Creating competitive advantages through innovative supply chain solutions

3rd Supply Chain Leaders Forum 2014, CBS

September 2014

Thomas Stig Lundstrøm

GN ReSound Global Supply Chain

Danish logistics

Award 2013

2

Thomas Stig Lundstrøm

GN ReSound – VP, Global Supply Chain

Valcon – Management consultant

GN ReSound – VP, European Operation and Purchasing – VP, Global Operations (acting SVP) – Production Manager – Supply Chain Project Manager

Accenture – Management consultant

Technical University of Denmark (DTU), Copenhagen, Denmark – Master of Science in Management of

Planning and Technology – Master thesis “Supply chain modeling

at the strategic level” in cooperation with Mærsk

Nanyang Business School, Singapore

Education

Experience Thomas Stig Lundstrøm VP, Global Supply Chain

[email protected]

mobile (+45) 20820120

3

Agenda

1. Company introduction

2. The supply chain as a competitive advantage

3. Lessons learned and next steps

In-the-ear hearing instruments Behind-the-ear hearing instruments

GN ReSound is the world’s fourth biggest hearing instrument manufacturer

4

GN ReSound

Company

Vision and mission

Products and market

Part of GN Store Nord

~3.800 employees worldwide

Turnover at 4.200 MDKK in 2013

Market share around 16%

Help people rediscover hearing

Increase user satisfaction and acceptance

Strive for innovation

BTEs and ITEs

Wireless accessories

Sales in more than 80 countries

In collaboration with Apple Inc., we have launched the first Made for Iphone Hearing aid with direct stereo sound streaming

Collaboration with Apple

Adjust the sound of the

television as well as the

surroundings

Use the iPhone’s GPS to find

your missing hearing aid

Collaboration with Apple Inc. – developing the world’s first Made for iPhone hearing aids

Based on GN ReSound’s unique 2.4 GHz technology

ReSound LiNXTM

The world’s first Made for iPhone hearing aid with direct stereo sound streaming

New premium audiological features

After tough times, GN ReSound is closing the EBITA margin gap vs competition and the stock exchange has acknowledged the achievements…

6

The failed merger with Sonova led GN ReSound to a poor economic situation

The need for a new operating model was

mandatory to ensure sustainable results thanks to – An increased customer focus – A control of the costs in all the value

chain

After 3 years of in-depth change, GN ReSound has achieved tremendous results : – The EBITA margin has been multiplied

by 4 in 5 years – The price of a GN ReSound share has

increased by more than 2000% in 5 years

– 12 consecutive quarters with positive organic growth and above market growth

Comments

Share price development

EBITA (%) margin development

0

5

10

15

20

25

30

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

GNR

WDH

Sonova

… and so has the media

7

8

Agenda

1. Company introduction

2. The supply chain as a competitive advantage

3. Lessons learned and next steps

GN ReSound’s supply chain has largely contributed to the impressive results of the company

9

How?

All improvements have generated an EBITA run rate effect of 200 MDKK and a positive impact on cash flows

Increased customer satisfaction and consistent performance

Sales focuses on sales

Platform for future optimization

Supply chain as a competitive advantage

Results

5-d

ay t

urn

aro

un

d o

n c

ust

om

h

eari

ng

aid

s m

anu

fcat

uri

ng

in

Ch

ina

1

Sam

e d

ay s

hip

pin

g fr

om

co

nso

lidat

ed in

ven

tory

lo

cati

on

s

2

Sam

e d

ay r

epai

r u

sin

g SW

AP

co

nce

pt

3

Ad

dit

ion

al in

itia

tive

s

4

Global

processes Continuous

improvement Performance management

Solution 1: the supply chain offers a 5 day turnaround on custom hearing aids manufacturing in China, leveraging its low cost production platform

10

Centralizing custom manufacturing in China to

– Offer fast turnaround for custom fitted products

– Leverage 24 hour production in China

– Leverage low cost production and economies of scale

Concept: 5 day turnaround on custom product Benefit

Receive Order

Clean and scan mold

1 day

Cleaning of the mold

Ship to region 1-2 days

Build mold

Electrical assembly

Mechanical assembly

Test and QC

E-sculpt

2 days

(95% in 1 day)

E-sculpting of the mold

Completion of the ITE

Pick, pack and ship 1 day

Total TAT: 5 days Packing and Shipping

Solution 2: Same day shipping across Europe and US from consolidated inventory locations improves delivery performance and reduces logistics cost

11

Moving local handling and shipping activities to regional distribution centers to

– consistent high delivery performance across all markets

– lower total inventory levels through consolidated safety stocks

– reduce number of local inventory locations

– reduced 'double-handling' of goods

Concept: Consolidated inventory locations Benefit

New regional Distribution center

Previous global distribution center

Previous local distribution centers

Solution 3: The supply chain offers same day repair across Europe and US using an innovative SWAP concept

12

Innovative repair solution that offers minimum inconvenience for the customer by fast turn though

– Prioritization of local fast repair for easy fixes or regional SWAP for more complex repairs

– Maintain customer settings

– increased utilization of returned devices

Pick swap device

Download setting

Receive Order

Fast Diagnose

Upload setting 1 day

Ship to customer

Concept: same day repair setup Benefit

Several supporting initiatives have also been executed to support the supply chain optimization

13

Initiatives

Warehouse optimization

Design for value

Reducing complexity

Implementing a Lean setup in regional warehouses

Deploying scanner solutions to improve efficiency and reduce pick errors

Creating products with the right features at the right cost

Making cost break downs in cross functional workshops

Reducing SKUs on packaging and hearing instruments

Reducing freight agreement from 100 different local carriers to 5 in one global agreement

S&OP

Monthly aligning of sales, finance and supply chain on future demand, supply and risks

All initiatives is tracked rigorously in a dedicated Program Management Office (PMO) to ensure progress and avoid surprises

14

Detailed scoping of all projects Weekly tracking in PMO

STRICTLY PRIVATE & CONFIDENTIAL

AP1 – Oxford location

Background information

Key milestones (Critical path)

incl. communication Deadline

Description

• The overall objective is to set up a Regional Operations

Center (ROC) in Oxford to handle all direct distribution,

ITE, SWAP and return logistics for Europe by

– Finding an appropriate location

– Setting up the local organization

– Ramping up the ROC

– Implementing new HUB template

– Providing systems training

– Make system and processes able to direct ship

(DC & ITE) and SWAP

• Feb 2010 – Jul 2010

• Execution groups

• Agree terms on chosen property

• New org and shared services

• Job description new org.

• Announcement direct ship & comm. Pl.

• Recruitment start

• Summary building surveyor

• Legal meeting

• Completion sought

• Layout (detailed architect drawings)

• Construction start

• Purchasing list (Place orders)

• New employees first work day in oxf

• Go-live system

• Construction finished

• Setup workstations, warehouse

• System training

• Warehouse transfer UK

• DC ramp-up

• Warehouse transfer (NL)

• ITE production transfer to new location

(UK)

• Feb 19

• Feb 22

• Feb 26

• Feb 26

• Mar 1

• Mar 1

• Mar 2

• Mar 17

• Mar 24

• Apr 1

• Apr 2

• Apr 14

• May 1

• Jun 1

• Jun 11

• Jun 16

• Jun 16

• Jun 25

• Jul 1

• Aug 27

• Aug 27

Impact

assessment• Not finalized yet

Team

members

• Søren Christensen 50% PM

• Michael Wahl ? PM logistics

• Salvatore Oppido 40% ITE manager/ROC manager

• Thomas Møgelberg 50% PM HUB template

• Peter Baier 50% DC manager

Inter-

dependencies• HUB template is enabling for this project

Initial priority

• High priority:

– enabling for direct ship to Europe

– enabling for customs consolidation

Key risks

• Insufficient allocation of Peter Baier, Göran Hall and Sal

within the short layout phase.

• Insufficient local resources (incl. Navision resources)

• Insufficient allocation of VPs (Thomas & Sal) the project

Need to execute on staffing and communication

HighLow

Preliminary

STRICTLY PRIVATE & CONFIDENTIAL

Project plan (high level) COPx

2010

Finance & legal

setup

Finance & legal

setup

Communication

& staffing

Communication

& staffing

Activities

Today

Communication plan & Q&A

New org. chart, names, job spec

Announcement direct ship

Recruitment & interview

Training

Negotiation & signing

Layout (production floor)

Purchasing & planning

Move in & Construction

Setup warehouse & workstations

Define setup and process

KPMG approval

Changed cost price process

System training

System go-live

Navision support

Plan for transition of inventory

Freight setup

DC ramp-up

Define R&R HQ vs ROC

Define reverse flow

Business continuity plan (BCP)

Documenting process

Warehouse transfer UK

Warehouse transfer NL

Warehouse transfer GE

ITE production transfer to

new location

Building

readiness

Building

readiness

MarchFebr April June July OctSeptAugMay

√ Completed

(√) in progress

Go live direct ship

Assumptions

Resp.

System

implementation

System

implementation

DC readinessDC readiness

DocumentationDocumentation

Direct ship

warehouse

Direct ship

warehouse

Custom moveCustom move

(√)(√)

(√)

(√)

Go live direct ship

SC

TSL,SO

TSLPM

n/a

JS

SO,PB

SC

external

PB,RC

SJ/JH

SJ

SJ/JH

TM

TM

TM

JPJ

PB

JPJ

SC

LL

RM

SC

MW

MW

MW

SO

STRICTLY PRIVATE & CONFIDENTIAL

AP1 - Overview of proposed solution

ROC

Direct Ship

Custom manufac.

HUB template

Location People

• New consolidated site for

– Custom manufacturing

– Direct distribution

– Service and repairs

• New warehouse mgr.

• New warehouse team

• ROC mgr.

• CS/LP function

Scoping and critical milestones

Work plan

Conceptualization of end-state

STRICTLY PRIVATE & CONFIDENTIAL

E2E progress report for "A. Do-or-die" projects

• First phase (system preparation) to be completed March 1st

• Second phase (ramp up) to be initiated shortly

• Uncertain whether end-solution will work

Xiamen DCAH3.

• Negotiation on building initiated

• Aggressive critical path and key risks defined, but no time bufferOxford locationAH1.

USAH2.

AH4.

AP5.

AP4.

AP3.

AP2.

AP1.

Number Project Status

HUB template• Test in progress on Master Data, Forecast & Planning

• Development of system in full progress

• No time buffer left – further acceleration initiated

Advanced order

interface

• Automation to be completed (phase 1) this week

• Critical milestone for entire HUB template

• Uncertain whether critical resource will complete before leaving GNR

Scanner solution• System tested (inbound) but not implemented

• Wireless environment and scanner to be purchased for use in BLM

• Go-live on inbound March 15th, outbound April 15th

Master data• Planning and scoping of project completed

• Project execution to be initiated

Configurator

(ITE+BTE)

• ITE: alignment with US to be addressed during March

• BTE: to be defined – basics already in place

GROC

• First phase (system preparation) to be completed March 1st

• Second phase (ramp up) to be initiated shortly

• Uncertain whether end-solution will work

A

Ongoing according to plan According to plan but critical Behind plan

Not yet started Completed

STRICTLY PRIVATE & CONFIDENTIAL

E2E progress report for "B. Country consolidation" projects: EUB

Warehouse transfer

Repairs and BTE

ITEs

BP3. Direct

Ship

Ear moulds

Repair (ITE + BTE)

New & remake

Milestone

BP2. SWAP

BP1. Custom

consolidation

Project

Not started Announced Implementation

Go-live Stabilized and handed over

STRICTLY PRIVATE & CONFIDENTIAL

E2E progress report for "C. Optimization" projects

• CompletedMarketing materialCP13.

• Project being definedReturn-logistics of face platesCP12.

CP14.

CP11.

CP10.

CP9.

CP8.

CP7.

CP6.

CP5.

CP4.

CP3.

CP2.

CP1.

Number Project Status

Core component location • Project being defined, deadline June 30

Streamlining • Streamlining on track

Online services• Currently scoping project

• Preliminary go-live phase 1 in June

Packaging • Ready for roll-out

Distributors to Xiamen• Transfer to be planned. Consideration to customer specific issues and

resource constraints in Distributor Sales

KA to Xiamen• Until HUB template is in place only few part numbers can be handled

• Currently in dialogue with Amplifon to have a pilot on an Italian tender

Control tower / forecasting• CT: Platform decided. Development started. Waiting on GUI decision

• FT: Scope completed. Searching for possible suppliers/solutions

Transportation setup • Not yet started

Supplier consolidation• Supplier base analyzed & categorized. Non-moving suppliers to be

terminated while re-sourcing potential suppliers. Resources allocated.

Portfolio rationalization • Project being defined

Indirect purchasing • Many individual projects – overall progressing according to plan

Data cleanup

C

Ongoing according to plan According to plan but critical Behind plan

Not yet started Completed

"A" projects

"B" projects

"C" projects

On-going communication to key stakeholders Board meetings Steering committee

meetings GN Resound

management

Tracking tools developed to provide transparent overview Each project is

reported with status and comment

Opportunities for acceleration flagged

Critical issues flagged to avoid surprises

Going forward, a pragmatic continuous improvement approach combined with performance management ensures realization of results

Measure

Identify biggest impact

Name action

Do

15

Performance management principles Continuous improvement approach

Clear KPIs and targets

Weekly and monthly cycles

Actions identified based on balance between biggest impact and required effort

Linked to long term plans(strategy and budgets)

Share best practice and ensure cross organization involvement

16

Agenda

1. Company introduction

2. The supply chain as a competitive advantage

3. Lessons learned and next steps

Lesson learned

The supply chain organization has capitalized on the transformation journey and has defined key principles for future transformation

17

Management support

Process focused

Goals and performance

Support from top management

Buy-in from country managers

Will facilitate the success of an important change project

Necessity to be process oriented from the start

Will facilitate a broad implementation across sites

Will ensure a solid basis for further developments

Agree from the beginning on clear targets inside and outside the supply

chain organization (e.g service level agreements)

Use KPI tracking to have a clear and unbiased overview of the reality

Broad involvement

Inform, Involve and ask for the support of all the departments from Operations

Will guarantee the change mindset needed for success

The next step in the journey toward further competitive advantages has begun

18

Next steps

Building new regional operational centers

Setup new processes

Develop IT capabilities

Transfer activities

Develop the platform

Aug-Oct

Further competitive advantages

Simplification outside the supply chain - Customer care - Finance - IT

Improved reverse logistics

flow

Fine tune S&OP

Go further with cost optimization: 5% reduction on cost per unit every year

Optimize and fine tune the setup

Warehouse optimization

Design for value

Simplicity e.g. packaging and freight setup

S&OP

Q&A