CS4311 Spring 2011
Verification & Validation
Dr. Guoqiang Hu
Department of Computer ScienceUTEP
Announcement
What: CS4390 (Cross-listed with CS5390): “Software Testing”
Testing Only, Nothing Else!
When: This Summer
Prerequisite: CS4311
* Note: The V&V content covered in this course (CS4311) can be considered as an introduction to the above course
What Are Verification and Validation?Groups of 2
Why? Who? What? Against what? When? How?
5 minutes
Verification:Evaluating the product (a system or component) of a development phase to determine whether the product satisfies the specification at the start of the phase.
Did we build the system or component right?
Validation:Evaluating the product (mostly the system or subsystem) during or at the end of the development process to determine whether it satisfies the specified requirements.
Did we build the right system?
V&V Activities and the Software Lifecycle
Requirements engineering:Determine general test strategy/plan(techniques, criteria, team)
Test requirements specification
• Completeness
• Consistency
• Feasibility
(Functional, performance requirements)
• Testability
(Specific; Unambiguous; Quantitative; Traceable)
Generate acceptance/validation testing data
Design:Determine integration test strategy
Assess/Test the design: Completeness; Consistency; Handling scenarios; Traceability (to and fro). (design walkthrough, inspection)
V&V Activities and the Software Lifecycle
Implementation:Determine unit test strategy
Techniques (Static v. Dynamic):
• Read/Have it read
• Code walkthrough/Formal code inspection
• Formal verification/Proof
• Manual testing
Tools, and whistles and bells (driver/harness, stub)
Maintenance:Determine regression test strategy
Documentation maintenance (vital)
V&V Activities and the Software Lifecycle
The “V” model:
Where Do the Errors Come From?Groups of 2
What kinds of errors? Who?
3 minutes
Kinds of errors:Missing information
Wrong information/design/implementation
Extra information
Facts about errors:To err is human (but different person has different error rate).
Different studies indicate 30 to 85 errors per 1000 lines. After extensive testing, 0.5 to 3 errors per 1000 lines remain.
The longer an error goes undetected, the more costly to correct.
Basic Concepts
Correct specification:Specification matches the client’s intent.
Correct program:Program matches its specification.
Error:A human activity that leads to the creation of a fault.
Fault/Bug:The physical manifestation of an error. It can cause a failure.
Failure:The state when a fault is encountered during execution.
Basic Concepts
Fault identification:Process of determining what fault caused a failure
Fault correction:Process of changing a system to remove a fault
Debugging:Process of finding and fixing program faults
Testing:Designing and executing tests. And (if bugs present) debugging.
Test case:A particular set of input and the expected output
Basic Concepts
Test set:A finite set of test cases working together with the same purpose
Test objective:The main goal for a particular test. Ex., finding faults/fault detection, or, demonstrating reliability/confidence building (no/low failure rate in normal use).
Test objective affects test strategy, test criteria, and test selection.
Test criteria:Specifies testing requirements/stopping rule/measurement. It is closely linked to test techniques. Ex., for coverage-based test techniques, 100% statements, or branches, coverage, or both.
The General Approaches of Verification & ValidationGroups of 2
How?
2 minutes
The Exhaustive Test Examples
Groups of 2
3 minutes
How many test cases are required?
How long will it take?
The Exhaustive Test Examples
Groups of 23 minutes
A
B
C
The Exhaustive Test Examples
Groups of 2
3 minutes
The Purpose of TestingThe purpose of testing is NOT to prove the program is correct
Instead, it is to find problems in the program so that the found problems can be fixed
Interesting phenomena of testing results:Successful test:
The more faults are found, the more successful is a test case/ set.
Quality of the code:
The more faults are found in a unit of code, it normally means the worse is the quality of the code.
Studies found that more faults may still go undetected in the same piece of code.
Although you can say the quality of the code has been improved after the found faults are fixed.
Hierarchy of V&V techniques
V&V
Dynamic Techniques
Symbolic
ExecutionTesting
Informal
Analysis
Formal
Analysis
Static Techniques
Review
Inspection
Walkthrough
Hierarchy of TestingTesting
Program Testing
Top Down
Bottom Up
Integration Testing
Unit Testing
System Testing
Big Bang
Sandwich
Black Box
White Box
Function
Performance
Reliability
Availability
Acceptance
TestingProperties
Security
Equivalence
Boundary
Decision Table
State Transition
Use Case
Domain Analysis
Control Flow Data Flow
Usability
Documentation
Portability
Capacity
Ad hoc
Pilot
Alpha
Beta
Hierarchy of TestingTesting
Program Testing
Top Down
Bottom Up
Integration Testing
Unit Testing
System Testing
Big Bang
Sandwich
Black Box
White Box
Function
Performance
Reliability
Availability
Acceptance
TestingProperties
Security
Equivalence
Boundary
Decision Table
State Transition
Use Case
Domain Analysis
Control Flow Data Flow
Usability
Documentation
Portability
Capacity
Ad hoc
PilotAlphaBeta
Types of System Testing
Function Testing: Integrated system performs specified function
• Scenarios
• Black-box techniques
Properties Testing: Integrated system tests against non-functional requirements
• Performance, Reliability, Security, Usability, etc.
• Performance: Stress test: maximum throughput
Overload test: exceed specification
Volume test: sustained large throughput
Response time Robustness: test things not specified, but quite possible
Recovery: crash, or, recoverable?
Acceptance Testing: Customers test system
• Pilot (initial, customer), Alpha test (in-house), Beta test (on-site)
Types of Faults (not exhaustive)
Algorithmic: algorithm or logic does not produce the proper output for the given input
Syntax: improper use of language constructs
Computation (precision): formula’s implementation wrong or result not to correct degree of accuracy
Documentation: documentation does not match what program does
Stress (overload): data structures filled past capacity
Capacity: system performance unacceptable as activity reaches its specified limit
Timing: coordinating of events not correct
Throughput: system does not perform at speed required
Recovery: failure encountered and does not recover (crashed)
Who Are Involved?
Professional/Third party testers: organize and run tests
Analysts: involved in system requirements definition and specification
Designers: involved in the design and understand proposed solution and solution’s constraints
Implementers: involved in the implementation and understand the constraints associated with implementation
Configuration management representative: arranges for changes to be made consistently across all artifacts
The Advice
View testing as part of the development process
Testing is the last line of defense: Errors indicate that there is a problem with the development process
Test Plan
Objectives of Test Plan:Facilitate task of testing (strategy):
• The scope, approach, resources, and schedule
• Test techniques
• Test criteria
• Test documentation requirements
• Avoid repetition
• Improve test coverage
• Improve test efficiency
• Provide structure for final tests
Improve communication about testing
Provide structure for:
• Organizing
• Scheduling
• Managing
Test Plan ReportTable of Contents
DOCUMENT CONTROL
Approval
Document Change Control
Distribution List
Change Summary
1. INTRODUCTION
1.1. Purpose
1.2. Scope
1.3. System Overview
1.4. Test Approach Overview
2. APPLICABLE REFERENCES
3. TESTING APPROACH
4. TEST SCHEDULE
5. TEST XX
3. TESTING APPROACH
Specify types of tests to be performed
List specific tests
Test descriptions are in section 5
May include
• Test Management Requirements: how testing is to be managed
• Personnel Requirements
• Hardware Requirements
• Software Requirements
• Cost
Section 5 and later
Test No.
Current Status (Passed / Failed / Pending)
Test title
Testing approach
Concluding Remarks
Testing Team
Date Completed:
Assignments
Lead: V&V
Due Date: Tuesday, April 19, 2011
Due Time: Midnight MDT