Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
FLORIDA POWER CORPORATION
CRYSTAL RIVER UNIT 3
DOCKET NUMBER 50-302 / LICENSE NUMBER DPR-72
ATTACHMENT E
TECHNICAL REPORT ANP-3052:CR-3 EPU FEEDWATER LINE BREAK ANALYSIS WITH
FAILURE OF FIRST SAFETY GRADE TRIP,REVISION 2
J! 11 1
ANP-3052Revision 2
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
June 2012
AAREVAAREVA NP Inc.
Controlled Document
ANP-3052Revision 2
June 2012
CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip
Copyright © 2012
AREVA Inc.All Rights Reserved
Page 2
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
ANP-3052Revision 2
Page 3
Record of Revision
Revision PageslSections/ParagraphsNo. Changed Brief Description I Change Authorization
000 All Initial Release
001 All The FWLB analysis with the first safety grade trip failedwas re-evaluated using the model and limiting conditionsfrom Reference [3]. Revision 001 is a complete revision.
002 Page 10 Added discussion on the rod worth and break location
Page 11 Added Figure 3-1
Table 3-1 Added critical flow models used
i +
4 +
+ +
Page 3
AAREVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 4
Table of Contents
1.0 Introduction ....................................................................................................................................... 82.0 Analytical M ethodology ............................................................................................................ 93.0 Analysis Inputs ................................................................................................................................ 104.0 Results / Conclusions ..................................................................................................................... 145.0 References ..................................................................................................................................... 31
Page 4
AAREVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 5
List of Tables
Table 3-1: Input to Feedwater Line Break Analysis with First Trip Failed ........................................... 12Table 4-1: Sequence of Events for FWLB with First Trip Failed ......................................................... 15Table 4-2: Results for FW LB with First Trip Failed ............................................................................... 15
Page 5
AAR EVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safetv Grade Trio
ANP-3052Revision 2
Page 6
List of Figures
Figure 3-1: Feedwater Line Break Locations ........................................................................................ 11Figure 4-1: FWLB with Fail First Trip - RCS Pressure ........................................................................ 16Figure 4-2: FWLB with Fail First Trip - Reactor Power ........................................................................ 17Figure 4-3: FWLB with Fail First Trip - Reactivity ................................................................................. 18Figure 4-4: FWLB with Fail First Trip - Primary System Temperatures .............................................. 19Figure 4-5: FWLB with Fail First Trip - Indicated Pressurizer Level ..................................................... 20Figure 4-6: FWLB with Fail First Trip - Pressurizer Collapsed Liquid Level ......................................... 21Figure 4-7: FWLB with Fail First Trip - Pressurizer Surge Line Flow ................................................... 22Figure 4-8: FWLB with Fail First Trip - RCS Volumetric Flow Rate ...................................................... 23Figure 4-9: FWLB with Fail First Trip - Pressurizer Safety Valve Flow ................................................ 24Figure 4-10: FWLB with Fail First Trip - SG Secondary Side Liquid Level .......................................... 25Figure 4-11: FWLB with Fail First Trip - SG Secondary Side Inventory .............................................. 26Figure 4-12: FWLB with Fail First Trip - SG % Operating Range ........................................................ 27Figure 4-13: FWLB with Fail First Trip - SG Pressure ........................................................................ 28Figure 4-14: FWL1B with Fail First Trip - EFW Flow ............................................................................. 29Figure 4-15: FWLB with Fail First Trip - Integrated MSSV Flow ......................................................... 30
Page 6
AAR EVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
ANP-3052Revision 2
Page 7
Nomenclature
Acronym Definition
BOC Beginning of Cycle
CR-3 Crystal River Unit 3
DSS Diverse Scram System
EFIC Emergency Feedwater Initiation and Control
EFW Emergency Feedwater
EPU Extended Power Uprate
FWLB Feedwater Line Break
LAR Licensing Amendment Request
LOOP Loss of Offsite Power
MFW Main Feedwater
MSSV Main Steam Safety Valves
NRC Nuclear Regulatory Commission
PORV Pilot Operated Relief Valve
PSV Pressurizer Safety Valve
RCP Reactor Coolant Pump
RCPB Reactor Coolant Pressure Boundary
RCS Reactor Coolant System
RPS Reactor Protection System
SG Steam Generator
Tave Average RCS Temperature
TSV Turbine Stop Valves
Page 7
M
H
AAR EVA ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 8
1.0 INTRODUCTION
The Nuclear Regulatory Commission (NRC) Reactor Systems Branch staff requested an additional analysis beperformed to support the review of the Crystal River Unit 3 (CR-3) extended power uprate (EPU) licensingamendment request (LAR). In particular, the staff requested an analysis of the feedwater line break (FWLB)transient assuming that the first safety grade reactor protection system (RPS) trip function fails to trip the reactor.This report documents the results of the requested analysis.
The analysis documented in this report assumes that the RPS high reactor coolant system (RCS) pressure tripfunction fails to trip the reactor. This analysis models the non-safety grade diverse scram system (DSS) trip,which inserts the regulating control rod banks upon reaching the DSS high RCS pressure trip setpoint. The peakRCS pressure during the FWLB transient is reported and compared to an acceptance criterion of 120% of thereactor coolant pressure boundary (RCPB) design pressure (1.20 * 2500 = 3000 psig).
The evaluations of the FWLB transient with the first safety grade trip failed are based on the model andconclusions in Reference (3]. The model refinements described in Section 4.1 of Reference [3] and the limitinginitial conditions described in Section 4.12 of Reference [3] are included in the model for evaluating the first safetygrade trip being failed.
Page 8
AAREVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 9
2.0 ANALYTICAL METHODOLOGY
The thermal-hydraulic analysis of the FWLB transient at the CR-3 EPU power level with the first safety grade tripfailed is performed using the RELAP5/MOD2-B&W computer program (Reference [1]). The code simulates RCSand secondary system operation. The reactor core model is based on a point kinetics solution with reactivityfeedback for control rod assembly insertion, fuel temperature changes, moderator temperature changes, andchanges in boron concentration. The RCS model provides for heat transfer from the core, transport of the coolantto the steam generators (SG), and heat transfer to the steam generators. The secondary model includes adetailed depiction of the main steam system, including steam relief to the atmosphere through the main steamsafety valves (MSSVs) and simulation of the turbine stop valves (TSVs). The secondary model also includes thedelivery of feedwater, both main and emergency, to the steam generators.
The RELAP5/MOD2-B&W code has been approved by the NRC for use in non-LOCA safety analyses (Reference
[2]). The analysis documented in this report is consistent with Reference [2] with two exceptions:
1) The first safety grade trip is not credited. Instead, this analysis credits the next available trip, which is thenon-safety grade DSS trip on high RCS pressure.
2) Reference [2] was not used to define the initial conditions for the transient. The initial conditions arebased on the FWLB sensitivity studies documented in Reference (3]. The conditions in Reference [3] thatresult in the highest peak RCS pressure during a FWLB transient are:
a. Nominal RCS pressure (2170 psia hot leg pressure)b. Maximum RCS flow (398,850 gpm)c. 100.4 %FPd. Beginning of Cycle (BOC)e. 585 °F Average RCS Temperature (Tave)f. 940 psia turbine header pressureg. 80 %OR SG levelh. 290 inch indicated pressurizer level
Page 9
AAR EVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2
with Failure of First Safety Grade Trip Page 10
3.0 ANALYSIS INPUTS
The FWLB analysis with the first safety grade trip failed is based the FWLB sensitivity analyses in Reference [3].Section 3.0 of Reference [3] describes how the sensitivity analyses compare to the FWLB analyses withoutpressurizer spray performed to support Section 2.8.5.2.4 of the CR-3 EPU LAR.
The key input changed to model the first safety grade trip being failed includes:
1. The RPS high RCS pressure trip function is disabled.
2. The DSS high RCS pressure trip function is modeled. The DSS trip setpoint is modeled as 2465 psia.The DSS high RCS pressure trip setpoint includes margin to bound possible changes in the containmentpressure during a FWLB. The DSS trip delay time is modeled as 1.23 seconds. Finally, the rod worthavailable to the DSS system is modeled as only 2.0 %AkIk, since the DSS system only inserts theregulating control rod groups. The rod worth is based on the regulating control rod groups having a worthof 2.2 %Ak/k at the rod insertion limits. The worth is then reduced by 10% (0.2 %Ak/k) for uncertainty. Anexplicit allowance for the worth of a stuck regulating control rod is not considered.
3. Section 4.10 of Reference [3] contains a sensitivity study on the break location. The failed first tripanalysis was performed at the three limiting break locations from that study, to ensure that the limitingbreak location is captured. The break locations considered are shown in Figure 3-1. The peak RCSpressures for the three break locations ranged from 2911.61 psia to 2915.39 psia. The limiting breaklocation is a 1.418 ft2 break in one of the side branches of steam generator B at the junction connectingthe main feedwater line to the side branches.
Table 3-1 summarizes all of the key input to the FWLB analysis with the first safety grade trip failed, including thechanges highlighted above.
The peak RCS pressure is reached shortly after reactor trip before any active safety systems such as emergencyfeedwater (EFW) are credited to mitigate the results. Therefore, there are no single failure assumptions thatwould result in a more limiting peak RCS pressure. However, the FWLB overpressure protection analysis with thefirst safety grade trip failed assumes the same single failure assumption as the FWLB analysis performed tosupport Section 2.8.5.2.4 of the CR-3 EPU LAR. The single failure assumption modeled is the failure of one trainof Emergency Feedwater Initiation and Control (EFIC) such that EFW flow is not initiated automatically in onetrain. Consequently, only one of the two EFW pumps is assumed available to provide flow to the SGs. Thissingle failure assumption produces a conservative long-term transient response.
Page 10
AAR EVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trio
ANP-3052Revision 2
Page 11
Figure 3-1: Feedwater Line Break Locations
Isolation Check Valve.
18"
14" 14"
SG
Page 11
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
ANP-3052Revision 2
Page 12
Table 3-1: Input to Feedwater Line Break Analysis with First Trip Failed
Parameter Value
RCS Conditions
Core Power, MWt 3014 * 1.004 = 3026.1
Decay Heat 1.0*ANS71 plus B&W Actinides
Total Net Reactor Coolant Pump (RCP) Heat, MWt 16.4
Average RCS Temperature, OF 585
Initial Hot Leg Pressure, psia 2170
Total RCS Flow Rate, gpm 398,850
Pressurizer
Initial Indicated Pressurizer Level, in 290
Pressurizer Spray Not Modeled
Pressurizer Heaters Not Modeled
Pilot Operated Relief Valve (PORV) Not Modeled
Pressurizer Safety Valve (PSV) Setpoints, psig 2500 * (1 + 0.03) (open)2500 * (1 - 0.04) (close)
Total PSV Rated Capacity, Ibm/hr 2 * 317,973 @ 2750 psig
Secondary Side
Initial Main Feedwater (MFW) Temperature, OF 460 OF
Tube Plugging, % 5
Initial SG Level, %OR 80
EFW Temperature, OF 120
EFW Minimum Required Flow, gpm 660
EFW Delay Time, sec 40
Turbine Trip Delay Time, s 0.0
TSV Stroke Time, s 0.2
Number of Main Steam Safety Valves (MSSVs) per SG 8
MSSV Capacity per SG 7 @ 845,759 Ibm/hr1 @ 583,574 Ibm/hr
MSSV Nominal Setpoints 2 @ 1050 psig2 @ 1070 psig2 @ 1090 psig
2 @ 1100 psig including small MSSV
MSSV Setpoint Tolerance +3%
MSSV Accumulation +3%
Page 12
, " 11 d, 'L.)
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
ANP-3052Revision 2
Page 13
Parameter Value
MSSV Blowdown -5%
Core Kinetics Parameters
Doppler Temperature Coefficient (Ak/°kIF) -1.30 E-5
Moderator Temperature Coefficient (Ak/k/IF) 0.0 E-4
Prompt Neutron Generation Time, (ps) 24.8
Effective Delayed Neutron Fraction 0.0070
DSS Insertable Rod Worth, %Ak/k 2.000
RPS High RCS Pressure Trip Assumed Failed
DSS High RCS Pressure Trip Setpoint, psia 2465
DSS Trip Delay Time, s 1.23
Critical Flow Models
Subcooled Liquid Homogeneous Equilibrium Model
Two-Phase and Superheated Fluid Moody
Miscellaneous
Offsite Power Available
Single Failures One Train of EFIC
Operator Actions None
Page 13
AAREVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 14
4.0 RESULTS I CONCLUSIONS
The sequence of events for the FWLB accident with the first safety grade trip failed is listed in Table 4-1 and thecalculated results are tabulated in Table 4-2. Plots that demonstrate the transient response following a FWLB areprovided in Figures 4-1 through 4-15.
Following initiation of the FWLB, the blowdown of the affected SG results in a reduction in the secondary heatremoval. The mismatch between energy addition to the reactor coolant and the secondary heat removal causesthe reactor coolant to heat up and pressurize. The pressure increases to the RPS high RCS pressure tripsetpoint, but the trip is assumed to fail. The pressure continues to increase to the DSS high RCS pressure tripsetpoint. After the appropriate delay time, the DSS trip inserts the regulating control rod banks.
After reactor trip, the RCS pressure continues to increase until the PSVs lift. Shortly after the PSVs lift, thepressure begins to decrease. The peak RCS pressure occurs in the bottom of the reactor vessel and does notexceed 120% of the design pressure of 2500 psig (3000 psig).
EFIC actuates on low SG level in the affected SG. After considering the possible 40 second delay, EFW isprovided to the unaffected SG at the flow rate of one EFW pump (660 gpm). During this time, the PSVs maintainthe RCS pressure based on the PSV open and close setpoints. The FWLB event is sufficiently severe that thepressurizer fills. As a result, the PSVs begin to pass single-phase liquid. The PSVs of the type installed at CR-3achieve satisfactory performance for fluid temperatures greater than -550 0F. An additional check is performed toshow that the PSV fluid inlet temperature remains greater than 600 OF to ensure that the PSVs operate asintended. Figure 4-4 demonstrates that at all times throughout the FWLB transient, the liquid temperature at thetop of the pressurizer remains above 600 OF. The PSVs close for the final time at -170 seconds. At -8 minutes,the secondary heat removal from EFW causes the pressurizer level to drop.
A sensitivity study was performed modeling the FWLB transient with the first safety grade trip failed and a loss ofoffsite power (LOOP). The LOOP is conservatively considered to occur coincident with the turbine trip thatfollows reactor trip. The case with a LOOP included the insertion of the safety control rod banks on LOOP. Thesensitivity study determined that the peak RCS pressure from a LOOP case is less limiting than the peak RCSpressure without a LOOP. Therefore, the FWLB evaluation using the DSS trip function and no LOOP is thebounding case.
Page 14
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safetv Grade Trio
ANP-3052Revision 2
Page 15
Table 4-1: Sequence of Events for FWLB with First Trip Failed
Parameter Time, sec
Transient Initiated 0.0MFW to unaffected SG Interrupted 0.01Peak Thermal Power Occurs 7.59
DSS High RCS Pressure Trip Setpoint Reached 10.26EFIC Actuated on Low SG-B Level 10.42Regulating Control Rod Groups Begin to Insert 11.49Turbine Trip, TSVs Begin to Close 11.49Initial PSV Lift -12.5
Peak RCS Pressure occurs 15.02Pressurizer becomes liquid solid -50
Affected SG depressurization complete -50EFW to Unaffected SG Begins 50.43Final PSV closure -170Peak Tave occurs -240Transient Analysis Ends 600
Table 4-2: Results for FWLB with First Trip Failed
Parameter ValuePeak RCS pressure (psia) 2915.39Peak thermal power (%RTP) 100.51Peak Tave ('F) 622.22
Page 15
)'
AAR EVA ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 16
Figure 4-1: FWLB with Fail First Trip - RCS Pressure3000
n Hot Leg I (CV 110-4)- Hot Leg 2 (CV 210-4)A Core Exit (CV 352-01)
2900 ...........- Top of PZR (CV 405-01)-- Lower RV.Downcomer (CV 324-04)
2800- -- ---- -- ---
2700O-- - .... ....2600 .............................. ..... .................. ............... .. -....... ...... ......
2600
2 2 0 .. .. ...... ... ... ....... .....
2500
200630 60 120 180 240 300 360 420 480 540 600
Time (s)
Page 16
(-It "',(JIý
AAREVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 17
Figure 4-2: FWLB with Fail First Trip - Reactor Power3200
-- a Total Reactor Power (CVAR 370)-- Thermal Power (CVAR 379)
2800
2400
2000 . ... .. .. ..
o 1600
1200
800
400
60 120 180 240 300 360 420 480 540 600Time (s)
Page 17
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trio
ANP-3052Revision 2
Page 18
Figure 4-3: FWLB with Fail First Trip - Reactivity
-• CVAR 1970.010
0.000 @W•
-0.010
$$0
a- -~---45A------{A - -a-- ,J -Fl fl;
-0.020
-0.030
-0.040
-0.0500 60 120 180 240 300
Time (s)360 420 480 540 600
Page 18
AAREVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 19
Figure 4-4: FWLB with Fail First Trip - Primary System Temperatures720-
RCS Ave Temp (CVAR 900)-- 0 Loop I Hot Leg (CV 110-4)
A Loop 2 Hot Leg (CV 210-4)
700 .- < Loop 1A Cold Leg (CV 160-4)--V Loop 1 B Cold Leg (CV 180-4)
E> Loop 2A Cold Leg (CV 280-4)Loop 213 Cold Leg (CV 280-4)
680 -- Top of Pressurizer Liquid Temperature (CV 405o --44-
660. ...........
640 . . ...
(-
CI)620
S 600 : ::
540 ............. i ............................. - ... ...... ..................................... ........ .......
5200 60 120 180 240 300 360 420 480 540 600
Time (s)
Page 19
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade TriD
ANP-3052Revision 2
Page 20
4)
4)
._N
400
380
360
340
320
300
280
260
240
220
Figure 4-5: FWLB with Fail First Trip - Indicated Pressurizer Level
-4 CVAR 409
... .. .... ... .. ... .. ---- ---- --- -- ----
.. . .. . ... . ... .. . . .. . ... .. . . ---------. .
iAnn60 120 180 240 300
Time (s)360 420 480 540 600
Page 20
I
AAREVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 21
Figure 4-6: FWLB with Fail First Trip - Pressurizer Collapsed Liquid Level44
-- CVAR 325
42 --R: - - -•-- ,
40
38
0 36
S34
S32
30
28
26
240 60 120 180 240 300 360 420 480 540 600
Time (s)
Page 21
AAREVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2
with Failure of First Safety Grade Trip Page 22
Figure 4-7: FWLB with Fail First Trip - Pressurizer Surge Line Flow500
-- mflow4-41 001 0000
250
0 El E 9R-----2 5 0- ----- ----. . ... . .. ... . .. --- -- --- -- -- --- -- -- --- -- --.-- -- -- --- -- -- --- -- -- --- -- --
r-250
-500
• ) -750... . ... ... ..
Page 22
Ai, k nIr
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade TriOD
ANP-3052Revision 2
Page 23
Figure 4-8: FWLB with Fail First Trip - RCS Volumetric Flow Rate
Ei
U
500000
450000
400000
350000
300000
250000
200000
150000
100000
50000
-• CVAR 332
.- . . . . ... . U -.. ...... - .... . . ... . . g .. [.. . . . ... ....
060 120 180 240 300
Time (s)360 420 480 540 600
Page 23
AAREVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 24
Figure 4-9: FWLB with Fail First Trip - Pressurizer Safety Valve Flow500
--- mflowj-492000000
450
4003 5 0 . . . . . . . . . . . . .7 . . . . . . . . . . . . . .. ... . . . . . . . . . . .. .... . . . . . . . . . . . .. ..... - - -- . . . ..
~n 300
o 250 --- - ...
S 200 -- -- - --- -- -- -
4 0 0 . . . . . . . . . . . . . . . ..- .- . . . . . ... . . . . ....-- --
1 0 0 -.-.-.-. .-.- --.-. .-.-.- -.... ....... . . . .. ... . ........... ... . i.. .... .. ... ........... .. ....... ... ... . .. ...
100
50
0 60 120 180 240 300 360 420 480 540 600
Time (s)
Page 24
AAREVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 25
Figure 4-10: FWLB with Fail First Trip - SG Secondary Side Liquid Level12
SG-A (CVAR 814)~SG-B (CVAR 714)
10
-~6
0
4C# 4
60 120 180 240 300Time (s)
360 420 480 540 600
Page 25
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
ANP-3052Revision 2
Page 26
24
0
80000
70000
60000
50000
40000
30000
20000
10000
Figure 4-11: FWLB with Fail First Trip - SG Secondary Side Inventory
-• SG-A (CVAR 607)SG-B (CVAR 707)
E3 R R U
U -0 60 120 180 240 300
Time (s)360 420 480 540 600
Page 26
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade Trip
ANP-3052Revision 2
Page 27
100
90
80o
0
0
70
60
50
40
30
20
10
0
Figure 4-12: FWLB with Fail First Trip - SG % Operating Range
-u SG-A (CVAR 612)-1SG-B V . AR72)
.. .... .. ... .. ...... ....
.. ....... ... .. ....... ...... ......... ..........
T60 120 180 240 300
Time (s)360 420 480 540 600
Page 27
AAREVA
ANP-3052
CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 28
Figure 4-13: FWLB with Fail First Trip - SG Pressure1200U
Unaffected (CV 648-1) 1L Affected (CV 748-1)1 10 • 'A .( • _ _8 ! . ............. -- ---J
801000 ..... ....................................................................................................-----
1900 ----
1 000 -- -- -- .. . . . ... .. . . .. ..
700 ...... .... ....... ........... ........... ......... ....... ... .. ... ........ .. ........
W 300 -- ---............. ......... ....... ................. . ..... . ... . ........................ .... ...
S500
400
300 .... ..
200 - -- ... .....
100 - --.. .
60 120 180 240 300 360 420 480 540 600Time (s)
Page 28
,ýk ri t
AAREVA
CR-3 EPU Feedwater Line Break Analysiswith Failure of First Safety Grade TriD
ANP-3052Revision 2
Page 29
Figure 4-14: FWLB with Fail First Trip - EFW FlowIOU
To Unaffected SG (JUN 626)--o To Affected SG (JUN 726)
.2
90
80
70
60
50
40
30
20
10
.......... - ...
a- - - ; ul- e
o 60 120 180 240 300
Time (s)360 420 480 540 600
Page 29
AAR EVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 30
Figure 4-15: FWLB with Fail First Trip - Integrated MSSV Flow100000
o Unaffected SG (CVAR 669)-- Affected SG (CVAR 660)
90000
80000
70000
E!
60000
CIO 50000IT
40000
30000
20000
10000
0-0 60 120 180 240 300 360 420 480 540 600
Time (s)
Page 30
AAREVA
ANP-3052CR-3 EPU Feedwater Line Break Analysis Revision 2with Failure of First Safety Grade Trip Page 31
5.0 REFERENCES
1. BAW-1 01 64PA-06, "RELAP5/MOD2-B&W - An Advanced Computer Program for Light Water ReactorLOCA and Non-LOCA Transient Analysis."
2. BAW-1 01 93PA-00, "RELAP5/MOD2-B&W for Safety Analysis of B&W-Designed Pressurizer WaterReactors."
3. ANP-3114NP-000, "CR-3 EPU - Feedwater Line Break Analysis Sensitivity Studies."
Page 31