CTS Wireless Pilot Status Quarterly Customer Meeting. January 22, 2013. Develop and implement a secure, enterprise Wireless service providing agency employees and guest agencies greater mobility and productivity . In Scope: Use Case #1 – Local Agency Access Use Case #2 – Guest Access - PowerPoint PPT Presentation

Citation preview

Page 1: CTS Wireless Pilot Status Quarterly Customer Meeting

CTS Wireless Pilot StatusQuarterly Customer Meeting

January 22, 2013

Page 2: CTS Wireless Pilot Status Quarterly Customer Meeting

Pilot Objective & ScopeDevelop and implement a secure, enterprise Wireless service providing agency employees and guest agencies greater mobility and productivity.

In Scope:•Use Case #1 – Local Agency Access •Use Case #2 – Guest Access•Use Case #3 – Roaming Agency Access

Not in Scope:•BYOD access to state resources (is available using Guest Access + VPN)•Public Access (internet access without any password)

Page 3: CTS Wireless Pilot Status Quarterly Customer Meeting

Pilot Participants

• There are 4 agencies participating along with CTS. The agencies include:– DSHS– DOR– DFI– LSC (Use Case #3 - roaming access only)

Page 4: CTS Wireless Pilot Status Quarterly Customer Meeting

Pilot Timeline

Page 5: CTS Wireless Pilot Status Quarterly Customer Meeting

Pilot Status

• Customer onboarding is complete:– Customer admin training has occurred– Agency and CTS readiness activity has completed

• Necessary firewall changes were made• Necessary IP and DHCP configuration changes were made• Floor maps were loaded into the Prime Infrastructure application

– All Access Points (APs) have been installed– Customers are testing

• Initial feedback regarding user experience is positive, however the teams are identifying and resolving issues

Page 6: CTS Wireless Pilot Status Quarterly Customer Meeting

Pilot Issues

• Some issues discovered so far during the pilot:– Each agency has needed to work through missed onboarding prep

steps during the onsite installations. – Agency application firewalls needed to be opened to allow access.– POP3 firewalls needed to be opened.– Short time-out cycles and complex passwords were difficult for users

and admins.– Settings needed to be adjusted to block inappropriate sites.– Initially, logs/reports were unavailable.

• Guest Registration processes were not developed prior to the initial AP installs, however two options have now been configured. Automated email notification of registration was also added.

Page 7: CTS Wireless Pilot Status Quarterly Customer Meeting

Client Configuration

CTS shared instructions to the agencies for the creation of a Group Policy Object (GPO) which agency admins will deploy to automatically update users’ machines with the appropriate client configuration and user certificates when users log in to Active Directory.

Page 8: CTS Wireless Pilot Status Quarterly Customer Meeting

Pilot Testing

CTS provided agencies with 54 pilot test cases and encouraged agencies to supplement with additional test cases to address accessing customer- specific applications.

Page 9: CTS Wireless Pilot Status Quarterly Customer Meeting

Next Steps

• Finish test case execution and gather results.

• Finish the Business Model.

• Finalize Business Plan by end of testing to inform the Go / No Go decision.

• Pending a “Go” decision, tear down pilot environment and build production environment