74
Critical Success Factors for Application of BIM for Singapore Architectural Firms Thant Zin Oo H00118354 A dissertation submitted in partial fulfilment of the requirements for the degree of MSc in Construction Project Management Dissertation supervisor: Lim Jee Yat, Nicola Naismith Heriot‐Watt University School of the Built Environment 4 April 2014 Declaration: I hereby confirm that this dissertation is my own work. Thant Zin Oo 4 April 2014 ___________________________ ________________ Signature Date

CSF for application of BIM for singapore architectural firms.pdf

Embed Size (px)

Citation preview

  • CriticalSuccessFactorsfor

    ApplicationofBIMfor

    SingaporeArchitecturalFirms

    ThantZinOo

    H00118354

    Adissertationsubmittedinpartialfulfilmentoftherequirementsforthedegree

    of

    MScinConstructionProjectManagement

    Dissertationsupervisor:LimJeeYat,NicolaNaismith

    HeriotWattUniversity

    SchooloftheBuiltEnvironment

    4April2014

    Declaration:

    Iherebyconfirmthatthisdissertationismyownwork.

    ThantZinOo 4April2014

    ___________________________ ________________

    Signature Date

  • i

  • ii

    TABLE OF CONTENTS

    1 Page

    ALP STUDENT DECLARATION................................................................................................i

    ALP LOCAL ADVISOR DECLARATION..................................................................................i

    TABLE OF CONTENTS..............................................................................................................ii

    LIST OF TABLES........................................................................................................................v

    LIST OF ILLUSTRUATIONS....................................................................................................vi

    ACKNOWLEDGEMENTS........................................................................................................vii

    ABSTRACT...............................................................................................................................viii

    GLOSSARY OF ABBREVIATIONS..........................................................................................ix

    Chapter 1 Introduction to the research.......................................................................................10

    1.1 Introduction...................................................................................................................10

    1.2 Rationale of the research..................................................................................................10

    1.3 Aim...................................................................................................................................11

    1.4 Objectives.........................................................................................................................11

    1.5 Hypothesis........................................................................................................................12

    1.6 Research methodology.....................................................................................................12

    1.7 Outlined of research method............................................................................................12

    1.8 Scope of the research........................................................................................................13

    1.9 Structure of dissertation....................................................................................................13

    Chapter 2 Literature Review......................................................................................................16

    2.1 Introduction......................................................................................................................16

    2.2 BIM in design...................................................................................................................16

    2.3 State of the industry..........................................................................................................17

    2.2.1 Removing impediment to ease transition from 2D to BIM.......................................19

    2.2.2 Providing incentives for early adopters.....................................................................20

    2.2.3 Creating the demand public sector taking the lead.................................................20

    2.2.4 Building capability and capacity...............................................................................20

    2.2.5 Promoting Success Stories........................................................................................21

    2.4 Design Services................................................................................................................22

    2.5 Design Coordination Process...........................................................................................23

    2.6 Integrated Deliveries: Design-Construction Integration...................................................24

    2.7 BIM benefits and Challenge.............................................................................................24

    2.8 BIM design productivity benefits.....................................................................................26

    2.9 New and changed staffing within design firms................................................................26

    2.10 BIM contractual terms....................................................................................................27

    2.11 Conclusion......................................................................................................................28

    Chapter 3 Research methodology...............................................................................................29

  • iii

    3.1 Introduction......................................................................................................................29

    3.2 Selection of research methods..........................................................................................29

    3.3 Research process..............................................................................................................30

    3.4 Research techniques.........................................................................................................30

    3.5 Literature Review.............................................................................................................31

    3.6 Semi-structured interview................................................................................................32

    3.7 Interviews Candidates: Selection of Interviewees...........................................................33

    3.8 Interview process and procedure......................................................................................33

    3.9 Content Analysis..............................................................................................................34

    3.10 Conclusion......................................................................................................................34

    Chapter 4 BIM Executive Planning............................................................................................35

    4.1 Introduction......................................................................................................................35

    4.2 Background Information..................................................................................................35

    4.2.1 Participants................................................................................................................35

    4.2.2 Architectural Firms....................................................................................................36

    4.2.3 Previous BIM experience..........................................................................................37

    4.3 Experience on BIM Execution Planning..........................................................................37

    4.4 Conclusion........................................................................................................................39

    Chapter 5 BIM Uses in Singapore Architectural Firms..............................................................40

    5.1 Introduction......................................................................................................................40

    5.2 BIM uses in Singapore Architectural Firms.....................................................................40

    5.2.1 Design Authoring......................................................................................................40

    5.2.2 Programming.............................................................................................................41

    5.2.3 Existing Condition Modelling...................................................................................41

    5.2.4 Design Reviews.........................................................................................................42

    5.2.5 System Analyses.......................................................................................................44

    5.2.6 Phase Planning and 4D modelling.............................................................................45

    5.2.7 Estimating.................................................................................................................46

    5.2.8 3D printing................................................................................................................46

    5.3 Model content and level of details....................................................................................46

    5.4 Taxonomy of BIM use in Design.....................................................................................47

    5.5 Conclusion........................................................................................................................48

    Chapter 6 BIM Impact Analysis.................................................................................................49

    6.1 Introduction......................................................................................................................49

    6.2 Impact Analysis on BIM..................................................................................................49

    6.3 Impact Analysis on Time, Cost, Quality, Sustainability and Safety.................................50

    6.3.1 Time..........................................................................................................................50

    6.3.2 Cost...........................................................................................................................51

    6.3.3 Quality.......................................................................................................................52

  • iv

    6.3.4 Sustainability.............................................................................................................52

    6.3.5 Safety.........................................................................................................................53

    6.4 Design Staff Composition................................................................................................53

    6.6 Issues and concern............................................................................................................54

    6.7 Modelling Process and software Application...................................................................55

    6.8 Team Competencies.........................................................................................................55

    6.9 Legal, Insurance, and Contractual Considerations...........................................................56

    6.10 Risks...............................................................................................................................56

    6.11 Future Industry Trends...................................................................................................57

    6.12 Critical success factors...................................................................................................58

    6.13 Conclusion......................................................................................................................59

    Chapter 7 Conclusion.................................................................................................................61

    7.1 Introduction......................................................................................................................61

    7.2 Recommendation for best practice of BIM Execution planning......................................61

    7.2.1 Participants of BIM Execution Planning...................................................................62

    7.2.2 Decision making process for BIM Execution Planning.............................................63

    7.2.3 BIM Execution Plan Development process...............................................................64

    7.5 Limitation of the Research...............................................................................................65

    7.6 Recommendation for further study...................................................................................65

    Bibliography...............................................................................................................................66

    Appendix A Interview Questions...............................................................................................70

    Appendix B Interview Questions Mind Map.............................................................................73

  • v

    LIST OF TABLES

    Table 4-1 General overview of the position of interviewees......................................................36

  • vi

    LIST OF ILLUSTRUATIONS

    Figure 1-1 Research Process Diagram.......................................................................................15

    Figure 2-1 Roadmap for BIM (Source: BCA, 2013)..................................................................19

    Figure 5-1 Taxonomy of BIM uses in design stage by Singapore Architectural firms..............48

    Figure 7-1Potential Participants in the Creation of BIM Execution Plan...................................63

  • vii

    ACKNOWLEDGEMENTS

    The master course was an exciting journey for me. In 2010 I joint as an Architectural

    Coordinator in Downtown Line Stage 1 Bugis Station Construction. I notice that almost all of the staffs at manager level in the office are master degree holders. That makes me to realise that

    if I want to get higher position I need to have a master degree. Late 2010, my colleague gave

    me a link of a school that he has been perusing MSc. It took me another 6 months to think. After

    that I enrolled and accepted by Heriot-Watt University.

    Im so satisfied with the learning journey. In 2012, I met with Mr. Lim Jee Yat and I got my

    first A in the subject taught me. I learned a lot of knowledge from him. Not only the knowledge to sit an exam but also for the life lessons. He always helped me and encouraged me for the

    course. Thanks for your guidance and supervision. I have a deep sense of gratitude to him.

    I like to say thanks of my colleague, Goh Sin Rong. We had studied together in the office for

    years. Without his help, I may not start this journey. I am very much indebted to Goh, who

    showed me the incredible opportunity to give my life and career a different path, and at the

    same time guided, supported, and inspired me to achieve my best. Thanks for helping me.

    I would like to say thank to my bosses, Koh Lye Hock and Andrew Reeves for letting me study

    in the office and always giving me leave when the exam is near. Our C903 project team has been so nice to me. Without your supports, I wouldnt be able achieve this. I got determination

    and motivation to enrol this MSc program by joining this SBKB JV C903 team. The team

    support me through out the learning journey. The learning culture was some how grown in our

    team. Probably, the seniors in the firm are holding highly professional status and younger ones need to fill in their shoes. Obviously, two people in the office have received advance academic

    qualifications during this project period. Thanks everyone from our team.

    I would like to offer my sincere thanks to all the Architectural firms and their staffs who

    volunteered to participate in this research in the March 2014. Your contributions were really

    valuable and made enormous contribution to this research. I have greatly benefitted from you. Without your kind help this dissertation would not have been possible.

    I would like to say thanks to my mother any my aunt, Khin May Aung. Youre my inspiration.

    Thanks to my girlfriend, Mo Mo Tun because you have been so nice to me all these year.

  • viii

    ABSTRACT

    The Client, Facility Manager, and project participants (Project Managers, Architects,

    Engineers, Contractors, Subcontractors, and Fabricators) are exploring the best usage of

    emerging technology, Building Information Modelling (BIM) on their projects. In

    general there are four individual stages of the project; planning, design, construction,

    and operation. The project team required to make decision on BIM execution at those

    stages. This study is focused on the implementation of BIM in the design stage of

    Singapore Architectural firms. The goals is to discover and define BIM uses in design

    process by developing taxonomy with the purposed of as the basis for BIM execution

    plan.

    The research methods involved in this study are a focused literature review, expert

    interviews, and qualitative analysis of the collected data. In-depth interview with

    industrial experts from Singapore Architectural Firms were conducted, and their

    opinions on BIM were recorded. By using content analysis procedure, quantitative data

    were analysed. The results were presented in details including taxonomy of BIM uses

    in design stage of Singapore Architectural firms and recommended for future studies.

    From the expert interviews, collected data were analysed.

    The centric focus of the result was presented as a taxonomy including 15 BIM

    applications in design with present regular usage in three distinctive categories. These

    are Design Communication, System Analysis, and Scheduling.

  • ix

    GLOSSARY OF ABBREVIATIONS

    2D Two Dimensional

    3D Three Dimensional

    AEC Architecture, Engineering, and Construction

    BCA Building and Construction Authority

    BDS Building Description System

    BIM Building Information Modelling

    CAD Computer Aided Drafting

    CCIT Centre for Construction Information Technology

    CORENET Construction and Real Estate Network

    CPCF Construction Productivity and Capability Fund

    CSFs Critical Success Factors

    CURT Construction Users Round Table

    CORENET Construction Productivity Network

    CPCF Construction Productivity Fund

    C&S Civil and Structural

    GFA Gross Floor Area

    GIS Global Information System

    HDB Housing Development Board

    IHL Institutes of Higher Learning

    LOD Level of Details

    LTA Land Transport Authority

    M&E Mechanical and Electrical

    MOE Ministry of Education

    OMM Operation and Maintenance Manual

    PSSCOC Public Sector Standard Condition of Contract for Construction Works

    RFI Request for Information

  • 10

    Chapter 1 Introduction to the research

    1.1 Introduction

    The successful implementation of Building Information Modelling (BIM) at project

    level needs thorough planning by client and all the project participants (Project

    Managers, Architects, Engineers, Contractors, Subcontractors, and Fabricators) to

    achieve smooth transition from traditional approach to integrate this emerging

    technology, BIM into the project workflow (Arayici et al, 2011a). Implementation of

    BIM takes time, resources and creates unavoidable learning curve. The implementation

    of BIM can be counter-productive if it is not supported by new workflow (Arayici et al.,

    2011a, Arayici et al., 2011b). A potential answer to smooth and successful transition

    would be to establish the BIM execution plan in the various stages of the project:

    planning, design, construction, and operation. Prior to producing the BIM execution

    plan, the project team should concentrate on the desire outcomes and agree on

    appropriate BIM uses on the project. This dissertation particularly focuses on the

    implementation of BIM at the design stage of Singapore Architectural firms.

    1.2 Rationale of the research

    Building information modelling (BIM) has been made mandatory for public-sector

    projects in developed countries in recent years (BCA, 2013a). During the past 10 years,

    there were many discussions on BIM that changed the Architectural, Engineering and

    Construction (AEC) industry work practice. In particular, Architects and Engineers are

    affected by the change (CURT, 2005). Further, BIM has been acclaimed as a proven

    tool for increasing productivity and efficiency in the AEC industry (Arayici et al,

    2011a).

    Thus, the governments in the UK, Canada, Finland, and New Zealand are implementing

    BIM in their AEC industry to improve their productivity. According to the NBS

    survey 39%, 64%, 65% and 57% of the respective respondents from the UK, Canada,

    Finland and New Zealand answered that they are aware of BIM and currently using

    (NBS, 2014). In year 2010, the Building, and Construction Authority (BCA) of

  • 11

    Singapore implemented the BIM Roadmap. The authority targeted for 80% of the

    construction industry to use BIM by 2015 (BCA, 2011c).

    The most recent insightful research for BIM implementation rate in Singapore was done

    in 2012 (Ang, 2012). His research was conducted on the Client, Facility Manager, and

    project participants (Project Managers, Architects, Engineers, Contractors,

    Subcontractors, and Fabricators). However, only 20% of the local firms use BIM in

    some of their projects (Ang, 2012; Keung, 2011b) and as low as 12% of the firms use

    BIM in all of their projects. These figures may not fully reflect todays Singapores

    state of the industry. However, these figures, arguably, reflect todays Singapores state

    of the industry. There is no exploratory study on the uses of BIM for Singapore

    Architect firms in design stage. There are limited capacity of data to observe the uses

    of BIM in Singapore Architectural firms and deciding the critical success factors.

    Therefore, this dissertation is exploratory study to explore the uses of BIM in Singapore

    in Singapore Architectural firms in design stage by interviewing BIM experts from

    these firms. The collected will be analysed and presented by taxonomy. The critical

    success factors will be identify through literature and interviews.

    1.3 Aim

    The aim of the research is to investigate the use of BIM in Singapore Architectural firm

    and develop taxonomy to see an overview of a BIM Execution Plan in the early stage of

    a construction project. This dissertation focuses exclusively on the design stage of BIM

    Execution Plan. This aim is realised by analysing the results from interviewing

    industrial experts practicing in Singapore and reviewing literature on BIM and it uses.

    The following research objectives were identified.

    1.4 Objectives

    To investigate the trends of BIM implementation process and develop taxonomy

    in design practice of in Singapore Architectural firms;

    To identify the critical success factors for implementation of BIM

    To recommend the best practice for BIM Executive Planning for Singapore

    Architectural Firms

  • 12

    1.5 Hypothesis

    BIM improves Singapore Architectural design firms to be more productive.

    1.6 Research methodology

    Chapter 3 explains the detail of research methodology by justifying the chosen research

    methods and techniques. This chapter clarifies why this research is exploratory in

    nature. Different types of research techniques were employed in this study and why

    these techniques were chosen were rationalised. The research techniques, literature,

    interviews, and content analysis, are briefly explained during the research process.

    1.7 Outlined of research method

    To achieve the objectives of the study, following research steps were executed.

    Step 1, Literature review: This step explains the definition of BIM while

    discovering many issues on BIM, its current status, barriers and success factors.

    From the industrial aspect, literature review on BIM implementation in design

    was conducted. The review papers are academic journals, BIM guides,

    unpublished thesis, conference proceeding and expert articles.

    Step 2, Semi-structured interview: In this step, BIM methods in design, together

    with challenges and opportunities were discovered. Interview questions were

    established after literature review. Interviews were conducted with four BIM

    experts practicing in three of the leading Singapore Architectural firms.

    Step 3, Content analysis: In this step, the collected data were analysed. The

    summary and conclusion were made based on the result of analysis. Data

    analysis was performed by analysing the content and mapping to organise the

    information. Quantifiable data were averaged as well as those were organised

    base on their frequencies.

  • 13

    Step 4, BIM uses in Design: Taxonomy was created in this step. The uses of

    BIM in design stage are established in detail manner. The taxonomy of BIM

    application in design stage as a research product was provided as part of

    establishing critical success factors for application of BIM for Singapore

    Architectural firms for design stage.

    1.8 Scope of the research

    The focus of the study is the implementation of BIM in the design phase for Singapore

    Architectural firms. The research participants of the study are various architectural

    firms in Singapore, currently using BIM. The interviews were conducted on March

    2014 to fulfil aims, objectives and hypothesis of the research.

    1.9 Structure of dissertation

    The dissertation is structured as follow. The research process together with their

    corresponding chapters is illustrated in Figure 1-1.

    Chapter 1 provides the introduction to the topic along with the rationale of the

    study, aims, and objectives of the research, outline methodology, scope of the

    research and the structure of dissertation.

    Chapter 2 acts as commencement, and gives the literature review on BIM

    implementation in design was conducted. This chapter outlines current uses,

    motives, critical factors, and different outlook, and explains approached that

    Architectural firms take upon.

    Chapter 3 explains the procedures and techniques that were employed:

    literature, expert interviews, and content analysis; gives justification for why

    these methods are selected for the dissertation; and also details the procedure of

    data collection, data analysis and research results.

  • 14

    Chapter 4 explains the background of interviewees and their BIM Execution

    Planning.

    Chapter 5 details BIM Uses in Singapore Architectural Firms. It discusses the

    numerous items related to BIM uses in design stage of Singapore Architectural

    firms. All the important results regarding the uses of BIM implementation on

    Singapore Architectural from expert interview are mapped and presented.

    Taxonomy of BIM uses in design stage of Singapore Architectural firms is

    presented.

    Chapter 6 provides the results of the research, summarising of the expert

    interviews. All the important results regarding the impact on of BIM

    implementation on Singapore Architectural from expert interview are mapped

    and presented. Eventually critical success factors are identified

    Chapter 7 concludes the research by summarising the results and provides the

    final conclusions of the research, recommendation for BIM Executive Planning

    for Singapore Architectural firms in design stage and recommendation for future

    studies. The aim, objectives and hypothesis of the research were review.

  • 15

    Figure 1-1 Research Process Diagram

    Chapter1Interoduc>onoftheresearch

    Chapter2literaturereviewonresearchtopic

    Chapter3

    Researchmethodologyandra>onaleforchoosingpar>cularresearchmethod

    Chapter4

    Backgroundofinterviewees

    Evalua>onofcollecteddata

    Chapter5

    BIMUsesinSingaporeArchitecturalFirm

    Evalua>onofcollecteddata

    TaxonomyofBIMusesindesignstage

    Chapter6

    Theresultsoftheresearch

    Evalua>onofcollecteddata

    Cri>calSuccessFactors

    Chapter7

    Conclusionandrecommenda>onthebestprac>ceofBIMExecu>vePlanning

    Recommenda>onforfuturestudy

  • 16

    Chapter 2 Literature Review

    2.1 Introduction

    BIM can be considered as a paradigm shift in the Architectural, Engineering, and

    Construction (AEC) industry (Arayici et al., 2011). BIM technology has been used in

    other industries such as automobile factories, shipbuilding and aircrafts building (Birx,

    2006). BIM has been proven a successful technique in these industries. Also, BIM is a

    breakthrough technology that improves the construction productivity by integrating

    various disciplines in the construction value chain (BCA, 2013d). Nowadays, AEC

    industry starts adopting BIM. The impact of BIM can be seen in the architectural

    design firms. During conception design stages, the BIM technology brings better

    visualisation that architects can get design feedback from Client. Furthermore, in

    Construction level design stage, with BIM, detailing, specifications, and cost estimation

    can do easier than traditional 2D drawings (Eastman et al, 2011). However, changing

    from traditional 2D to BIM is not straightforward (Loh, 2011, Eastman et al, 2011).

    Practically, effective implementation of BIM required significant changes in AEC

    industry (Arayici et al., 2011)

    2.2 BIM in design

    Over the past decades, there have been many discussions focused on the potential of

    BIM changing AEC industrys design practice (Construction Users Round Table

    (CURT), 2005, AIA 2006). After meticulous literature review, BIM is viewed as a

    great potential to help effective coordination and collaboration of different disciplines

    (Architects, Engineers, Contractors, Sub-contractors, Facility Managers, and Owners)

    working complex projects (Birx, 2006, Eastman et al, 2011).

    The concept of BIM was stated as it is seen today in Eastmans Building Description

    System (BDS) in 1970s (Eastman et al., 1974, Eastman et al., 1976). However the term

    was first used in van Nederveens 1992 paper. (Van Nederveen and Tolman 1992).

    Nevertheless, commercial BIM software became plentiful and architecture engineering

    and construction (AEC) industry gradually started adopting BIM in its process

  • 17

    (Autodesk., 2003, Bentley and Workman., 2003, Cylon Research Corporation, 2003,

    Laiserin, 2003).

    The Building and Construction Authority (BCA) of Singapore defined BIM as,

    Building Information Modelling (BIM) is a new three-dimensional modelling

    technology and an integrated process that allows the building professionals of

    various disciplines to explore the building project digitally, before it is built

    (BCA, 2011a).

    BIM can be applied into mumerous numbers of dimensions such as three dimensional

    modelling (3D), construction scheduling and sequencing (4D), costing (5D),

    sustainability (6D) and as-built modelling for facilities operations and maintenance (7D)

    (Redmond et al., 2012). The benefits for implementing BIM include, faster drafting

    without compromising the quality consistency across all drawings and reports, clash

    analysis with building services even before the actual construction and producing

    accurate quantity surveys and cost estimating, simulation and enhance visualisation

    (Eastman et al, 2011, Azhar, 2011). Although many benefits have been acclaimed, there

    are practical concerns for Singapore Architectural firms on the selection of hardware

    and software support BIM, training, initiating BIM project, shifting, or changing of

    liability among project participants (Loh, 2011).

    2.3 State of the industry

    In 2010 the Singapore government announced that a $250-million funding to the

    construction sector through Construction Productivity and Capability Fund (CPCF)

    (Keung, 2010). This fund is intended to assist construction firms in three main areas.

    These are

    - Manpower development and skills upgrading;

    - Technology adoption and

    - Capability building.

  • 18

    In Singapore CPCF support many technology adoption. BIM is one of the technologies

    supported by it (Keung, 2010). All Singapore registered business enterprises are

    eligible to apply for the scheme (Keung, 2010).

    In 2001, BCA launched the CORENET (Construction and Real Estate Network) e-

    submission system to facilitate electronic submission and approval process of all types

    of application made to government agencies. This system transformed Singapore AEC

    industrys time-consuming submission process to easy and efficient paperless

    submission process (Keung, 2011a).

    In January 2010, BCA has launched the worlds first BIM e-submission of architectural

    model for regulatory approval. Nowadays in Singapore, the whole industry already

    adopted 100% CORENT e-submission system. The BIM technology adoption also

    shares the same experience as that of the CORENET. In 2011, only 20% of the local

    firms use BIM in some of their projects. BCA set up a target of getting industry to use

    BIM widely by 2015 in a view of higher productivity and better integration (Keung,

    2011b),

    Out of $250 million CPCF, $5.7 million was reserved as BIM fund for adopting BIM

    (Keung, 2011b). This BIM fund covers cost for BIM supporting software and hardware

    as well training and consultancy. BCA launched Construction Productivity Centre and

    Centre for Construction IT (CCIT) which have been guiding and funding on training,

    technology adoption and improving the way things work in the construction sector

    (BCA, 2011b).

    BCA set up a road map to extensive adoption of BIM in AEC industry. (BCA, 2011a):

    - Removing impediment to ease transition from 2D to BIM;

    - Providing incentives for early adopters;

    - Creating the demand public sector taking the lead;

    - Building BIM capability and capacity;

    - Promoting success stories;

  • 19

    Figure 2-1 Roadmap for BIM (Source: BCA, 2013d)

    2.2.1 Removing impediment to ease transition from 2D to BIM

    BIM submission templates have been developed by BCA with the intention of smooth

    transition from 2D CAD drawings to BIM. Architectural BIM submission template was

    introduced in January 2010 and Structural BIM submission template was introduced in

    April 2011 (BCA, 2013d).

    BCA and buildingSMART Singapore create a library for building and design objects.

    This is to facilitate information sharing. More than 200 projects used BIM models e-via

    CORENET submission system to respective regulatory agencies for review and

    approval (BCA, 2013d).

  • 20

    2.2.2 Providing incentives for early adopters

    In June 2010, the BCA introduced a Singapore $5.7-million BIM Fund under the

    Construction Productivity and Capability Fund for early adoption of BIM in Singapore

    AEC industry. The BIM Fund covers costs for BIM supporting software, hardware,

    training staffs. In year 2011, 70% of the BIM Fund has been committed (BCA, 2011c).

    Firms can either apply for the firm specific scheme or project collaboration scheme

    (BCA, 2013d). The latter allows them learn how to operate in a multi-party

    environment.

    2.2.3 Creating the demand public sector taking the lead

    BIM has been mandatory for public-sector projects in United States, and Scandinavian

    countries such as Finland and Norway. In Singapore, the public sector is taking the

    leads by making BIM as requirement for new building projects. Notably, key public

    sector agencies are the Ministry of Education (MOE), Land Transport Authority (LTA)

    and Housing Development Board (HDB) (BCA, 2013a).

    Additionally, mandatory regulatory BIM submission was enforced by BCA. Starting

    from July 2013, building projects which are larger than 20000 gross floor areas (GFA)

    are required to submit electronically Architectural BIM model for regulatory approval

    via CORENET. Similarly, starting from July 2014, there will be mandatory BIM model

    submission for engineering design if building projects are larger than 20000 gross floor

    areas. Eventually, projects larger than gross floor area of 5,000 square meters are

    required to submit architectural and engineering BIM model in 2015 (BCA, 2013a).

    2.2.4 Building capability and capacity

    BCA engaged Institutes of Higher Learning (IHL) in Singapore to incorporate BIM in

    their curriculum with the intention of equipping the new entrants with BIM skills.

    These IHL include Singapore Polytechnic and National University of Singapore.

    Starting from 2011, students from the department of architecture in these institutions

  • 21

    have to learn BIM as part of their curriculum. Furthermore, BCA arranges intensive

    BIM training programmes for the students graduated in 2011 (BCA, 2011c).

    In May 2011, BCA Academy of Build Environment initiated a Specialist Diploma in

    BIM. In September 2011, the academy started BIM Modelling and Management course

    (BCA, 2011c).

    Since 2011, the BCA Academy has been offering various BIM courses to equip industry

    professionals with the necessary know-how in BIM (BCA, 2011c). The courses

    include:

    - BIM Planning for Client and Facility Managers

    - BIM Management

    - BIM Modelling (covering Architectural, M&E and C&S disciplines)

    - Specialist Diploma in BIM (a five month in-depth course to train BIM

    managers and coordinators)

    Currently, more than 1,000 professionals in the industry and graduates are trained in

    BIM at BCA academy. Today BIM is taught at Vocational Institutes, ITE, Diploma,

    Bachelor, and Master degree levels. Approximately 2,000 students are trained BIM

    each year. (BCA, 2013d)

    BIM vendors also play important roles in providing BIM training. Besides conducting

    training courses, they are also provides consultancy clinic and in-depth workshops.

    Today, more than 3,400 industry professionals have been trained by them (BCA,

    2011c).

    2.2.5 Promoting Success Stories

    In September 2010, BCA established the Centre for Construction Information

    Technology (CCIT). The objective of CCIT is to provide guidance for BIM adoption

    for companies and professionals in the AEC industry. The Centre is promoting BIM

    success case studies and best practices for adoption of BIM via webpage. Additionally,

  • 22

    the CCIT collaborates with buildingSMART Singapore and work with the industry to

    organise regular BIM workshops and seminars (BCA, 2011c).

    Having supports form the government, some Singapore Architectural firms adopt BIM

    with great enthusiasm and they used BIM in some of their projects. As government is

    promoting the success stories, BIM is viewed as a great potential to streamline costs and

    process, to help effective coordination and collaboration of different disciplines and to

    minimise the confusion on job sites. However, these successful stories have though

    learning path before success. Thus, there are many of pros and cons, and unknowns that

    have to be considered when implementing BIM. Immediate benefits cannot be

    harvested by applying the BIM software to old process because implementing BIM

    effectively not only requires learning new software application but also training staffs,

    assigning responsibilities, and changing way of modelling the construction (Bearnstein

    and Pittman, 2004, Eastman et al., 2011).

    2.4 Design Services

    Traditionally, exchanging of two dimension (2D) drawings and documents has been

    practised as inter-disciplinary collaboration in the AEC industry (Singh et al., 2011). In

    these two dimensional drawings, each building professionals such as architects,

    engineers and contractors, prepare their own plans for clash analysis. Therefore design

    clashes, for example, pipe running in to the air-con ducts, cannot be foreseen, and solve

    before it actually happen during the construction stage. With assistant of BIM, 3D

    model of project can be share among the professionals, allowing them to simulate the

    situation and resolve potential design clashes before the construction begins. The

    simulation capability of BIM helps reduce unnecessary reworks at site. However, better

    teamwork is necessary (Eastman et al, 2011).

    Current design practice is only limited to providing drawings while schedules and

    specifications are provided in separate packages. For example, full specification of

    material cannot be found in the drawings as it is usually mentioned in material and

    workmanship specification, which is a separate document. This inadequacy of

    information is a drawback to maintain consistency of interrelated packages. According

  • 23

    to BCAs public sector standard condition of contract for construction works (PSSCOC)

    (BCA, 2008), and Singapore Institute of Architects (SIA)s Condition of Contract (SIA,

    2010), the drawings, specification, schedule of rate (if any), schedule of quantity (if

    any) etc., to supply to the Contractor. Current practice in Singapore, those documents

    packages are supplied to the Contractor in separate packages. Current practice does not

    provide BIM model. Therefore, the way it works in AEC should change and the

    building contracts should be amended.

    Also, with BIM technology, unlike traditional practice, Architects can do digital

    analysis for performance of the building such as to run thermal, energy usage, lighting

    design, and clash analysis. The analyses of building performance are considered value

    added services. BCAs BIM essential Guide for Architectural Consultants (BCA,

    2013b) suggested additional fees should be negotiated and value added services.

    Such value added BIM services may have potential cost implication to the employer.

    Therefore additional fees for these services should be negotiated between all the parties

    involved. BIM objectives and BIM deliverables must be identified. Finally, BIM

    Responsibility Matrix should be signed off at the earlier stage of the project (Eastman et

    al., 2011, BCA, 2013c).

    2.5 Design Coordination Process

    BIM places the effective use and exchange of information at its heart. Effective

    implementation of BIM needs substantial changes in AEC industry. However, BIM is

    not the technical solution to CAD integration (Arayici et al., 2011). Going from

    tradition 2D drawings to BIM is not an easy way. This transformation is required good

    preparation and organised approach. (BCA, 2012) recommended following process.

    Notably, BCA did not include the dispute resolution process.

    (1) BIM Objectives and Responsibility Matrix to be signed off by the parties

    involved;

    (2) Identify the BIM deliverables to be produced of project members to meet

    project objectives with every project stage;

  • 24

    (3) To collaboration procedure for how the step taken to be enable a BIM

    deliverables to be created and shared through the project;

    And Sub-French and Khanzode (2007) recommended

    (4) To establish dispute resolution procedure;

    2.6 Integrated Deliveries: Design-Construction Integration

    BIM is a proven tool for the integration of design-Construction. Some of the benefits

    that Architects teaming with Contractors are early identification of long lead-time items,

    value engineering as BIM based designing process provides automate material take-off

    and costing and sharing BIM and better visualisation assist better analysis for

    fabrication and detailing (Eastman et al., 2011).

    One of the main advantages of BIM for Architects is Construction level BIM models as

    the Architects design intent can be represent to the Client easily. This is widely

    accepted among Architects today to minimise or eliminate the liability of Construction

    issue (Eastman et al., 2011).

    2.7 BIM benefits and Challenge

    Benefits and challenges of BIM were studied for the adoption of BIM form Architects

    point of view.

    After through literature review the benefits of BIM are.

    - BIM creates accurate and standardised construction documents (Azhar, 2011);

    - BIM can do 3D visualization, renderings and fly-through (Azhar, 2011);

    - BIM can do faster drafting without compromising the quality (Azhar, 2011);

    - BIM creates repetitive elements in drafting automatically (Azhar, 2011);

    - BIM can detect and do the clash analysis with building services even before the

    actual construction happen (Eastman et al, 2011);

    - BIM can produce accurate quantity surveys and cost estimating (Azhar, 2011);

    - BIM can do better time planning and project management by as visualise

    construction simulation can be done (Azhar, 2011);

  • 25

    - With BIM design change can be tracked and record easier better and transparent

    change management (Langroodi and Staub-French, 2012);

    - With the assistance of BIM, off site production become easier therefore BIM can

    minimizing material wastages (Eastman et al, 2011, Lu and Korman. 2010)

    - BIM helps facility management and assets management easier (Eastman et al,

    2011, Kelly et al, 2013);

    - BIM can fulfilling government or regulatory requirements (BCA newsroom,

    CORENET, Azhar, 2011);

    - Construction simulation process can simulate different options and choose the

    best alternative at design phase (Azhar, 2011) and this simulation include all

    factors including safety by building design (Zhang and Hu, 2011, Lee et al,

    2012, Zhou et al, 2013);

    - BIM can do energy analysis (Bynum et al, 2013, Azhar, 2011) and carbon

    emission analysis (Li et al., 2012);

    After through literature review the challenges of BIM are.

    - Investment Cost (Bernstein et al., 2012, Gilligan and Kunz, 2007, Eastman et al,

    2011, Loh, 2011);

    - Unavoidable Learning Curve (Bernstein et al., 2012, Gilligan and Kunz, 2007,

    Eastman et al, 2011, DAgostinoet al., 2007, Young et al., 2009);

    - Lack of Management buy-in (Koo, 2012);

    - Shift of Liability among project Participants (DAgostino et al, 2007, Building

    and Construction Authority, 2012 and 2013);

    - Poor collaboration between project participants (Eastman et al, 2011, Won and

    Lee. 2008, DAgostino et al, 2007);

    - Poor interoperability among BIM software (Gilligan and Kunz, 2007, Won and

    Lee 2008, Young et al., 2009);

    - Management problem with BIM master model (Eastman et al., 2011)

    - Security risk (Eastman et al., 2011);

    - Lack of subcontractor who can use BIM technology (Alva, 2012);

    The benefits of BIM is obvious but the additional cost such as BIM supporting software,

    hardware, training staffs, productivity downtime before staffs are not familiar with new

  • 26

    system. These additional cost should be offset by providing value added services such

    as performance based analysis and simulation (Eastman et al., 2011).

    2.8 BIM design productivity benefits

    To rationalise the extra cost for implementing BIM, the benefit of productivity for

    Singapore Architectural firms should be accessed. This can be accessed by number of

    Request of Information (RFI), Variation Orders (VO) and productivity lost/gain of

    salaried staffs (Ang, 2012). There are not many empirical study focuses on these

    aspects of Singapore Architectural firms. BIM is expected to be improved code

    checking process, visualisation, fabrication, clash analysis, shop drawings, cost

    estimating, and change management (Ang, 2012).

    Presently in Singapore, Architectural firms are not keeping track of cost involvement of

    implementing BIM and cost gain by the improvement of productivity. Therefore, these

    metrics needs to be studied systematically to quantify the cost benefit ratio (Ang, 2012).

    The identified key success factors are (NBIM, 2007)

    1. Strong leadership to move the BIM implementation;

    2. Management buy-in and building up BIM skill in the team;

    3. Transparency and accessibility of BIM model;

    4. Ability to use BIM among project participants such as, Architects,

    Contractors;

    5. Collaborative sprit and mutual trust;

    6. Proper quality assurance procedure for BIM process;

    7. Reorganisation of new liability among project participants, i.e. BIM manager;

    2.9 New and changed staffing within design firms

    Singapore architectural firms struggled with the steep learning curve. Learning new

    software and new workflows and trying to break from traditional CAD dogma can be

    daunting (Koo, 2012).

  • 27

    BCA introduced two new professionals to facilitate BIM process. Those are BIM

    Manager and BIM Coordinator (BCA, 2012; BCA 2013c).

    Additionally, the PAS 1192-2:2012 requires the BIM Manager to:

    Provide a focal point for all information modelling issues in the project;

    ensure that the constituent parts of the Project Information Model are compliant

    with the MIDP [Master Information Delivery Plan]; [and] ensuring that the

    constituent parts of the Project Information Model have been approved and

    authorized as suitable for purpose before sharing and before issuing for

    approval.

    BCA (BCA, 2012, BCA 2013c) suggested the responsibly BIM coordinator as

    maintaining a register to record the latest information incorporated in the model and

    BIM manager is responsible for the coordination for the application BIM in a project

    and appropriate implementation by implementing BIM Execution Plan among project

    members. BIM Manager can be a person, firm, or corporation appointed by the Client.

    BCA (BCA, 2012, BCA 2013c) suggested new roles can be carried out by existing

    member in the project team for example, project manager, and architect. There may be

    more than one BIM manager in a project. However, project participants are reluctant to

    take up new liabilities and risks (Bernstein et al, 2012, Gilligan and Kunz, 2007,

    Eastman et al., 2011, DAgostino et al., 2007).

    2.10 BIM contractual terms

    Unlike traditional 2 dimensional drawings, and 3D CAD, BIM model consist of

    geometric attributes such as size, volume, shape and orientation and non-geometric

    attribute such as system data, performance data, regulatory compliance, specification

    and cost (Building and Construction Authority (BCA), 2012, Singh et al., 2011).

    Because of new deliverables, building contracts, liabilities, risk management, and

    insurability need to be tackled.

  • 28

    In 2012, Singapores Building and Construction Authority have published Particular

    Condition for Building information modelling in Singapore BIM Guide Version.1 on

    how to incorporate in Contract document in the Principal Agreement (BCA, 2012,

    BCA, 2013c).

    2.11 Conclusion

    There are still limited numbers of reports and papers on implementation of BIM for

    Singapore Architectural firms (Ang, 2012). Although, Singapores Building and

    Construction Authority published in the guidelines in 2012 and 2013 for

    implementation of BIM, there is no study for the actual application of BIM for

    Singapore Architectural firms. The aim of the research is to provide taxonomy of BIM

    uses in Singapore Architectural firms for early stage of construction projects. This

    dissertation focuses exclusively on the design stage of BIM Execution Plan. Next

    chapter will discuss research methodology in details.

  • 29

    Chapter 3 Research methodology

    3.1 Introduction

    This chapter explains the research methodology employed in this exploratory study.

    The methods are explained in details to justify for their selection. Different types of

    research techniques were employed in this study and why these techniques were chosen

    were rationalised. The research techniques, literature, interviews, and content analysis,

    are briefly explained during the research process.

    The first objective of the research is realised by developing taxonomy of BIM uses in

    Singapore Architectural firms. This taxonomy was constructed based on the quantified

    data, content analysis, conclusions were made, utilising categorisation and frequency of

    the answers given on certain subjects.

    The second objective of the research is realised by identifying the critical success

    factors through the literature review and expert interviews.

    The third objective of the research is realised by recommending the best practice of

    BIM Execution Planning.

    3.2 Selection of research methods

    Generally, there are two strategies of research. They are quantitative research and

    qualitative research (Naoum, 2007). To determine what type of research to be

    selected depends on the purpose of research, the type and availability of the information

    required (Naoum, 2007).

    This study focuses on the BIM design experience for the BIM experts in the Singapores

    AEC industry. In this research, social science research techniques have been chosen

    because the nature of this research is exploratory. Exploratory research is selected

    because it is the appropriate approach when the amount of the knowledge about the

    topic is limited. Exploratory research is used to investigate less understood phenomena

  • 30

    and identify variables and generate hypotheses for further research (Fellows and Liu,

    2008). The research techniques consist of literature review, expert interviews, and

    content analysis. The collected data are qualitative in nature. However, some collected

    data can be quantitatively analysed.

    3.3 Research process

    Secondary data were collected by reviewing literature to establish a clear perspective on

    subject matter prior to primary data collection. The literature covered academic

    journals, trade journal, conference proceeding, text books, periodicals, websites, etc.

    Subsequent to a focused literature review on numerous BIM topics, interview with

    Architects and BIM managers were conducted and their opinions on BIM were recorded

    and analysed. Success stories, important lessons learned, and recommendations were

    recorded from these expert interviews. The summary and conclusion were made based

    on the data received with the intention of integrating in the taxonomy for BIM use in

    Singapore architectural firms.

    In this exploratory study, following research steps were performed;

    1. Literature Review;

    2. Semi-structured Interviews;

    3. Content Analysis;

    4. BIM Uses in Design Taxonomy;

    3.4 Research techniques

    The literature review and interviews were used as research techniques for an exploratory

    study. These techniques are appropriate for diagnosing a situation, screening

    alternatives and to discover new ideas for current hot issues (Naoum, 2007).

    Personal interview is considered as qualitative method of data collection whereas an

    interviewer asks respondents. The questions of the interview are designed to obtain

    answers relevant to the research hypothesis. Many forms of interview are evaluated for

  • 31

    this research. Those are structure and semi-structured interviews along with open-ended

    questions.

    Structured interview: All the interviewees receive same order and wording of

    questionnaire (Naoum, 2007). Structured interviews are, by nature, close to

    questionnaire survey as questions are carefully structured and arranged and let

    the interviewees a limited number of choices to answer. As a result, the

    interviewer full control on the interview process.

    Semi-structured interview: This type of interview is more formal than the

    former. This method is chosen because it allows to interviewees to give their

    opinions on specific issues that interviewer needs to explore to build up reports

    (Naoum, 2007). Open-ended questions were proposed because this is

    appropriate to find peoples opinion where the answers towards hypothesis are

    unclear. Therefore analysis of open-ended question can be complicated compare

    to structured interviews. Pre-coding of question into ideas and themes assists

    the large number of individual responses to a few general categories of answers

    that can be assigned a numerical code (Naoum, 2007).

    Content analysis was employed of the research to systematically analyse the

    facets of a set of data through qualitative research. This qualitative research

    emphasised on the judging of the meaning of collected data. Data are given

    coded allocations to categories Data collected from the interviewees are filled

    into these categories. Therefore, matrix of categorised data can be acquired.

    (Fellows and Liu, 2008).

    3.5 Literature Review

    The research started with literature review on BIM implementation in practice through

    available references. The intention of the literature review is to explain the definition of

    Building Information Modelling, its current status, barriers, and success factors. From

    the industrial aspect, literature review on BIM implementation in design was conducted.

  • 32

    The review papers are academic journals, BIM guides, unpublished thesis, conference

    proceeding and expert articles.

    3.6 Semi-structured interview

    The purposed of semi-structure interview was to find out as much as possible on the

    issues architectural firms faced during BIM implementation in design phase in their

    projects. They outlined previous experiences, current best practices, major challenges,

    lessons learned, and the success factors for implementing BIM. The interview results

    were presented together with initial taxonomy for the uses of BIM in design process.

    Integration with other project stages and future studies were discussed.

    A draft list of interview questions was established after literature review. Draft

    interview question were emailed to dissertation supervisors for comments and feedback.

    The final interview questions were created based on the feedback and comments of

    dissertation supervisors. The interview questions and mind map of interview question

    are enclosed in the Appendix A and B.

    Then in-depth interview with Architects and BIM managers currently using were

    conducted, and their opinions on BIM were recorded. Semi-structured interview

    technique was selected to avoid similar responses like in structured interview. However

    at the same time data collected from the interviews holds certain structure. The

    interviewees were given the chance to talk about the subject without restriction but the

    discussion was controlled. Therefore, data collected could be analyzed, summarised

    and then reported. The rationale for selection semi-structured interviewed was to allow

    interviewer to share in-depth knowledge on the subject (Naoum, 2007) and the nature of

    the research was exploratory research. In this way, semi-structured interview permits

    the interviewees to lead the talk and give their own input which is not reconceptualised

    by the interviewer.

  • 33

    3.7 Interviews Candidates: Selection of Interviewees

    Numerous benchmarking were used for the selection of participants for the study. The

    participants were limited to architects and BIM managers having more than one year of

    experiences on implementing BIM in Singapore architectural firms who interested to

    share their experience and knowledge. First, a list of possible Singapore Architectural

    design firms developed based on the literature review. Those professionals had

    contributed their knowledge on Singapore Building and Construction Authority

    (BCA)s publication, Build Smart Magazine, BIM Essential Guide for Architectural

    Consultants and Singapore BIM Guides. Invitations for participation in the research

    was emailed to potential interviewees and followed up with phone calls within 3 days

    after the invitations were disseminated. Positive responds were received from this

    approach. As many as four practicing professionals from three Singapore Architectural

    firms accepted the invitations for interview. The interview was conducted in March

    2014.

    3.8 Interview process and procedure

    Semi-structured in-depth interviews with Architects and BIM managers were conducted

    within 2 weeks. Informed Consent Proforma was distributed to protect the rights and

    welfare of interviewees. Permission to audio record was requested from the

    interviewees prior to the interviews. The interviewees were briefed on the aims,

    objectives, and scope of the research. The interviews generally took 45 minutes to an

    hour. The interview question were categorised into six sections Background

    Information, BIM Execution Plan, BIM Uses in Singapore Architectural Firms, BIM

    Impact, Case Study and Conclusion Questions.

    Background information focused on previous experience of interviewee on BIM

    implementation of Singapore Architectural firm, their position, and responsibilities.

    BIM Execution Plan question focused on major decisions and steps for implementation

    of BIM. BIM Uses in Singapore Architectural Firms questions focused on majors uses

    of BIM. These questions identified contract consideration, insurance, legal issues, team

    competencies, application, process, content and model detail. BIM Impact question

  • 34

    focused on possible metrics and results including its impact on time, cost, quality, and

    changes in staffs. Case Study questions focused the potential of BIM uses in projects

    and its prospect. Conclusion Questions wrapped up interviews with prospect of BIM

    for the future, possible trends and additional opinion on Singapore Architectural firms.

    Interviews were performed in person. Open-ended questions were used. These types of

    question reduced interviewers bias by allowing the interviewees to express their

    opinions on the subject within the framework. During the interview periods the

    interviewer did not make any judgement or leading answers. The interviews were audio

    recorded for accurate interpretation and future referencing. All the interviews were

    written out and mind mapped to summarise and apply for content analysis.

    3.9 Content Analysis

    The interviews were systematically interpreted and categorised by their meanings,

    intentions, etc. Content analyses were performed for every interview. This technique

    systematically analysed the facets of a set of data through qualitative research. Content

    analysis yield quantitative data for each content category. Detailed content analysis can

    be found in Chapters 4, 5 and 6 with some quantitative data collected and evaluated.

    Taxonomy is created in Chapter 5 and critical success factors are identified in Chapter

    6. A summary of the topics covered and conclusions drawn can be found in Chapter 7.

    3.10 Conclusion

    As stated procedures and techniques used in this research was explained. Justification

    has made for the selection of the methods and techniques. Next chapter will discuss on

    the BIM Executive Planning of Singapore Architectural firms in details.

  • 35

    Chapter 4 BIM Executive Planning

    4.1 Introduction

    Together with the data collection process, the expert interviews were performed. In the

    Chapter 4, 5, and 6, the collected data were analysed and discussed in specific category:

    Background Information, BIM Execution Plan, and BIM Uses in Singapore

    Architectural Firms, BIM Impact, Case Study, and Conclusion Questions. The

    collected information is described with the designation of [I-#] to identify the number

    of interviewee that made the statement. Each analysis result is followed by short

    discussion. Chapter 7 gives a conclusion with general findings and recommendation for

    further study.

    4.2 Background Information

    The background information of the respondents were asked. Those questions included

    the background information of interview participants, of firms. The year of BIM

    implementation personnel experience and company wise experience were recorded..

    4.2.1 Participants

    Interviews stared with simple questions such as the interview participants name, the

    name of the company for record and sharing. Addition to this, their role, and

    responsibilities in the Architectural firm were asked. Table 4-1 provide a general

    overview of the positions of the interviewees. Notably, these interviewees are all

    belongs to 3 main groups; Executives, Architects and Technical Supports. All of the

    interviewees have more than 10 years experience with BIM in Singapore and abroad.

    They implemented BIM in their respective Singapore Architectural firms more than 5

    years ago.

  • 36

    Interviewees

    Number

    Position Group Firm

    number

    I-1 Principal (Technical) Executive/Implementation

    Group

    Firm A

    I-2 Senior Technical Manager Implementation

    Group/Technical Staff

    Firm A

    I-3 Director Building Information

    Modelling (BIM)

    Executive/Implementation

    Group

    Firm B

    I-4 Director & Principal

    Architect

    Executive/Implementation

    Group

    Firm C

    Table 4-1 General overview of the position of interviewees

    4.2.2 Architectural Firms

    Firm A is an international architectural firm with more than 2000 staffs within Asia, the

    Middle East, Europe, and America. There are more than 300 staffs in Singapore. The

    firm offers services in architecture, interior design, master planning, landscape, urban

    design, and building consultancy. This firm was formed in early 2000s by merger of a

    UK based firm and Hong Kong based firms. Firm A has been working with BIM for

    Singapore office since Singapore 10 years ago.

    Firm B was founded in Singapore four decades ago. The firm has more than 600 staffs

    globally 400 staffs working in Singapore. The firm offers a complete design

    consultancy and project management solution, such as architectural design services,

    civil and structural engineering design services, electrical, mechanical and plumbing

    (MEP) design services, construction project management, urban and environmental

    planning, landscape, interiors and environmental. It has operation in China, India,

    Vietnam, Indonesia, Malaysia, Mongolia, United Arab Emirates and United States, and

    Singapore. Firm B has implemented BIM more than 5 years ago.

    Firm C was founded approximately 3 decades ago in Singapore. The firm has more

    than 100 staffs in Singapore. The firm offer architectural design service, interior design

    service and project management services. It involved many building project in

    Malaysia, India, Indonesia, Sri Lanka, the Middle East, China, Vietnam, and Singapore.

  • 37

    For all three firms, their executives and technical staffs are actively supporting and

    industry wide implementation of BIM leaded by BCA. They participated in annual

    BIM competition arranged by BCA.

    4.2.3 Previous BIM experience

    All the interviewees stated that they have previous experience with BIM and they

    implemented BIM into their respected Architectural design firm and they have been

    working win BIM in their day-to-day basis. Thus the interview could continue,

    otherwise the interview would be stopped as the interviewees could not be consist red as

    a competent person in this area.

    All the interviewees have more than 10 years experience in implantation BIM and

    managing projects which use BIM. Interestingly, all of the interviewees also have BIM

    experience in other counties, such as, the UK and Australia. They have been

    implemented BIM and managed BIM projects in others countries before they moved to

    Singapore. They have more than 5 years experience for managing and implantation of

    BIM for Singapore projects.

    4.3 Experience on BIM Execution Planning

    Interviewees were asked about their experience on BIM Execution Plan (BEP). All of

    them have experience for developed BEP for Singapore Architectural firms. All of the

    interviewees considered that the development of BEP is a valuable activity. The

    respondents answers will be summarized and reviewed. The conclusions will be drawn

    in Chapter 7.

    Participants: The participants of BEP are usually singed off between the Client,

    Architects, Engineers, other Consultants, Contractors, Sub-Contractors, and Suppliers.

    Therefore, they can be divided into two groups: internal parties who are the people

    within the Architectural design firm. External Parties can be Structural Engineers,

    Mechanical Engineers, Electrical Engineers, Plumbing Engineers, Landscape Designers,

    Interior Designers, the Client, Contractors, Sub-Contractors, Fabricators,

  • 38

    Manufacturers, and Facility Manager. Internal participants are Executives, Architects,

    designers, and technical support team members. The commitment from all parties,

    internal and external, is so crucial for successful implementation and to get the best

    value out of BIM. Senior buy-in is equally important as having the lower level staffs to

    use BIM.

    Interviewee No. 3 [I-3] All the parties needs to be involved. The senior

    management provides required facilities and support the teams to carry out the

    job success fully. The feedback from technical staffs, architects, and designers

    to senior management is important as well because in practice the technical

    team needs supports from the senior management. Again, these technical staffs

    need to communicate and share the BIM knowledge between each other.

    Therefore, for successful implementation of BIM all the level of staff within the

    company needs to proactive in BIM and the external parties need to use BIM as

    well.

    Interviewee No. 1 [I-1] we try to ensure that our teams are harmonious and

    collaborative and we encourage people to share knowledge.

    Interviewee No. 4 [I-4] BIM will not provide the best value if it is not being

    adopted by the other consultants.

    Decision: These participated architectural firms made the commitment to the

    development of the project using BIM because of the urgency within the industry to

    embrace this approach. These Singapore Architectural firms are utilising BIM not only

    for Singapore but also for other over sea projects.

    Interviewee No. 1 [I-1] There are other projects were doing regionally, we

    dont use BIM because, and there is no man day either from the client or

    statutory board point of view. It is the case of this stage, within the industry and

    the maturity, senior management make careful selection based on availability of

    the staff, client direction, and way up to the benefits that we generate.

  • 39

    Interviewee No. 3 [I-3] In Singapore BIM is statutory requirement but we

    encouraged our clients and project members from other countries to use BIM

    although those countries like Indonesia, and Malaysia BIM is not the statutory

    requirement.

    Process: The firms which participated in the interview are constantly reviewing their

    core competencies and the demand of the market to leverage them and to expend their

    market to get more Clients. The mind sets of these firms are to provide design solutions

    that exceed Clients expatiation. The practice is more on selling the value products

    rather than selling the consultation time. The participated firms are providing the best

    architectural design solution without pricing the extra than traditional two dimensional

    designs and documentation system. This is because the competitiveness in the market

    and the firms commitment to provided the best design solution by using the best

    available technology of the time. These firms confirmed that BEP needs to be separated

    into two parts which are internal BEP and external BEP as the objectives are slightly

    different.

    Interviewee No. 2 [I-2] I like to add the actual fact. We have split the execution

    plan in two. One is project execution plan, somewhat internal. So there are

    slightly different objectives for the project and internal execution plan. There are

    times when you roll; youll need to split the execution plan.

    4.4 Conclusion

    Background information of the interviewee, architectural firm and their experience were

    summarised in this chapter. All of the interviewed firms have local and international

    design offices. The smallest design office participate in the interview has more than

    100 staffs and biggest design office has more than 300 staffs. All the interviewees

    stated that they have more than 10 years overall BIM experience and approximately 5

    years experience working with BIM in Singapore Architectural firms. Small

    Architectural firms did not participate in the research. Next chapter will discuss about

    various items related to BIM uses in design by Singapore Architectural Firms.

  • 40

    Chapter 5 BIM Uses in Singapore Architectural Firms

    5.1 Introduction

    This chapter details the numerous items related to BIM uses in design. It begins from

    the discovery of BIM uses which were evaluated from this study. Then it investigates

    the topics of model contents and level of details, modelling process and software

    application, team competencies, and legal, insurance, and contractual, consideration.

    The uses of BIM are summarised with interview comments about the uses. The

    collected information is described with the designation of [I-#] to indentify the

    number of interviewee that made the statement.

    The BIM uses are outlined along with interview comments regarding the uses. The

    information obtained from the interviewees is reported and indicated with the

    designation of [I-#] to indicate the number of the interviewee that made the statement.

    Not all statements have been validated through research so the reader should only

    evaluate these statements as one opinion from an experienced person.

    5.2 BIM uses in Singapore Architectural Firms

    The taxonomy of BIM used was produced based on the literature review and expert

    interview. There are 21 number of BIM uses were identified. After the taxonomy was

    created, each BIM use was systemically looked into the details for BEP guide.

    5.2.1 Design Authoring

    Design authoring is 3D tools to develop the BIM model in regard to the criteria which is

    important to building design translation. The common users of these tools are:

    architects and designers, 2D to 3D conversion teams, and subcontractors.

    Basically, there are two main type of BIM use for design phase.

    - Design Authoring tools and

    - Audit and Analysis tools.

  • 41

    Authoring tools create models with geometrical attributes whereas audit and analysis

    tool can analyse non-geometrical attributes. Those non-geometrical attributes are very

    useful for engineering analysis such as sustainability analysis, sun path analysis etc.

    Design authoring tools are the fundamental of BIM by combining 3D model with useful

    building database system which allows extraction of building data and simulation for

    engineering analyses.

    5.2.2 Programming

    The definition of Programming is an assessment process on design performance to

    spatial requirements. All the interviewees answered that they had done special analysis

    by using BIM. They have used this feature form the schematic stage; from early

    conceptualisation and massing to the construction design are done by BIM based

    software in their offices. All of them confirmed that this feature of BIM improved their

    quality of design solution.

    5.2.3 Existing Condition Modelling

    Existing Condition Modelling is a process of developing a 3D model of existing

    condition of a site, building, facility, or specific area. Protecting Singapores culture

    and heritage is clearly an important part of the Urban Redevelopment Authority (URA)

    Draft Master Plan. Currently, there are more than 7000 buildings are protected. In

    other words, Singapore really familiar with brown field construction/addition and

    alteration works. All the respondents have experience in existing condition modelling

    because doing architectural practise in Singapore brown field construction/addition and

    alteration works is unavoidable. The outputs are usually BIM model of the whole

    existing building or a portion of the existing building and 3D site topography model

    combine with Global Information Systems (GIS).

  • 42

    5.2.4 Design Reviews

    Design review process for Singapore Architectural Firms is to review the quality of the

    design product to meet client expectation [I-1]. This process can be internal process,

    which is within the Architect firms and external, which includes stakeholders using

    BIM models.

    Interviewee No. 1 [I-1] The design review of our firm is about the quality of our

    product. What our products look like and ensuring that is meeting expectation

    of our Client.

    Design review can be categorised in to:

    - Clash analysis

    - 3D Design Coordination and

    - Virtual Mock-ups

    All of the interviewees answered that they used design review for all three categories.

    All of them answered that with BIM model the design review meetings are must faster

    go get the design resolutions because people can see things better when they are

    presented in isometric 3 dimensional with BIM.

    Interviewee No. 4 [I-4]: BIM models allow us to coordinate a much greater

    detail, a much greater understanding.

    Interviewee No. 3 [I-3]: BIM models provide ability to communicate the

    stakeholders better using a 3 dimensional model.

    Clash analysis is an important and it is the integral part of the BIM modelling process.

    Clash analysis feature of BIM allow various stakeholders to investigate the building

    project digitally in the design studio before it is built. Clash detection in BIM could be

    not only one model but also several, those are, eventually, integrated into a master BIM

    model. This can be consider as one of the greatest benefits of BIM as visualising the

    ideas and iterating of information are more precise and faster than before by eliminating

    the manual tedious and error prone process.

  • 43

    This study is focused on design stage. Therefore design coordination at design stage

    can be defined as an iterative process which includes a process of evolution, iteration,

    revising to the point where the Client has been able to incrementally understand the

    building as a end product and as a cost to him and architectural firm produce a design

    that is efficient, and exemplary as a design product.

    Three Dimensional Design coordination at design stage can be defined as an iterative

    process which includes a process of evolution, iteration, revising to the point where the

    Client has been able to incrementally understand the building as a end product and as a

    cost to him and architectural firm produce a design that is efficient, and exemplary as a

    design product.

    All the interviewees answered that they used BIM as three dimensional design

    coordination tool. All of the interviewees agreed that BIM helps Architects and other

    consultants to resolve coordination during design stage and BIM enables to develop

    more accurate and better-coordinated design product which ensure the clients

    satisfaction.

    Interviewee No. 1 [I-1]: For a client, they dont want to understand that detail of

    coordination. They just wanted to be correct. BIM enables us to provide more

    accurate information and better-coordinated design product.

    It is mostly done either in complicated projects for construction details like wall

    sections or ceilings, or for certain chosen spaces in the project that would benefit greatly

    from building the virtual mock-up.

    Virtual Mock-ups assist all the project participants to understand complicated projects

    for construction.

    BIM enables to construct virtual mock-ups. This helps all the project participants to

    understand complicated projects for construction. It would be an ideal situation to use

    BIM, when each supplier or contractor have relevant BIM model, such as a chiller plant,

    to insert in to the building model and everyone understand the possible implication to

    other components. All the interviewees answer that they are using this feature. They

  • 44

    have been using virtual mock-ups allows to resolve not only coordination issue but also

    use as an analysis tool for lighting, security, ergonomics, acoustics, textures and

    colours, etc.

    5.2.5 System Analyses

    System Analysis can be divided into Site Analysis, Engineering Analyses, and Code

    Checking.

    Site Analysis is a process to analyse specific location to decide the optimal use of site

    location for proposed project by using BIM/GIS tools. All the interviewees answered

    that they had done site analysis using BIM technology as they view that this analysis

    has great potential to do necessary calculation, to determine the building orientation, to

    develop topographical model and to create existing building model, etc.

    Engineering Analyses are a series of BIM uses in design. Engineering Analysis in

    design stage can be defined as a process of judging the most optimal and effective

    methods depend on design specification. During the interview, interviewee answered

    that their firm have done the following engineering analyses -

    - Building and energy consumption analysis

    - Sustainability analyses

    - Egress analysis

    - Traffic and human analysis

    - Peak load analysis

    - Fire protection analysis

    Engineering analyses are a series of BIM uses in design. Engineering Analysis in

    design stage can be defined as a process of judging the most optimal and effective

    methods depend on design specification. BIM model enables many types of

    engineering analyses. These engineering analyses and building performance simulation

    improve the energy consumption, and design of the building for entire lifecycle. These

    abilities make BIM superior to 2D designs. All the interviewees answers that they did

    egress analysis, traffic and human analysis, peak load analysis, and fire protect analysis.

    Additionally, they merge with engineering BIM model and architectural BIM model as

    part of the sustainability analyses.

  • 45

    Interviewee No. 1 [I-1]:The technology make the designing process more

    interesting because its not just about an architect standing there in a

    presentation saying to a client, weve open this frontage of the building up to

    allow for the breeze way and this will be very nice. Its ability to say weve open

    this up because when we did the analytic we can see 60% of the year the

    prevailing wind from the North-East generate some fantastic air movement

    through the area and well be able to through very complex modelling. Exactly

    why they should buy our design and why they should embrace these ideas.

    Code checking is a process of checking of the compliance of the building code of

    building design by using BIM. In 2001, BCA launched the CORENET (Construction

    and Real Estate Network) e-submission system to facilitate electronic submission and

    approval process of all types of application made to government agencies. This system

    transformed Singapore AEC industrys time-consuming submission process to easy and

    efficient paperless submission process (Keung, 2011a). BIM submission templates

    have been developed by BCA with the intention of smooth transition from 2D CAD

    drawings to BIM. Architectural BIM submission template was introduced in January

    2010 (BCA, 2013a). Firm A, B, and C have volunteered to developed CORENET

    statutory BIM model submission system for authorities approval process. These firms

    believe that eventually the system will be very robust.

    5.2.6 Phase Planning and 4D modelling

    Phase planning is usually defined a 4D model because adding dimension of time to 3D

    model for the purpose of effective time scheduling. All the interviewees indicated that

    they used 4D modelling which is a BIM model corporate with adding time schedule.

    They do not put huge emphasis on this for green field, new development. However,

    they used this feature for additional and alteration, renovation, retrofitting, and

    preservation