12
CS-411W VII – Resource Planning and Allocation

CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Embed Size (px)

Citation preview

Page 1: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

CS-411W

VII – Resource Planning and Allocation

Page 2: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Definition

• Resource – any person, item, tool, or service that is needed by the project that is either scarce or has limited availability

Page 3: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Types of Resources

• Computer equipment– Shared lab, mainframe, server time

• Locations– Labs, temporary office space

• Services– Contractors, trainers, support team

• Special equipment– Temporary use

Page 4: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Most Common

• People– Schedule their time– Budget their salary

• Time– Project Schedule– Resource Availability (People, Equipment,

facility)

Page 5: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Resource Requirements - Project Cycle

Identify scope

• Establish task list

• Estimate task duration

• Identify requirements

• Begin staffing and procurement processes to acquire the resources needed

• Assign resources to tasks

Page 6: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

At this point

• Identify the resources needed

• Seek approval

• Procurement

• Enter this information into the project plan

Page 7: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Next Step

• Determine dependencies

• Definition

Page 8: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Resource Allocation Process

• Challenge– To properly identify resources required to meet project

objectives (schedule, performance, cost)

• Allocation Process – identifies durations and the relationships of key activities– compares the resources required by each of the activities to

the specified project resource availability.

Page 9: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Resource Allocation Process

• Resource allocation builds from schedule dates which determine when resources of a given type are required: – The scheduled start determines when the resources will be

available– The schedule finish projects when the resources will no

longer be required– Availability of these resources may vary throughout the life

of a project

Page 10: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Resource AllocationAvailability vs Requirements Assessment

• The resource allocation requirements may be influenced by the need for establishing availability from a fixed time or a fixed resource perspective.

Page 11: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Resource AllocationAvailability vs Requirements Assessment

• Fixed Time– a fixed time requirement will not allow the “finish” date (the

date the activity is scheduled to end and the date the resource is no longer expected to be needed) to be exceeded

• Extra resources over and above the stated requirement may be allocated to make sure the end-date is held constant.

• In effect , this is answering the question: Given the resources I have planned - is the time allotted sufficient to complete my project?

Page 12: CS-411W VII – Resource Planning and Allocation. Definition Resource – any person, item, tool, or service that is needed by the project that is either

Resource Allocation Availability vs Requirements Assessment

Fixed Resource – a fixed resource constraint will not allow for exceeding the

amount of resources allocated (independent of progress or expandedmneed for the resource).

• Extra resources to compensate for slow progress or other factors are not available to meet specific time schedules

• In effect, this is answering the question: Are the resources available sufficient to complete my project on time?