Upload
dayo
View
16
Download
5
Embed Size (px)
DESCRIPTION
Curing System for Mat-foundation
Citation preview
CURING SYSTEM FOR MAT-FOUNDATION
ICON COMPLEX PROJECT
CONCRETING TOWER I
Casting Mat Foundation for Tower I • PP divided into 3 (three) zone for pouring the Mat
Foundation; Zone 3 – Zone 4 – Zone 7 • Total Area for Tower I : 5.554,6 m2 • Mat Foundation thickness : 4,1 m
• Zone 3 : had been poured started from June 20th 2015 until June 21st 2015 (10.00 A.M – 11.00 PM)
• Total Volume for Zone 3 : 5.765 m3 • Zone 4 : had been poured started from July 02nd
2015 until July 04th 2015 (11.00 PM – 12.00 AM) • Total Volume for Zone 4 : 6.563 m3
4,1 M
• Zone 7 : still on progress preparation
THERMOCOUPLE
Thermocouple Plan for Tower I • For Tower I, should be provided 25 (twenty five)
thermocouple for controlling the temperature of concrete mat foundation.
• For zone 3 : there are 8 (eight) points of thermocouple in the Tower area • For Zone 4 : there are 9 (nine) points of thermocouple • And for Zone 7 : there will be 8 (eight) points of thermocouple
• Total : 25 thermocouples; • Each thermocouple divided into 4 layers –reading control wire (Top, Middle I, Middle II, Bottom).
Installing Thermocouple
• Install the thermocouple in the suitable area.
• Grouting the cable pipe by using grouting cement.
• Read the thermocouple after the concrete poured and covered by plastic & plywood.
THERMOCOUPLE MONITORING ZONE 3
Thermocouple at Zone 3 • Zone 3 : there are 8 (eight) thermocouples • After concreting finish per subzone and layering by floor hardener,
then the concrete covered by concrete plastic and plywood as the curing method.
• Temperature monitoring is started in the 1st hour after the concrete covered by plastic and plywood.
• Reading the thermocouple in every an hour for two days to control the critical hour of concrete temperature; then temperature reading will be continued in every 3 hours until day-7.
• Maximum temperature at Zone 3 :
- Top : 83°C - Middle I : 96°C - Middle II : 96°C - Bottom : 87°C - Air : 35°C
THERMOCOUPLE MONITORING ZONE 4
Thermocouple at Zone 4 • Zone 4 : there are 9 (nine) thermocouples • After concreting finish per subzone and layering by floor hardener,
then the concrete covered by concrete plastic and plywood as the curing method.
• Temperature monitoring is started in the 1st hour after the concrete covered by plastic and plywood.
• Reading the thermocouple in every an hour for two days to control the critical hour of concrete temperature; then temperature reading will be continued in every 2 hours until day-7.
• Maximum temperature at Zone 4 :
- Top : 75°C - Middle I : 79°C - Middle II : 78°C - Bottom : 74°C - Air : 36°C
THERMOCOUPLE MONITORING ZONE 3 & 4
• Maximum temperature at Zone 4 :
- Top : 75°C - Middle I : 79°C - Middle II : 78°C - Bottom : 74°C - Air : 36°C
• Maximum temperature at Zone 3 :
- Top : 83°C - Middle I : 96°C - Middle II : 96°C - Bottom : 87°C - Air : 35°C
• Maximum concrete temperature at Zone 3 is higher than the temperature at Zone 4 (as shown in the monitoring table).
• At Zone 3, Temperature monitoring read every an hour for two days and continued every 3 hour until day-7.
• While at Zone 4, Temperature monitoring read every an hour for two days and continued every 2 hour until day-7 (to have more control for the temperature).
Concrete covered by plastic and plywood
Thermocouple
MONITORING Concrete TEMPERATURE
FINISH POURING (LAYERING BY FLOOR HARDENER)
COVERED THE CONCRETE BY PLASTIC AND PLYWOOD
After an hour
READ CONCRETE TEMPERATURE
(THERMOCOUPLE)
OPEN THE PLYWOOD WHETHER THE CONCRETE
TEMPERATURE IS GOING HIGHER (>15°C)
PUT THE PLYWOOD DOWN WHEN THE
CONCRETE TEMPERATURE IS GOING
LOWER AND STABLE
START
FINISH
TEMPERATURE MONITORING UNTIL DAY-7
• The curing system by covering the concrete with plastic and plywood.
• Opening the plywood when the temperature is going higher to control the concrete temperature.
Concrete curing at ZONE 3 & 4
• Basically, the curing system for zone 3 and zone 4 has no difference.
• Up and down plywood to control the temperature is executed in turn.
• For getting a better control at Zone 4, we read the concrete temperaure more often for every 2 hour in the day-3 to day-7.
•Based on the monitoring result for zone 3, we did a better control management for concrete curing by up-down the plywood regularly at Zone 4 and read the temperature more often. •We would also apply this curing control management for the next zone.