    Creating Production Lines

    Trigger:

    Concept

    A production line describes a unique set of operations departments, or manufacturing areas that

    produce one or more of your products. You can associate production lines with flow assemblies

    and discrete jobs.

    In this topic, you define manufacturing production lines in the Production Lines page.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/14/2010 02:03:00 PM Page 1

  • 8/14/2019 Creating Production Lines_SPD

    2/16

    System Process DocumentCreating Production Lines

    Procedure

    Step Action

    1. Begin by navigating to the Production Lines page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    3/16

    System Process DocumentCreating Production Lines

    Step Action

    2. Click the Production Lines object.

    Last changed on: 1/14/2010 02:03:00 PM Page 3

  • 8/14/2019 Creating Production Lines_SPD

    4/16

    System Process DocumentCreating Production Lines

    Step Action

    3. The Production Lines page is used to define a line that is a rate-based resource.

    Production lines encompass a set of operations, departments, or manufacturing

    areas. You can use ATP rules to determine capable to promise status of the line.

    Step Action

    4. Click in the Name field.

    Page 4 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    5/16

    System Process DocumentCreating Production Lines

    Step Action

    5. Enter the desired information into the Name field. Enter "Laptop1".

    Last changed on: 1/14/2010 02:03:00 PM Page 5

  • 8/14/2019 Creating Production Lines_SPD

    6/16

    System Process DocumentCreating Production Lines

    Step Action

    6. Click in the Description field.

    Step Action

    7. Enter the desired information into the Description field. Enter "Laptop line".

    Page 6 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    7/16

    System Process DocumentCreating Production Lines

    Step Action

    8. Exception sets can help you identify capacity problems.

    Click in the Exception Set field.

    Last changed on: 1/14/2010 02:03:00 PM Page 7

  • 8/14/2019 Creating Production Lines_SPD

    8/16

    System Process DocumentCreating Production Lines

    Step Action

    9. Enter the desired information into the Exception Set field. Enter "Standard".

    Step Action

    10. The Minimum Hourly Rate represents the minimum number of assemblies the

    line can produce per hour.

    Click in the Minimum Hourly Rate field.

    Page 8 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    9/16

    System Process DocumentCreating Production Lines

    Step Action

    11. Enter the desired information into the Minimum Hourly Rate field. Enter "30".

    Last changed on: 1/14/2010 02:03:00 PM Page 9

  • 8/14/2019 Creating Production Lines_SPD

    10/16

    System Process DocumentCreating Production Lines

    Step Action

    12. The Maximum Hourly Rate must be greater than or equal to the minimum rate.

    Click in the Maximum Hourly Rate field.

    Step Action

    13. Enter the desired information into the Maximum Hourly Rate field. Enter "40".

    Page 10 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    11/16

    System Process DocumentCreating Production Lines

    Step Action

    14. Click in the Start Time field.

    Last changed on: 1/14/2010 02:03:00 PM Page 11

  • 8/14/2019 Creating Production Lines_SPD

    12/16

    System Process DocumentCreating Production Lines

    Step Action

    15. Enter the desired information into the Start Time field. Enter "08:00:00".

    Step Action

    16. Click in the Stop Time field.

    Page 12 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    13/16

    System Process DocumentCreating Production Lines

    Step Action

    17. Enter the desired information into the Stop Time field. Enter "17:00:00".

    Last changed on: 1/14/2010 02:03:00 PM Page 13

  • 8/14/2019 Creating Production Lines_SPD

    14/16

    System Process DocumentCreating Production Lines

    Step Action

    18. Click the Lead Time Basis option.

    Step Action

    19. Click the Routing-Based list item.

    Page 14 Last changed on: 1/14/2010 02:03:00 PM

  • 8/14/2019 Creating Production Lines_SPD

    15/16

    System Process DocumentCreating Production Lines

    Step Action

    20. Click the Save button.

    Last changed on: 1/14/2010 02:03:00 PM Page 15

  • 8/14/2019 Creating Production Lines_SPD

    16/16

    System Process DocumentCreating Production Lines

    Step Action

    21. You have completed the Creating Production Lines procedure.

    End of Procedure.

    Page 16 Last changed on: 1/14/2010 02:03:00 PM