13
10 th International Conference on Short and Medium Span Bridges Quebec City, Quebec, Canada, July 31 – August 3, 2018 PERFORMANCE OF GFRP COMPOSITE SLAB-ON-CONCRETE GIRDER BRIDGE – 10 YEARS AFTER CONSTRUCTION BASED ON LOAD TESTS Au, Alexander 1 and Mermigas, Kris Bridge Office, Ontario Ministry of Transportation, Canada 1 [email protected] Abstract: The 1st edition of the Canadian Highway Bridge Design Code (CSA 2000) did not permit the use of glass-fibre-reinforced polymer (GFRP) for the main reinforcement in the bridge deck. However, this limitation was removed in the 2 nd edition (CSA 2006), based on field observations of GFRP performance in concrete (Mufti et al. 2007). The rehabilitation of the 3 rd Concession Road Underpass in 2008 took advantage of this material (Lee et al. 2010). The four- span superstructure consists of a composite concrete slab-on-CPCI girder system built in a semi-continuous sequence. The entire deck is reinforced with GFRP reinforcement. In order to assess the structural performance of this material under field conditions, the deck was not protected with the customary waterproofing system and was left with an exposed concrete surface, and the bridge is monitored visually and through behavioural load tests. The first behavioural load test of the bridge was performed in July 2010 (Au and Lam 2010). Strain gauges were installed on the GFRP reinforcement during construction while displacement transducers were installed at other locations. The purpose of the first load test was to confirm the short term behaviour of the bridge and provide base data against which future performance could be compared. The bridge was re-tested in July 2017, nine years after the rehabilitation and seven years after the first load test. The paper compares the performance of the deck and the GFRP reinforcement from the tests in 2010 and 2017. 1 INTRODUCTION The bridge deck is an early MTO structure to be completely reinforced by GFRP bars. MTO planned to monitor the long-term performance of this bridge. During 014-1

csce.ca · Web viewThis bridge was rehabilitated in 2008 with a superstructure replacement. The new superstructure consists of semi-integral abutment connections, 5 new CPCI 900 beams,

  • Upload
    others

  • View
    1

  • Download
    2

Embed Size (px)

Citation preview

10th International Conference on Short and Medium Span Bridges

Quebec City, Quebec, Canada,

July 31 – August 3, 2018

PERFORMANCE OF GFRP COMPOSITE SLAB-ON-CONCRETE GIRDER BRIDGE – 10 YEARS AFTER CONSTRUCTION BASED ON LOAD TESTS

Au, Alexander1 and Mermigas, Kris

Bridge Office, Ontario Ministry of Transportation, Canada

1 [email protected]

Abstract: The 1st edition of the Canadian Highway Bridge Design Code (CSA 2000) did not permit the use of glass-fibre-reinforced polymer (GFRP) for the main reinforcement in the bridge deck. However, this limitation was removed in the 2nd edition (CSA 2006), based on field observations of GFRP performance in concrete (Mufti et al. 2007). The rehabilitation of the 3rd Concession Road Underpass in 2008 took advantage of this material (Lee et al. 2010). The four-span superstructure consists of a composite concrete slab-on-CPCI girder system built in a semi-continuous sequence. The entire deck is reinforced with GFRP reinforcement. In order to assess the structural performance of this material under field conditions, the deck was not protected with the customary waterproofing system and was left with an exposed concrete surface, and the bridge is monitored visually and through behavioural load tests. The first behavioural load test of the bridge was performed in July 2010 (Au and Lam 2010). Strain gauges were installed on the GFRP reinforcement during construction while displacement transducers were installed at other locations. The purpose of the first load test was to confirm the short term behaviour of the bridge and provide base data against which future performance could be compared. The bridge was re-tested in July 2017, nine years after the rehabilitation and seven years after the first load test. The paper compares the performance of the deck and the GFRP reinforcement from the tests in 2010 and 2017.

1. INTRODUCTION

The bridge deck is an early MTO structure to be completely reinforced by GFRP bars. MTO planned to monitor the long-term performance of this bridge. During the deck construction in 2008, 24 strain gauges were installed on the GFRP bars. The initial behavioural load test was in July 2010 as close as practically possible to the bridge’s initial construction. The observations from this load test indicated that the bridge performed very well (Au and Lam 2011). The bridge is inspected regularly with the latest inspection in early 2017. The second load test was performed in July 2017. More external gauges were installed on the bridge deck and more load steps were applied to the bridge. Dynamic tests were also carried out. Two additional accelerometer sets were used to monitor the bridge’s performance.

1 BRIDGE DETAILS

The Highway 401/3rd Concession Road Underpass (MTO Site# 6-236) is a four-span (10.67 m end spans and two 19.20 m main spans) composite slab-on prestressed concrete girder bridge carrying traffic on 3rd Concession Road over Highway 401 in Western Ontario. Its location is on Highway 401 at Lakeshore Road 113, about 30 km east of Windsor. Originally constructed in 1967, the deck system consisted of 5 prestressed concrete girders. This bridge was rehabilitated in 2008 with a superstructure replacement. The new superstructure consists of semi-integral abutment connections, 5 new CPCI 900 beams, and a GFRP-reinforced concrete deck with new parapet walls, also reinforced with GFRP bars. The deteriorated concrete on the pier caps was removed and replaced with new concrete. The 215 mm thick new deck has an exposed concrete surface. Figure 1 shows the bridge details and Figure 2 shows photos of the GFRP reinforcement in the deck and in the parapet wall. Details of the bridge design features are found in Lee et al. (2010).

(a) Elevation

(b) Deck GFRP rebar details

Figure 1: Details of the Hwy401/3rd Concession Underpass

(a) GFRP Bar in Deck

(b) GFRP Bar in Barrier

Figure 2: Photos of GFRP reinforcement

2 INSTRUMENTATION

A total of 47 gauges were installed on the bridge. At a section near the mid-span of the end span as shown in Figure 3(a), five LVDTs and five strain gauges were installed. At a section near the north pier as shown in Figure 3(b), 10 strain gauges were installed. There were three strain gauges installed on top of the concrete deck. During the rehabilitation of the bridge deck in 2008, MTO installed 24 strain gauges on the GFRP bars. Figure 3(c) indicates the strain gauges on two longitudinal and two transverse GFRP bars. The instrumented longitudinal GRFP bars were over the north pier and the transverse GFRP bars were near the mid-span of the north end span. Figure 4 shows photos of typical gauges. Also, two sets of accelerometer were used to monitor the dynamic performance of the deck during dynamic test runs.

(a) Mid-span location

(b) Near the north pier

(c) Strain gauges at GFRP bars

Figure 3: Instrumentation on the Hwy401/3rd Concession Underpass

(a) Strain gauge on GFRP bars

(b) LVDT and strain gauge on girder

Figure 4: Photos of typical gauges

3 APPLIED LOADS

The test loads were applied on the bridge using two test trucks, each consisting of a three-axle tractor and a two-axle semi-trailer. The trucks were loaded with concrete blocks, each weighing approximately 1 tonne, and carrying a maximum load of 36 concrete blocks each. The first truck (Volvo Auto-car) had a maximum gross weight of 539.5 kN and the second one (Western Star), 548.7 kN (see Figure 5)

The test trucks were loaded incrementally to three different load levels i.e. with12, 24 and 36 concrete blocks. For each load level, the trucks were moved longitudinally on the bridge in four pre-set combinations, referred to as load lines 2 to 5 (Figure 6). Load lines 2 and 3 were single truck cases while load lines 4 and 5 involved both trucks. It can be seen that load line 4 is effectively a combination of load lines 2 and 3. To obtain the bridge response under static conditions, each truck was positioned at 17 pre-determined locations or steps along each load line, as shown in Figure 7. For each truck step, the readings from all the instrumentation devices were recorded by a computerized data acquisition system. The truck steps were selected in order to generate maximum theoretical responses in the bridge.

A dynamic test was performed after the static load test. Dynamic runs were provided by a test truck loaded with 24 concrete blocks, running with 40 km/hr across the bridge. The time variation of the responses was measured together with data collected by two accelerometers on the deck.

Figure 5: Test truck loads and dimensions

Figure 6: Transverse locations of the test trucks

Figure 7: Step locations of the test trucks

4 TEST RESULTS

4.1 Girder Deflections

The deflections from 2010 and 2017 load tests match closely. Figure 8(a) shows deflections vs load steps. The truck steps were indicated in Figure 7 (over three spans). The deflection patterns (positive and negative) are similar for all test truck steps. Figure 8(b) shows deflections vs load levels. Linear relations were observed for both 2010 and 2017 deflections. The comparison for the exterior girders was similar. Therefore, it could be concluded that there is no change in the deflection performance within this period.

(a) Deflections(Line 5) vs Steps

(b) Deflections (Line 5 Step 5) Vs Load Levels

Figure 8: Comparison of girder deflections

4.2 Girder Strains

The measured longitudinal strains from 2010 and 2017 load tests are very close, as shown in Figure 9 at the bottom of the middle girder. Figure 9(a) shows strains vs load steps. The strain patterns (positive and negative) are similar for all test truck steps. Figure 9(b) shows strains vs load levels. Linear relations were observed for both 2010 and 2017 measured strains. This is also the case for exterior girders. Therefore, it could be concluded that there is no change in the girder strain response within this period.

(a) Interior girder (Line 5)

(b) Linearity of girder strain (Line 5 Step 7)

Figure 9: Comparison of girder strains

4.3 Strains in GFRP Bars

24 strain gauges were installed on the GFRP bars during the bridge deck construction in August 2008 (see Figure 3(c)). Figure 10 shows the comparison of the longitudinal GFRP bar strains under load line 5. It indicates that the measured GFRP strains from 2010 and 2017 load tests are very close. The GFRP strain patterns are similar for all test truck steps. Figure 10(b) shows longitudinal GFRP bar strains vs load levels. The GFRP strains were linear with the applied load for both 2010 and 2017 measurements. Therefore, it could be concluded that the longitudinal GFRP bar strain response didn’t change in this period.

Figure 11 shows the comparison of the transverse GFRP bar strains. It also indicates that the measured GFRP strains from 2010 and 2017 load tests are very close. The strain patterns are similar for all test truck steps shown in Figure 11(a). Figure 11(b) shows transverse GFRP bar strains vs load levels. It was observed that for both 2010 and 2017 measured strains were linear and very close. Therefore, it could be concluded that the transverse GFRP bar strain response also didn’t change in this period.

4.4 Uncracked Condition over the Pier

In the negative moment area, the crack control for the GFRP design is 0.5 mm against the traditional steel design of 0.25 mm (Lee et.al. (2010)). GFRP design allows higher concrete crack width over the pier. Figure 12 shows the distribution of longitudinal strain at a section near to the north pier. The strains at the girder bottom and at the girder web were plotted at all the load levels. The strains in the girder were negative indicating a negative moment region. Figure 12 also shows the location of the theoretical neutral axis (NA) for the naked girder and the uncracked section. The neutral axis projected from the measured strains is somewhere above the theoretical neutral axis of the uncracked section. It indicates that the girder-GFRP reinforced deck remains in an uncracked condition in the negative moment region. It is in agreement with the bridge inspection where no crack was observed at the negative moment region.

(a) Longitudinal GFRP bar (Line 5)

(b) Linearity of strain in longitudinal GFRP bar (Line 5 Step 11)

Figure 10: Comparison of strains in longitudinal GFRP bars

(a) Transverse GFRP Bar (Line5)

(b) Linearity of strain in transverse GFRP bar (Line 5 Step 11)

Figure 11: Comparison of strains in transverse GFRP bars

Figure 12: Strain distribution in a girder section near the north pier (2017 data - Line 5 Step 11)

4.5 Dynamic Behaviours

(a) Longitudinal GFRP bars

(b) Transverse GFRP bars

Figure 13: Dynamic measurement of the GFRP bars (2017 data)

Figure 13(a) shows the longitudinal GFRP bar strains measured in the dynamic test. It shows similar responses at 4 different gauges along the same longitudinal GFRP bar. It could be concluded that the GFRP bar performed well under the live load and the GFRP bars were perfectly bonded to the concrete. Figure 13(b) shows the transverse GFRP bar strains at 4 gauges along the same transverse GFRP bar. It clearly shows the individual axle effect from a five-axle truck. Therefore, the GFRP bars are working under dynamic loads. Figure 14(a) shows the vibration velocity of the deck during a test truck run. It could be observed that the vibration velocity changes sign a few times due to the effect of a moving truck on a 4-span bridge. Figure 14(b) shows the bridge acceleration vs time. The maximum acceleration at the deck was 0.03g. Detailed analysis of the acceleration vs time and the prediction of the vibration measurement will be presented in a future publication.

(a) Vibration Velocity vs Time

(b) Acceleration vs Time

Figure 14: Dynamic measurement of the deck (2017 data)

5 CONCLUSIONS

Based on the observations from 2010 and 2017 load tests, the following conclusions could be deduced:

· There is no change in the girder performance (deflection and strain) within this period.

· There is no change in the GFRP bar performance (longitudinal and transverse) within this period.

· The girder-concrete deck remains in an uncracked condition in the negative moment region.

· There has been no loss of elastic stiffness in positive and negative moment regions, based on an applied live load.

· The GFRP reinforced deck performing very well in the first ten years in the service.

Acknowledgements

The instrumentation on the GFRP bars was designed by Dr. Clifford Lam, former Head of Bridge Research, Bridge Office. He also worked on the load test in 2010. His contribution is gratefully acknowledged. Both load tests were performed with the hard work of the MTO technical staff, Ping Kang and Nebojsa Lukic. Their efforts are greatly appreciated. The authors also like to thank the contribution of a summer student from McMaster University, Patrick Wilkon, for his work on the load test in 2017.

References

Au, A. and Lam, C. 2011. Testing of Hwy 401/3rd Concession Road Underpass. Bridge Office Report (BRO-054), Bridge Office, Ministry of Transportation, Ontario, Canada.

CSA. 2000. Canadian Highway Bridge Design Code CAN/CSA-S6-00. Canadian Standard Association (CSA) International, Toronto, Ontario, Canada.

CSA. 2006. Canadian Highway Bridge Design Code CAN/CSA-S6-06. Canadian Standard Association, Mississauga, Ontario, Canada.

Mufti,A.A., Onofrei, M., Benmokrane, B., Banthia N., Boulfiza, M., Newhook, J.P., Bakht, B., Tadros G.S. and Brett, P. 2007. Field study of glass-fibre-reinforced polymer durability in concrete. Canadian J. Civil Engineering, 34(3), 355-366.

Lee, J., Craig, B., Loh P. and Dimitrovski, V. 2010. Working towards maintenance-free bridge decks using glass fibre-reinforced polymer reinforcing bars. Proceedings of 8th International Conference on Short and Medium Span Bridges, Niagara Falls, Ontario, Canada, 165: 1-10.

014-1

014-9

CONCRETE PARAPET

WALL WITH RAILING

C

L

PIER #1

C

L

PIER #2

C

L

PIER #3

NORTH ABUTMENT

BEARINGS

C

L

SOUTH ABUTMENT

BEARINGS

C

L

GUIDERAIL AND

CHANNEL

ANCHORAGE

33.5333.53

0.86

4.76 (min.)

ROCK SLOPE

PROTECTION

3.6710.6719.2019.2010.67

3.67

All dimensions in meteres

�

�

G

Box sizes with text.Press to start anew line of text.

All dimensions in meteres

NORTH ABUTMENTBEARINGS

C

L

CONCRETE PARAPETWALL WITH RAILING

PIER #1

C

L

PIER #2

C

L

PIER #3

C

L

SOUTH ABUTMENTBEARINGS

C

L

GUIDERAIL ANDCHANNEL ANCHORAGE

G19M @ 150

West

East

G16M @ 300

G19M @ 150

STRUCTURE AND

3RD CONCESSION RD.

C

L

G19MG16MG19M

G19M

G16M

G16M @ 300

G19M @ 150

G19M @ 150

G16M

G16M ES

�

�

G

Box sizes with text.Press to start anew line of text.

G19M @ 150

GIRDER #1

GIRDER #2

GIRDER #3

C

L

C

L

C

L

C

L

500

500

500

500

141

140

1000

1000

1000

1000

18

19

22

23

1415

16

13

67

8

5

500500

G19M (Bot)

G19M (Top)

C

L

N.Abut.

Brg.

Pier #3

6185

1011

12

23

4

1

X

27

26

25

9

30

31

32

16

Strain gauge

25

LVDT

20

24

17

21

3890310

L1

L2

T1

T2

�

G

Box sizes with text.Press to start anew line of text.

19

C

G19M (Bot)

G19M (Top)

GIRDER #1

GIRDER #2

GIRDER #3

6185

X

C

L

20

L

L1

T1

12

16

10

22

23

500

13

2

500

C

L

C

L

3810182948771829axle No.axle load, kNwheel load, kNgross load, 548.7 kN155.927.952113.756.853113.756.854132.766.355132.766.351830Travel

axle No.axle load, kNwheel load, kN

gross load, 548.7 kN

155.927.95

2113.756.85

3113.756.85

4132.766.35

5132.766.35

Travel

Volvo

Line 2

Line 5

WestEast

Girder 1Girder 2Girder 3Girder 4Girder 5

Line 4

Western

600600

600

47504750

STRUCTURE AND

3RD CONCESSION RD.

C

L

Line 3

Box sizes with text.Press to start anew line of text.

600

600

600

4750

4750

Western

Volvo

Line 2

Line 3

Line 4

Line 5

West

East

Girder 1

Girder 2

Girder 3

Girder 4

Girder 5

STRUCTURE AND3RD CONCESSION RD.

C

L