 0.83
Plant Dirty Water Canal (Channel 3)
C3-01 Dirty water channel 103 0.013 Trapezoidal 0.8 1.0 1.0 1.0 0.0059 0.00 0.00 0.00 0.00
C3-02 Dirty water channel 116 0.013 Trapezoidal 0.8 1.0 1.0 1.0 0.0050 0.00 0.00 0.00 0.00
C3-03 Dirty water channel 121 0.013 Trapezoidal 0.8 1.0 1.0 1.0 0.0000 0.00 0.00 0.00 0.35
C3-04 Dirty water channel 73 0.013 Trapezoidal 0.8 1.0 1.0 1.0 0.0138 3.18 7.39 0.42 0.41
Discard Dump Dirty Water
Canal (Channel 4)
C4-01 Dirty water channel 344 0.013 Trapezoidal 1.0 0.5 1.0 1.0 0.0000 0.00 0.00 0.00 0.33
C4-02 Dirty water channel 33 0.013 Trapezoidal 1.0 0.5 1.0 1.0 0.0211 3.68 10.29 0.37 0.40
Table 6-10: Culvert arrangement and hydraulic properties
Culvert Section Description Length
(m) Roughness Cross-Section
Depth (m)
Width (m)
Left slope (if appl.)
(1:X)
Right slope (if
appl.) (1:X)
Number of
Barrels
Culvert Code
Slope (m/m)
Max. Flow (m³/s)
Max. Velocity (m/s)
Max/Full Flow
Max/Full Depth
Inlet Control (fraction)
Culvert 1 Culvert Culverts 60 0.013 Closed Rectangular 1.0 1.0 0 0 1 53 0.0045 1.54 2.46 0.72 0.63 0.13
Outlet Culverts 67 0.013 Trapezoidal 0.5 1.0 3 3 1 0 0.0090 1.54 2.53 0.38 0.63 0
Culvert 2 Culvert Culverts 49 0.013 Closed Rectangular 1.0 1.0 0 0 2 53 0.0041 3.12 2.07 0.8 0.76 0.5
Outlet Culverts 32 0.013 Trapezoidal 0.7 1.0 3 3 1 0 0.0032 3.12 4.76 0.61 0.47 0
Culvert 3 Culvert Culverts 32 0.013 Closed Rectangular 1.5 1.0 0 0 4 53 0.0250 11.22 2.43 0.34 0.78 0.51
Outlet Culverts 84 0.013 Trapezoidal 1.0 1.0 3 3 1 0 0.0048 11.47 3.36 0.81 0.92 0
Culvert 4 Culvert Culverts 33 0.013 Closed Rectangular 1.6 1.0 0 0 4 53 0.0276 13.50 2.43 0.36 0.87 1
Outlet Culverts 49 0.013 Trapezoidal 1.6 1.0 3 3 1 0 0.0021 13.66 2.57 0.48 0.74 0
Culvert 5 Culvert Culverts 31 0.013 Closed Rectangular 1.4 1.0 0 0 4 53 0.0000 10.47 2.25 0.44 0.83 1
Outlet Culverts 34 0.013 Trapezoidal 1.4 1.0 3 3 1 0 0.0030 10.59 2.75 0.43 0.7 0
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 20
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure 6-3: Proposed stormwater management plan for Cygnus Coal Mine
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 21
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
7 Water Balance
The water is undertaken as prescribed by the Best Practice Guideline G2: Water and Salt Balances
by DWAF, 2007.
Included in the study are the workshops, offices and the pit. Information was obtained where possible
from CCM. The average annual water balance is shown in Figure 7-1. The wet and dry scenarios are
presented in Appendix A (Figures A1 to A2).
7.1 Methodology
A high level annual, wet season and dry season water balance was set up based on a Microsoft Excel
spreadsheet. The water balance uses average monthly rainfall and evaporation for the hydrological
year. Average rainfall and other rainfall statistics for the various wet and dry rainfall scenarios have
been determined from observed long-term rainfall records.
Much of the water use indicated in the water balance is (currently) estimated by calculation because
the project is still in a development phase. These assumptions will need to be modified at a later stage
so that a dynamic water balance can be created and automatically updated. The key parameters used
in the water balance are shown in Table 7-1.
Table 7-1: Key parameters used for the water balance
Rainfall Evaporation Groundwater Potable water
Monthly rainfall
was used in the
water balance
Monthly evaporation
data was used in the
water balance
Groundwater figures were
obtained from the Mine Works
Programme report and a
Groundwater
inflows/discharge value of 0.1
l/s was used. This value will
be updated upon completion
of the groundwater study
0.20 m3 was
allocated per
person per day
and applied to a
staff complement
of 213 employees
and contractors.
Part of the role of the water balance is to present to the mine, the options available to decrease firstly
the cost to the mine of raw water supply through municipal infrastructure and secondly, to decrease
the reliance on the environment for water supply in new raw water use. The mine is able to save on
both of the above points by reusing water (dirty water) in their processes.
Groundwater collected in the sump of the opencast pit is classed as dirty water and as a result requires
containment, treatment and use, where possible. If the mine has an idea of the volume of water likely
to be classed as dirty, their reliance on the municipal raw water streams decreases by that amount.
This water balance will need to be incorporated into the overall mine water balance to determine if the
mine can accommodate extra mine water from the pump. Based on the balance, it is evident that mine
will need to implement water efficiency strategies as the bulk of losses will be due to evaporative
losses, with about 3.4% due to operational losses at this conceptual stage.
SRK Consulting: Project No: 535300 – Cygnus Surface Water Specialist Study Page 22
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure 7-1: Annual average water balance for the proposed Cygnus Coal Mine
SRK Consulting: 477989 Page 23
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
8 Surface Water Impact Assessment
8.1 Impact Assessment Methodology
All specialists are required to assess each potential impact identified according to the following Impact
Assessment Methodology as described below.
This Impact Assessment Methodology has been formalised to comply the 2014 EIA Regulations of the
NEMA, which states the following:
An environmental impact assessment report must contain all information that is necessary for the competent authority to consider the application and to reach a decision, and must include –
• an assessment of each identified potentially significant impact, including –
(i) cumulative impacts;
(ii) the nature, significance and consequence of the impact and risk;
(iii) the extent and duration of the impact and risk;
(iv) the probability of the impact and risk occurring;
(v) the degree to which the impact and risk can be reversed;
(vi) the degree to which the impact and risk may cause irreplaceable loss of resources; and
(vii) the degree to which the impact and risk can be mitigated.
Specialists were required to identify impacts (positive and negative) associated with the project.
Specialists were also required to specify the type of impact (direct/indirect) and including an
assessment of cumulative impacts that may occur because of the proposed project. The anticipated
impacts associated with the proposed project were assessed according to SRK’s standardised impact
assessment methodology based on the following factors:
• Severity - the degree of change to the receptor status in terms of the reversibility of the impact; sensitivity of receptor to stressor; duration of impact (increasing or decreasing with time); controversy potential and precedent setting; threat to environmental and health standards;
• Spatial scope - the geographical scale of the impact;
• Duration - the length of time over which the stressor will cause a change in the resource or receptor;
• Frequency of activity - how often the proposed activity will take place; and
• Frequency of impact - the frequency with which a stressor (aspect) will impact on the receptor.
To enable a scientific approach for the determination of the environmental significance (importance)
of each identified potential impact, a numerical value has been linked to each factor. The interpretation
of the impact ratings are shown in Table 4-2 of the Impact Assessment Methodology prescribed.
SRK Consulting: 477989 Page 24
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
8.2 Activities to be rated
Table 8-1 provides the anticipated activities relating to each project and project phase for which
potential impacts should be identified and assessed, and mitigation measures provided. Please note
that this table is not limited to only the stated activities identified, but should be used as a guideline
when determining and identifying activities that could have potential impact on the biophysical and
social environment.
Table 8-1: Cygnus Project Activities
8.3 Project activities with potential to impact surface water resources
Although it is recognised that existing legislation is in place that would not allow a project to be
developed that would have a material detrimental impact on surface water resources, there are a
number of potential impacts on water resources that can arise from mining activities related to both
Project Phase Activity
Pre-construction • Site clearing and grubbing of the footprint areas associated with the opencast pit
and box-cut, diversion canals, pipeline, buildings, and proposed access and haul roads.
Construction • Excavation of the pit, construction of diversion canals, pipeline, building (and foundations) and proposed access and haul roads.
Operation • Operation, management and maintenance of the opencast pit, workshop and contractors laydown areas, pipeline, and proposed access and haul roads.
• Operation, management and maintenance of the powerlines.
• Mining of the pit area.
Rehabilitation • The pit will be back-filled.
Post-closure • Demolition of all other project related infrastructure.
• Removal of all access and haul roads.
• Handling of potential contaminated soils.
• Monitoring of groundwater.
SRK Consulting: 477989 Page 25
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
the volume and quality of water entering, or leaving, water resources which may include some of the
following:
• Reduced availability to downstream/down-gradient water users due to changes in water quantity or flow regime;
• Reduced availability of water to downstream water users due to changes in water quality;
• Reduced availability of water to surrounding water users due to physical obstruction from mine infrastructure pit and stormwater diversions etc.);
• Linear crossings of the watercourses may cause scouring around the infrastructure in the river;
• Damage to the aquatic ecosystem due to substances contained in releases from the mine;
• Scouring effect on stream banks and bed due to releases from the mine (clean water diversions, storm water drains, road culverts etc.);
• Increased erosion from areas of exposed soils; and
• Increased risk of flooding due to changes in catchment hydrology.
Impacts may be envisaged for the various phases of the pit development, being construction,
operational, closure and rehabilitation phases. The general activities that are common to construction
and rehabilitation of the pit, plant, discard dump and office building areas include the following:
• Removal of the vegetation.
• Removal and stockpiling of the topsoil.
• Earthworks and excavation of foundations for infrastructure e.g. buildings, roads, pipelines etc.
• Provision of stormwater management measures.
• Construction of concrete structures, pump stations and laying of pipelines.
• Rehabilitation of disturbed areas after general site construction is completed.
• Operation of the pit, on-going revegetation of berms around pit, water management systems, maintenance and monitoring.
• Decommissioning and closure of the pit once life of pit is reached.
• Rehabilitation of the pit and discard dump once decommissioning is completed.
• Post Closure including maintenance and monitoring.
8.4 Impacts associated with all activities
The impacts for all activities during the construction, operation and closure of the access roads,
opencast pit and diversion canals are discussed in greater detail below. They are detailed in Table 8-2
to Table 8-3.
8.4.1 Pre-construction - site clearing and grubbing of the footprint areas
An increase in erosion from cleared areas, topsoil stockpiles or any other area where there are
exposed soils can occur during storm events (direct impact). Increased erosion can result in an
increase in turbidity, suspended solids and sedimentation in the unnamed tributary (indirect and
cumulative impact). Some level of sedimentation is expected to occur in the Brakrivier pre-
development as runoff is naturally anticipated to pick up environmental debris as it crosses natural
areas.
Increased turbidity is reversible and surface water should return to pre-impact turbidity levels once
sediment levels entering the watercourse are reduced. Settled sediments should naturally move
downstream during periods of high flow flowing storm events.
By minimising the area cleared for construction the potential for erosion will be reduced. Construction
of appropriate stormwater controls in the form of clean water diversion bunds upstream of the
construction site and paddocks downstream of the working activities will minimise the sediment loads
SRK Consulting: 477989 Page 26
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
leaving the construction area. Such sediments will be further reduced by temporary erosion
prevention berms or similar measures within the path of the diverted clean water.
Rehabilitation of disturbed areas immediately after construction will facilitate re-establishment of
vegetation thus reducing the potential for erosion post-construction.
8.4.2 Impacts during closure/rehabilitation
Similar water quality and erosions impacts as in the construction phase have the potential to occur
during the demolition of infrastructure and rehabilitation of the pit and associated infrastructure despite
the pit becoming a permanent fixture in the landscape. No additional impacts are envisaged as this
activity should be restricted to the already disturbed area. These impacts will therefore be addressed
in the construction phase.
The pit will be revegetated to manage on-going dust generation and erosion after back-filling. All
rehabilitation activities should be monitored until vegetation is well established and no further surface
water quality impacts are deemed likely.
8.4.3 Post-closure
The main activity identified during the post-closure phase that has the potential to impact on surface
water resources is dispersion of the contaminated groundwater plume which is discussed in the
groundwater specialist report.
During the post-closure phase, all infrastructures will have been removed; therefore the surface water
quality should not be further impacted by any of the post-closure activities.
8.5 Impacts associated with the pit, plant area and associated infrastructure (e.g. pipelines, stormwater management)
8.5.1 Construction of the pit and associated infrastructure (access roads, pipelines)
Changes to surface water hydrology could result due to placement of infrastructure within drainage
lines and containment of dirty runoff within the pit footprint Without adequate clean water diversions
or suitable grading of areas there is an increased risk of flooding upstream (impedance of flow) which
could result in damage to property and infrastructure. The impact will be localised but will remain
throughout the life of the mine. The probability that local water courses will be diverted and will not
carry the water falling directly on the pit and considered dirty water, is definite and the overall
significance of the impact is rated as medium high. The impact will affect the flow regime and
morphology of the watercourse and thus overall functionality of the local surface water courses. Water
course functions are beyond the scope of this study and are described in the biodiversity or similar
study.
Appropriately designed and constructed clean water diversion structures and outlets in compliance
with Regulation 704 will return clean water runoff generated up gradient of the pit to the Brakrivier in
a manner as close to natural/pre-mining conditions as possible. Energy dissipaters should be
constructed at points where there are concentrated discharges of water to the environment that could
cause significant erosion and scouring within water channels to reduce the energy and speed of the
water flow. This is applicable to the Clean Water Diversion Canal 2 and the two dirty water channels
at the discard dump and plant area.
Appropriately designed and constructed structures and stormwater outlets in compliance with
Regulation 704 will reduce the potential for erosion. Erosion protection and energy dissipaters should
SRK Consulting: 477989 Page 27
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
be constructed at points where there are concentrated, high velocity flows of water to the environment
that could cause significant erosion to slow the speed of water. The standard WUL conditions require
that construction takes place in the dry season and starts from upstream to downstream with
concurrent rehabilitation taking place. Weekly water monitoring is also required during construction
and for three months post construction.
8.5.2 Operation of the Opencast Pit and Plant Area
Changes to the hydrology within the Brakrivier catchment will continue from the construction phase
and no additional mitigation is indicated.
The rainfall water within the designated dirty water areas of the Opencast Pit and Plant and Discard
Dump Area that form part of the MAR to the local water courses will continue to be removed from the
catchment and may continue to reduce the quantity of water available to downstream users.
The potential for contamination of surface water due to releases of dirty water (runoff and return water)
from all access roads due to transportation of product remains of moderate significance both pre- and
post-mitigation. It is recommended that regular dust suppression be conducted as far as possible using
water from the pollution control dam thereby keeping the PCD as close to empty as possible to allow
for accommodation of the design storm.
Spillages and accidental discharges could result in the contamination of surface water resources.
Spillage of return water from the piped transfer systems has the potential to impact indirectly on the
Brakrivier via cumulative waste load build-up and subsequent wash off during storm events (via runoff).
The impact is of medium high significance but can be mitigated by maintaining the PCD as close to
empty as possible and reversible through a combination of clean-up and assimilation/natural recovery
in the watercourse.
8.5.3 Operation of the buildings and workshop areas
Changes to the hydrology within the Brakrivier catchment will continue from the construction phase
and no additional mitigation is indicated. The rainfall and storm water within the buildings and
workshop areas will result in increased peak flows due to the impervious nature of the ground being
introduced. The effluent generated within workshop the workshop areas should be controlled and
managed using localised sumps at various areas.
The potential for contamination of surface water due to releases of dirty water (runoff and return water)
remains of medium high significance for the pre-mitigation scenario due to high concentration as a
result of pollutant build up, and can be improved to a low rating for the post-mitigation.
Spillages and accidental discharges could result in the contamination of surface water resources.
Spillage from these areas also have the potential to impact indirectly on the Brakrivier via cumulative
waste load build-up and subsequent wash off during storm events (via runoff) but the impacts will be
very localised to the areas due to proximity limitations of the first flush event. The impact is of moderate
significance but can be mitigated and reversible through a combination of on-site clean-up using spill
kits and assimilation/natural recovery in the watercourse or drainage areas.
SRK Consulting: 477989 Page 28
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Table 8-2: Impact assessment for the access roads
Type of Impact POTENTIAL IMPACT DESCRIPTION IN
TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE MITIGATION
IMPACT MANAGEMENT ACTIONS (PROPOSED
MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME (ENVIRONMENTAL SIGNIFICANCE AFTER MITIGATION)
degree of mitigation
(%)
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: A
ctiv
ity
Fre
qu
ency
: Im
pac
t
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: Act
ivit
y
Fre
qu
ency
: Im
pac
t
Pre-Construction Phase
Direct Increased solids transport due to clearing/grubbing
4 1 1 2 3 30 Medium
Low Construct in dry season and install silt bunds
2 1 1 2 3 20 Low 33
Indirect Increased runoff requiring retention on site
4 1 1 1 3 24 Low Limit footprint and install retardation structures
2 1 1 1 3 16 Low 33
Direct Accidental hazardous substance spillages during construction phase
5 1 1 2 4 42 Medium
High Operate using best practices 2 1 1 2 4 24 Low 43
Construction Phase
Direct Impeding flow while under construction 4 1 1 3 2 30 Medium
Low
Construct in dry season.
3 1 1 2 2 20 Low 33 Protect with gabions & mattresses.
Remove litter & debris to stop blocking.
Direct Accidental spillages of hazardous substances from construction vehicles used during construction of the crossings.
5 1 2 4 4 64 Medium
High
Control site access;
2 1 2 2 4 30 Medium
Low 53
Control refueling areas;
Restrict vehicular access to stream;
Clean spillages immediately they occur and remediate as necessary using spill kits.
Direct Contamination of runoff by poor materials/waste handling practices
4 1 2 3 2 35 Medium
Low
Park vehicles on hard standing with sump;
2 1 2 3 2 25 Low 29
Store hydrocarbons and other contaminants responsibly;
Bund fuel storage areas;
Store and dispose of waste responsibly.
Direct Debris from poor handling of materials and/or waste blocking watercourse
2 1 2 4 2 30 Medium
Low Operate using best practices 2 1 2 3 2 25 Low 17
Operational Phase
Direct Debris from upstream blocking watercourse at pipes/canals/culverts
1 2 4 4 3 49 Medium
High Operate using best practices 1 2 2 4 2 30
Medium Low
39
Closure/Rehabilitation Phase
SRK Consulting: 477989 Page 29
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Type of Impact POTENTIAL IMPACT DESCRIPTION IN
TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE MITIGATION
IMPACT MANAGEMENT ACTIONS (PROPOSED
MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME (ENVIRONMENTAL SIGNIFICANCE AFTER MITIGATION)
degree of mitigation
(%)
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: A
ctiv
ity
Fre
qu
ency
: Im
pac
t
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: Act
ivit
y
Fre
qu
ency
: Im
pac
t
Direct Debris blocking watercourses if road continues to be used by the community.
1 2 4 4 3 49 Medium
High
Community needs to remove litter & debris to prevent blocking.
1 2 2 2 3 25 Low 49
Direct Impeding flow while under demolition 3 2 2 1 3 28 Medium
Low Demolish infrastructure as far as possible in the dry season
1 2 2 1 3 20 Low 29
Direct Increased turbidity due to demolition. 3 2 1 2 4 36 Medium
Low Demolish during dry season, limit the disturbed footprint.
1 2 2 1 3 20 Low 44
Direct Accidental spillages of hazardous substances from construction vehicles used during demolition.
3 2 1 2 4 36 Medium
Low
Operate using best practices and clean spillages immediately they occur and remediate as necessary using spill kits.
1 2 1 2 4 24 Low 33
Post-Closure Phase
Direct Flooding caused by extreme rainfall event 4 2 1 1 4 35 Medium
Low
Warning signs to discourage crossing if pipes/culverts are submerged.
2 2 1 1 4 25 Low 29
Direct Damage to the crossings themselves 4 2 1 1 4 35 Medium
Low
Regular periodic inspections by successor in title and remediation as necessary.
2 2 1 1 3 20 Low 43
SRK Consulting: 477989 Page 30
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Table 8-3: Impact assessment for the opencast pit and plant area
Type of Impact
POTENTIAL IMPACT DESCRIPTION IN TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE MITIGATION
IMPACT MANAGEMENT ACTIONS (PROPOSED MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME (ENVIRONMENTAL SIGNIFICANCE AFTER MITIGATION)
degree of mitigation
(%)
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: Act
ivit
y
Fre
qu
ency
: Im
pac
t
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: Act
ivit
y
Fre
qu
ency
: Im
pac
t
Pre-Construction Phase
Direct Water runoff requiring retention on site 3 1 1 1 2 15 Low Construct in dry season;
1 1 1 1 2 9 Low 40 Limit footprint.
Direct Accidental hazardous substance spillages during construction phase
4 1 1 4 2 36 Medium
Low Operate using best practices 4 1 1 2 2 24 Low 33
Construction Phase
Direct Impeding flow while under construction 4 1 2 1 3 28 Medium
Low
Construct in dry season and
2 1 2 1 3 20 Low 29 protect with gabions & mattresses and
remove litter & debris to stop blocking.
Direct Accidental spillages of hazardous substances from construction vehicles used during construction of the crossings.
4 1 2 2 3 35 Medium
Low
Control site access;
2 1 2 2 3 25 Low 29
Control refueling areas;
Restrict vehicular access to stream;
Clean spillages immediately they occur and remediate as necessary.
Direct Contamination of runoff by poor materials/waste handling practices
4 1 2 2 3 35 Medium
Low
Park vehicles on hard standing with sump;
3 1 2 2 2 24 Low 31
Store hydrocarbons and other contaminants responsibly;
Bund fuel storage areas;
Store and dispose of waste responsibly.
Indirect Separate clean and dirty water streams 3 3 3 1 2 27 Medium
Low Construct diversion drains timeously 2 2 3 1 2 21 Low 22
Operational Phase
Indirect Pump failure will result in dirty water accumulation in the pit
4 1 1 1 4 30 Medium
Low
Undertake regular structural inspections of pumps and pipes exiting pit. Ensure groundwater investigation is done to understand groundwater levels.
2 1 1 1 4 20 Low 33
Direct Reduction in catchment Mean Annual Runoff
2 3 4 4 2 54 Medium
High
Minimise dirty water areas requiring containment as far as practically possible
2 1 2 3 2 25 Low 54
Direct Spilling of the pollution control dam 2 3 4 4 2 54 Medium
High
Maintain stormwater levels as close to empty as possible by using it for dust suppression
2 3 2 1 2 21 Low 61
SRK Consulting: 477989 Page 31
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Type of Impact
POTENTIAL IMPACT DESCRIPTION IN TERMS OF ENVIRONMENTAL ASPECTS
ENVIRONMENTAL SIGNIFICANCE BEFORE MITIGATION
IMPACT MANAGEMENT ACTIONS (PROPOSED MITIGATION MEASURES)
IMPACT MANAGEMENT OUTCOME (ENVIRONMENTAL SIGNIFICANCE AFTER MITIGATION)
degree of mitigation
(%)
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Consequence Likelihood
(Probability) Significance (Degree to
which impact may
cause irreplaceable
loss of resources)
Significance Rating
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: Act
ivit
y
Fre
qu
ency
: Im
pac
t
Seve
rity
Spat
ial
Du
rati
on
Fre
qu
ency
: Act
ivit
y
Fre
qu
ency
: Im
pac
t
Indirect High rate of ground water ingress 4 3 4 1 2 33 Medium
Low
Implement recommendations from groundwater study with regards to pumping and dewatering
2 3 3 1 2 24 Low 27
Closure/Rehabilitation Phase
Direct Pit reaching capacity and overflowing to the environment.
3 1 4 1 4 40 Medium
High Understand groundwater in the area and optimise mine planning activities
2 1 3 1 3 24 Low 40
Post-Closure Phase
Indirect Water quality changes downstream 3 1 4 1 4 40 Medium
High
Maintain stormwater collection system and monitoring. Consider an treatment effluent treatment plant if decanting is envisaged from the groundwater study
2 1 2 1 2 15 Low 63
SRK Consulting: 477989 Page 32
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
9 Conclusions and Recommendations
The surface water specialist study provides an indication of the steps and processes required in order
to meet the Regulation 704 criteria. These include the;
• Separation of clean and dirty water streams and the release and containment of each stream respectively by constructing diversion berms and canals;
• Assessment of the impact of MAR changes on the local and quaternary catchment level
• Operating water balance for the mine, especially the Opencast Pit
• Groundwater collected in the sump of the opencast pit requires containment, treatment and or use, where possible;
• Constructing five culverts at various locations around the mine along the haul and access roads to route water efficiently back into the environment
The opencast pit requires a clean water cut off canal to the south west to prevent the situation of
surface runoff from entering the opencast pit during rainfall events. The canal will discharge the water
to the west and east as it straddles a high point in the middle of the canal.
The nature of a pit excavation results in a reduced likelihood of dirty water, generated at the opencast
pit, flowing into the environment. A sump has been proposed for the pit as a means of creating a point
from which to pump the water out and to a suitable containment and treatment location.
The rainfall and storm water within the buildings and workshop areas will result in increased peak flows
of the local catchment but any effluent generated within workshop areas should be controlled and
managed using localised sumps at various isolated areas.
The effects of mining activity on the catchment MAR in which all infrastructure are located, will be a
reduction a reduction of MAR of 43 641 m3 per annum (0.5%) on a local scale and 0.04% on a
quaternary catchment scale. With the mining activity located about 3 km away, this further lowers the
likelihood of negative impacts on the nearest surface water resource, the Brakrivier.
The project area is located in a very dry region of the Water Management Area resulting in a reduced
to absence of surface runoff for the majority of the year. As a result, the mine is likely to experience a
deficit in surface water supply resulting in an exclusive use of groundwater for the operations. The
foregoing ultimately results in surface water quality changes in the environment being very low.
SRK Consulting: 477989 Page 33
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Prepared by
Oliver Malete, Pr. Sci. Nat.
Hydrologist
Reviewed by
Peter Shepherd, Pr. Sci. Nat.
Partner
All data used as source material plus the text, tables, figures, and attachments of this document have
been reviewed and prepared in accordance with generally accepted professional engineering and
environmental practices.
SRK Consulting: 477989 Page 34
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
10 References
Department of Water Affairs and Forestry (2000) Regulation 704: Operational Guideline No. M6.1.
Guideline document for the implementation of regulations on use of water for mining and related
activities aimed at the protection of water resources. Second Edition. Pretoria, South Africa.
Department of Water Affairs and Forestry (2006), Best Practice Guideline G1: Storm Water
Management, Pretoria, South Africa.
Smithers, J and Schulze, R (2002) Design rainfall and flood estimation in South Africa. Water Research
Commission Report No. K5/1060. Pretoria, South Africa
SRK Consulting: 477989 Page 35
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Appendices
SRK Consulting: 477989 Page 36
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Appendix A: Wet and Dry Seasons Water Balance
SRK Consulting: 477989 Page 37
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure A-1: Wet season scenario water balance
SRK Consulting: 477989 Page 38
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
Figure A-2: Dry scenario water balance
SRK Consulting: 477989 Page 39
MALE/SHEP 535300_Cygnus_Surface_Water_20190803_Final_Draft August 2019
SRK Report Distribution Record
Report No. 535300
Copy No. 1.pdf
Name/Title Company Copy Date Authorised by
Ndomupei Masawi SRK Consulting, Pretoria 1.pdf 2019/08/03 P Shepherd
Library SRK Consulting HC 2019/08/03 P Shepherd
Approval Signature:
This report is protected by copyright vested in SRK (SA) (Pty) Ltd. It may not be reproduced or
transmitted in any form or by any means whatsoever to any person without the written permission of
the copyright holder, SRK.