Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
BOEM.gov
CVOW-C Offshore Wind Farm
CVOW-C Project ConstructionInstallation of Foundations • The Wind Turbine Generator (WTG) Foundation concept
consists of two parts, a lower foundation pile (monopile) driven into the seabed and an upper transition piece mounted on top of the monopile, referred to as the WTG Foundation.
• Installation of the WTG Foundations would entail lifting, upending, and placement of each WTG Foundation at its construction and installation location.
• A two-part WTG Foundation would comprise a monopile with grouted or bolted transition piece or a single part, continuous monopile integrated with the transition piece.
• The WTG Foundations would have scour protection installed around the base of the monopile.
Installation of Wind Turbines • The WTG construction and installation process consists of
the load-out, offshore transport, mechanical erection, and offshore commissioning of the WTGs.
• Depending on the water depth at the WTG construction and installation location, one or two-layers of scour protection would be required. Scour protection would consist of large rocks sourced from the U.S. and/or Canada and would be installed with either a jack-up vessel (JUV) or dynamically positioned (DP) vessel equipped with a fallpipe.
• The monopile would be placed on the seabed on top of the pre-installed scour protection layers and driven to the target depth of penetration by an onboard hydraulic hammer, which is guided by the pile gripper.
• Monopiles would be installed by either one or more dynamically positioned heavy lift vessels (HLVs) or JUVs.
• Monopiles would be installed in one or more years between May 1 and October 31 to avoid the North Atlantic right whale migration season.
• WTG construction and installation activities are anticipated to last up to 30 months.
Offshore Substations • A piled jacket foundation would be used to support the
offshore substations.
• Construction and installation of the offshore substation topside would take place following the construction and installation of the piled jacket foundation.
• After the offshore substation topside is brought to the site, the topside would be lifted and placed on the foundation via a crane on a floating HLV or floating crane vessel. The topside would then be welded or grouted to the foundation.
Cable Laying • The target cable burial depth is 4 to 6 feet.
• Cable installation methods would include jet trenching, chain cutting, trench former, hydroplow, mechanical plowing, pre-trenching, mechanical trenching, and/or other available technologies.
• A narrow temporary trench would be created, into which the cable is fed while the equipment is towed along the seabed. The cable burial equipment rests on skids or wheels.
• The final installation methods and target burial depths would be determined by the final engineering design.
Offshore Wind Turbine Installation
245
° 28
5°
N
EXTERNAL PLATFORM
BOLTING PLATFORM
INTERMEDIATE PLATFORM
INTERFACE FLANGE
BOAT LANDING LADDER WITH
UPPER EXERNAL LADDER
BOAT LANDING FENDER
SERVICE CRANE
SINGLE LINE GROUT PIPE
ICCP CABLE PIPE
ICCP ANODE (x6)
GROUT DISTRIBUTION CHANNEL
UPPER ICCP DISTRIBUTION PIPE
TRANSITION PIECE
LAYDOWN AREA
LOWER ICCP DISTRIBUTION PIPE
GUARD RAIL
WALKWAY
DOUBLE GATES (x3)
SCOUR PROTECTIONFILTER LAYER
SCOUR PROTECTIONARMOR LAYER
Ver. Date Prepared Checked Approved Description
1 2020-12-11 SEP/TPRO KENS OBL ISSUED FOR INFORMATION
245
° 28
5°
4321
C
1 2 3 4
A
B
D
E
F
E
B
A
D
F
C
1Ver.
1690016328-CVOW-C-419-WTG-SS-01-006NOTED A1Drawing No.SizeScale
COASTAL VIRGINIA OFFSHORE WIND COMMERCIAL
Project Number
Project Name
Client
1690016328
GENERAL ARRANGEMENT3D VIEW - WITH SCOUR PROTECTION
Title
ALL RIGHTS STRICTLY RESERVED. REPRODUCTION OR ISSUE TO THIRD PARTY IN ANY FORM WHATEVER, IS NOT PERMITTED WITHOUT WRITTEN AUTHORITY FROM THE PROPRIETOR.
NOTESKEY-PLAN
DAVIT CRANE
CL BOAT LANDING
FOR DESIGNERS REQUIREMENTS SEE REPORTS:1.CVOW-C-3_2_3_1-001 FOR MATERIALS AND FABRICATION AND CVOW-C 3_2_3_1-002 FOR COATING.
ALL ELEVATIONS ARE RELATIVE TO M.S.L.2.
THIS DRAWING IS PRELIMINARY AND IS SUBJECT TO CHANGE 3.DEPENDING ON THE DETAILED DESIGN.
Illustrative Example of the WTG Foundation
For more information on BOEM’s Renewable Energy Program, visit www.boem.gov/Renewable-Energy