Texas Nodal Congestion Revenue Rights (CRR) EDS 3 Release 7 - Overview EDS 3 Phase 2 MP Planning Workshop July 11, 2007. CRR EDS3-R7 Overview. CRR will begin conducting Market Trials in early February of 2008 as part of EDS 3 Release 7 (EDS3-R7) CRR EDS3-R7 will consist of 4 phases - PowerPoint PPT Presentation
Citation preview
http://nodal.ercot.com 1Lead from the front
Texas Nodal
Texas Nodal
Congestion Revenue Rights (CRR)EDS 3 Release 7 - Overview
EDS 3 Phase 2 MP Planning Workshop
July 11, 2007
http://nodal.ercot.com 2Lead from the front
Texas Nodal
CRR EDS3-R7 Overview
• CRR will begin conducting Market Trials in early February of 2008 as part of EDS 3 Release 7 (EDS3-R7)
• CRR EDS3-R7 will consist of 4 phases
• CRR EDS3-R7 will take approximately 4-5 months, ending in May 2008
• Market Participants wishing to participate in CRR EDS3-R7 will have to complete some activities in advance (e.g. Registration)
• The CRR EDS3-R7 plans are currently based on Market Participants interacting with the CRR User Interface, NOT an API/Machine to Machine interface– This is per the ERCOT Board of Directors statement that CRR API is
currently out of scope
http://nodal.ercot.com 3Lead from the front
Texas Nodal
Pre-Activity
Registration and digital certification; NOIE PCRR contract submission
• Market Participants will have to register with ERCOT CRR Account Holders and have an appropriate digital certificate (by mid January 2008)
• NOIEs must send contracts and desired entitlements (by early December 2007)
• NOIEs wishing to identify themselves as Competitive Load Zones shall indicate their intention to do so (by early December 2007)
• Wind Generators within the boundaries of the McCamey Area must identify themselves for McFRI eligibility (by early December 2007)
• ERCOT to verify receipt to ERCOT of contracts and entitlements information; input into system (prior to Phase 1)
http://nodal.ercot.com 4Lead from the front
Texas Nodal
Phase 1 – beginning early February 2008
UI connectivity, data upload; limited Market Participants (~2 weeks)
• Limited number of Market Participants based on MPs prepared by early deadlines
• CRR environment for Market Participant EDS Activities made available
• Verify CRR Account Holders’ ability to connect to the CRR System using a digital certificate
• Verify CRR Account Holders’ ability to utilize Online User Interface to retrieve market information, submit nominations, bids and offers
http://nodal.ercot.com 5Lead from the front
Texas Nodal
Phase 2
Mock Auction (ERCOT provided bids/offers), mock bilateral trades; expanded Market Participants (~3 weeks)
• Expanded number of Market Participants; verify expanded CRR Account Holders’ ability submit nominations, bids and offers via UI
• Conduct mock monthly allocation with Account Holders self-created nominations
• Conduct mock monthly auction with ERCOT provided bids and offers and defined Credit
• Verify CRR Account Holders’ ability to download market results via UI
• Verify bilateral trade functionality orchestrated by ERCOT
http://nodal.ercot.com 6Lead from the front
Texas Nodal
Phase 3
Mock Monthly Auction (MP created bids/offers) (~3 weeks)
• Conduct a mock CRR Monthly Auction with CRR AH created bids and offers
• Verify bilateral trade functionality as created by AHs
• Credit constraint will self defined within ERCOT identified boundaries
http://nodal.ercot.com 7Lead from the front
Texas Nodal
Phase 4
Mock Multi-Month Auction (MP created bids/offers) (~4 weeks)
• Conduct a mock CRR Multi-Month Allocation with CRR AHs created nominations
• Conduct a mock CRR Multi-Month Auction with CRR AHs created bids and offers
http://nodal.ercot.com 8Lead from the front
Texas Nodal
Outstanding Items
The following items must be included in one of the above phases of the EDS 3 Release 7 or must result in a new phase:
• Additional ‘practice’ Auctions – if Market Participants wish, additional rounds of practice bidding may be possible (current phases run though April, EDS3-R7 is scheduled to end June 2007)
• Credit – based on design decisions and detailed development timeline, the implementation and testing timeline for Credit data input module TBD
• Training – an 8 hour training course is currently planned for Fall 2007 delivery. However, there may be additional hands on UI training that is TBD
Note: Settlements and Billing will produce invoices as part of EDS4, auction and allocation results will be available for each CRR phase
http://nodal.ercot.com 9Lead from the front
Texas Nodal
Jan Feb Mar Apr MayDec
CRR EDS3-R7 – One-Pager
Objectives • Validate MP CRR Digital
Certificate rights• Validate AH system
connection – uploads and downloads
System Needs (incremental)CRR/MIS• CRR External UIData / Stubs • Registration• Network ModelTesting Tools• Defect tracking &
communication process / toolInfrastructure• EDS 3 Hardware
Objectives (Incremental)• Conduct mock CRR monthly
auction – ERCOT directed bids• Conduct mock CRR monthly
allocation – AH created nominations
• Verify market result download• Verify bilateral trade functionality
System Needs (incremental) CRR• No ChangeData / Stubs• No ChangeTesting Tools• No ChangeInfrastructure• No Change
Objectives (Incremental)• Conduct mock CRR monthly
auction – AH determined bids
• Conduct secondary trading – AH directed
• Verify Credit constraint in optimization
System Needs (incremental)CRR• Bug fixes onlyData / Stubs• CMMTesting Tools• No ChangeInfrastructure• No Change
SME Support levels:
8 * 5 support for CRR
SMEs available to MPs per schedule
SME Support levels:
8 * 5 support for CRR
SMEs available to MPs per schedule
SME Support levels:
8 * 5 support for CRR
SMEs available to MPs per schedule
Objectives (Incremental)• Conduct mock CRR annual
auction – AH determined bids
• Conduct mock CRR annual allocation – AH created nominations
System Needs (incremental)CRR• Bug fixes onlyData / Stubs• No ChangeTesting Tools• No ChangeInfrastructure• No Change
SME Support levels:
8 * 5 support for CRR
SMEs available to MPs per schedule
Objectives • Registration of MPs as CRR
Account Holders• Assign MP CRR Digital
Certificate rights• NOIE contract receipt and
entitlement creation in the system
• NOIE load zone identification
System Needs CRR• CRR System (Market
Operator)NMMS• Network Model w/ NOIE load
zones• Network Model output for CRRRegistration• CRR AH RegistrationData/Stubs• NoneInfrastructure• CRR FAT
SME Support levels:
Estimated at 1man day per week
Pre EDS3-R7 Activities Phase 1 Phase 2 Phase 3 Phase 4
TBD• Interface timing
from NMMS, Registration, CMM
• Interface timing to S&B, MMS, CMM
• EDW Data Extract functionality
• Credit data input module