Upload
others
View
13
Download
0
Embed Size (px)
Citation preview
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 1
CXI Detector Status, Cost & ScheduleNiels van Bakel
LCLS Detector PhysicistJune 3, 2009
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Outline
• Technical Scope– Basic detector module (Cornell)– Detector assembly– Data acquisition
• Major Interfaces• Design Reviews• Cost & Schedule
2
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Team
3
• Gruner Group at Cornell University- Biophysics, Soft Condensed Matter, and X-ray Detector Development Lab
• Sol Gruner; project leader• Hugh Philipp, Mark Tate, Marianne Hromalik, Lucas Koerner
• SLAC PPA Electrical & Software Engineering - Gunther Haller, Ryan Herbst, Amedeo Perazzo, Chris O’Grady, Matt Weaver,
Dieter Freytag
• SLAC PPA Mechanical Engineering- Martin Nordby, Matthew Swift
• LUSI CXI team- Sebastien Boutet - CXI Instrument Scientist- Paul Montanez - CXI Lead Engineer
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
LDAC
• LCLS Detector Advisory Committee:– Gareth Derbyshire (chair): Rutherford Appleton Laboratory, UK– Erik Heijne (interim chair): CERN, Switzerland– Eric Eikenberry: PSI, Switzerland– Heinz Graafsma: DESY / XFEL, Germany– Ronnie Shepherd: LLNL, USA– Lothar Struder: MPI / Semiconductor Laboratory, Germany– Albert Walenta: University of Siegen, Germany– Yoshiyuki Amemiya: University of Tokyo, Japan
• Track technical progress, check if detector specs meet the original requirements and involved in technology choices
• Other topics e.g. DAQ and system integration• LDAC report
4
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
CXI Requirements• The Coherent X-ray Imaging instrument will image nanoscale objects,
including single or small clusters of bio-molecules• The detector needs to image the 2D diffraction pattern with a large area
detector with minimum dead area• With the intense (1012 ph) and short (100 fs) LCLS pulses at 120 Hz
one needs integrating detectors with fast readout (< 8 ms)
5
CXI spec.
Readout noise < 0.3 ph
Full well capacity 1-103 ph
Pixel size 110 μm
Number of pixels 750 (10242).
Energy 4 - 8 keV
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 6
CXI Detector • Detector in vacuum 10-7
Torr• Resolution depends on
the sample-detector distance
– Requires translation stage 600 mm
– Remote Aperture resizing 1 - 10 mm
• Cooling 10 - 25 °C
LCLS beam
~110 microns
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Test results
7
Low gain: ‘Full Well’ ~ >2500 8 keV x-rays
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Characterization of Detector
8 keV x-rays, 75 micron pinhole.
12
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 9
CXI Assembly
Cold strap
Quadrant raft
Analog board2x1
Digital board
2x2 detector package (4 per quadrant)
Simulations changed designPackaging
Bump & wire bondingAssembly toolsAlignment & position stability
Interface to DAQ1.1 Gbps per quadrant
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
CXI 2x1 Module Packaging
2x1 Detector Assembly Jig•Diode-ASIC assembly bonded to carrier board•2x1 assembly held for wire bonding and testing
Pixel array detector
ASIC’s on back side of detector
Carrier board
Front End Board•One board per detector•Part of detector assembly
Flex cable—bent back out of the way
13
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
LDAC Recommendations• Increase interaction with user community
– Close interaction with Instrument Scientists– Team leader meetings & Instrument workshops
• Cornell progress– Focus on ‘full’ array with 16 ASICs
• Since prototype detector functions according to specs – Foresee adequate cooling for stable operation– Need a 2x1 module operational in May 2009
• Progress towards a first tested module appears to be relatively slow
– The 2x1 modules to be delivered to SLAC after full testing at Cornell. • It is recommended to discuss this in detail, so that resources can be found, if needed• Assemble only known good die (KGD)
– The basic components for a full system are available• Recommended that the desirable redesign of the CMOS chip is discussed in the
framework of a future, follow-up project, so that priority can be given to the schedule of delivery of detector modules this Fall 2009
14
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Cornell Plan
• Technical Addendum-D (5/1/08-4/30/09, $1,235k):– Measurement of the existing prototypes with x-rays– Identification of areas for improvement– Identification of areas that need to be developed for full-array implementation– Design and redesign of circuitry as driven by steps 2 and 3.– Simulation of circuits to be included in next submission– Low-level physical layout of circuits– Verification of layout– Submission of design to MOSIS, including second full-lot submission.– Design and fabrication of test electronics for a particular submission– Work with the SLAC science team to define geometrical format and packaging
of detector
16
Needs extension
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Cornell Plan
• Technical Addendum-D (5/1/08-4/30/09, $1,235k):– Test and calibrate final detector; develop calibration procedures.– Design and fabricate hybrid compatible with the packaging scheme– Write test reports and documentation– Design & fabricate 2nd large detector diode; development of 2x1 module– Design high speed data transfer and storage for final detector compatible with
LCLS DAQ– Bump bond final detector diodes and ASICs– Prepare report/ conduct review– Perform radiation tests– Assembly of final detector; work with SLAC on shielding and EMI– Test vacuum compatibility of detector module
17
Needs extension
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 18
CXI vs. Cornell milestones
• CXI Schedule (WBS 1.3):– CXI 05710 FDR Cornell Detector packaging in Feb 16 2009– CXI 07125 RCV: Cornell detector from LCLS in April 24 2009 (needs update)– CXI 07220 AVAIL: Ready for installation, CXI detector stage in Oct 18 2010– CXI 00450 COMP: CXI Early Science Components Installation in May 12 2011
• Conservative, driven by KB mirrors– CXI 00540 COMP: CXI Final Installation Complete in November 11 2011
• Cornell Schedule:– XE254_2160 2D detector received at SLAC in November 2009
• Cornell 2D PAD detector installed February 2010 → optimistically CXI ready in December 2010
– Early installation in hutch 3 in September 2010
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 19
Detector - DAQ Interface
• Detector - Experiment Specific• Front-End Electronics - Local configuration registers and state machines,
FPGA used to transmit to DAQ system• Timing info from the accelerator timing system, distributed to the
detectors and L1 boards • L0 Control: operate DAQ, control a run & configure the detector,
telemetry monitoring• Beam Line Data is beam quality information, used to veto events• L1 DAQ: Acquire FEE data, detector calibration, event building (beam
line data), image processing, veto, 10 Gb/s ethernet
Detector + ASIC FEE
Timing L0: Control
L1: Acquisition
L2: Processing L3: Data Cache
Beam LineData
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Detector DAQ
• Each quadrant connects to external interface board via LVDS signals– 125Mhz Clock– Reset (Optional)– Command– 2 Data Output Lines
• Interface board interfaces to RCE via 2 PGP links• Data Rates
– 1 ASIC = 16 bits * 185 rows * 194 cols * 120Hz = 68.9Mbs– 1 Quadrant = 16 ASICS * 68.9Mbps = 1.1Gbps– 1 Chamber = 1.1Gbps * 4 = 4.4Gbps
20
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 21
Register Command Data Interface
• Interface defined between FEE and L1 - Common interface among different
experiments
- Provide data, command and register interfaces
- Custom point-to-point protocol (Pretty Good Protocol, PGP) implemented as FPGA IP core
- FEE FPGA assumed to be Xilinx family with Multi Gigabit Transceivers (MGT)
FEE FPGA
RegisterBlock
RegAddr[23:0]
RegDataOut[31:0]
RegReq
RegOp
ReqAck
RegFail
RegDataIn[31:0]
PGPBlock
PCDS blocksDetector specific blocks
L1 NodeMGT
Tran
scei
ver
Tran
scei
ver
MGT
Fiber
CommandBlock
DataBlock
CmdCtxOut[23:0]
CmdOpcode[6 :0]
CmdEn
FrameTxEnable
FrameTxSof
FrameTxDataWidth
FrameTxEof
FrameTxEofe
FrameTxData[15:0]
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Mechanical Interface
• Mechanical interface• Detector stability• Thermal & Cooling
interface• Vacuum requirements• Electrical interface• Power requirements• Controls interface
22
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 23
Detector Testing at SLACSLAC Front End Development board, ‘Digital’ & Analog PCB for CXIAdditional testing; feedback to Detector GroupsImproves integration into LCLS & LUSI instruments
SLAC custom made DAQ board (L1) available for detector groupsStart testing at SLAC
Bench testsSSRL beam testsDetector test lab; x-ray tube
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Summary & Outlook
• Technical progress• Schedule updated to meet CXI • CXI Detector ready for early scientific
experiments:– CXI Detector phase I Nov 09– CXI Detector phase II Feb 10– CXI Installation at SLAC Complete Dec 10
– CXI Early Science ....
24
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009
Summary & Outlook
• Technical progress• Schedule updated to meet CXI • CXI Detector ready for early scientific
experiments:– CXI Detector phase I Nov 09– CXI Detector phase II Feb 10– CXI Installation at SLAC Complete Dec 10
– CXI Early Science ....
24
Niels van [email protected]
CXI DetectorCXI FIDR - June 3 2009 25